Home / Financial Firm (Unknown - Insurer) / Determination 242150

Determination 242150

Denial of water inundation claim under flood exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2012-09-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant's home and contents were inundated in January 2011 and the FSP denied the claim as flood. The Panel found the inundation fell within flash flood cover and ordered the FSP to meet repair and contents costs within policy caps, with interest from 9 May 2011, but refused the roof leak damage and legal costs.

Heavy rain within 24 hours of the inundation brings the loss within the flash flood and stormwater runoff insured event, and the policy clearly informed the insured of the flood exclusion.

Issues

Subjects and remedies

natural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 242150 Determination Page 1 of 15 Case number: 242150 General Insurance - Domestic Insurance - Home Contents - FSP Decision - Denial of claim (Flood) 3 September 2012 Background 1. The Applicant insured her home and contents with the Financial Services Provider (FSP). The relevant period of insurance operated for twelve months beginning from 18 November 2010. During this period, the building was insured up to a sum of $215,000 and the contents for $70,000. 2. On 13 January 2011, the Applicant lodged a claim under the policy due to extensive water inundation following severe weather events in Queensland. 3. The FSP denied the claim on the basis the damage was due to “flood”. The Applicant, through her solicitors, has disputed this. 4. For the sake of simplicity, reference to the Applicant will include her legal representatives. 5. Both the Applicant and the FSP have provided detailed submissions on the relevant issues. For the sake of brevity, the Panel will only briefly summarise these submissions given all of the material made available has been exchanged with the other party. Summary of Applicant ’s position 6. The Applicant submits the following as alternative arguments in response to the FSP’s decision: a. The Applicant applied for and received confirmation in mid 2010 that she was covered for flood. Accordingly, the FSP should honour this acceptance despite stating there was no such record on its system. Alternatively, the FSP should be bound by this representation. b. The FSP’s policy failed to clearly inform her that “flood” was excluded as required under Section 35 of the Insurance Contracts Act 1984 (the Act). c. The damage was due to “Flash flood and stormwater run - off”, which is an insured event. In particular, the inundation was due to heavy rain that fell from 4.00am on 11 January 2011 which resulted in the Wivenhoe Dam operators elevating their strategy to W4. This decision Determination Case No: 242150 Determination Page 2 of 15 resulted in massive discharges of water into the Brisbane River that ultimately inundated her property. d. The FSP is unable to discharge its onus in establishing the loss was caused by “flood”. e. Her roof sustained damage from this event as water leaked into her bedroom. This has never occurred previously and is therefore also covered under the policy. 7. The Applicant seeks to be indemnified for her claim in addition to legal costs. Summary of FSP’s position 8. In response to the Applicant ’ s arguments, the FSP submits the following: a. There is no record that the Applicant ever applied for flood cover and/or was accepted. In particular, it has provided a transcript of a conversation she had with it on 10 January 2011 which contradicts her evidence in this regard. b. It has provided evidence from an appropriately qualified individual to corroborate that a PDS was sent to the Applicant prior to the claim. Further, the policy structure and layout in conjunction with this evidence enables it to rely on the exclusion clause of “flood” pursuant to Section 35(2) of the Act. c. The damage was not caused by “Flash flood and stormwater run - off”. 9. The FSP relies on a number of hydrology reports authored by SC and the following policy provisions to deny the Applicant’s claim : “ Words / terms with special meanings Flood Rising water which enters your home as a result of it running off or overflowing from any origin or cause. This policy does not cover flood unless we have agreed and it is shown on your certificate of insurance. Flash flood and stormwater run-off A sudden flood caused by heavy rain that fell no more than 24 hours prior to the flash flood or stormwater run-off. … Storm A violent disturbance of the atmosphere associated with strong winds including a cyclone, lightning, heavy rain, hail or snow, but not continuous bad weather by itself. … Insured events you are covered for Damage caused by weather … Case No: 242150 Determination Page 3 of 15 What is covered What is not covered Storm Loss or damage:  caused by rain, hail or snow after it has reached the ground; Flash flood and stormwater run - off A sudden flood caused by heavy rain that fell no more than 24 hours prior to the flash flood or stormwater run - off Loss or damage caused:  by flood; … Your home The most we will pay you for home claims What is covered What is n ot covered Flash flood and stormwater run - off We will pay up to 50% of your home sum insured or $25,000 whichever is higher. … Your contents The most we will pay you for contents claims What is covered What is not covered Flash flood and stormwater run - off We will pay up to 50% of your contents sum insured or $25,000 whichever is higher, but not exceeding your contents sum insured. …” Issues 10. Whether the Applicant is able to establish that she had applied for and was covered for flood in 2010. 