Flood exclusion applied to January 2011 water inundation of business premises and dwelling
Text of the determination
Case No: 240024 Determination Page 1 of 9
Case number: 240024
General Insurance - Small Business/Farm Insurance - Commercial Property -
FSP Decision - Denial of claim-Exclusion/ condition
09 February 2012
Background
1. The Applicants hold a small business policy, incorporating cover for business
property damage, with the Financial Services Provider (FSP). The buildings
insured under the policy include the business premises and connected
domestic dwelling.
2. After heavy rain in January 2011, the Applicants‘ business premises and
domestic dwelling were inundated with water, with damage occurring to the
building and their business stock as a result.
3. A claim for the damage was lodged by the Applicants, but the FSP denied
liability for the damage on the basis that it was caused by flood.
4. The Applicants sought a review of the claim decision, saying that the cause of
the damage was stormwater.
5. The FSP reviewed the matter, and upheld its decision to de ny liability for the
damage.
Summary of Applicants ’ Position
6. In September 2010, the FSP accepted a claim for water inundation, finding on
that occasion that the cause of the damage was stormwater.
7. They say that the water inundation in September 2010 occurred in the same
way as in January 2011.
8. They also say that their January 2011 claim for stormwater damage to the
contents of their home was accepted by the relevant insurer and several of their
neighbours has also had their claims paid by their insurers.
9. They have stateme nts from several witnesses who corroborate the Applicants‘
version of events and photographs of the overflowing stormwater channel near
their house on the day of the inundation. All this evidence points to stormwater
Determination
Case No: 240024 Determination Page 2 of 9
being the cause of the inundation, which directly contradicts the evidence put
forward by the FSP‘s hydrologist.
Summary of FSP’s Position
10. The expert evidence from the hydrologist ‗W‘ indicates the water that caused
the inundation of the Applicants‘ busin ess premises came from McCallum
Creek surcharging up the stormwater channel which is nearby to the
Applicants‘ property.
11. Floodwater from McCallum Creek and Tullaroop Creek also would have flowed
overland to the Applicants‘ property sometime after the initi al inundation by
water from the surcharged stormwater channel.
12. The circumstances of the September 2010 claim were fundamentally different
to those of the January 2011 claim, and therefore one cannot be directly
compared to the other. The September 2010 claim was accepted on the basis
that the hydrology report clearly indicated that stormwater was the cause, and
that floodwater from the McCallum Creek would not have been a factor.
13. The decisions by other insurers to accept claims for damages are based on the
policy wordings applicable to those contracts of insurance, and the
circumstances of those claims (e.g. topography of the premises), so should not
be used to benchmarks for the decision for the Applicants‘ Ja nuary 2011 claim
with the FSP.
14. Much of the content of the statements provided by the Applicants in support of
their position is not inconsistent with the position of the FSP.
15. In the absence of expert evidence to the contrary, the FSP is entitled to rely on
the expert evidence from its hydrologist ‗W‘.
16. The FSP relies on the following policy provisions:
― The events You are insured against:
This policy insures You for physical loss of or physical damage to:
a Building, if ‗Buildings‘ is shown on the certificate of insurance
...
Stock, if ‗Stock‘ is shown on the certificate of insurance
Other Property, if ‗Other Property‘ is shown on the certificate of insurance.
This policy only insures You if the loss or damage is directly caused by an event listed
below and occurs during the Period of Insurance and in the case of:
Buildings, Stock and Other Property, occurs at the Business Premises.
1 accident
but not for :
Case No: 240024 Determination Page 3 of 9
loss or damage directly or indirectly caused by or arising out of:
fire, lightning, explosion or implosion, earthquake, subterranean fire or
volcanic eruption, wind, rain, hail, snow or escape of liquid, damage directly
caused by a burglar or thief, riot or civil commotion, vandalism or impact
...
6 wind, rain, hail, snow or escape of liquid
but not for :
Loss or damage directly caused by Flood
General definitions
applying to words We use in this Plan (Policy) as follows:-
...
Flood means the escape or release of water from the normal confines of a pond, lake,
reservoir, canal, dam or uncovered watercourse. ‖
Issues
17. Whether the water that caused the inu ndation of the Applicants‘ business
premises was stormwater run-off, or water overflowing from McCallum Creek
and surcharging the stormwater channel, and overflowing the Creek banks and
flowing overland to later cause further inundation of the Applicants‘ premises.
Reasons for Decision
18. Due to the nature of the dispute, it has been referred to the Panel for
Determination in accordance with the Operational Guidelines to the Financial
Ombudsman Service‘s Terms of Reference.
