Home / Financial Firm (Unknown - Insurer) / Determination 242431
Determination 242431
Cash settlement amount for hail damage repairs
Summary
After a hailstorm the FSP elected to repair the home, but the repairs were poor and incomplete, and it offered a cash settlement well below the repair cost. AFCA found the FSP had lost its right to repair and ordered payment of the independent quantity surveyor's estimate, with interest if unpaid.
An insurer that fails to complete repairs within a reasonable time may forfeit its right to repair and must pay an amount sufficient for the insured to complete the repairs.
Issues
- Claim amount dispute primary · upheld
“I determine that the FSP is to pay the Applicant the sum of $115,380”
- Delay secondary · upheld
“the FSP has lost a right to insist on entitlement to repair the home, being unable to discharge its obligation for some 21 months”
- Repairs or contractors secondary · upheld
“repairs carried out by UBS were poor and incomplete”
Subjects and remedies
home or building damagenatural disasterpay claimpay interest
Text of the determination
Case No: 242431 Determination Page 1 of 6
Case number: 242431
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
28 February 2012
Background
1. The Applicant’s home was insured with the Fi nancial Services Provider (FSP).
2. The home was damaged by a hailstorm in March 2010.
3. A claim was lodged with the FSP who accepted liability and elected to repair
the home. The repairs were apparently poor and incomplete.
4. Following discussions between the parties, the FSP proposed to resolve the
claim with a cash settlement offer of $24,723; contending that this amount was
sufficient to cover the cost of completing incomplete repair works and
rectification of poor repairs.
5. The Applicant rejected the offer, contending that its builder had quoted him
$112,776 to carry out the relevant repairs.
6. As the parties do not dispute the scope of works involved, the Service engaged
quantity surveyor PQS to provide an independent review of the cost to carry out
the agreed scope of works. PQS estimated that the relevant repairs would cost
$115,380.
7. The parties were unable to agree to an amicable resolution following PQS’s
review of the cost involved, so this matter has now been referred for a
Determination.
Summary of Applicant’s Position
8. The FSP’s offer is underquoted and unsa tisfactory.
9. The FSP has mismanaged his claim. It was given ample opportunity to repair
the damage to his home, but the repairs were poorly carried out and
incomplete. The FSP then tried to force a cash settlement on him with a grossly
unreasonable cash offer; which would have left him substantially out of pocket if
he had accepted.
Determination
Case No: 242431 Determination Page 2 of 6
10. He does not consider it fair for the FSP to be given a further opportunity to
repair his home.
Summary of FSP’s Position
11. The costing prepared by PQS was inappropriate and unreasonable. Its building
consultant (AV) has acknowledged that the original costing of $20,000 was too
low. He has advised that the appropriate amount should be $30,000.
12. The policy entitles the FSP to decide whether it wishes to repair the damage or
cash settle the claim. In deciding the cost to repair, it is its right to decide the
reasonable cost of repair.
13. It is prepared to repair the storm damage to the Applicant’s home and rectify
the poor repair works out by its original builder. It is also prepared to repair the
maintenance related damage as a gesture of goodwill. If the matter is to be
cash settled, it is prepared to pay $30,000.
14. The FSP relies on the following policy provisions:
“ Settling building claims
…
Once we accept your claim, we will decide whether to:
repair or rebuild the damaged portion of your building; or
pay you the amount we determine to be the reasonable cost of repairing the
damaged part of your building.
If we decide to pay you, the payment will be based on the amount we would have
expected to pay if the work was authorised and completed by us, and after deducting
any excess which applies to the claim. ”
Issues
15. Whether the Applicant is entitled to have his claim cash settled and if so, for
how much.
Reasons for Decision
16. This dispute has not been the subject to a FOS Recommendation and has
proceeded directly to Determination.
17. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with the Operational Guidelines to the FOS Terms of
Reference. This is because of:
The monetary value involved.
Case No: 242431 Determination Page 3 of 6
The parties were unable to amicably resolve their differences despite the
Service’s assistance.
18. I am satisfied that the material has been exchanged and the parties have had
the opportunity to respond to the issues raised.
19. I consider the FOS Terms of Reference relevant to this dispute are:
“ 8.2 Dispute resolution criteria
Subject to paragraph 8.1, when deciding a Dispute and whether a remedy
should be provided in accordance with paragraph 9, FOS will do what in its
opinion is fair in all the circumstances, having regard to each of the following:
a) legal principles;
b) applicable industry codes or guidance as to practice;
c) good industry practice; and
d) previous relevant decisions of FOS or a Predecessor Scheme (although
FOS will not be bound by these). ”
20. It is unnecessary to repeat the history of the dispute in any detail other than to
note as follows:
The Applicant’s home was damaged by a hailstorm in March 2010.
The FSP initially elected to repair the damage a nd engaged builder UBS
to carry out the relevant works.
The Applicant and his wife were unhappy with the repairs carried out by
UBS and also with the manner it was handling the repair.
The FSP engaged building consultancy “SBC” to report on the repair
foll owing the Applicant’s complaint .
SBC confirmed that repairs carried out by UBS were poor and incomplete.
