Claim refused for January 2011 flood damage to contents

FirmFinancial Firm (Unknown - Insurer)
Decided2012-02-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The insurer refused a home contents claim for water damage from the January 2011 Victorian flood, relying on the flood exclusion and stating a PDS had been sent. AFCA found the PDS was sent and that stormwater damage up to 50mm is covered, so the insurer must pay contents damage to that level.

Stormwater damage that occurred before flood water combined with it is covered, while damage after the flood and stormwater combined falls within the flood exclusion; the Panel found the covered stormwater damage was limited to 50mm.

Issues

Subjects and remedies

natural disasterpay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 239237 Determination Page 1 of 13 Case number: 239237 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 13 February 2012 Background 1. The Applicant held a home contents policy with the Financial Services Provider (FSP). 2. In January 2011, the Applicant’s home was inundated with water following severe weather events in Victoria. 3. The Applicant’s claim was assessed and the FSP refused liability on the basis the loss was caused by flood, which is an exclusion under the policy. 4. The Applicant disputed the decision, arguing the loss was caused by stormwater. The Applicant lodged a dispute with the Financial Ombudsman Service and has also raised the issue that she was not provided a copy of the terms and conditions of the policy by the FSP. Summary of Applicant’s Position 5. The home was inundated with rainwater on 14 January 2011. The loss occurred due to exceptionally heavy rain and poorly maintained infrastr ucture in the area. 6. Other insurers have paid claims for the same event, including one that does not cover flood. 7. The hydrologist clearly did not understand what was said at the site visit as he quoted incorrect details twice. The hydrologist had a thick accent and therefore communication was difficult. 8. She questions the hydrologi st’s practical experience, noting he was only qualified in 2008 and it is easy to download graphs and express an opinion. 9. The flood peaked during the heavy rain, not 6 to 12 hours later as reported. Lake Beaufort did not break its banks. The water began inundating the property on 12 January 2011, not 14 January 2011. Determination Case No: 239237 Determination Page 2 of 13 10. Some towns were flooded by rivers breaking their banks but this did not happen in Beaufort. 11. She provides a signed declaration from six other residents in the area which states water was on the property on 12 January 2011 and entered the home at approximately 5:00am on 14 January 2011. 12. Her original insurer was changed to the FSP without notification from either insurer and she was never provided a copy of the Product Disclosure Statement (PDS) with the terms and conditions of the policy. 13. When she changed addresses, she informed the FSP but still did not receive a PDS. She believes an insurer has to provide a PDS every year at law. 14. She had raised the PDS issue in a submission to the Financial Ombudsman Service earlier and submits the FSP has breach confidentially and creditability in raising her daughter in law’s dispute. 15. The Applicant believes the FSP should cover the claim, as per its obligation under the insured event of storm. Summary of FS P’s Position 16. The Applicant’s insurance policy does not provide cover for flood. The policy is a listed events policy covering the Applicant’s building and contents (the policy in fact only covers the Applicant’s contents). 17. The FSP arranged for an Assessor to attend the property and carry out an inspection on 18 January 2011. The Assessor noted the Applicant’s assertion that authorities had warned residents of potential flooding by telephone at 5:00a.m. on 14 January 2011 and that the Applicant evacuated her property at approximately 5:30a.m. Flood waters had inundated the yard at that time b ut had not reached house level. 18. Flood waters began to recede in the afternoon. The FSP accepts that there was heavy rain from Wednesday, 12 January 2011 that caused minor flooding in Beaufort on the south side of the railway and the flood water was a combination of both overflow from Cemetery Creek and local run-off. FSP acknowledges there was heavy rain again on Thursday, 13 January 2011 and argues that water levels in the creek rose overnight and inundated much of the town. The FSP acknowledges that the rainfall measured over 13 and 14 January was significantly higher than that of 11 and 12 January and notes that the flooding was disproportionately more severe due to:  the later rain falling on more saturated grounds resulting in a higher conversion of rainfall to run-off;  run-off from the latter then combining with the remnant/remained run-off from earlier rain; Case No: 239237 Determination Page 3 of 13  Lake Beaufort overtopping reducing the retardation upstream of Cemetery Creek;  flows through the township exceeding the capacity of a greater number of drains, culverts and bridges – and exceeding their capacity by a greater margin. 