19. This decision has been made by a Pa nel consisting of an Ombudsman, a
representative with extensive experience in insurance industry matters and a
representative with extensive experience in consumer claims.
20. There has been an exchange of information between the parties and the Panel
is satisfied that each party has had an opportunity to address the issues raised.
21. The Panel notes that the FSP has accepted the portion of the Applicants‘ claim
that relates to damage to the air-conditioning units on the roof, which were
damaged by rainwater.
22. The following issues are not in dispute:
The Applicants claim for damage to their business premises in September
2010 was accepted by the FSP as having been caused by stormwater,
after the nearby stormwater channel overflowed.
The Applicants‘ business premise s and domestic dwelling experienced
inundation by water in January 2011.
Case No: 240024 Determination Page 4 of 9
In the days leading up to the inundation, heavy rain fell over the local
catchments, and across western Victoria.
The nearby stormwater channel, which is designed to capture stormwater
from the surrounding land to the south and west and discharge into
McCallum Creek, filled with water and overflowed during the January
2011 event.
Tullaroop Creek, and its tributary McCallum Creek, broke their banks and
flooded the township of Carisbrook on Friday 14 January 2011.
Date and Time of Inundation
23. There is some contention regarding the date time of inundation of the
Applicants‘ business premises.
24. The FSP‘s assessor, ‗M‘, spok e to the Applicants on 1 February 2011, and
reported that between 6am and 6:30am on Friday 14 January 2011, water was
lying in the laneway (of their business premises), on the floor of the storeroom,
and coming through the rear door and front door of the main shop.
25. The report from ‗M‘ goes on to state that at around 9am, water had risen higher
and started to enter through the rear residential door and that by 9:30am the
Applicants were evacuated from the property.
26. The Panel notes that the Applicants‘ reside nce adjoins the business premises.
The floor elevation of the house is approximately 200-300mm higher than the
floor of the business premises.
27. The hydrologist ‗W‘ spoke to the Applicants and inspected their property (date
unknown), and in a report dated 5 August 2011 stated that by 6:30am, water
had started to enter the lower shop premises through the door on the south
side of the building.
28. According to ‗W‘, the Applicants had also advised that the peak rainfall event
occurred on Thursday night (13 January 2011).
29. The Applicants have not directly disputed the dates and times as presented by
the assessor ‗M‘, or by the hydrologist ‗W‘.
30. However, the Applicants have provided a copy of a statement from the Captain
of the local fire brigade ‗I‘, which includes a timeline of events relevant to the
inundation of the Applicants‘ premises.
31. According to ‗I‘ the following occurred at the times indicated:
Thursday 13 January 2011:
1900 – Sandbagging drain [Be] St (to the south of the Applicants‘
business premises)
2000 ( text of time not completely legible; possibly 2030 – Panel comment)
– Sandbags to Applicants‘ street
Case No: 240024 Determination Page 5 of 9
2058 – Applicants‘ street impacted
2306 – residents evacuated (from premises opposite the Applicants‘)
Friday 14 January 2011
0430 – water over road at [U] St and Applicants‘ St (to the east of the
Applicants‘ business premises)
0735 – Houses and Applicants‘ business premises impacted with flooding
along Applicants‘ street
0850 – [P] Hwy to be closed
0910 – Evacuations to begin along [P] Hwy between [C] Rd and [L] Rd (to
the west and east of Applicants‘ business premises)
0917 – [P] Hwy breached at several places between Applicants‘ business
premises and [P] Lane (to the west of the Applicants‘ business premises)
32. The statement from ‗I‘ also indicated that the Applicants‘ home was
sandbagged on Thursday 13 January 2011 as it was being impacted by
overland flow (stormwater), and that McCallum Creek did not flood ‗I‘s‘ fire
station until 1010 on Friday 14 January 2011.
33. The FSP has raised a concern that the statement by ‗I‘ that the inundation of
the Applicants‘ premises occurred on 14 January 2011 is inconsistent with the
information provided by the Applicants to its assessor ‗M‘ and hydrologist ‗W‘.
34. In the Panel‘s view, the sandbagging of the Applicants‘ premises to protect it
from stormwater run-off (on Thursday 13 January 2011) does not of itself
demonstrate that water from any source had entered the premises.
35. A Site inspection was conducted by the Panel Chair Omb udsman on 20
January 2012. In attendance were the Applicants and representatives from the
FSP. The Applicants confirmed that the property was first inundated at
approximately 6:00am on 14 January 2011. According to the Applicants, the
water that inundated the property came from the west in the direction of the
Pyrenees Highway from the Maryborough area. According to the Applicants,
the water entered the front of the building and down the sideway of the building.
