Determination 240632

Delay in building claim and compensation for additional losses

FirmFinancial Firm (Unknown - Insurer)
Decided2012-01-20
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$11,184
SourceAFCA PDF

Summary

The applicant's investment property had ceiling damage from a roof leak, and the FSP required maintenance repairs before paying for internal damage. The applicant claimed $11,184 for delay and related losses. AFCA found the delay was not unreasonable and made no award.

Delays inherent in the claims process, including scope changes and contractor coordination, were not unreasonable, and the consequential losses claimed fall outside the policy and were not proven.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 240632 Determination Page 1 of 7 Case number: 240632 General Insurance - Delay in the FSP’s claim handling – Service quality - Compensation assessment -Terms of Reference 9.3. 20 January 2012 Background 1. This is a review of a Recommendation by the Service’s Case Manager dated 5 December 2011 in favour of the Financial Services Provider (FSP). The Applicant has rejected the Recommendation and in accordance with the Terms of Reference, the matter has been referred to me for Determination. 2. The relevant background, summary of the parties position and issues in dispute have been set out in paragraphs 1 to 27 of the Recommendation and in the interest of clarity and completeness, I will repeat same. 3. The Applicant held a home insurance policy with the Financial Services Provider for his investment property. The building was insured for complete replacement, with a basic excess of $200. 4. On 23 December 2010, the Applicant advised the FSP that the ceiling in one of the bedrooms of his rental property had collapsed and he wished to lodge a claim on the policy for this loss. 5. The FSP accepted liability for the internal resultant damage. However, it advised the Applicant that he was required to complete maintenance related repairs before it can authorise repairs for the resultant damage. 6. On 21 April 2011, the Applicant contacted the Financial Ombudsman Service (FOS) regarding his claim with the FSP. Repairs for the resultant damage were subsequently completed. However, the Applicant was unsatisfied with the FSP’s handling of the c laim and he had made a claim for compensation for stress and for the following additional financial losses: Premium increase $153 Excess Refund $500 Loss of rent (increased rate of rent) $2,600 Annual leave $850 Mobile call costs $1,500 Determination Case No: 240632 Determination Page 2 of 7 Plumbing & chimney repairs $5,581 Total $11,184 7. A dispute has arisen as the FSP rejected the Applicant’s request for compensation of the above costs. Summary of Applicant’s Position 8. The Applicant believes he is entitled to the additional costs as the FSP had handled his claim poorly. In particular, he has referred to the delays associated with the commencement of the repairs to the resultant damage. 9. As a result of the FSP’s instructions, he had completed repairs to the chimney which had not caused or contributed to the ingress of water into the property. Therefore, he believes the FSP is liable for these costs. 10. The FSP is required to reimburse him the policy excess and the increase in the renewal premium he incurred as a result of this claim. 11. He was u nable to increase the rent by $50 per week due to the FSP’s delay in authorising repairs and settlement of the claim. 12. The FSP’s action of reimbursing him the sum of $605 for maintenance repairs is an admission of liability that the cause of the water ingress into his property did not occur as a result of debris in the gutters, rust and corrosion or his failure to maintain the property. The Applicant considers that if the FSP was correct in its assessment of the cause of damage, he would not have incurred the costs associated with undertaking unnecessary repairs. 13. As a result of the FSP’s poor handling of the claim, he was required to take unscheduled annual leave from work to deal with this claim and had incurred substantial mobile telephone bills. Therefore, he submits the FSP is required to indemnify him for these costs. Summary of FSP’s Position 14. It has at all times assisted the Applicant in a professional manner. It had addressed each issue raised by the Applicant and gone above and beyond normal expectations in offering him assistance. 15. The policy is an insured events policy and is not designed to cover all types of risk. Whilst the policy provides cover for loss or damage resulting from storm and rainwater (including stormwater run-off from areas surrounding the site, or water escaping from any water main, drain, pipe, street gutter, guttering or surface), it specifically excludes cover for loss or damage caused by, arising from or involving an unreasonable failure to properly maintain or repair the building, wear and tear, rust, deterioration or corrosion. Case No: 240632 Determination Page 3 of 7 16. The FSP rejected the Applicant’s allegation that it had handled his claim poorly . It submits that it acted efficiently in establishing the damage sustained to the Applicant’s home and arranging for it to be secured on the same day. 17. The FSP submits that two days after the Applicant lodged the claim it had determined the extent of its liability and informed the Applicant of the maintenance related repairs that he was required to complete prior to the internal resultant damage being authorised. 