19. The FSP further argues that the floodwaters in Beaufort peaked six to twelve hours a fter the rain had stopped. So far as the Applicant’s specific site information is concerned, the FSP noted the Applicant’s statement that the floodwaters came from stormwater drain at the front of the property and that the drain backflowed onto the site as it was restricted from flowing out under the railway crossing. The drain at the front of the property was highly vegetated and had not been cleaned for over 14 years. 20. The FSP argues whilst it accepts many of the points raised by the Applicant, it concludes that:  heavy rainfall over a period of days caused Cemetery Creek to break out and flow onto the site in the early hours of Friday morning;  there was no rain for much of the flood event and water levels peaked approximately 6 to 12 hours after the peak rain had ceased;  the water inundating the site was predominantly overflow from Cemetery Creek as it backflooded through the stormwater drains. Local run-off was not a significant component; and  restriction of flows at the railway line would have contributed to higher flood levels. 21. The FSP notes that the Applicant’s statement which is signed by six persons is that the rainfall peaked on Thursday late afternoon and evening. The FSP argues that is consistent with the hydrologist finding that the floodwater levels peaked between six and twelve hours after the peak rainfall had ended on Thursday afternoon. The FSP argues this excludes any possibility of localised flooding caused by stormwater. 22. The fact other insurers have paid claims has no relevance where the contract between itself and the Applicant states there is no flood cover. 23. In relation to providing the PDS, it notes the Applicant never raised the issue before her daughter in law’s claim (also with the FSP) had been accepted as the result of an issue with the PDS. 24. It notes the Applicant’s daughter in law claimed she did not get a PDS from the bank at the time of purchasing her policy. The FSP obtained a Statutory Declaration from the bank employees; however, after the Applicant’s daughter in law went and spoke to the staff at the bank, they retracted their statement. 25. On the basis it could no longer prove the PDS was provided to the Applicant’s daughter in law, the FSP agreed to accept the daughter in law’s claim and sent a letter confirming this on 27 July 2011. Case No: 239237 Determination Page 4 of 13 26. The Applicant’s Statutory Declaration that she did not g et a PDS is dated 29 July 2011, only two days later and very likely after she was aware of the decision with relation to her daughter in law’s claim. 27. The FSP questions why this issue did not arise until after the daughter in law’s claim had been accepted due to the issue with the PDS. 28. It notes the Insurance Schedule sent to the Applicant in 2008 makes reference to the enclosed PDS. 29. With relation to the change in the FSP’s policies (an update), the FSP notes that both policies excluded flood cover. 30. It provides dispatch material in support of its submission a PDS was sent to the Applicant at least twice, and it notes it is highly unlikely the Applicant did not receive the PDS. 31. The FSP relies on the following policy provisions: “ Listed Events cover We will cover your buildings or contents for loss or damage as a result of the incidents listed on the following pages. … Any cover we provide is subject to exclusions. For exclusions to this cover, see page 35 ► … Storm, rainwater or wind We will cover your buildings or contents for loss or damage as a result of storm, rainwater or wind… … Water or liquid damage We will cover your buildings or contents for loss or damage caused by water or liquid… … Exclusions to your cover Any cover we provide is subject to the following exclusions. We will NOT cover any loss or damage as a result of, or caused by … Case No: 239237 Determination Page 5 of 13  flood … General exclusions We will NOT cover any loss or damage, or liability as a result of, or arising from …  flood or storm surge … glossary of words with a special meaning … flood the covering of normally dry land by water escaping or released from the normal confines of a watercourse or lake, whether or not it is altered or modified. Flood also includes water escaping from the confines of any reservo ir, channel, canal or dam.” Issues 32. Whether the Applicant was provided a copy of the PDS outlining the terms and conditions of the policy. 33. Whether the loss was caused by rainwater or flood. 34. Whether the FSP is entitled to refuse liability on the basis of the terms and conditions of the policy. Reasons for Decision 35. Due to the nature of the dispute, it has been referred to the Panel for Determination in accordance with the Operational Guidelines to the Financial Ombudsman Service’s Terms of Reference. 36. This decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in insurance industry matters and a representative with extensive experience in consumer claims. 37. There has been an exchange of information between the parties and the Panel is satisfied that each party has had an opportunity to address the issues raised. 