Determination 241903

FSP honoured a withdrawal slip despite customer's instruction to cancel it

FirmFinancial Firm (Unknown - Bank)
Decided2013-07-15
ProductDeposit Taking · Business account
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$750
Amount claimed$156,473
SourceAFCA PDF

Summary

A joint account holder's builder withdrew $47,532 from a two-to-sign account after the FSP honoured a withdrawal slip the holder had cancelled, and the statements were not sent to him. AFCA found the FSP breached the mandate and statement obligations, ordered $750 for non-financial loss, and rejected the claim for the balance of the funds and consequential losses.

A bank must act only on a valid mandate, and the innocent joint holder's loss is one half of the funds withdrawn, which the QCAT consent orders had already restored, while consequential losses were too remote or outside FOS rules.

Issues

Subjects and remedies

pay non financial loss

Related

All Financial Firm (Unknown - Bank) determinations · Find similar determinations

Text of the determination

Case No: 241903 Determination Page 1 of 14 Case number: 241903 Deposit Taking - Current Accounts - Business Transaction Accounts - Transactions - Unauthorised transactions 21 June 2013 Background 1. In October 2009 the Applicant entered into a residential building contract (the Building Contract) with C-Pty Ltd (the Builder) for $475,320. The Building Contract related to substantial renovations to be made to the Applicant’s home (the Building Works). 2. The terms of the Building Contract required the Applicant and Builder to open a joint bank account, and required the Applicant to deposit of funds into that joint bank as security for progress payments payable under the Building Contract. The Applicant and Builder opened a joint account numbered ***0528, with the FSP (the Account). 3. The signing authority for the Account required that both the Applicant and the Builder’s authorised representative, Mr C, jointly sign for any withdrawals from the Account. That is, The Account was established on a “two to sign basis”. 4. On 12 January 2010 the Applicant deposited the sum of $47,532 into the Account (the Funds). He also signed a withdrawal slip for $47,532 (the Withdrawal Slip) authorising the FSP to pay the Funds to the Builder by way of a progress payment. 5. The Builder informed the Applicant that the payment could not be made from the Account, as funds were to remain in the Account as security under the Building Contract. The Applicant therefore paid the progress claim by cheque and instructed the Builder to destroy the Withdrawal Slip. 6. On 15 January 2010 the Applicant attended the FSP’s branch at Toowong and gave instructions to the FSP not to honour the Withdrawal Slip as it had been cancelled. The FSP representative with whom the Applicant spoke confirmed that a note to that effect wo uld be placed on the FSP’s IT system in relation to the Account. 7. On 29 January 2010, without the Applicant’s knowledge, the Builder presented the Withdrawal Slip – signed by himself and the Applicant - to the FSP. Despite the Applicant’s instructions to th e contrary, the FSP honoured payment of the Funds to the Builder. Determination Case No: 241903 Determination Page 2 of 14 8. The Applicant had not received statements for the Account from the FSP and so was unaware that the Funds had been withdrawn until 24 March 2011. 9. The dispute relates to the FSP allowing the Builder to withdraw the Funds from the Account on 29 January 2010, and the appropriate recompense for that conduct. 10. In the initial stages of the dispute in 2011, the Applicant indicated to FOS that had been prepared to settle the dispute for a sum in the vicinity of $5,000, but then re-considered his position and the extent of the consequential losses that he attributed to the FSP’s conduct. 11. FOS was advised by the FSP in 2011 that it has offered to settle the dispute with the Applicant for a sum of just under $3,500. The Applicant rejected that offer on the basis that he did not believe it to be “genuine”. 12. At present the Applicant is claiming a sum of $156,473.21 from the FSP. Summary of Applicant’s position 13. On 30 November 2010 the Applicant’s solicito rs terminated the Building Contract for alleged breaches by the Builder. 14. On 24 December 2010 the Builder filed an application in the Queensland Civil and Administrative Tribunal (QCAT) to recover amounts allegedly owed by the Applicant under the Building Contract. On 2 March 2011 the Applicant filed a Defence and Counterclaim in the same proceeding seeking the costs of completing and rectifying the Builder’s various works. 15. On 24 March 2011 the Applicant attended the FSP’s branch at Indooroopilly and requested copies of statements of the Account. It was at that time that the Applicant discovered the Builder had withdrawn the Funds on 29 January 2010. 16. In early June 2011 the Applicant commenced proceedings in the Brisbane Magistrates’ Court to recover the Funds (the Magistrates’ Court Proceeding). 