18. On 5 April 2011, the Applicant advised the FSP of his claim for additional damages to the foyer floor and carpet. This necessitated a further assessment in order to determine the extent of its liability for the additional damage claimed and to prepare an amended scope of works. 19. The FSP maintains that the delays in settlement of the claim occurred as a result of the Applicant’s obligation to investigate and rectify the maintenance related issues, his refusal to allow access to the FSP’s contractor into the property to prepare a repair quotation and his late notification of the additional internal damage. 20. The FSP states that whilst its builder reported the chimney was in a state of disrepair, there is no evidence to show that it had instructed the Applicant to attend repairs to the chimney, or that the chimney’s state of disrepair caused or contributed to the water ingress. 21. The policy terms and conditions clearly and unambiguously provide that the Applicant has an obligation to properly maintain his building. Thus, the cost of repairing the chimney was an expense that the Applicant would have incurred irrespective of the storm events. 22. The policy clearly states the excess is the amount the Applicant is required to contribute towards each claim and there is no provision under the policy requiring the FSP to waive the excess for any perceived inconvenience suffered during the repair process. 23. In respect to the Applicant ’s request for compensation of the increase in his renewal premium, the Applicant did not renew his policy with the FSP and therefore has not remitted payment for the money he is seeking to be reimbursed. Furthermore, the Applicant’s request does not fall within the scope of cover provided by the policy and therefore the FSP considers it is not obliged to indemnify the Applicant in this regard. 24. The Applicant’s request for compensation for loss of the proposed increase in rent does not fall within the scope of cover provided by the policy. Further, whilst the Applicant provided a letter from his real estate agent in support of his claim, this evidence does not discharge the Applicant ’s onus to establish that he would have been successful in securing an increase in the rent. 25. The FSP acknowledges that it had inadvertently reimbursed the Applicant $605 for maintenance related repairs. However, the FSP submits that this is not an Case No: 240632 Determination Page 4 of 7 admission of liability nor does it entitle the Applicant to cover under the policy for the costs he incurred in maintaining and safeguarding his property. 26. It is not responsible for the costs incurred by the Applicant in the management of his claim. Even if the Applicant was entitled to reimbursement for these costs he still needs to provide documentary evidence to support the exact amount of the alleged costs. 27. It had fulfilled its obligation in settlement of the claim and any delay in reaching a resolution on the claim was caused by the Applicant. 28. The FSP relies on the following policy provisions: “ What we cover – insured events This section describes under the heading: ... Yes – the insured events you are covered for, You are covered for damage or loss to your home building occurring during the period of cover and caused by the following events: ... Storm and rainwater including stormwater runoff from areas surrounding the site, or water escaping from any water main, drain, pipe, street gutter, guttering or surface. Storm means violent wind (including a cyclone or tornado), thunderstorm or a heavy fall of rain, snow or hail. ... What we do not cover – general exclusions You are not covered under any section of the policy for damage, loss, cost or liability caused by or arising from or involving: An unreasonable failure to properly maintain or repair your building Wear and tear, rust, deterioration or corrosion ... Precautions that you need to take Precautions You must at all times, and at your expense, take all reasonable precautions: For the safety and protection of your building and the site To prevent bodily injury or damage to the building To prevent damage to your building ... When you claim on your policy, your responsibility include Preventing further damage or loss Following an event that is likely to result in a claim, you must take all reasonable precautions to prevent any further damage, loss, cost or liability Allowing us access Case No: 240632 Determination Page 5 of 7 You must provide us with access to your building and the site to inspect damage or loss, arrange quotations, repair or rebuilding, and undertake progress inspections if required ” Issues 29. Whether the FSP has fulfilled its obligations under the terms and conditions of the policy, and whether the Applicant is entitled to compensation for additional losses incurred. Reasons for Decision 30. There has been a full exchange of information between the parties and each has had the opportunity to address the issues raised. 