11. Whether the FSP clearly informed the Applicant, pursuant to Section 35 of the Act, that she was not covered for flood. Case No: 242150 Determination Page 4 of 15 12. Whether the FSP was entitled to deny the claim pursuant to the “flood” exclusion or the lack of an insured event. 13. Whether the Applicant is entitled to legal costs. Reasons for decision 14. Due to the nature of the dispute, the parties have been informed that the matter has been referred to the Panel for Determination in line with the Operational Guidelines to FOS’s Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 15. This decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in the insurance industry and a representative with extensive experience in consumer claims. 16. It is appropriate to consider the issues under the various headings. Application for flood 17. The Applicant’s evidence in this regard has been summarised by her solicitors. In particular, she has alleged that:  In early to mid 2010, she contacted the FSP to change her car insurance. In this conversation, she also requested flood coverage for her home and contents insurance policy.  The consultant posted to her an application form and told her that the cost of adding this optional cover would be included in her next bill. She received the form, completed it and sent it back.  A few weeks later she received a letter from the FSP stating that her application had been approved.  On 10 January 2011, in light of the news abo ut the flash flooding in Toowoomba, she consulted her renewal notice and identified she was not covered for flood. Based on this, she telephoned the FSP to query her lack of cover.  The FSP responded to the Applicant’s query stating she was not covered for flood according to its records. She responded by referring to the letter she had received confirming she was covered in this regard. The FSP asked her to send a copy of this letter, to which she agreed.  The letter had been contained in a folder that included other documents. Following her conversation with the FSP, she left this folder on the floor of her home. During the events that occurred the next day, she evacuated the property and unintentionally left the folder at home. As a result of the inundation, the folder became wet. Case No: 242150 Determination Page 5 of 15  On Thursday, 13 January 2011 an individual CR assisted the Applicant in cleaning the house. CR saw the open folder lying on the ground to dry. The Applicant showed CR the flood approval letter in the folder and expressed her displeasure that the FSP had told her she was not covered for flood despite this letter. CR recalls seeing this letter.  On Friday 14 January 2011, whilst she was cleaning her house, she retrieved the folder and placed it on the pavers by her front door to dry out. On Sunday 16 January 2011, after realising the folder was still outside, she went to retrieve it and found it was no longer there. She presumed a volunteer had disposed of it in the rubbish and the council had picked up her rubbish by that stage. 18. The Applicant stated both she and CR were prepared to provide statutory declarations corroborating the existence of the letter but have failed to do so. Regardless, the Panel does not accept this would assist her case for the reasons to follow. 19. The FSP conducte d a search of its records using the Applicant’s phone numbers and located 6 calls. The dates of these calls were 28 February 2010, 6 October 2010, 25 October 2010 (twice), 2 November 2010 and 10 January 2011. Due to technical difficulties, it was only able to retrieve the recordings for 28 February 2010 and 10 January 2011 and has provided transcripts for those calls. 20. The first conversation on 28 February 2010 relates to the cover for the insured property being incepted after the previous policy the Applicant had with the FSP lapsed due to non-payment of the premium. The Panel notes the following was discussed with respect to flood: “FSP: No. Now this policy automatically covers flash flood and stormwater run-off. If you would like a more comprehensive cover against flood damage you will need to apply for this separately. Also, our standard policy includes cover for glass breakage. Would you like to include our advance cover option which covers you for accidental damage to selected items and includes the motor burn out. App: Nah. … FSP: … Alright. Now this building is sum insured for $200,000; the contents are $65,000. Specifically listed items for $1,900. You have not elected a higher flood cover, pet cover, advance cover or motor burn out. …” 21. The Panel accepts that the application for flood cover was not discussed in this conversation although the FSP did inform the Applicant on at least two occasions that she was not covered for flood. This therefore implies the flood application was discussed in one of the subsequent conversations on 6 October, 25 October or 2 November 2010. The Panel notes these dates are proximate to the renewal date of this policy. 