38. As the Applicant submits she did not receive a PDS, it is appropriate to deal with this aspect of the dispute prior to considering the overall aspects of the dispute. Case No: 239237 Determination Page 6 of 13 Did the FSP send the Applicant a PDS? 39. Section 35 of the Insurance Contract Act 1984 , provides that an insurer that wishes to exclude an event covered under a Prescribed Contract in the Insurance Contracts Regulations 1985 , must do so by clearly informing the insured that it is derogating from the prescribed cover. 40. Under Regulation 13 of the Insurance Contracts Regulations 1985 , home contents insurance is described as a prescribed contract. Under Regulation 14 flood is described as a Prescribed Event. Therefore, if an insurer chooses not to cover flood, it has the onus to clearly inform the insured that it is excluding loss or damage caused by flood. This is usually done by providing a PDS outlining that flood is excluded. 41. The FSP has made c omments in relation to the Applicant’s daughter in law’s claim and policy, with an inference that the Applicant has only raised the issue after she was aware her daughter in law’s claim was covered. 42. The Panel notes that when an insured submits they did not receive a PDS, the onus shifts to the insurer to establish, on the balance of the probabilities, that the PDS has been sent. 43. Therefore, the Panel will not consider the issues relating to the daughter in law’s policy as either way, the FSP still bears the onus to establish the PDS was provided. 44. The FSP has provided a Statutory Declaration from its National Underwriting Service Manager, dated 19 September 2011, which states: “In 2006, [FSP] undertook a program to inf orm all existing policy holders of change s to [FSP’s] new PDS. The process included sending the new PDS with the renewal invitation and renewal schedule. Three bulk mail outs were undertaken based on the customers renewal date on their policy. The renewal date determined in which block mail out they would receive their letter. The first block of mail out commenced on 09/10/2006, the second block mail outs occurred on 09/11/2006 and the third 09/12/2006. The first block mail out commenced October 9 th 2006 incorporated all customers whose policies were to be renewed, October 2006, November 2006, December 2006 and January 2007. The second block commencing November 9 th 2006 was for policy renewals for February 2007, March 2007, April 2007 and May 2007. The third commenced December 9 th , for renewals in June 2007, July 2007, August 2007 and September 2007. I verily believe that given the renewal date (March 2007) PDS was sent to the Applicant with the covering letter in the second block commencing November 9 th 2006. While policy upgrades occurred there was no change to the policy cover for flood. Flood remained an excluded peril. Enclosed and marked with the “A” is a copy of the pro-forma letter sent in October 2006 together with the attached relevant 2006 version of the PDS. On 16th of March 2008 and another letter was sent to the Applicant advising of further changes and enhancements to the policy cover. Consistent with the Case No: 239237 Determination Page 7 of 13 process undertaken in 2006, a new PDS and Renewal Schedule was enclosed with the letter. Enclosed and marked with the letter “B” is a copy of the letter dated March 16 th 2008 including the details of improved benefits renewal invitation and renewal schedule and 2008 PDS print. The bar code on the left hand side of letter dated 16 th March 2008 is the coding for the mail agency [name] to indicate the documentation enclosed with the letter which in this case includes the relevant PDS. [FSP’s] process for dispatch of documentation through the external agency of the [name] corporation is outlined in the enclosed statutory declaration of [General Manager of agent], the organisation vested with the responsibility to handle [FSP’s] bulk mail out of documentation. The policy has continued to be renewed in accordance with each renewal invitation. I verily believe that the [FSP] mail system for dispatch of documentation verifies that the Applicant received a current [FSP] PDS on at least 2 occasions October 2006 and 16 th March 2008.” (sic) 45. The FSP has provided a copy of the letter reportedly sent to customers in October 2006. It outlines there is a change in the policy and “you should refer to the enclosed Product Disclosure Statement (PDS) for the full terms and conditions”. 46. The FSP has provided a copy of a letter addressed and reportedly sent to the Applicant on 16 March 2008. The letter states there has been a change to the FSP’s policy and “ you should refer to the enclosed Product Disclosure Statement (PDS) for the full terms and conditions” . 47. The FSP provides a Statutory Declaration from the General Manager of the agent charged with the duty to dispatch its bulk mail outs to customers, a copy of its process and a copy of the general instructions and requirements for the FSP to the change of PDS in 2006. 