Text of the determination
Case No: 241131 Determination Page 1 of 10
Case number: 241131
General Insurance - Domestic Insurance - Home Building and Contents - FSP
Decision - Cause of Damage - Storm vs Flood – Extent of Flood Damage Cover
- Clear and Unambiguous
9 December 2011
Background
1. The Applicant held a home building and contents insurance policy with the
Financial Services Provider (FSP) during the policy period 28 January 2010 to
28 January 2011. The Applicant obtained the policy through his insurance
broker.
2. On 9 – 13 January 2011, Queensland suffered a devastating storm and the
insured property was inundated with water. The Applicant and his family were
on holidays in Tasmania at the time the water entered the property.
3. The Applicant lodged a claim with the FSP for damage to the building and
contents.
4. The FSP considered flood as the cause of damage. It indemnified the Applicant
as follows:
$10,000 – based on the policy limitation of $10,000 for flood damage;
$40,000 – 12 months temporary accommodation.
5. The Applicant is not satisfied with the FSP‟s decision, hence this dispute.
Summary of Applicant’s Position
6. The Applicant, after seeking legal advice, has provided a summary of his
alternative arguments:
a) the damage sustained by his home “was caused by storm and storm
water run-off which is fully covered by his insurance policy”. Thus, he “is
entitled to be paid out for all of the damage suffered to his property in
January 2011;
b) the insured property “was affected by both storm water and flood water
and the proximate cause of that dam age was storm water”. Thus, he is
entitled “to a full payout of all his losses under his insurance contract”;
c) the damage to the insured property “was caused by multiple events”. The
property “first suffered damage as a result of storm and storm water run -
Determination
Case No: 241131 Determination Page 2 of 10
off and then after being damaged by this water suffered further damage
as a result of water flooding his property from the Brisbane River.” Thus,
he is “entitled to a full payout for the storm damage caused to his property
as there is no cap on the payout”. In addition, he “is [also] entitled to be
paid out for the damage then l ater caused by flooding”;
The policy limit on flood damage in the PDS “did not meet the
requirements of sections 35 and 37 of the Insurance Contracts Act (1984)
to adequately inform [ the Applicant] of these terms.” Consequently, the
FSP cannot rely on the policy limit and the Applicant “is entitled to a full
payout for the damage caused to his property by flood waters as that
event is cover ed under his insurance policy”;
d) the damage to the insured property “was caused by floodwater”. However,
the policy limit on flood damage in the PDS “did not meet the
requirements of sections 35 and 37 of the Insurance Contracts Act (1984)
to adequately inform [the Applicant] of these terms.” Consequen tly, the
FSP cannot rely on the policy limit and the Applicant “is entitled to a full
payout for the damage caused to his property by flood waters as that
event is cover ed under his insurance policy”.;
7. The Applicant has provided a copy of a 26-page Product Disclosure Statement
dated 18 October 2008 (2008 PDS). He argues that this is the relevant PDS.
8. Following a site inspection by the Panel Chair Ombudsman, the Applicant
provided a further submission together with Statutory Declarations and a
Brisbane City Council Floodwise Property Report. It is the Applicant‟s argument
that the Statutory Declaration supports a view that the property was flooded
from water from the drains. The Applicant relies on the fact that the Statutory
Declaration from a neighbour who lives closer to the river, than he, indicates
that water did not enter that property until nearly midnight on Tuesday 11
January whilst by contrast water entered his home, which is slightly higher
above sea level and further from the river, at approximately 7:30 p.m. on
Tuesday 11 January 2011. The Applicant maintains this is consistent with his
property being inundated by stormwater.
Summary of FSP’s Position
9. The FSP contends that:
it complies with its obligation under section 35 of the Insurance Contracts
Act (1984) to clearly inform the Applicant of the flood policy limitation;
section 37 is not relevant because it deals with contracts of insurance
which are “not prescribed”. The Applicant‟s contract of insurance is
“prescribed”;
the policy is clear and unambiguous in its meaning;
the water damage to the insured property was the result of flood, and not
stormwater run-off;
Case No: 241131 Determination Page 3 of 10
the Applicant‟s claim for damage should be limited to the maximum
amount payable for flood under the policy terms and conditions. The
Applicant, through his insurance broker, was provided a copy of the
policy;
it has already satisfied its contractual obligations to the Applicant upon
payment of $50,000.