22. However, the Panel considers the conversation on 10 January 2011 contains significant inconsistent evid ence to the Applicant’s position that a flood Case No: 242150 Determination Page 6 of 15 application was ever sent. In particular, the Panel considers the following excerpts of this transcript to be relevant: “FSP: Welcome to [FSP] line, this is [A], how can I help you? App: Hi, I just want to make sure my house is insured for flood please. … FSP: Okay, if you don’t have flood cover at the moment, it’s not something you can add on immediately anyway um App: Well, I requested it when I first got it done.… … FSP: Okay, so this insurance has the standard flash flood and stormwater runoff, not the additional flood cover, so depending on what it is that you’re referring to, it depends on whether they would class it as a flash flood or whether it comes under the additional flood cover as to whether they would allow you to lodge a claim for that. If there was damages you would definitely need to look at lodging a claim for consideration. … FSP: You are required to add the cover at new business or renewal only. App: Well, I requested it [unintelligible] FSP: Okay, so you received a flood application pack from us and you filled it out and sent it back to us? App: I didn’t receive one. … FSP: Yea, look like I said you can apply for the if there is something App: Well, f***ing I applied for it when I bloody rang up about it, and it’s my fault that someone is incompetent enough they don’t send the thing!” (Panel emphasis) 23. Upon being presented with the significant inconsistency evident in this recording, the Applicant’s explanation was that she was in an extrem ely distressed state when the call was made. As a result, she confused the consultant’s reference to a flood pack to be an emergency kit that was to be sent out to parties in preparation of any flood event. 24. The Panel considers this explanation is highly implausible for the following reasons:  The subject of the whole conversation was clearly centred and isolated to the flood cover. There is no discussion or any reference to an emergency kit or any confusion that the FSP’s question about the flood application pack was in reference to this.  In the second highlighted extract, the Applicant was clearly upset about not being sent information she requested. The Panel considers it is improbable she would be upset in the context of an emergency kit Case No: 242150 Determination Page 7 of 15 given the subject of the conversation preceding this was still about the flood cover. 25. At no point in the whole conversation does the Applicant ever mention, or even infer, that she had received confirmation from the FSP she was covered for flood by reference to a letter. Further, there is no reference whatsoever to her promising to send the letter to the FSP to confirm this application. 26. Based on the evidence as provided the Panel is not satisfied that the Applicant has been able to establish on the balance of probabilities that she had completed an application for flood. The Panel is satisfied given the evidence provided by the FSP that no such application was made on inception or after inception of the policy and is satisfied that the Applicant is mistaken as to her belief with respect to this. 27. The Applicant has also argued that the policy fails to clearly inform as to the derogation from flood cover and/or the limitations on the extent of cover for flash flood. There is no dispute that the Applicant had received the policy documentation and Certificate of Insurance. 28. It is established law that in order to satisfy the requirement to clearly inform, the language of section 35 (2) allows for a proposed insured to be clearly informed by providing the relevant documentation in writing and that the relevant exclusion and/or limitation in this case is clear and unambiguous and in a manner which a person of average intelligence and education is likely to have little difficulty in finding and understanding if that person reads the policy in question. 