17. In late June 2011 the Court ordered that: 1. The [Builder] pay into Court the sum of $47,532.00 within 28 days; 2. The [Builder] pay to the trust account of [the Applicant’s lawyers], on behalf of the Applicant, interest at the rate of 10% per annum from 29 January 2010 until 20 June 2011 totalling $6,614.16; 3. The [Builder] pay the Applicant’s costs of and incidental to the Application and the proceeding fixed at $2,035.00.” 18. In October 2011 consent orders were filed in the QCAT proceeding. Those orders included the following: Case No: 241903 Determination Page 3 of 14 The Applicant and [the Builder] will each be paid half of the money currently held in trust by the Magistrates’ Court Brisbane. 1. This order is in full and final satisfaction of the [Magistrate s’ Court] application ... and counter-claim of the [Applicant]. 2. The parties mutually release each other from all existing or future claims arising out of the work performed by [the Builder] ... ” 19. The October 2011 consent orders filed in the QCAT proceeding allowed the Applicant to recover $23,766 from the $47,532.00 paid to the Court, being an amount equal to half of the Funds taken from the Account by the Builder using the Withdrawal Slip. 20. The Applicant claimed the balance of the Funds taken by the Builder from the Account from the FSP, being an additional $23,766. 21. The Applicant also said that because of the FSP’s error he: a. lost the opportunity to terminate the Building Contract at the time the Builder withdrew the Funds and so avoid the rectification and completion costs incurred as a result; b. incurred legal and professional costs in having to conduct the QCAT Proceeding and the Magistrates’ Court Proceeding; and c. suffered anxiety, stress and inconvenience. 22. The Applicant estimates the total value of these additional losses to be $132,707.21, making his total claim against the FSP $156,473.21. Summary of FSP’s position 23. The Applicant and Mr C signed the Withdrawal Slip authorising withdrawal of the Funds. 24. The payment was honoured because while the employee assisting the Applicant on 15 January 2010 made a note on the Applicant’s customer profile for the FSP to dishonour the Withdrawal Slip, no such notation was made on the Builder’s customer profile. 25. The FSP acknowledges that it honoured the Withdrawal Slip in error, but said that the losses claimed by the Applicant are not attributable to such error because: a. from 20 June 2011 the Funds were in the control of the Magistrates’ Court until released following orders made in the QCAT Proceeding; b. the legal fees claimed by the Applicant in seeking to recover the Funds through the Magistrates’ Court proceedings were the subject of an order by the Court on 20 June 2011; Case No: 241903 Determination Page 4 of 14 c. the Applicant’s other legal fees were not incurred as a result of the FSP’s error but as a result of the dispute with the Builder about the Building Works and the Building Contract. 26. Had the Withdrawal Slip been dishonoured from the outset, the FSP would have been ordered by the Court to put a stop on the Account until the issues in dispute between the Applicant and the Builder were resolved. 27. The FSP rejects the Applicant’s claim for compensation. Issues 28. Did the FSP breach an obligation to the Applicant in honouring the Withdrawal Slip? 29. Did the FSP breach an obligation to the Applicant in failing to provide account statements? 30. If the FSP did breach either of both of the above mentioned obligations to the Applicant, what, if any, loss did the Applicant suffer by reason of such breaches? 31. Is the Applicant entitled to be compensated and if so, to what degree? Reasons for findings on the Issues set out in the Recommendation Did the FSP breach an obligation in honouring the Withdrawal Slip? 32. It is fundamental to the banker-customer relationship that a bank shall not pay any part of an amount due to a customer (i.e. the customer’s account balance) unless it has an unambiguous written order from the customer to that effect. The customer’s instruction to the bank is known as the customer’s “mandate”. Therefore, a bank must have a valid mandate from its customer to debit funds from that customer’s account. 33. The bank is also obliged to accept an instruction from a customer to stop a payment in circumstances where the customer has previously given a valid mandate, but the bank has not yet acted on that mandate and is in a position to stop payment. 34. The FSP has acknowledged that it acted in error when it allowed the Builder to withdraw the Funds. 35. On that basis the Case Manager accepted that the FSP breached the Applicant’s mandate and turned to consider whether than breach caused the Applicant any loss, together with the appropriate level of compensation for any such losses. Case No: 241903 Determination Page 5 of 14 Did the FSP breach an obligation in failing to provide account statements? 36. The Applicant claimed that he did not discover the Funds had been withdrawn from the Account until 24 March 2011, some two months after the withdrawal. He said that had the FSP provided him with regular statements of account, he would have discovered the unauthorised withdrawal and would then have terminated the Building Contract earlier. He said he would not have incurred the rectification and completion costs had he terminated the Building Contract at the first available opportunity. 