10. The FSP has provided a copy of a 52 -page Product Disclosure Statement
dated 1 June 2010 (2010 PDS). The FSP says this is the relevant PDS.
11. Following the receipt of a further submission by the Applicant, the FSP made a
further submission in which the FSP has argued:
there are topographical differences between the Applicant‟s property and
th at of the witness‟ property. It does not dispute that water was observed
overflowing from the drains in Jolimont Street at about 7:30 p.m. on
Tuesday 11 January 2011. The FSP maintains that the times of initial
inundation observed by the residents in the A pplicant‟s street and by the
person who has provided the subsequent Statutory Declaration are
entirely consistent and within the estimated times at which the Brisbane
River flood water levels would have reached the ground level of each
location. The FSP maintains that the Statutory Declarations in fact
supports FSP‟s view that the property was inundated by floodwaters from
the Brisbane River. The FSP in reaching this view has relied on a
supplementary report supplied by its hydrologist W.
12. Insofar as the provision of the policy documentation is concerned, the FSP
maintains that the documentation and policy were arranged on behalf of the
Applicant through the Applicant‟s broker and insofar as the policy may not
provide the level of cover the Applicant had soug ht, this is an issue of dispute
between the Applicant and his broker; not the Applicant and the FSP. The FSP
relies on section 71 (2) of the Act with respect to this.
13. Finally, the FSP maintains that in the event FOS determines the property was
inundated by a combination of stormwater run-off and Brisbane River flood
water, the legal principle of Wayne T ank would apply to restrict the Applicant‟s
claim.
Issues
14. What is the relevant Product Disclosure Statement;
15. Whether the policy provision on flood damage cover is clear and unambiguous;
16. Whether the damage was caused by the storm;
17. Whether the damage was caused by the flood.
Case No: 241131 Determination Page 4 of 10
Reasons for Decision
18. Due to the nature of the dispute, the FOS has considered it appropriate to
expedite the dispute in accordance with the Operational Guidelines to the FOS
Terms of Reference. Thus, this dispute has not been the subject of a FOS
Recommendation and has proceeded directly to Determination. The parties
have been previously advised that a Determination will be issued in this case.
19. In view of the complexities associated with this matter, a site inspection was
conducted by the Panel Chair Ombudsman. Present were the Applicant, his
legal representative and the FSP.
20. The Applicant confirmed that the policy had been arranged through his broker
and not an agent of the FSP. The Applicant advised that he had instructed the
broker to arrange full flood cover and this is what he believed he had.
21. There was discussion as to whether the 2008 or 2010 PDS was the relevant
document.
22. It is apparent from the discussions that the relevant PDS, that is, the PDS that
had been supplied to the Applicant and was applicable to the Applicant‟s policy
at the time of the loss, was the 2008 PDS.
23. In respect of the 2008 PDS, it is clear from the submissions p reviously made,
that the FSP was confused and had provided a copy of the June 2010 PDS as
the relevant PDS document. The FSP agrees that this document was only sent
to the Applicant with the renewal notice for the prospective insurance period of
2011 to 2012. This was forwarded to the Applicant on 5 January 2011 for
renewal of the policy from 28 January 2011.
24. The 2008 PDS contains the following policy provisions.
Pages 8 and 9:
“DEFINITIONS
…
“Flood” means the inundation of normally dry land by water escaping or being
released from the normal confines of any natural water course, lake, reservoir, canal or
dam.
…
“Storm” means a violent disturbance of the atmosphere, including strong winds which
may be accompanied by lighting, rain, snow, sleet and hail.”