29. The Panel has reviewed the FSP’s policy on a number of occasions. The policy is indexed with relevant sections covering the insured events. The policy sets out the definitions of storm and flash flood and stormwater runoff. The policy clearly indentifies that flood and storm surge is an optional cover but otherwise flood is excluded from cover. The Certificate of Insurance also clearly identifies that with respect to the Applicant’s policy flood and storm surge is not covered. Having considered the Applicant’s submissions and the FSP’s policy documents, the Panel is satisfied that the FSP has met its obligations to clearly inform the Applicant of the extent of the exclusions and limitations in accordance with the requirements of the Insurance Contracts Act. Roof Claim 30. The Applicant’s evidence regarding this damage is based on her version and a couple of black and white photographs she has produced. According to the Applicant, rainwater had come through the roof in her bedroom and caused damage during the storms preceding the inundation. Further, the roof had never leaked prior to the storm. Case No: 242150 Determination Page 8 of 15 31. The two photographs were allegedly taken at the time of the event and show mould on the ceiling. The Panel considers it is unusual for mould to form so quickly after a leak. Instead, mould is more indicative of an ongoing issue. 32. Accordingly, the Panel considers the photographs are inconsistent with the Applicant’s evidence that the roof had never leaked previously. 33. The Applicant has not provided any o ther evidence to support her contention, such as photographs of the roof or any expert report. Given the absence of this and the inconsistent photographic evidence, the Panel is not inclined to accept that the Applicant has established the roof was damaged as a result of the storms in January 2011. 34. Instead, the evidence of mould indicates an ongoing issue rather than a one- off event. Accordingly, the Panel is not satisfied, on the balance of probabilities, the Applicant has established that the FSP is liable for any of the costs associated with this event. Water Inundation 35. The Applicant has provided some evidence regarding her recollection of the events on 11 January 2011. In particular:  She recalls it was windy and raining heavily on the day. At 5.30 am when she woke up, the yard was ankle deep with water.  At approximately 8am, the house lost power and there was a lull in the rain at 1.15pm. By this stage, she had begun to panic as the rainwater in the yard had reached the path leading to her front door. She went for a walk and saw that houses on N Street were under water and water was gushing down the Brisbane Valley Highway.  She returned home and started packing personal items up high. She recalls there was more rain in the afternoon.  At approximately 6.00pm, she drove along S Road (which is the road her house is located on) and observed water that stretched along the road for approximately five houses down the street.  At approximately 6.45pm, she sought refuge with her children at the school along with a number of other Fernvale residents. 36. The FSP has provided a number of hydrology reports from SC. The latest one was dated 24 July 2012 and this contains the hydrologist’s latest conclusion regarding the likely method of inundation. 37. In summary, SC identified that the likely cause of the inundation was due to the releases of water from the Wivenhoe Dam. In particular, in his report dated 24 July 2012, he provided the following updated information regarding the likely method of inundation to the Applicant’s pr operty due to the elevated levels in the Brisbane River caused by these releases:  The water from the Brisbane River reached properties in Fernvale by means of what is known as “breakout flow”. This is where high levels of Case No: 242150 Determination Page 9 of 15 flow cause elevated river levels that caused the flow path of a river to change (because the elevated river levels enable the river to cross areas which would normally be dry).  This occurred in a particular area in Fernvale (between Titmarsh Circuit and Poole Road) where the inundation of properties occurred due to breakout flow travelling along a breakout flow path (a portion of which is referred to as “Titmarsh Gully”).  This breakout flow path travels from the breakout point in the Brisbane River and crossed the unnamed road between Brisbane Valley Highway and P Road. This flow, running in a south-easterly direction adjacent to Titmarsh Circuit then enters an open drainage channel which flows under S Road, then P Road prior to entering Ferny Gully. Ferny Gully enters the Brisbane River in the immediate vicinity of the Savages Crossing gauge. 38. Although the Applicant has provided some evidence to dispute this, the Panel intends to adopt and accept SC’s conclusion in this regard for the purposes of the following analysis. 39. On 21 May 2012, FOS issued a memorandum to all relevant stakeholders advising of the broad approach adopted in considering the proximate cause of the implementation of the W4 Wivenhoe Dam strategy that led to the development of a flood wave in the Brisbane River. This in turn led to significant inundation of properties below the Wivenhoe Dam in the time after the W4 strategy was invoked. 