Text of the determination
Case No: 237897 Determination Page 1 of 12
Case number: 237897
Credit - Consumer Credit - Home Loans - Advice - Failure to provide advice –
Misleading information
21 May 2013
Background
1. This dispute concerns loans the Applicants arranged with the FSP in 2010 to
enable their purchase of land and construction of a house on that land.
2. The Applicants said the FSP misled them by:
a. Not adequately explaining to them its lending processes and that a low
valuation of their land purchase and construction project would
increase the cost of lenders’ mortgage insurance (LMI); and
b. Informing them that taking into account their savings of $26,000 and
entitlement to the First Home Owners Grant (FHOG) of $20,000 they
would need to obtain a loan of $315,000 inclusive of all costs and fees
to meet the total expected cost of $353,500 required to purchase the
land and build their house. It transpired that the sum of $315,000 was
insufficient to meet all of the costs and the figure quoted to them should
have been around $322,000.
3. The Applicants said that on 30 July 2010 they entered into a contract to
purchase land for $191,900 on the basis of an anticipated loan amount of
$315,000. They initially said that if the FSP had provided them with an
accurate figure for the loan they required they would have obtained the funds
from another lender they had made enquiries with (who I shall refer to as
“the other lender”) . They later said that they would not have proceeded with
the purchase of the land.
4. On 18 August 2010 they entered into a loan of $171,251 (the Land Loan) to
purchase the land.
5. While they initially entered into a building contract with GB and paid a $3,000
deposit to that builder, they decided to change builders and on 30 October
2010 entered into a building contract for $164,632 with MH.
6. In early November 2010 they then entered into a loan contract for $312,062
(the Combined Loan) to pay out the Land Loan and provide funds for the
construction of their house. They met the additional costs from their own
resources but said this prevented them from buying a second car and meant
that the male Applicant had to spend four hours each day commuting to and
from work.
Determination
Case No: 237897 Determination Page 2 of 12
7. They said the construction of their house should have been completed by
December 2010 but, because of delays by the FSP, construction did not
commence until November 2010.
8. The Applicants also said the FSP did not appropriately respond to their
complaints.
Conclusions in Recommendation
9. The case manager provided the parties with a Recommendation on the
issues in dispute. The Recommendation was in favour of the FSP in that it
concluded that the FSP was not required to compensate the Applicants
further than it had already in relation to the dispute.
10. In the Recommendation the case manager reached the following
conclusions about the issues raised by the dispute:
a. The Applicants were provided with information regarding the FSP’s
lending process prior to them entering into both the Land Loan and the
Combined Loan;
b. The FSP’s estimate that the Applicants would need to borrow
$315,000, inclusive of all fees and costs, to purchase the land and
construct the house was inaccurate as it did not include the cost of LMI;
c. If the Applicants had been informed of the correct amount of the
contribution they would be required to make and had obtained the loan
from the other lender they had made enquiries with, they would have
paid $154.52 less in interest to the other lender up until August 2012.
However, that ‘loss’ had been sufficiently compensated by the FSP’s
refund of the LMI cost of $670.34 it was entitled to charge on the
Combined Loan and the $250 annual fee it was entitled to charge on
their credit card facility . Because the FSP’s interest rate was lower
than the other lender ’s after August 2012, the Applicants did not suffer
‘loss’ going forward ;
d. The case manager did not accept that the Applicants would not have
proceeded with the land purchase and construction if they had been
informed correctly of the amount they needed to borrow;
e. The case manager was not satisfied that the FSP caused a delay in the
construction of the Applicants’ residence; and
f. While the FSP was outside the timeframes stipulated on the Code of
Banking Practice in responding to the Applicants’ complaint, it
nevertheless responded appropriately by offering the Applicants an
explanation and a resolution to their dispute and ultimately referring
them to FOS.
11. The FSP accepted the Recommendation but it was rejected by the
Applicants.