SBC issued 3 separate scope of works identifying the works necessary to:
(a) Rectify previous poor repairs by UBS
(b) Complete unrepaired storm damage
(c) Repair maintenance related issues.
The parties do not dispute that the above scope of works covers all that is
necessary to reinstate the Applicant’s home.
The Applicant does not dispute that he is responsible for the maintenance
related issues identified in SBC’s third scope of works (ie. (c) above).
The dispute between the parties solely concerns the reasonable cost to
carry out the repairs identified in the first two scope of works (ie. (a) and
(b) above).
The FSP believes some $24,723 is sufficient to carry out the relevant
repairs and is prepared to offer cash settlement on that basis. It has since
acknowledged that the amount is inadequate and is now prepared to offer
$30,000 if the claim is cash settled.
Case No: 242431 Determination Page 4 of 6
The Applicant was quoted some $112,776 to carry out the relevant
repairs.
The matter was referred to the Service because the parties were unable
to resolve their differences as to the cost to carry out the works stipulated
in SBC’s first two scope of works.
The Service attempted to assist the parties by suggesting that PQS, a
quantity surveyor, conduct an independent review of the costing. The
parties agreed.
PQS has advised the Service that it would cost about $115,380 to carry
out the relevant repairs. This was communicated to the parties who were
given time to resolve their differences amicably.
The FSP believes PQS’s estimation was unreasonably high. It proposed
settlement by offering to:
- complete the repair with the use of its “most reputable builder” ;
- have a senior monitor the claim from now; and
- repair the home’s maintenance related damage as a gesture of
goodwill.
The Applicant rejected the offer, citing previous experience had led he
and his wife to distrust the FSP’s handling of the repair. He also
questioned why the FSP did not use its most reputable builder from the
beginning.
The FSP maintains that it is entitled to complete the repair and can
complete the same. In the alternative, it is prepared to cash settle the
claim for $30,000.
21. It is plain that the policy terms entitle the FSP to decide whether it wishes to
repair the Applicant’s home or pay the cost to repair the home. The Applicant
does not dispute this. His contention is that the FSP has had the opportunity to
repair his home but it failed to do so. For this reason, he believes that a cash
settlement based on the amount it would cost him to carry out the relevant
repairs would be the better outcome.
22. The FSP maintains that it is its right to decide repair the damage. It is prepared
to complete the repair and in view of the delays the Applicant had encountered,
it is also prepared to repair the uninsured damage in his home.
23. Whilst the policy entitles the FSP to repair the Applicant’s home, I must do what
I consider is fair in all the circumstances having regard to relevant legal
principles, industry codes, good insurance practice, and previous decisions of
the Service. In this respect, I have had regard to the following:
It is an implied term of an insurance contract that parties to it must treat
each other with the utmost good faith. Case law has indicated that a
failure to address a claim within reasonable time may constitute a breach
of that obligation.
Case No: 242431 Determination Page 5 of 6
It is also good insurance practice and consistent with the spirit of the
General Insurance Code of Practice that insurers should resolve claims
within a reasonable time.
The Service has previously determined:
- An insurer may be taken to have forfeited an entitlement to
repair if it fails to discharge that obligation within a reasonable time.
- An insurer who elects to cash settle a claim should pay an
amount sufficient to enable a policyholder to complete repairs. It must
be borne in mind that policyholders are rarely able to get the prices
insurers are able to obtain.
24. In this matter, the FSP has had an opportunity to repair the Applicant’s hom e
but was unable to give a satisfactory discharge of its obligation for some 21
months now.
25. I am of the view that the FSP has lost a right to insist on entitlement to repair
the home and that it is fair in all the circumstances that the dispute is resolved
by means of a cash settlement.
26. Turning to the question of cost, the FSP contends that its liability is limited to
$30,000. Although it argues that PQS’s quote was “inappropriate” and
“unreasonable” , it has not provided any independent evidence to substantiate
such claims. Its evidence on this issue comes from SBC, whose costing is
being questioned. Furthermore, the fact that SBC now admits that its initial
$20,000 costing was inaccurate creates doubt as to whether its costing can
generally be relied upon.
27. The Service arranged for further explanation to be provided by PQS as to its
estimates by reference to a series of questions and comments from the FSP.
PQS’s response has been referred to the FSP and its builder SBC has in turn
commented on those matters. I have carefully considered those matters and I
confirm my acceptance of the costing provided by PQS.
28. The general comment by the builder SBC that PQS’s costing is too high ,
without further detail or comparative example, is not helpful. Further, the
criticism that allowance for the cost of scaffolding is beyond the scope of works
flies in the face of the cogent opinion by PQS that scaffolding will be required
for work to be carried out above a certain level. In all other respects, I also
accept the sp ecific explanations given by PQS and reject SBC’s further
comments and opinion. I am satisfied to rely upon the PQS costing as
reasonable.
Case No: 242431 Determination Page 6 of 6
Determination
29. I determine that the FSP is to pay the Applicant the sum of $115,380 within five
(5) business days of its receipt of notification that the Applicant has accepted
the Determination failing which, it is to pay interest on that amount at the
statutory rate from the expiry of the said five (5) business days until the claim is
settled.