Pages 10 and 11:
“DEFINED EVENTS
The following are the Defined Events for which cover is provided under Section 1
Building Cover and Section 2 Contents Cover where applicable (see these Sections for
details):
…
Case No: 241131 Determination Page 5 of 10
7. Storm (see Definitions)
Excluding loss or damage caused:
(a) to free standing walls and retaining wall whether they form part of the Building or
not,
(b) to a glass house, greenhouse or conservatory whether constructed principally of
glass or not,
(c) by water, hail or wind entering the Building or building at the Situation, through an
opening made for the purpose of construction, demolition, alteration or repair
irrespective of the value of such work,
(d) to wooden gates and fences more than 15 years of age,
(e) as a result of structural defects, faulty workmanship in the construction of the
Building or building at the Situation, faulty designs of the Building or your failure to
adequately maintain the Building or building at the Situation.”
Page 12:
“ Section 1 BUILDING COVER
…
1.2 Defined Events cover
We will cover you for loss of or damage to your Building at the Situation when caused
by any of the Defined Events occurring during the Period of Insurance.”
Pages 15, 16 and 18:
“ SECTION 2 CONTENTS COVER
…
2.2 Defined Events cover
We will cover you for loss of or damage to your Contents whilst contained at the
Situation when caused by any of the Defined events occurring during the Period of
Insurance.
…
2.4 Additional Benefits and Limitations:
…
(h) Flood Damage to Contents
We will cover loss or damage to your Contents, excluding swimming pools and spas,
caused by Flood up to a maximum of $10,000 or 5% of the Contents Sum Insured,
whichever is less. This clause operates notwithstanding the provisions of General
Exclusions 6.15.”
Pages 22 and 23:
“SECTIO N 5 GENERAL EXCLUSIONS
These General Exclusions apply to the whole of your Policy unless otherwise stated.
Your Policy does not cover:
…
5.15 Flood damage except as provided in Section 2. Contents Cover under Additional
Benefits „Flood damage to Contents‟”.
Case No: 241131 Determination Page 6 of 10
25. There is no dispute the Applicant‟s policy was obtained through his insurance
broker. Section 71 of the Insurance Contracts Act 1984 (ICA) relevantly
provides where there is a provision of the Act requiring the giving of a notice, a
statement, any other document or any information to an insured before a
contract of insurance is entered into, it does not apply where the contract was
arranged by an insurance broker. In other words, it is not necessary for the FSP
to supply the Applicant with the PDS where the contract is arranged by his
insurance broker. In terms of providing the Applicant with notification of the
derogation from standard cover, it is reasonable to believe this information was
within his insurance broker‟s knowledge.
26. In the circumstances, the Panel is satisfied that by arranging the policy through
his insurance broker, the Applicant is unable to rely upon the provisions of
section 35 (2) of the Insurance Contracts Act to argue that the FSP has not
clearly informed the Applicant of the derogation from standard cover.
27. The central issue now becomes whether the Applicant‟s property was
inundated by storm, water run-off or flood. There has been considerable
information provided in this regard.
Storm v Flood
Insurance Council of Australia (ICA) Hydrology Report
28. The Insurance Council Australia hydrology report entitled “FLOODING IN THE
BRISBANE RIVER CATCHMENT JANUARY 2011 VOLUME 2 FLOODING IN
BRISBANE CITY LGA” contains the following information:
the most significant rainfall across the Brisbane City Local Government
Area (LGA) occurred between approximately 6:00am to 4:00pm on
Tuesday, 11 January 2011;
after about 6:00pm on 11 January 2011, there was little or no rainfall
across the LGA;
the Brisbane River water levels through the city peaked about 24 -30
hours after rainfall had ceased, that is, from the late hours of
Wednesday, 12 January 2011 to the early hours of Thursday, 13
January 2011;
any area that was inundated after 6:00pm on 11 January 2011 will have
been water flow inundation from the Brisbane River and its tributary
creeks. The inundation along the tributaries was associated with
backwater flooding from the Brisbane River, which in turn was principally
caused by the dam release flood from the Wivenhoe Dam;
overland flow inundation is generally associated with intense rainfalls of
short duration. In general, such rainfalls did not occur across the
Brisbane City LGA in January 2011. It is expected that overland flow
inundation would generally not have occurred in the Brisbane City LGA;
Case No: 241131 Determination Page 7 of 10
uncertainties exist on whether properties flooded by water flows also
suffered initial inundation from overland flow flooding. Investigation of
local factors such as local topography and the area and characteristics
of overland flow, hydrologic/hydraulic modelling of the storm event and
local stormwater drainage system is required to resolve this issue.