37. The FSP said that its records show it was instructed to send statements to the Builder only, as the mailing address for the Account was set up as that of the Builder. The FSP said that had it been instructed to provide both parties with statements, two addresses would have been added to the Account. It added that it was also instructed to link the Account to the Builder’s i nternet banking, but that no such instruction was provided in respect of the Applicant. 38. The Applicant said that he would not have instructed the FSP to send statements of the Account to the Builder only. 39. During a telephone conversation between the FSP and a FOS Case Manager on 31 July 2012, the FSP advised that, ordinarily on a joint account, statements are sent to both account holders. It said, however, that the fact that there is an instruction in the FSP’s system to send statements to only the Builder indicates that an instruction to that effect would have been provided to the FSP at some point in time. The FSP was unable to provide any further information in relation to the instruction given. It said it would have been given verbally to the staff member who opened the Account. 40. However, the FSP also advised that its usual practice with respect to joint business transaction accounts is that the FSP inputs only one address, unless a customer requests that statements also be sent to another address. 41. The FOS Case Manager noted that these explanations are contradictory. On the one hand, the FSP said that it received instructions to only send statements to the Builder. On the other hand, however, it said that its default position for business transaction accounts is to send statements to one account holder only, unless specifically instructed to the contrary. If that is the case, for business transaction accounts, there is no need for the FSP to be provide d with any instructions. In the FOS Case Manager’s view, these facts supported a conclusion that no instructions were provided. 42. The FSP said that the instructions on which it relied would have been given verbally to FSP staff at the time of the Account opening. The FSP did not provide any documentation to support this claim. The FSP did, however, provided FOS with a copy of the Account and Authority Form and accompanying declaration which, in the Case Manager’s view, weighed against the likelihood that instructions not to issue statements to the Applicant were given. Case No: 241903 Determination Page 6 of 14 43. Accompanying each Account Application and Authority Form is a signed declaration which states “I direct the Bank to issue statements of account to the mailing (postal) address only”. On ea ch Account Application and Authority Form the Builder and the Applicant provided their respective postal addresses to the FSP. On this basis, one would interpret the instruction to the FSP as requiring that statements be sent to both. 44. There is nothing on the face of the Account Application and Authority Form to suggest the FSP had been instructed to the contrary. Nor is there any notification to the customer that it is the FSP’s practice to input only one of the addresses provided, and that express instructions were to be given if both account holders wished to receive account statements. 45. The Case Manager found that the Account Applicant and Authority Form is consistent with the Applicant’s assertion that he did not instruct the FSP to provide only the Builder with statements. There being no documentary support for the FSP’s position that he did so, the Case Manager accepted that the Applicant did not instruct the FSP that he didn’t require statements. 46. On the basis of the above reasoning and information, the Case Manager found that the Applicant was entitled as joint account holder to receive statements from the FSP, and that the FSP had breached its obligation to provide the Applicant with statements. Did the FSP’s errors cause the Applicant loss? 47. The Applicant claimed that the FSP’s conduct caused him lo sses in excess of $150,000. Those losses were itemised in Annexure A to the Case Manager’s Recommendation 48. They losses claimed fell into four categories - being: a. The balance of the Funds; b. Rectification and completion costs; c. Legal/consultancy costs; and d. Non-financial loss. The balance of the Funds 49. The Applicant claimed that at the time of the disputed withdrawal he was entitled to the full amount of the Funds held in the Account. He initially claimed tha t as a result of the FSP’s actions he had lost the Funds in their entirety and that the FSP should therefore compensate him for the full amount of the Funds. 50. The FSP said that as the Account was held jointly between the Builder and the Applicant, the Applicant was only ever entitled to one-half of the Funds in the Account and, since the Applicant received his half-share as a result of the proceedings between him and the Builder, the Applicant has recovered Case No: 241903 Determination Page 7 of 14 all that he was ever entitled to receive. The Applicant disputes this and seeks to recover the remaining one-half of the Funds. 