Water also came from paddocks at the back of the building. These paddocks
are slightly elevated to the Applicants‘ property. Water eventually rose to a
height of about 300mm entering through the shop and then into their domestic
dwelling.
36. The floor of the house is two steps (about 200mm) higher than the shop. The
shop is on a concrete floor set at ground level. There is no elevation above
ground level at all in the shop. The shop also sits significantly below the crest of
the road.
37. According to the Applicants, they received notification to evacuate the property
at approximately 10:20am on 14 January 2011. By that time they had already
evacuated the property and were in the heart of town. Their property, as they
have stated, was inundated from 6:00am.
Case No: 240024 Determination Page 6 of 9
38. The Applicants accept that at a later time the water from McCallum Creek, Big
Creek and Tullaroop Creek merged and would have flooded the town. They
maintain strongly that the water that initially inundated their property did not
come from the creeks but came from the opposite direction.
39. The Panel notes that the description of flow of water provided by the Applicants
is consistent with other information of the flow of water in the Carisbrook area.
There is no doubt that there would have been significant stormwater run-off as
the area had been saturated after four days of heavy rain. The area is largely
red clay soil which does not absorb a lot of water. The Panel also notes that the
hydrology reports refer to the lack of accuracy in flows in the creeks, the river
gauges and the inability to accurately estimate the creek levels or when the
creek overtopped. There was also a lack of data concerning flood levels within
the Carisbrook area.
40. After reviewing the other information provided by the Applicants, the Panel is
satisfied that the Applicants‘ business premis es were first inundated by water at
approximately 6:30am on 14 January 2011, and all the evidence is consistent in
this respect.
September 2010 Claim for Storm Damage
41. The Applicants have pointed to the claim they made with the FSP for storm
damage, including some water inundation, in September 2010, saying that the
FSP accepted the 2010 claim and the circumstances in the September 2010
and January 2011 weather events were similar.
42. If anything, according to the Applicants, the rainfall during the January 2011
event was heavier that in September 2010, and so it stands to reason that the
likelihood of stormwater run-off during the 2011 event would be even greater
than for the 2010 event.
43. The FSP says that the circumstances of the earlier claim were similar but not
identical to those of the later claim.
44. The FSP has provided a copy of the hydrology report for the earlier claim,
which indicates that after heavy rain the stormwater drain running alongside the
Applicants‘ street filled with run-off, then overflowed t owards the Applicants‘
house and business premises, and water also entered through the roof.
45. The FSP has also highlighted the fact that the hydrology report for the
September 2010 claim specifically concluded that floodwater from McCallum
Creek could not h ave inundated the Applicants‘ property.
46. The FSP has submitted that as such, the September 2010 claim is not relevant
to the current dispute.
47. The Panel has reviewed the material available, and agrees with the FSP that
the circumstances of the 2010 claim are such that it is not relevant to the
current dispute, and cannot be used as a benchmark against which other
decisions should be measured.
Case No: 240024 Determination Page 7 of 9
Other Claims for January 2011 Event
48. The Applicants have indicated that the insurer for the contents of their home
(which is the adjoining building to their business premises), has accepted their
claim for water inundation damage to their home contents.
49. The Applicants have also pointed to the claims acceptances of several
neighbours for the January 2011 event, including one claim for the property
adjacent to the stormwater channel nearby to the Applicants.
50. The Applicants say that all these claims have been accepted by the relevant
insurers, and therefore the FSP should also accept their claim for stormwater
damage.
51. The FSP argues that it is not aware of the terms and conditions of the policies
against which these other claims have been made, or the particular
circumstances surrounding the claims (e.g. topography of the premises), and /
or the bases for the decisions by the other insurers to accept those claims.
52. The FSP argues that because of the likely differences involved, it would not be
appropriate to draw any comparison between those claims‘ decisions and the
FSP‘s own decision regarding the Applicants‘ claim.
53. It shoul d be noted that the Panel‘s decision regarding the Applicants‘ dispute
with the FSP is made with reference to the evidence presented by the parties.
54. The Panel accepts that other claims may have been accepted by other insurers
for damage to neighbouring pro perties, and for damage to the Applicants‘ home
contents in the house adjoining their business premises.
55. The Panel has reviewed the information relating to the claim for a neighbour,
‗KM‘, who resided adjacent to the stormwater drain, and notes that a copy of a
Final Decision Letter (FDL) from the insurer for that claim has been presented
by the Applicants, and that this FDL makes reference to a hydrology report
produced by ‗F‘.