Water Damage Assessment by W dated 24 January 2011
29. The FSP arranged for the inspection of the insured property by W who then
inspected the insured property on 21 January 2011.
30. W issued a Water Damage Assessment report dated 24 January 2011. W‟s
findings are as follows:
Inundation by watercourse – Yes. Brisbane River.
Prior inundation by stormwater – No.
Comments – The insured property is located approximately 400m from
the Brisbane River. The timing of inundation of the upper level is
consistent with the estimated time of inundation by floodwaters from the
Brisbane River. The time of initial inundation of the lower level is not
known.
Conclusion – Peak inundation of 1m above floor level in the upper level
and over ceiling height in the lower level by floodwaters overflowing from
the Brisbane River.
W’s Further Assessment Dated 3 March 2011
31. W issued another report on 3 March 2011. This report states, among others:
Rainfall effectively ceased at about 6:00pm on 11 January 2011.
The Applicant has provided statutory declarations from residents of J
Street who witnessed water flowing from three drains on J Street near the
subject property. The neighbours observed water flowing out of these
drains around 7:30pm-9:00pm on 11 January 2011 prior to the inundation
of homes on the street.
The drains are located at a level of approximately 5.5m AHD. The
Brisbane River reached this level at the Jindalee Alert at 12:00noon and
at the Oxley Creek Mouth Alert at 9:00pm. Water levels in the Brisbane
River near the subject property would have reac hed a level of 5.5m AHD
and surcharged through the stormwater drains on J Street at sometime
between 12:00 noon and 8:00pm. This corresponds with the time period
residents observed water surcharging through the drains.
The Applicant has commented that the Brisbane River never breached the
hill at the end of Jolimont Street or flowed into the Sherwood Arboretum.
An aerial photograph of the subject property taken on 13 January 2011
after the peak had occurred at the property shows that the property is
clearly located within the flood extent. The hill was not inundated during
Case No: 241131 Determination Page 8 of 10
the event but the Brisbane River broke its banks north of this location and
overflowed into the Sherwood Arboretum.
Thus, the water observed by the Applicant‟s neighbours surcharging
through the drains on J Street was floodwater from the Brisbane River.
W’s Further Assessment dated 23 September 2011
32. Following the further submissions by the Applicant and the site inspection
conducted by the Panel Chair Ombudsman, the FSP provided a further
supplementary report from W dated 23 September 2011. That report addresses
a number of the issues that were raised in the course of the site inspection and
the Statutory Declaration provided by the Applicant
33. W considered, based on the times of the initial inundation observed by the
residents in the Applicant‟s street and Ms A from D Street, the timing of the
inundation is entirely consistent with the estimated time at which the Brisbane
River water levels would have reached the ground level at each location.
34. W also considers the rainfall data from the ICA Hydrology Panel Report is
consistent with a band of rainfall appearing to break up during the afternoon of
11 January 2011 and consistent with rainfall in the Brisbane area ceasing
around 1700 hours on 11 January 2011. These observations are consistent
with the radar patterns provided.
Neighbours’ Statutory Declarations
35. The Applicant submitted Statutory Declarations from seven witnesses.
36. Witness BH of 72 J street said that at around 8:00pm of 11 January 2011, he
“witnessed the significant overflow of the storm water drain directly in front of
our property as well as the two drains across the road which service the
Sherwood Arboretum”. “The amount of water was considerable and within two
hours was waist deep”.
37. Witness KG said that between 7:30- 8:00pm on 11 January 2011, he “observed
water emerge from storm water drain points in [J Street]”. “Water continued to
emerge from the stormwater drains, to cover the road surface of [J Street] and
cause subsequent flooding of residential properties in the area”.