40. In that memorandum FOS advised that after considerable deliberation, the Panel formed the view that the heavy rain occurring from 4.00am on 11 January 2011 and in particular the heavy rain between 4.00am and 8.00am was a proximate cause of the W4 strategy being invoked. This was therefore a proximate or effective cause that led to the flooding of many of the properties along the lower reaches of the Brisbane River. 41. The approach was reached after consideration of all material that had been provided to FOS by stakeholders and contrary to the comments of the FSP in its reference documents, after the FSP was given the opportunity of addressing the issue of the relationship between the heavy rain that fell from 4.00am on 11 January 2011, the adoption of the W4 strategy and the particular wording of its policy. 42. The Panel noted in relation to the broad approach that each individual dispute will depend upon the basis of the individual and unique factors relevant to the dispute. In that regard, the parties were invited to make further submissions in relation to the disputes before FOS. 43. In view of the issues arising, detailed further submissions were made b y the FSP on 14 June 2012. Included with the submissions were the following documents: Case No: 242150 Determination Page 10 of 15 a. A reference document for disputes relating to Queensland Floods (this is a general reference document). This sets out various submissions the FSP makes in relation to a number of topics. Not all issues raised in the reference document appear in the current dispute. b. Letter from SC attaching a key information sheet for the Applicant’s property dated 7 June 2012 (This document was updated by SC in a subsequent letter dated 24 July 2012). c. WT Report “Investigation of the January 2011 Inundation event – Brisbane” dated March 2011. d. Statement from SC dated 7 June 2012. 44. The FSP’s reference document does not specifically address the individual factors relating to the current dispute. However, it argues that the heavy rain that fell from 4.00am on 11 January 2011 should not be seen as being unrelated to the rain that had fallen in the dam’s catchment of the previous days and should not be seen as the proximate cause or effective cause that led to the adoption of the W4 strategy. 45. The FSP maintains that on any reasonable view, the damage sustained to the downstream properties was the combined effect of all of the rainfall that had fallen and not just the rain that had fallen from 4.00am on 11 January 2011. By adopting a commonsense valuation of the facts, the FSP argues that the proximate cause could not be the rain that fell from 4.00am on 11 January 2011. Instead, on any reasonable view, the damage sustained was the combined effect of all of the rainfall that had fallen. 46. The Applicant has argued that the final report from the Flood Commission does not call into question the evidence of the engineers about the move from W3 to W4 strategy. Further, the Applicant argues essentially that the transition from W3 to W4 by the Wivenhoe Dam engineers on the morning of Tuesday 11 January 2011 was caused as a result of the significant rainfall that fell commencing at approximately 4.00am on 11 January 2011 over the Wivenhoe Dam catchment area. 47. There is no dispute that heavy rain fell over the Wivenhoe Dam catchment area and in fact parts of the Brisbane River from 4.00am on 11 January 2011. 48. The information exchanged and relied upon by all parties and contained in the SEQWater report dated 2 March 2011 identifies the rapid increase in the inflows to the Wivenhoe Dam commencing from about 4.00am. The information confirms that the inflows into the dam had been steadily decreasing from 3.00pm on 10 January 2011 to 2.00am on 11 January 2011. 49. The information exchanged confirms that prior to approximately 4.00am on 11 January 2011, the dam releases were being managed at the W3 strategy. Whilst the W3 strategy had led to an increase in the levels of the Brisbane River, the W3 strategy was designed to avoid where possible inundation of the properties below the Wivenhoe Dam by flooding from the Brisbane River. Case No: 242150 Determination Page 11 of 15 50. The rainfall data and information relied upon by the parties and not disputed confirms that there were two significant rainfall spikes, with the rain that fell from 9 to 10 January 2011 being the “first spike” and the rain that fell on 11 January 2011 being the “second spike”. This is confirmed by the FSP’s hydrologist in his statement of 7 June 2012. 51. There is no dispute that following the second spike, that is, the heavy rainfall which commenced on or about 4.00am on 11 January 2011 over the Wivenhoe Dam, the W4 release strategy was adopted. 52. The information provided by SEQWater confirms that from about 4.00am on 11 January 2011, there was a significant increase in the inflows to the Wivenhoe Dam and that as a result of the significant increase in the inflows, by 8.00am on 11 January 2011, the Wivenhoe Dam engineers were left with no alternative but to adopt the W4 release strategy. 