56. In addition, a copy of a Statutory Declaration from ‗KM‘ — attesting to the timi ng
of the water entering her property, the direction from which the water
approached, and the timing of the inundation of her home — has also been
presented by the Applicants in support of their case.
57. The Panel notes that the insurer for ‗KM‘ was persuaded that the evidence
available was sufficient for it to accept a claim for stormwater damage to the
home involved.
58. Although the FDL from the insurer for ‗KM‘ makes reference to a hydrology
report from ‗F‘, a copy of this report was not made available to the F SP or the
Panel for review.
59. The Panel has considered the information in the Statutory Declaration from
‗KM‘ regarding the timing of the water entry to her property and the inundation
of her home, and finds that is broadly consistent with the position of the FSP.
Case No: 240024 Determination Page 8 of 9
60. In relation to the path taken by the water that caused the inundation of the
home of ‗KM‘, the Panel notes that the Statutory Declaration states that this
water flowed through property and into the adjacent stormwater drain.
Source of Water in Stormwater Channel
61. The Applicants have said that the stormwater drain nearby to their property
filled with stormwater then overflowed, and that it was this overflowing
stormwater that entered their property and inundated their business premises.
62. The Applicants have provided photographs of the vicinity around their property
at the time of the inundation event, showing that the stormwater drain filled and
then overflowed with water. According to the Applicants, these photographs
show that the water in the stormwater drain was flowing towards the Creek, not
away from it.
63. The FSP has said that the stormwater drain became surcharged with water
‗back - flooding‘ from McCallum Creek, and that this overflowing floodwater was
responsible for the inundation of the Appl icants‘ business premises.
64. The Panel has considered the evidence from both parties in relation to the
source of the water in the stormwater drain at the time of the inundation of the
Applicants‘ business premises.
65. The Panel notes that the hydrology report by ‗W‘ dated 5 August 2011
concedes that at approximately 7am on 14 January 2011, some run-off from
the catchments to the west of the township would have surcharged the
stormwater drain, but that by this time McCallum Creek would have already
started to back-flood.
66. The photographs provided by the Applicants give an indication of the extent of
the water inundation around the vicinity of the Applicants‘ property ; however the
Panel is not satisfied that they represent conclusive evidence of the source of
the water in the drain.
67. Based on the information that has been exchanged and with the benefit of
having conducted a site inspection of the property, the Panel is satisfied that
the initial inundation of the Applicants‘ property was due to stormwater run-off.
The Panel is satisfied that the stormwater run-off was at such a level that it led
to the Applicants‘ need to evacuate the premises at approximately 6.00am prior
to the 10.20am flood warning being received and notice to evacuate. The Panel
accepts the Applic ants‘ evidence that most likely the stormwater run-off
commenced inundating the property around 6:00am The Panel accepts that
ultimately water from McCallum Creek, Big Creek and Tullaroop Creek merged
and flooded the town. It is impossible based on the information exchanged to
determine precisely the level of damage caused by the initial inundation by
stormwater as against the damage subsequently caused by the ultimate
inundation of the property by floodwater.
68. Under the Terms of Reference, it is appropriate for the Panel to consider what
is fair in all the circumstances having regard to the relevant legal principles,
Case No: 240024 Determination Page 9 of 9
terms of the policy, good insurance practice and any prior determinations
although not binding. In this dispute, again with the benefit of having conducted
a site inspection and discussions with the parties, the Panel is satisfied that the
initial stormwater inundation contributed to damage up to 300mm throughout
the shop. At such level, it would have also led to damage of the Applicants‘
domestic dwelling although the Panel accepts that damage through the
domestic dwelling would have been limited to a height of no more than 100mm
throughout.
69. Insofar as the Applicants have sought compensation with respect to business
interruption, this is not within the jurisdiction of FOS. The Panel has been
advised however by the FSP that in the event of FOS accepting the Applicants‘
submission for loss of income, the FSP will review its decision in relation to the
claim under business interruption.
Determination
70. Accordingly, the Panel determines the FSP meet its liability in accordance with
the terms of the policy with respect to the property damage and loss of stock.
71. In this regard the Panel notes the FSP has not had sufficient opportunity to
assess the extent of damage caused by stormwater as against floodwater in
accordance with this determination. The Panel determines it is appropriate for
the FSP to appoint an Assessor to determine the extent of the damage to the
business and domestic dwelling.
72. The Panel further notes that the Applicants are to provide a detailed list
identifying the loss of stock. The parties are asked to work cooperatively in
order to determine the extent of the loss of stock.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.