38. Witness RS said that at approximately 7:30pm of 11 January 2011, he
“witnessed the water backing up from the stormwater gully outside the property
of [72 J Street]”. “Within the next hour this had continue d to such an extent that
there was significant depth of water over the entire road and numerous property
driveways adjacent to… [72 J street].”
39. Witness MB said that at 8:00pm on 11 January 2011, while he was helping the
H Family to relocate property to a h igher ground, he “witnessed a considerable
flow of water coming from three storm water drains that are located in front of
[H‟s] property”.
Case No: 241131 Determination Page 9 of 10
40. Witness LG said that “following the continuation of excessive rain” on 11
January 2011, the storm water drain adjacent 72 J Street and two other major
drains on the other side of the road overflowed.
41. Witness DG said that he was at 72 J Street on 11 January 2011 and “saw water
rising quickly from the storm water drains out the front of [72 J Street]”. “The
water began to flow from the drains around 7.30pm”.
42. VA provided a Statutory Declaration dated 16 September 2011. According to
VA, her parents live in D Street. She can recall arriving at her parents‟ home at
approximately 11:30 p.m. Water had not entered the home at that time. At
approximately 11:45 p.m. she was standing at a drain cover just outside talking
to her mother when water started oozing out of the drain around her feet. She
believes that the inundation at this property commenced just after midnight and
during the early morning of 12 January 2011.
Consideration of the Evidence
43. The Panel has considered the arguments that have been put by both parties.
The information provided by the Applicant raises the possibility that there was
inundation to the Applicant‟s property as a result of water flowing out of the
stormwater drains in the near vicinity of the Applicant‟s property. The policy
documentation refers to flood as meaning the inundation of normally dry land
by water escaping or being released from the norma l confines of any natural
water course, lake, reservoir, canal or dam. This is a relatively straightforward
definition of flood. There is no dispute that the policy provides for limited flood
cover and that the FSP has met its liability with respect to that aspect of the
policy.
44. The policy is a defined events policy that does provide cover for storm damage,
being damage that arises from a violent disturbance of the atmosphere
including strong winds which may be accompanied by lightning, rain, snow,
sleet and hail. The Panel is satisfied that the events on 11 January 2011 would
fit within the storm definition contained within the policy. As indicated earlier,
the dispute is essentially a question of whether the policy‟s flood limitation
should apply, or whether the loss is due to storm rather than flood.
45. The Panel accepts the Applicant‟s evidence that water was observed escaping
from the stormwater drains near the property and that this water first inundated
the property.
46. The hydrology and BOM information suggests that the heavy rainfall ceased
around 6:00 p.m. on 11 January 2011, although the Panel accepts there may
have been rainfall after that time consistent with observations of the Applicant.
Most likely however, that rainfall would not have been sufficient to cause
significant stormwater run-off.
47. It is well established at law that where stormwater drains are unable to clear
due to the backup or backflow of floodwater emanating from a river or where
the backflow of water from the river causes the stormwate r drains to overflow,
the ensuing overflow is deemed to be flood.
Case No: 241131 Determination Page 10 of 10
48. It is accepted that the water was not observed flowing from the drains until
between 7:30 p.m. and 8:00 p.m. on 11 January 2011. The hydrology
information presented establishes to the Pan el‟s satisfaction that most likely
given the height of the drains in the Applicant‟s street and the local topography,
that there would have been a significant level of backflow from the Brisbane
River through the stormwater drains. The Panel also accepts the most likely
cause of the water escaping the stormwater drains, as observed by the
Applicant‟s witnesses, was due to the backflow of water from the Brisbane
River. Bearing this in mind, the Panel is satisfied, on the balance of
probabilities; the cause o f inundation of the Applicant‟s property was flood from
the Brisbane River.
49. Accordingly, the Panel is satisfied the FSP has met its obligations under the
terms of the policy by payment of $50,000 to the Applicant.
50. Insofar as the policy did not meet the App licant‟s expressed expectation, this
may be an issue between the Applicant and the Applicant‟s insurance broker.
Determination
51. The Panel determines the FSP‟s payment of $50,000 discharges its policy
obligations to the Applicant.