53. The information provided by the parties and in particular the information provided by the FSP’s hydrologist confirms that the increased releases from the Wivenhoe Dam after the adoption of the W4 strategy led to the development of a flood wave that ultimately caused the flooding from the Brisbane River downstream of the Wivenhoe Dam. 54. The Panel agrees with the FSP’s submission that the proximate cause is the cause determined by a commonsense evaluation of the relevant facts. In the event that there are two or more proximate causes, one within the policy and the other excluded, the policy does not respond. The proximate cause is not determined by identifying the last event or final trigger, but by determining what is the dominant, effective, direct or efficient cause of the loss. 55. The Panel is satisfied having considered all of the information that prior to the rainfall commencing on or about 4.00am on 11 January 2011, there had been a steady reduction in the inflows to the Wivenhoe Dam from about 3.00pm on 10 January 2011. At that time, the Wivenhoe Dam was being managed at the W3 release strategy. This release strategy whilst causing some increase in the level of the Brisbane River was being maintained with the aim of avoiding flooding of the areas below the Wivenhoe Dam wherever possible. 56. According to the information exchanged, including the information provided to the Queensland Flood Commission of Inquiry, following the heavy rain that commenced falling on or about 4.00am on 11 January 2011, the rapid increase in the level of inflows into the dam, left no real alternative but to adopt the W4 release strategy from 8.00am on 11 January 2011. The hydrology, including that from the ICA’s Panel of Hydrologists and from the FSP’s SC, supports the view that the adoption of the W4 strategy directly contributed to the development of a “flood wave” and the subsequent inundation of properties below the Wivenhoe Dam. 57. Whilst the Panel accepts there had been a significant impact on the levels of the Wivenhoe Dam by the rainfall that had commenced falling on or about 9 January 2011 (and earlier), the Panel is satisfied that having regard to all of Case No: 242150 Determination Page 12 of 15 the information exchanged and the relevant legal principles, that the heavy rain that commenced falling at or about 4.00am on 11 January 2011 was a proximate or effective cause of the adoption of the W4 strategy and this combined with the heavy rain fall that fell over the Brisbane River from about 4:00am on 11 January 2011, caused the inundation of many of the properties below the Wivenhoe Dam as a result of the flood wave created by the increased releases. 58. Alternatively, the FSP argues that if it is accepted that there are other proximate causes apart from the implementation of the W4 strategy, then the Wayne Tank principle applies, as the earlier rain was also a proximate cause of the inundation. The FSP also argues that with respect to the inundation caused by the W4 release that was due to an intervening decision by the dam operators and is not covered under the current policy. 59. With respect to the last argument, the Panel is of the view that it was not an intervening factor that led to the adoption of the W4 strategy; the fact was that the level the dam had reached by 8.00am on 11 January 2011 left the operators with no alternative but to adopt the W4 strategy at that time. 60. With respect to the argument regarding the Wayne Tank principle and the rainfall prior to the 24 hour period being a contributing factor or proximate cause of the loss, the Panel notes the policy wording provides cover for sudden flood caused within 24 hours of heavy rainfall. The relevant question is whether the inundation is caused by heavy rain that fell no more than 24 hours prior to the flood. The Applicant’s property 61. The A pplicant’s property is constructed on a concrete slab. A ccording to these key conclusions statement the benchmark level of the property is 42.8m AHD. 62. SC’s statement, particularly his updated key conclusions attachment dated 24 July 2012, indicates the effect of the W4 releases first reached the vicinity of the Applicant’s proper ty at 8.46am on 11 January 2011. 63. The Panel notes that the ultimate inundation of the property was 0.6m above the benchmark level. SC identified this peak inundation occurred at approximately 2.15am on Wednesday 12 January 2011. 64. In SC’s e arlier key conclusions statement he found the peak inundation occurred at 2.12am on 12 January 2011 to a height above benchmark of 0.9m 65. The Panel accepts the possibility that these assessments may not be entirely accurate and notes the arguments made by the Applicant with respect to this. However, as explained previously, the Panel accepts and adopts SC’s conclusions for the purposes of this dispute and considers it is appropriate to do so for the following reasons: Case No: 242150 Determination Page 13 of 15  The Applicant’s submissions about other possible methods of inundation is not supported by hydrology evidence;  SC’s conclusions are relatively consistent with the rainfall and gauges’ data, the Applicant’s version of the events of the day and the loss adj uster’s report. 