48. The Panel is satisfied the FSP had a process in place for the despatch of material including the PDS during the relevant period. In particular, the Panel notes that the process in March 2008 consistent with the process undertaken in 2006 is to provide a new PDS and Renewal Schedule with the letter to the Applicant. 49. The Case Manager (from the Financial Ombudsman Service) contacted the Applicant on 7 October 2011 to enquire if the Applicant had received the renewal documentation from the FSP. The Applicant confirmed she had received renewals on a yearly basis but had never received a PDS. 50. During a site inspection conducted by the Ombudsman on 18 November 2011, the Applicant confirmed her view that she had never at any stage received a PDS document from the FSP. Whilst the Applicant admitted receiving a PDS from the insurer of the building, she specifically denied receiving a PDS from the FSP as insurer of the contents. 51. Although the Applicant denies having received a copy of the PDS, she admits having received renewals on a yearly basis and admits that she maintained the policy on the basis of the renewal document sent to her. It is possible in these Case No: 239237 Determination Page 8 of 13 circumstances that the Applicant may not have appreciated that the policy documentation had been sent to her. It is unlikely that she did not receive the mail given the Applicant admits receiving the renewal notices and admits payment of the policy on that basis. 52. Having considered the evidence as a whole, the Panel is satisfied that the FSP has established that most likely the PDS was sent to the Applicant with the renewal notifications. The Panel is satisfied on the balance of probabilities it is unlikely the FSP would have failed to include the PDS on two occasions namely in 2006 and 2008. 53. Having been satisfied that the FSP has provided the PDS to the Applicant, the question arises as to whether the PDS is sufficient to clearly inform the Applicant as to the terms and conditions of the policy. 54. The Panel has examined the FSP’s policy. Whilst the policy is 67 pages in length, the policy is indexed. Page 1 of the policy sets out the contents including exclusions and identifies a glossary of words with special meanings. At page 5, there is a more detailed index as to what the policy covers. At page 16, the policy identifies that it covers storm, rain or wind and water damage. It does not at that stage make mention to the flood exclusion. At page 35 the policy identifies the exclusions to cover. General exclusions are covered at page 39-40. On page 40 there is a general exclusion for flood or storm surge. 55. Under the glossary flood is clearly defined. Flood is defined as the covering of normally dry land by water escaping or released from normal confines of a water course or lake whether or not it is altered or modified. Flood also includes water escaping from the confines of any reservoir, channel from a canal or dam. At the back of the policy at page 67 there is a detailed index. 56. The Panel is satisfied in these circumstances that the policy does act to clearly inform the Applicant of the terms and conditions of the policy. The Panel is satisfied that the policy notifies the Applicant of the derogation from cover. Was the loss caused by rainwater or floodwater? 57. The Applicant submits the loss was caused by rainwater as the result of the storm that could not drain due to the failure of the local Council to maintain infrastructure. 58. The Applicant provides a declaration signed by six residents, which states: “ On Tuesday 11 th January, until approximately 10am on Friday the 14 th of January, a storm event took place in Beaufort Victoria, during this time we received over 275mm of rainfall. The storm peaked late Thursday afternoon and evening and did not peter out until approximately 10 am on Friday morning. Water was on the properties of [addresses – including the Applicant’s address] from Wednesday 12 th January and entered the house at approximately 0500 Friday 14 th January. It would have been in even earlier had it not been for the sandbagging of the properties. Friday at approximately 3pm water had left the houses and was almost gone from the land. Hydrologist report states that water didn’t enter the properties until 6 -12 hours after the rain had stopped, when infact Case No: 239237 Determination Page 9 of 13 the water had almost dissipated by this time. We the undersigned believe this statement to be true and correct.” (sic) 59. The Applicant also questions the hydrologist’s experience and notes he was difficult to communicate with and statements attributed to her in the hydrology report are inaccurate. 60. The FSP’s submission (at paragraph 13) discusses the flood events in Brisbane. The Panel presumes this is a typographical error and has ignored this evidence. 61. There are other parts of the FSP’s submission that appear to be directed to events other than the flood events at the Applicant’s property. For the purposes of the Panel’s determination, the P anel will consider only those aspects of the submission that are relevant to the current dispute. 