51. Where an FSP has debited funds from an account without the requisite authority of its customer, the customer will, subject to the following, be entitled to reimbursement of those funds. 52. In the case of joint account holders, where the FSP has paid monies out of the account on the instruction of one account holder, but not the other, in contravention of its mandate, the appropriate measure of damages to compensate the innocent party is one half of the monies withdrawn. 53. In cases where the FSP is able to retrieve the funds the subject of a disputed withdrawal, the FSP will restore the funds to the joint account and then freeze the account in order to give the parties an opportunity to deal with their dispute and to resolve their competing claims to the funds. 54. In the present case, it appears that after withdrawing the Funds, the Builder deposited them into a trust account pending resolution of the dispute regarding the Building Works. He then took that dispute to QCAT. Separately, the Applicant commenced proceedings in the Magistrates’ Court seeking the return of the Funds. 55. The Magistrates’ Court Proceeding resulted in orders requ iring that the Builder pay the Funds into Court, and that the Applicant be compensated for lost interest on the Funds. The Applicant was also awarded legal costs fixed at $2,035. 56. The Funds remained deposited with the Court until consent orders were made in the QCAT Proceeding on 18 October 2011 which, amongst other things, provided that the Applicant and the Builder split the Funds between them. 57. In the Case Manager’s view, the effect of the Orders made in the Magistrates’ Court proceeding was analogous t o what would have been the case had the Funds been retrieved by the FSP and restored to the Account which was then frozen. The Orders did not determine the parties’ respective rights to the funds - but maintained the status quo until such time as the dispute relating to the Building Works was resolved. The payment of the Funds into Court effectively restored the Applicant to the position he was in prior to the unauthorised Withdrawal. 58. The subsequent orders filed in the QCAT Proceeding were made by consent, and therefore represented an agreed distribution of the Funds in resolution of the building works dispute. Those orders were expressed to be in full and final satisfaction of the dispute between the Applicant and the Builder. 59. The Applicant said that he only agreed to settle the QCAT Proceeding because he could no longer deal with the “waste of time and money”, and not because he considered the Builder’s claim to have any merit. In the Case No: 241903 Determination Page 8 of 14 Case Manager’s view, the Applicant’s motives for settling th ose proceedings are irrelevant. The significance of the QCAT settlement is that the Applicant recovered a one-half share of the Funds, being equivalent to the compensation to which he would have been entitled from the FSP had he pursued his claim from the FSP directly. 60. If the Applicant considered that he was entitled to more than a one-half share, this was a matter for determination in the QCAT proceeding. Further, in relinquishing a half-share to the Builder as part of the QCAT settlement, the Applicant derived a benefit from the half-share foregone, in that the Builder’s claims against the Applicant were also extinguished in the settlement. 61. On the basis of the above the Case Manager did not consider that the Applicant was entitled to be compensated for the balance of the Funds. Rectification and completion costs 62. FOS can award compensation for both direct loss and consequential loss. Consequently loss, however, is capped at $3,000 for each claim for compensation. There may be more than one claim for consequential loss in a dispute. 63. The Applicant said that because of the FSP’s failure to provide him with regular account statements, he did not become aware of the unauthorised withdrawal until March 2011. He said that, had regular statements been provided, he would have learned of the unauthorised withdrawal sooner, which would have then enabled him to terminate the Building Contract and, in turn, avoid the losses associated with the Builder continuing with the Building Works. 64. The FSP said that FOS cannot hear this aspect of the dispute as the QCAT Proceeding dealt with the termination of the Building Contract. It said that even if FOS is able to determine this aspect of the dispute, the Applicant would first need to prove that he would have had grounds to terminate the Building Contract by reason of the FSP’s error. 65. In the Case Manager’s view, the Applicant’s claim for consequential losses (relating to rectification and completion costs) is problematic. 