31. I have read all of the exchanged material and I have carefully considered the submissions of the party including the Applicant’s very brief further submission dated 8 December 2011. 32. I have consider ed the Case Manager’s reasons and I am in agreement with her reasons and her recommended outcome. I make the following further comments. 33. This referral to the Service is typical of many building claims, particularly claims for internal damage arising from alleged roofing issues. It appears the claim was first made on or about 23 December 2010 as a result of a complaint by the Applicant’s tenant that the ceiling was collapsing into a bed room. Contractor s were provided by the FSP to complete “ make safe ” repairs and inspect the roof. It seems the Applicant was somewhat frustrated by the process, but the FSP needed to satisfy itself that water ingress had occurred through an insured event. If it was not caused by an insured event, the FSP is entitled, as it did in this case, to insist that roof related issues were attended to by the Applicant prior to the repair of internal damage. This is a normal insurance process and requires a good deal of coordination a nd clear communication as between the parties. 34. In the event, the FSP’s experts reported there was no evidence that the roof had been damaged as a result of an insured event, but, rather, had occurred because of lack of maintenance, gutter blockage due to debris and grass with consequent water overflow. The FSP informed the Applicant that it would indemnify him for the resultant internal damage, but that he first needed to attend to the repairs to the roof. 35. In passing, I note that in his initial referral to the Service, the Applicant alleges that he unnecessarily incurred costs in the sum of $4,975 to repair the roof and which he seeks to be repaid. There is nothing before me that supports that claim apart from hearsay comment from the Applicant that a roof specialist had informed him that the tiles/flashing of the roof had been dislodged due to storms and not maintenance issues. Case No: 240632 Determination Page 6 of 7 36. There appear to have been some delays in the completion of the internal repair, no doubt in part due to problems with completion of a scope of works and the inclusion of a claim by the Applicant for damages to the foyer, floor and carpet that were not included in the original scope of works. These delays cannot be attributed entirely to the FSP or its contractor, but rather to, I suspect, difficulties with communication and coordination of contractors. 37. I should mention the Applicant relies upon a payment by the FSP of an invoice in the sum of $605 for chimney repairs. The FSP acknowledges that through an administrative error that payment was made, but the FSP submits that it is not to be taken as any acceptance of liability. The Applicant’s allegation that the FSP’s contract or attributed water inundation to other than maintenance and wear and tear damage. 38. I have viewed the photographs pr ovided with the assessor’s report and confirm the Case Manager’s view that they provide supportive evidence for blockage of guttering and maintenance related issues. 39. Having considered the matter, whilst I agree with the Case Manager’s view that there was some delay, I believe that it was not in the circumstances unreasonable. The Applicant became frustrated and experienced inconvenience by the claims process, but I believe that in the circumstances of this case, those matters are consistent with the exigencies that invariably arise from the claims process, particularly in respect to building related matters that affect old buildings. In the circumstances, I am not prepared to make any award in respect of compensation for non-financial loss as, in my opinion, there was not an unusual degree of physical inconvenience or interference with the Applicant’s enjoyment of peace of mind that would attract such an award. In making that Determination, I am influenced by the FSP’s submission of copy documents in support of the process it has adopted. Determination 40. Further, I am not prepared to make any award in respect of the premium increase, refund of excess, claimed annual leave, or mobile call costs. 41. In respect of the alleged loss of rent, I note with concern the App licant’s allegation in the further submission dated 8 December 2011 that the FSP was prepared to compensate him for loss of rent, but the Case Manager revoked that offer. There is nothing in the file that indicates to me any proposal by the FSP to compensate the Applicant for loss of rent, rather to the contrary and I refer to the strong submission by the FSP in its initial notice of response on that issue. I do not accept that there was any offer by the FSP in respect of the loss of rent, rather to the contrary and that claim is rejected. Case No: 240632 Determination Page 7 of 7 42. Whilst I anticipate the Applicant will not be satisfied by my Determination, I am nevertheless required to decide the matter on the evidence before me and as stated above, the evidence, such as it is, does not support the Applicant’s claims.