66. The policy covers flash flood or stormwater runoff, that is, sudden flood caused by heavy rain that fell no more than 24 hours before the flash flood or stormwater runoff. The Panel accepts having considered all of the information provided, the relevant legal principles and terms of the policy that the proximate cause of the inundation of the Applicant’s property was the heavy rain that commenced falling from 4.00am on 11 January 2011 and that this caused the inundation of the Applicant’s pr operty within the relevant 24 hour period to fall within the terms of the policy. 67. Accordingly, the Panel is satisfied that the FSP is liable to meet the Applicant’s claim in accordance with the flash flood and stormwater runoff provisions of the policy. Quantum 68. The Renewal Certificate of Insurance for the relevant period provides a sum insured of $215,000 for the home with contents of $70,000. Pursuant to the policy cap for the insured event of “Flash flood and stormwater runoff”, the FSP is liable up to an amount of $107,500 for the damage to the building and $35,000 for the contents. 69. There is minimal evidence available regarding the extent of the Applicant’s loss. Although the Applicant has provided a number of quotes or estimates, this has not been consid ered by the FSP’s loss adjuster. As a result, it is unclear if the cost of repairs being sought is proportionate to the damage sustained. 70. The Panel has been provided with a copy of the loss adjuster’s site report. However, this contains no estimate or quotation regarding the extent of the loss. 71. Therefore, the Applicant and the FSP are asked to work cooperatively together to establish the extent of the loss and to reach an agreement as to the cost of repairs and the various contents lost. Insofar as the FSP may have made payment of a compassionate sum to the Applicant, FOS does not have jurisdiction to deal with this payment but acknowledges that the FSP, given the terms on which the compassionate payment was made, may be entitled to deduct this payment from any settlement sum. 72. The Panel notes that as explained previously, the cost of repairs should not include the damage caused by the leaking in the roof within the Applicant’s bedroom. In this regard, the Panel has not been satisfied this damage was due to an insured event. Case No: 242150 Determination Page 14 of 15 Legal Costs 73. The Applicant has requested that FOS award the maximum amount of legal costs. FOS’s Terms of Reference do allow for the awarding of legal costs pursuant to clause 9.4 of the Terms of Reference. 74. The Applicant is represented by a community legal centre. It is commonly understood that community legal centres do not charge their clients for their legal services although there are exceptions to this. 75. The Panel is aware that legislation does allow for pro bono schemes such as Legal Aid and Community Legal Services (if acting under a Legal Aid Grant) to seek an award for costs. The case of Desmond Francis Lewis and Telstra Corporation Limited [1995] AATA 94 is also authority that a Community Legal Service may seek its costs in limited circumstances. This case indicated that the legal service in question was able to do so because it reserved the right to recover costs from the Applicant. 76. There is no evidence of any such agreement between the community legal centre and the Applicant. 77. Further, although legislation may allow pro bono schemes to seek an award for costs, the Panel’s ability to provide such an award is not founded in statute. Instead, the sole basis it can provide such an award is pursuant to clause 9.4 of the Terms of Reference which states: “FOS may decide that the Financial Services Provider contribute to the legal or other professional costs or travel costs incurred by the Applicant in the course of the Dispute.” (Panel emphasis) 78. As evident, this provision is only enlivened if the Applicant has incurred the legal costs. It does not entitle a third party to seek its costs for advocating a dispute on behalf of the Applicant from the FSP. 79. There is no evidence that the solicitors have any entitlement to recover its costs from the Applicant. Instead, it appears the solicitors are acting on a no fee recoverable basis. 80. In such circumstances, the Panel has no jurisdiction to award legal costs. Determination 81. The FSP is to meet the cost of repairs incurred by the Applicant and the cost of the replacement of items damaged as a result of the inundation of the property, subject to the limitations under the terms of the policy for cover for “ flash flood ” and stormwater runoff. 82. Insofar as the FSP is to cash settle the claim, the FSP is to pay interest from 9 May 2011 (being the date of rejection of the claim) to date of payment of the claim, in accordance with Section 57 of the Act. Case No: 242150 Determination Page 15 of 15 83. The FSP is not liable for the cost of repairs caused by the leaking roof.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.