62. The Panel has reviewed the hydrology report, dated 28 February 2011. With relation to the Applicant’s insured property, it states: “The site is a residential property in Beaufort located just south of the railway line along [name] Street. A stormwater drain runs along the front of the property and discharges into Cemetery Creek upstream of the railway crossing. At the rear of the property, there is stormwater drain that discharges to the west, into Cemetery Creek. … Discussion with the owner of the subject site and her son who resides next door ([address]) indicated the following details:  The property started to flood early Friday morning (14 th January);  Floodwaters came from up from stormwater drain out the front. The water in the drain backflooded onto the site as it was restricted from flowing out under the railway crossing;  By 5:30am on Friday the owners were evacuated. At the time of evacuation floodwaters had inundated the yard but had not yet reached the house floor level;  According to the neighbour, it stopped raining at approximately 11:00am Friday morning;  The stormwater drain out front is highly vegetated and has not been cleaned in 14 years; and  The neighbours believe that Lake Beaufort did not overtop. Inspection of the site and surrounds identified:  Cemetery Creek and the nearby stormwater drains are heavily vegetated and overgrown;  Evidence of floodplain inundation at the front and rear of the property; Case No: 239237 Determination Page 10 of 13  Water marks inside the house indicated a peak water level of approximately 500mm; and  A site inspection of Lake Beaufort and its surrounding area confirms that the lake did overtop. Understanding of the wider flood events and mechanisms agrees with the points, with the exception of rainfall timing in the area. Rainfall data from the bureau and accounts from other residents indicate that there was no rainfall after 9:00am on Friday morning. It is concluded that:  Heavy rainfall over a period of days caused Cemetery Creek to break out and flow onto the site in the early hours of Friday morning;  There was no rain for much of the flood event and water levels peaked approximately 6 to 12 hours after the rain had ceased;  The water inundating the site was predominantly overflow from Cemetery Creek as it backflooded the stormwater drains (front and rear). Local run-off was not a significant component of the water or cause of inundation; and  Restriction of flows at the railway line would have contributed to higher flood levels.” (sic) 63. The hydrologist reports that the highest rainfall occurred on 13 and 14 January 2011 and with the area already saturated from rain on 11 and 12 January 2011, there was more run-off water and the infrastructure could not cope, resulting in flooding. 64. In view of the issues in dispute, the Panel Chair Ombudsman conducted a site inspection. Present at the site inspection were the Applicant and a representative at the FSP. There was also a representative from the Applicant’s building i nsurer present. The Applicant’s block slopes slightly to the rear of the property. The Applicant maintains water was coming from the levy to the drains and then draining to the creek. The Applicant maintains the ground was saturated. It commenced raining heavier on the Thursday night and did not cease. The Applicant thought she left the property about 4:45 a.m. (this is inconsistent with earlier advice that suggests that it was approximately 5:30 a.m.). At that time, water was starting to lap at the doors. The Applicant thought stormwater probably from the levy or Neill Street, and run-off stormwater that runs to the creek, was impacting on their property. The Applicant maintains that the creek was always known as a stormwater drain. The culvert from the railway line also runs to the drain. 65. When the Applicant left the property, she believed water started to come in through the front door and out through the back. Eventually water rose to about 8 to 10 inches in the house. As a result she has suffered damage including damage to her carpets, kitchen cupboards, a vanity heating system and furniture. Case No: 239237 Determination Page 11 of 13 66. The house is lower than Neill Street and the highway. It is the lowest part of town. The Panel notes that the hydrology confirms the property was in a low part of the town. 67. The Applicant maintains as she was leaving the property and in fact all through the night, there were trucks coming through the town. This caused a wave of water to come from the highway and Neill Street down through the properties. The Applicant thought the waves knocked down fences. The Panel notes the Applicant had previously raised these issues but they have not been addressed in the hydrology report. 68. The FSP’s comments in its notice of response that the peak rainfall was on the Thursday evening six to twelve hours prior to the floodwaters commencing. The FSP concedes that there is no accurate data for the time of the flood peak, however it was evidenced that the flood started to inundate the Applicant’s property long after the peak rainfall had fallen. The Panel disagrees with this aspect of the FSP’s submission. The evidence is that the rainfall inten sity was at its highest from the evening of 13 January. The rainfall continued until at least 9:30a.m on 14 January. The half hourly rainfall data indicates significant rainfall until this time. The hydrology does not state as alleged by the FSP that the floodwaters had peaked six to twelve hours after the peak rainfall. The hydrology in fact states that the floodwaters peaked six to twelve hours after all rain had stopped. If the rain stopped at 9:30a.m. in Beaufort then the floodwaters would have peaked between 3:30p.m. and 9:30p.m. on 14 January 2011. The Applicant’s evidence, that has not been disputed, is that the floodwaters started to recede from her property after 3:00p.m. on 14 January and the Applicant has provided photographic evidence of limited remaining water on the morning of 15 January 2011. Her evidence that is not disputed is that she left her property by 5.30a.m with the water lapping at her door. 69. The Panel also notes the hydrology found that the flooding that followed the heavy rainfall on 13 and 14 January 2011 was disproportionately more severe than the earlier flooding. This was because of:  the latter rain falling on more saturated ground resulting in a higher conversion to rainfall run-off;  run-off from the latter event combining with remnant-retained run-off from earlier rain;  Lake Beaufort overtopping, reducing the retardation upstream of Cemetery Creek; and  flows through the township exceeding the capacity of a greater number of drains, culverts and bridges and exceeding their capacity by a greater margin. The hydrologist concluded that all these points strongly suggest that though local stormwater might contribute to the flooding, the main cause was run-off from more distant catchments overflowing, Yam Holes Creek and its tributaries. 70. The Panel also notes the findings of the hydrologist that local run-off may have accumulated in the areas of the town mainly as a result of creek flows and surcharging stormwater. Case No: 239237 Determination Page 12 of 13 71. The Panel does not accept the FSP’s argument that the inundation of the Applicant’s property occurred after the rainfall had ceased. It is quite clear from the information exchanged that the inundatio n occurred as the rainfall was falling. 72. The Panel is also satisfied based on the information exchanged that whilst no doubt the level of Cemetery Creek and Yam Holes Creek was increasing, that at the time when the Applicant evacuated the property, the water was flowing towards the Applicant’s property towards the creek and most likely inundated the property shortly thereafter. 73. Based on the information exchanged, the Panel accepts the initial inundation was stormwater damage The Panel is also satisfied that eventually the stormwater mixed with floodwaters that would have flowed from Cemetery Creek and Yam Holes Creek further inundating the property. 74. A ccepting the FSP’s hydrology, it is likely that the peak level of flooding occurred at some time around 3:00p.m. It is evident that flooding to the property as a result of a mixture of the flood and stormwaters would have occurred at an earlier time. 75. It is necessary for the Panel to determine in these circumstances the proximate cause of the loss. 76. It is well established at law where an excluded peril (in this case flood) and an included peril (in this case stormwater damage) operate contemporaneously that is where the damage from both occurs at the same time, then the excluded peril will operate to defeat the claim (in other words, the flood exclusion would operate to defeat the claim). In this case that would operate to exclude any damage occurring after the waters mixed. Any damage that occurred as a result solely of the stormwater damage would be included. 77. While accepting there was initial stormwater run-off damage, it is impossible based on the information exchanged to determine with any accuracy at what level the stormwater damage flowed through the property. 78. In these circumstances it is necessary for the Panel to consider what is fair in all the circumstances having regard not only to the terms of the policy, good insurance practice and relevant legal principles but also prior determinations. It is clear that the policy wording in the current dispute does not include damage caused by waters backflowing through the stormwater drains from the creeks. To the extent that any inundation was due to water backflowing from the rising creeks through the drains, that would not be covered. Given the Applicant’s description of the events occurring at the time of inundation and taking into account all relevant material, the Panel determines it is fair in the circumstances to determine the initial inundation as stormwater run-off, would not have exceeded 50mm. Case No: 239237 Determination Page 13 of 13 Determination 79. Accordingly the Panel determines the FSP is liable to meet the costs of damage to contents sustained as a result of stormwater flowing through the property to a maximum height of 50mms. 80. Insofar as any damage sustained beyond this level is concerned, the Panel is satisfied that for the purposes of the terms of the policy, this damage occurred due to flood which is excluded under the general exclusions of the policy.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.