66. The Applicant’s claims for losses (which he said were incurred in completing and rectifying defi ciencies in the Builder’s work ) was in the view of the Case Manager - too remote. The Case Manager noted that it cannot be said to be reasonably foreseeable that a failure by the FSP to provide the Applicant with statements would lead to the Applicant incurring costs associated with rectification works and completion costs, or the loss of a right to terminate the Building Contract. 67. The Case Manager accepted the FSP’s argument that because the losses claimed by the Applicant flow from the alleged right to the terminate the Building Contract, the Applicant would first need to establish that he, in fact, Case No: 241903 Determination Page 9 of 14 had a right to terminate the contract on that ground on or about the time of the disputed withdrawal. This is not a finding that FOS can make, although the available information raises doubts as to whether such a right would have been available. For example, it is not clear whether the Builder’s withdrawal of the funds would have constituted grounds for termination and, in any event, the commencement of the QCAT Proceeding indicates that the Builder would have resisted any attempt to terminate the contract. 68. On the basis of the above reasons the Case Manager found that the Applicant was not entitled to compensation in respect of the rectification works and completion costs. Legal and Consultancy Costs 69. The Case Manager rightly noted that FOS’s processes are designed so that Applicants can bring disputes to FOS without needing legal assistance. Where an Applicant chooses to be legally represented – or to take legal action against an FSP before or rather than referring their dispute to FOS , this will usually be at their own cost. 70. In very limited cases, however, FOS may require a f inancial s ervices provider to reimb urse the reasonable fees charged by a legal adviser. When we assess this issue, we will take into account the complexity of the dispute and whether the dispute raised legal issues that reasonably required the Applicant to obtain expert legal advice. It mus t be emphasised that FOS will generally not require the financial services provider to contribute more than $3,000 to an Applicant’s legal costs. 71. The Applicant claims that the FSP should reimburse him for the following legal costs: a. $495 incurred in seeking advice from CB Solicitors as to how to “get away” from the building contract; and b. $8,220 incurred in seeking advice and assistance from BM in attempting to resolve the ongoing dispute with the Builder. c. $35,154 incurred in seeking advice from R&R Solicitors, to whom the Applicants were referred by BM after being “unable to work out a satisfactory outcome” of the disputes with the Builder. The Case Manager found that the Applicant was not entitled to be reimbursed for these costs. Non-financial loss 72. The Applicant also claimed $25,000 for the stress, time and inconvenience that he said he suffered as a result of the FSP’s error. 73. Under its Terms of Reference FOS can consider claims for non-financial loss, such as claims for stress or inconvenience caused by an error of a financial services provider. The maximum amount that can be awarded for Case No: 241903 Determination Page 10 of 14 non-financial loss is $3,000 for each claim. FOS will only award compensation for non-financial loss where there has been an unusual degree or extent of inconvenience. 74. FOS takes a conservative approach to compensation for non-financial loss and is unlikely to decide a substantial amount of monetary compensation should be paid. 75. When assessing whether the circumstances are of an unusual nature FOS will review:  the degree or extent of physical inconvenience suffered;  the general time taken to resolve the dispute, and  the extent to which the FSP’s actions interfered with the Applicant’s expectation of enjoyment or peace of mind. 76. We do expect, however, that an Applicant will:  be moderately robust in the way they deal with a problem; and  bear the ordinary degree of inconvenience involved in correcting an unexpected problem, and take reasonable steps to minimise any inconvenience suffered. 77. The Case Manager found that the FSP’s error in allowing the Builder to make the withdrawal in January 2010, when discovered by the Applicant, did cause him distress for which he ought to be compensated. The Case Manager found that it was appropriate for the FSP pay the Applicant the sum of $750 by way of compensation for non-financial loss resulting from its error. Findings of the FOS Case Manager in the Recommendation relating to the dispute 78. The FOS Case Manager issued a Recommendation in relation to the dispute on 11 January 2013 (Recommendation). 79. That Recommendation found that the FSP had breached the Applicant’s mandate in honouring the Withdrawal Slip contrary to his instructions, but that on the weight of the available information FOS could not be satisfied that the Applicant was entitled to be compensated for the losses claimed in relation to half of the Deposit and the Applicant’s legal fees . 80. The FOS Case Manager found that the Applica nt was entitled to be compensated $750 for non- financial loss resulting from the FSP’s error , with those losses attributable to stress and inconvenience. 