Case No: 237897 Determination Page 3 of 12
Further submissions
12. When rejecting the Recommendation, the Applicants made further
submissions that can be summarised as follows:
a. T heir complaint has been predominantly about the FSP’s
misrepresentation to them at the outset regarding the total amount they
would need to borrow;
b. They entered into the contract to purchase the land as they believed
they had arranged the finance to do so. They did not believe anything
would affect the purchase unless they changed the figures by reducing
or adding to their deposit;
c. They entered into the Land Loan based on the FSP ’s advice of an
incorrect loan amount which resulted in a loan that did not meet their
objectives;
d. The FSP did not explain why valuations were conducted and did not
advise them of the possible ramifications a low valuation could have on
the cost of LMI. The email exchange in this regard and on which the
FSP relies was after settlement of the land purchase and was far too
late;
e. The other lender they had considered borrowing from disclosed that the
LMI needed to be paid upfront and was not included in any figures or
absorbed into the loan. That lender does not do valuations but goes off
the contract price so they assume that lender’s figures would have
been extremely accurate with no chance of fluctuations by thousands of
dollars;
f. If they had more money at the time and had been provided the correct
loan amount by the FSP, they would not have requested finance from
the FSP ahead of the other lender;
g. However, if they known that the loan amount of $315,000 was incorrect
and the true amount should have been in the vicinity of $322,000, they
would not have purchased the land. They did not have any further
funds that they were willing or able to contribute towards the purchase
at that time. They had to find more money to finalise settlement and
ensure the LMI did not sky-rocket because they needed to keep the
LVR down to achieve this;
h. They felt they had to proceed with the construction of the house as they
were making repayments on the Land Loan and were paying rent. An
officer from the FSP’s complaints departmen t suggested they get the
construction up and running because she agreed that money was being
wasted;
i. They were informed they would have to pay an $8,000 LMI top up if
they added the construction funding to the Land loan. They did not
have the funds to pay that cost and, as a result:
They decided to change builders in the hope that the new
valuation would be higher than the initial valuation, given they
were building a larger home for the same cost. A higher
Case No: 237897 Determination Page 4 of 12
valuation would ensure they did not have to contribute more to a
LMI top up; and
They lost their place in the construction schedule and
commencement of construction was delayed. That delay was
contributed to by the FSP officer with whom they were dealing
not forwarding on the construction contract for some time after
they had delivered it to him;
j. The email from the male Applicant to the FSP (regarding why they
changed builders) was sent because the male Applicant felt they
needed to supply a reason why they were changing builders and he did
not want to offend the FSP’s officer because he felt that if he did the
situation may worsen;
k. The FSP then informed them the top up LMI figure was $3,700. After
they questioned this the FSP realised an error had been made and the
top up figure was reduced to $670.34, which comprised $100 for the
top up amount and $570 for an administration fee;
l. The FSP subsequently informed them that it would sort out the LVR
issue by accepting a higher valuation in comparison to the valuer who
had conducted the valuation of the property. If the FSP had informed
them of its complaints process when they expressed their concerns the
week after the land settlement, the delay could have been avoided
because, potentially, the FSP could have honoured their contract price
at that point and not some months later;
m. They are unsure why the case manager reached a conclusion that they
could have elected not to proceed with the construction of the house.
Their only alternative would have been to sell the land at a substantially
higher amount than they paid for it to cover their costs and they did not
believe this was possible;
n. It was the FSP’s officer who recorded the female Applicant’s marital
status as “Mrs” in July 2010. It was, therefore, the FSP’s error not the
Applicants’ that led to a la ter delay in having this error corrected in the
documentation;
o. They suffered stress because they had to meet mortgage payments
and rental payments. Their plan to purchase another vehicle could not
be achieved which meant that the male applicant suffered health issues
from travelling four hours a day to and from work. They also suffered
anxiety about how they were to obtain the additional money required to
finish off the house when they were considering signing the
construction contract; and
p. