Summary

The applicants disputed the FSP's cash settlement for ceiling, plaster and painting repairs after a storm leak, and claimed delays. AFCA accepted the FSP's plaster and painting settlements and ordered that a lounge ceiling top-up be paid only if the applicants could provide a laser-cut tile quotation, referring the handling complaints to the FSP's Code & Systemic Manager.

The policy requires the insurer to match damaged materials as near as reasonably practicable, not to replace undamaged items, and the insurer retains discretion over repair or cash settlement.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 238752 Determination Page 1 of 8 Case number: 238752 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 25 July 2011 Background 1. The Applicants hold a Home Building and Contents policy of insurance with the Financial Services Provider (FSP). The policy covers the home building for complete replacement and home contents for $213,950. 2. On 3 December 2010, the Applicants contacted the FSP to lodge a claim for storm damage which had resulted in a leaking roof. The leak caused damage to the ceiling, carpet, plaster and other items in the home. 3. The FSP accepted the claim and arranged for settlement. The FSP has offered cash settlement of the following items which are still in dispute - lounge ceiling repairs, plaster/painting repairs to the hall, study and lounge room walls , and extra ceiling batten installation if required. 4. The Applicants dispute these outstanding amounts on the basis that the cash settlement offered does not cover the repairs required. Summary of Applicants ’ Position 5. The Applicants note the FSP delayed dealing with their claim, provided wrong advice and offered incorrect settlement for items. In support of these contentions, the Applicants have provided a detailed record of events. Further, the FSP has failed to provide the written quotation for items or work that it relies upon. 6. The Applicants were particularly dissatisfied with the time taken to obtain quotations and a scope of works. Further, the Applicants informed the FSP of their holiday leave and noted they would be available during that time for the purpose of obtaining quotations. Due to the taking of annual leave , the Applicants were then unable to take additional time off to accommodate the requests to allow tradespersons and assessors access to the property. 7. The Applicants rely on the following policy terms and conditions: “Damage to fixed wall or floor coverings When we repair or replace damage to fixed wall, ceiling or floor coverings: Determin ation Case No: 238752 Determination Page 2 of 8 we also repair or replace undamaged coverings if this is reasonably required to achieve a match with the repair or replacement of the damaged area, the repair or replacement is limited to the room, passageway, stairwell or functional area where the damage occurred. Fixed wall and floor coverings are items such as tiles, floating floors, fixed cupboards and shelving.” 8. The Applicants are dissatisfied with the offer of $8,488.07 for lounge ceiling repairs. The Applicants submit that the works will not cover the ceiling tile replacement like for like as required by the policy. The tiles can be replaced like for like in size (but not pattern) although it would require laser cutting of the tiles. The FSP‟s proposal includes smalle r tiles and additional battens to accommodate same. Further, there was only one repairer in the Applicants‟ locale able to perform these works (“GCP”) . 9. The Applicants note the offer of $812.18 is an amount included within the ceiling tile/plaster quote by a repairer. The Applicants had not been informed of this amount previously and had not discussed the amount required with the FSP for these works. 10. The Applicants have noted the amount of $3,025 offered for painting the hall, study and lounge room walls bas ed on the quotation by “LPD” . However, as the cheque has not been provided for this amount, the Applicants consider it outstanding. 11. The Applicants dispute the figure of $500 offered for extra ceiling batten installation because it would not result in a like for like replacement of ceiling tiles. The Applicants have previously demonstrated that a like for like (except for tile pattern) is achievable. 12. The Applicants contend the FSP is picking and choosing which quotes to accept without consultation with the contractors. The FSP has only accepted the Applicants‟ quotation for carpet. 13. The Applicants prefer a cash settlement for all items as this will allow them to arrange all repairs in a sequential manner without reference to the FSP‟s repairers. Summary of FS P’s Position 14. The FSP relies on the following policy terms and conditions: “Repairing or rebuilding your building If your home building is damaged during the period of cover by an insured event, we will decide if the damage: can be properly repaired, or is so severe that we reasonable believe your building will need to be rebuilt. Repairing your building When we establish that your home building can be properly repaired, we will decide to: repair it, or Case No: 238752 Determination Page 3 of 8 pay the cost of repairing it When we repair your building, we will use new materials. We will make reasonable endeavours to match materials. Where this does not achieve an exact match, materials that in our opinion match the damaged or lost materials as near as reasonably practicable will be used. We will not pay to replace undamaged materials or any undamaged part of them to achieve a match. ... Repairing or rebuilding your building We ordinarily obtain independent, competitive quotes from repairers and suppliers recommended by [FSP name}. If you want, you can choose a repairer and/or supplier to provide one of the quotes. We review the quotes, including any quote from a repairer and/or supplier your choose, and what is necessary to properly repair or rebuild your building. We choose the repairer and/or supplier who submitted the more competitive and complete quote and that will be the repairer and/or supplier who repairs or rebuilds your building. We will enter into any building contract with the selected repairer and/or supplier on your behalf. We will ov ersee the repairs and keep you informed of their progress.” 15. The FSP submits that the policy requires it to make a near as possible match of materials. Further, that the FSP may consider the quotations of the Applicant‟s repairers but will choose the most competitive and complete quote. 16. The FSP has enclosed the Applicant ‟s quotation of $32,885.60 for the repairs to the Applicants‟ lounge ceiling. The FSP notes that the quotation also includes repair works for a previous claim and the quotation does not itemise each item of repair. 17. The FSP reviewed this quotation and concluded it was not fair and reasonable. This was based on its own repairer (“HR”) who advised the following: “To the best of our knowledge the decorative ceiling tile is no longer manufactured and is not available in marketplace. ... We understand that also that the ceiling is being referred to as an “acoustic ceiling ” and whilst the existing damaged decorative ceiling tiles would have some acoustic properties we have been unable to establish what there (sic) acoustic performance is. ... Most ceiling tiles and or acoustic ceiling tiles commonly used today are in commercial applications, manufactured from a wide variety of materials [usually involving some form of suspended ceiling grid] of which there are many differing aesthetic finished and levels of acoustic performance.” HR provided a quotation in the sum of $8,488.07 for repairs to the ceiling that would match as near as reasonably practical to the Applicants ‟ existing ceiling. The HR quotation confirms the tile type to be used in the repair. The FSP has also confirmed with its repairer that additional battens could be installed to avoid the need to cut the tiles. Case No: 238752 Determination Page 4 of 8 18. The FSP has also provided alternative quotation options for repair to the ceiling from HR. HR has indicated replacement of solely six tiles and the repainting the ceiling. Alternatively, HR recommends supplying and installing a new ceiling grid and tiles for $10,311.60. 19. The FSP submits that 1x1 foot tiles are no longer manufactured and the GCP does not include measurements of the tile they are offering or the specific type of tile used for the proposed repair. The FSP contends that a comparison of the HR and GCP quotations demonstrate it has fulfilled its obligations regarding matching the tiles as near as reasonably practicable pursuant to policy terms. In addition to this, the FSP argues that there is no evidence to suggest such repairs would be unsatisfactory. 20. The FSP has now agreed to cash settle the Applicants for painting costs based on the Applicants ‟ own quotation for $3,025. 21. The Applicants have requested cash settlement for the plaster repairs in the amount of $6,041 for repairs to the hallway only. In contrast, the FSP has obtained a quotation for $812.18 from HR to repair the hallway and study. 22. The FSP contends the Applicant‟s quotation is for the replacement of plaster to the entire hallway which is excessive as only the damaged portion of the hallway needs repairing. The FSP submits its quotation is fair and reasonable. 23. The FSP submits it has settled the Applicants‟ claim to the extent of its liability. Issues 24. Whether the FSP has appropriately settled the Applicants‟ claim. Reasons for Determination 25. There has been an exchange of material between each party, and I am satisfied each party has had an opportunity to reply to the issues raised. 26. I have read each party‟s submissions and materials and will only refer to the relevant submissions and materials raised. 27. The parties do not dispute the following:  The Applicants had an insured event which caused damage to their property.  The FSP accepted the claim for damage caused by the leaking roof.  The Applicants seek a cash settlement for repairs. 28. I note that the current outstanding items are the lounge ceiling repairs, plaster/painting repairs to the hall, study and lounge room walls and possible extra ceiling batten installation. I shall deal with the ceiling room/batten and the plaster repairs to the walls separately as I consider that each item raises a Case No: 238752 Determination Page 5 of 8 discrete issue. I will also deal with the issue of delay and claims handling separately. 29. I am aware that although the FSP‟s original position was that it could arrange for repairs, it has now offered cash settlement for the items in dispute. Accordingly, I will not address the issue of cash settlement as opposed to arranging repairs as it is no longer an issue in dispute. However, it is important for the Applicants to be aware that when the insured damage is repairable, that the FSP has discretion over whether to arrange repairs or provide cash settlement. The discretion belongs to the FSP and not to the Applicants. Lounge Room Ceiling Repair and potential extra batten installation 30. The Applicants seek the replacement of the entire set of ceiling tiles of the same original size to ensure a match. The Applicants acknowledge that an exact match of the old tile pattern cannot be located. 31. In contrast, the FSP contends that as the ceiling tile is no longer manufactured, that the HR quotation for ceiling repairs which provide a match as near as reasonably practicable to the Applicants‟ existing ceiling is appropriate. 32. The FSP and Applicants have relied on separate clauses of the policy wording to support their respective positions. 33. The FSP notes that it is required to make reasonable endeavours to match materials but may utilise a match to the damaged materials as near as reasonably practicable. 34. The Applicants have noted that the policy terms req uired the FSP to replaced undamaged fixed ceiling coverings if reasonably required to achieve a match. The replacement however is limited to the room where the damage occurred. 35. I have noted that the Applicants have continually stated their policy requires a „like for like replacement‟. This is not precisely the case. The FSP is required to attempt to match the damaged item, but only where reasonably practicable. 36. It appears accepted by the parties that the exact tile pattern is no longer available. 37. According ly, the question before me is whether the FSP‟s proposed method of repair is a close a match as reasonably practicable. 38. I have reviewed the Applicants‟ quotation for the works. The quotation from GCP states it will remove the water damaged insulation and MFT (Mineral Fibre Ceiling Tile) ceiling and reinstate with new insulation and MFT ceiling tiles to match as close as possible. There is no confirmation from GCP regarding whether it will source laser cut tiles to match the size specification of the tiles. 39. The FSP‟s quotation however indicates that the tiles would either be 12mm acoustic ceiling panels or 19mm fine fissured ceiling panels to line the existing battens. Further, additional battens may be required to be installed to accommodate the new ceiling tile size. Accordingly, the FSP may be able to match the acoustic quality of the tile but not the size or pattern of the tile. Case No: 238752 Determination Page 6 of 8 40. The Applicants have not established that laser cut tiles can be sourced and what the individual cost of re-tiling the lounge room ceiling would be. 41. I consider that if the FSP is able to arrange for the same size tiles by laser cutting that this would be the closest practicable match. This would also avoid the need to change the roofing battens. 42. I further note that the tile match is limited to the lounge room in accordance with the policy terms and conditions. Plaster and Painting Repairs to the Hall, study and Lounge Room Walls 43. I have reviewed both the LPD, GCP and HR quotations for repairs. I have also reviewed a quote from GPD in the sum of $3,608 for plaster and painting repairs. 44. There does not appear to be a dispute regarding the LPD quotation. The Applicants only continued to dispute this quotation for painting of the Hall, Study and Lounge-room walls until payment was received. I note that the Applicants have now received a cheque for $3,025 in line with their own quotation from LPD. Accordingly, I consider that as this item of repair has now been paid it has been appropriately settled. 45. In relation to the plaster repairs to the hallway and study, the FSP has received a quotation for $812.18 in writing - albeit by email. I am not troubled by the fact the quotation was received by email given it is clear which company the quote was provided by and the company‟s qualifications to quote for those works . 46. I also note that the GCP quotation appears to provide no reason why the entire plaster needs to be replaced rather than repair. Plaster normally can be repaired and it would be surprising if all the plaster sheets required a replacement. 47. Further, LPD, GPD and HR have both indicated patching of the walls is possible. Given GCP has provided no expert opinion as to why such a measure of replacement is required I do not accept this quote. 48. Given that there is no alternative quotation itemising this work, I accept the FSP‟s quotation in the sum of $812.18 as an appropriate settlement. Delay and claims handling 49. The FSP has essentially argued that it authorised repairs on 10 January 2011 but the Appl icants‟ desire to provide their own quotations extended the time frames. Case No: 238752 Determination Page 7 of 8 50. The FSP has acknowledged that the claim was later delayed whilst it obtained a quotation for the repairs to the lounge-room after the claims decision not to cash settle was confirmed. The FSP has apologised for any distress caused to the Applicant and notes this issue has been forwarded to its claims department for future purposes. The FSP has failed to provide an explanation of what training or procedures it has arranged to prevent this issue occurring again. 51. The Applicants have complained that the carpet would not have required replacement had the carpet dryers been arranged in a timely manner. I have noted the claims file records indicate that the party arranging such matters had the work logged twice with it in the three days. The FSP made enquiries and was informed that: “...TECH CAN ONLY ATT AS FAST AS THEY CAN” 52. I note the Applicants were dis satisfied with the explanation of „catastrophic event‟ making it difficult to obtain carp et driers because the Government had not declared a state of natural disaster. The Applicants should be aware that natural weather events such as strong storms can create a high volume of claims as well as requests for assistance from the authorities such as the SES without the Government being required to declare a state of natural disaster. Each claim to an insurer of course is from a paying customer, such as the Applicants, to whom the FSP must provide assistance based on the available resources. Further, the Applicants have provided no documentary evidence to the Service confirming the carpet driers were in fact available. 53. The Applicants further complained that on 7 December 2010 the FSP told them it would only replace cut out section. In contrast, the FSP has noted in its claims records it would only replace damaged sections. It is possible that a miscommunication has occurred at this point and this should have been cleared up on 15 December 2010 between the parties – according to their respective notes. 54. The FSP has indicated that the Applicants also created difficulties by not allowing repairers into the property or being unavailable. I note the Applicants however have claimed they were at home on annual leave for six weeks and believe the FSP was aware of same. However, I have been unable to locate confirmation the FSP was aware of during the material time in the notations from the parties. 55. It is clear from the materials that the FSP attempted to mitigate any incorrect information provided by its preferred repairers to the Applicants as well. However, it is concerning that this did occur and that the repairers have provided advice in relation to the extent of payment, which is essentially a matter for the claims department of the FSP. 56. Given the issues raised, the Applicants ‟ complaints regarding the FSP ‟s claims handling will be referred to the Code & Systemic Manager to determine whether investigation is required. Case No: 238752 Determination Page 8 of 8 Determination 57. On the basis of the available information, I determine that if the following should occur within 30 days of the Applicants‟ accepting this Determination: (a) The Applicants shall provide the FSP with a written quotation for the sourced tiles and repair to the tiled roof of the lounge- room (“the quotation”). (b) Within 14 days of receiving the quotation, the FSP determine the difference in cost between the amount paid and the amount of the quotation “the difference”. (c) Within 21 days of receiving the quotation the FSP is to pay the difference to the Applicants. (d) If the Applicants are unable to demonstrate within the 30 day period that the sourced tiles are laser cut 1 x 1 foot in size, then the FSP‟s previous settlement of the lounge-room roof repair will be deemed sufficient. 58. I determine that the sum of $3,025 has been paid and this sum constitutes an appropriate settlement in accordance with the LPD quotation for works for painting the study, hallway and lounge-room. 59. I determine that the sum of $812.18 is an appropriate settlement for plaster repairs. 60. This matter will be referred to the Code & Systemic Manager to determine whether further investigation is required.