81. The FSP Accepted the Recommendation and the Applicant rejected it. In March 2013 the Applicant supplied additional submissions and materials in Case No: 241903 Determination Page 11 of 14 support of his decision to reject the Recommendation. I have considered those materials and specifically address them below. 82. The FSP chose not to make further submissions after the issue of the Recommendation. Additional submission by Applicant in March 2013 83. The Applicant rejected the Recommendation and asserted that he believed that FOS did not properly consider his complaint or understand the level of stress, inconvenience and expense that the FSP’s errors cau sed him. 84. In support of his assertions the Applicant supplied FOS with a written submission detailing his grievances in relation to specific paragraphs of the Recommendation, together with a detailed building report showing the defects in the building work completed at his house by the Builder. 85. I acknowledge the distress and upset suffered by the Applicant and his wife and conveyed by him in his submission. That distress is also evident from my review of his case file. The Applicant’s submission indicate s that he has been left with unfinished and substandard building works, a court and QCAT outcome that he now feels he had no option but to agree to, and a financial position that he attributes to his builder and the errors of his FSP. 86. I will now turn to address the specific concerns of the Applicant as set out in his Submission by category rather than by paragraph (to save on repetition). Entitlement to the whole of the funds rather than half of the funds 87. In his submission, the Applicant re-asserts that he is entitled to the whole of the funds deposited into the Account and held on trust rather than half of those funds. In his submission, the Applicant states: The fact is that those funds were our moneys as we put them into the trust account. Never Callows which you seem to infer. They should have been used to pay for invoices from the builder. Having not been used those moneys were still ours. 88. I note that, while the moneys were deposited into the Account by the Applicant from the A pplicant’s own moneys held elsewhere, at law, once those moneys were deposited into the jointly held Account, they were jointly owned by the Builder and the Applicant. 89. Accordingly the Case Manager was correct in law to deal with the dispute on the basis that the moneys in the Account were joint-moneys. 90. At law, where an FSP has debited all funds from a joint (two-to-sign) account with the authority of only one account holder and cannot reverse that transaction, the FSP is obliged to refund the remaining and innocent account holder with one half of the monies withdrawn. Case No: 241903 Determination Page 12 of 14 91. Accordingly, as the Account was jointly held, the Applicant was only ever entitled to one-half of the Funds in the Account in the event of a dispute concerning the withdrawal of the full Account balance. 92. Had the Applicant raised his dispute with FOS prior to having his dispute heard by the Court and QCAT, it is unlikely - on the facts before me - that I would have determined that the Applicant was entitled to a refund of more than a half share of the Funds. I would, in such a situation have either required the FSP to both credit the funds to the Account and freeze the Account (so that neither party could access the Funds until the dispute between them could be resolved in QCAT or another forum), or alternatively have required the FSP to credit the Applicant with a sum equivalent to half of the Funds. 93. The Applicant ’s dispute was considered by QCAT prior to him raising a dispute with FOS. By virtue of the QCAT proceedings the Applicant received his half-share of the Funds before his dispute was raised with FOS, meaning that in relation to those Funds - he has already recovered all that he was entitled to receive. Conclusions in relation to the QCAT and court orders 94. The Applicant asserts that he was not happy with the agreed QCAT orders but consented to those orders in essence to bring the matter to a conclusion. In his submission, the Applicant said: We felt entitled to the whole amount of the trust fund but in the end, to bring the matter to a close we agreed to settle for half. 95. The Applicant believes that his motives in agreeing to the QCAT orders were not given due consideration and weight by the Case Manager. 96. I cannot, in discharging my obligation to be fair and balanced, give material weight to the Applicant’s motives in settling his proceedings before QCAT and agreeing to the consent orders, but must give due weight to the content and existence of those orders. 97. I agree with the Case Manager that the significance of the QCAT settlement is that the Applicant recovered a one-half share of the Funds, being equivalent to the compensation to which he would have been entitled from the FSP had he pursued his claim from the FSP directly with FOS prior to the origination of his proceedings in the Magistrates’ Court (and subsequent settlement of the related proceedings in QCAT). 98. I agree that the QCAT consent orders did represent an agreed distribution of the Funds in resolution of the building works dispute. Those orders were expressed to be in full and final satisfaction of the dispute between the Applicant and the Builder. The payment of the half share of the $47,532 did effectively restore the Applicant to the position he was in prior to the unauthorised Withdrawal by the Builder. Case No: 241903 Determination Page 13 of 14 99. I note that in relinquishing the remaining half-share of the Funds to the Builder as part of the QCAT settlement, the Applicant did derived a benefit, being the extinguishment upon settlement of the Builder’s claims against the Applicant for unpaid amounts under the Building Contract. 100. I agree with the weighting of the evidence and related conclusions made by the Case Manager in her Recommendation in so far as those conclusions relate to the QCAT and Magistrates’ C ourt orders. Compensation for completion costs 101. In his submission, the Applicant said: FOS cannot say that the contract would not have been investigated and possibly terminated.... Had we been made aware that the money had been misappropriated we would have then had sufficient grounds to cancel the contract. 102. I am not convinced that the Applicant has demonstrated that he would have had grounds (or the right) to terminate the Building Contract by reason of the FSP’s error and the Builder’s use of the Withdrawal Slip in and of itself. 103. Consequently, I agree with the Case Manager that t he Applicant’s claims for losses relating to building completion are problematic. 104. I agree with the Case Manager that it was not reasonably foreseeable that the FSP’s errors c ould lead to such financial losses in the form of completion costs, or the alleged loss of a right to terminate the Building Contract. Compensation for legal and other related consultancy fees 105. The Applicant claimed that the FSP should reimburse him for the $495 he spent in seekin g advice from CB Solicitors as to how to “get away” from the building contract. The materials available to me show that the payment to CB Solicitors was made prior to the Withdrawal, as acknowledged by the Applicant in his post-Recommendation submission. The Applicant dismisses the timing of the payment to be relevant, however I view it as material. 106. If the invoice predated the Withdrawal it could not have had any direct relation to the Withdrawal. Accordingly, I cannot find that the expense relates to the Withdrawal on the available facts. 107. The Applicant claimed that the FSP should reimburse him for the $35,154 that he spent seeking advice from R&R Solicitors. The Applicant also sought to recover the same lega l costs in his Magistrates’ Court Proceedings . I note that FOS does not permit Applicants to recover costs from an FSP in circumstances where those costs have previously been the subject of legal proceedings. 108. The Applicant was awarded costs totalling $2,0 35 in the Magistrates’ Court Proceedings following his (successful) recovery of the Funds from the Builder. On that basis the Case Manager found that FOS could not consider Case No: 241903 Determination Page 14 of 14 the Applicant’s claim in relation to his legal fees from R&R Solicitors further . I agree with the Case Manager’s view on that point . 109. The Applicant engaged BM for advice and assistance in attempting to resolve the ongoing dispute with the Builder and paid $8,220 for those services. I cannot a nexus between BM’s services and the Withdrawal and on that basis reject the Applicant’s claim for $8,220. Adequacy of compensation for non-financial loss 110. T he Applicant’s submission implies that he is offended at the Case Manager’s award of $750 to him for non financial loss (attributed to the stress he has suffered). If it were not for FOS’s low cap and stringent rules for the calculation non-financial losses (as set out earlier in this Determination), an award of $750 for non-financial loss may be viewed as inadequate in the Applicant’s c ircumstances. FOS is however required to adhere to the cap and calculation methodology, as the Case Manager did in the Applicant’s case. Determination 111. I have given detailed and lengthy consideration the available evidence, the additional materials supplied by the Applicant after the issue of the Recommendation, and the law. I am satisfied that the Case Manager did not err in her assessment of that evidence or in her Recommendation. 112. I determine that the FSP did breach the Applicant’s mandate in honouring the Withdrawal Slip contrary to his instructions. 113. I determine that the FSP did breach its obligation to supply the Applicant with statements. 114. For the reasons set out in this Determination I am not satisfied that the Applicant is entitled to be compensated for the losses claimed in relation to their legal and consultancy fees or building completion costs . 115. I am satisfied that that Applicant is entitled to be compensated $750 for non- financial loss resulting from the FSP’s error.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.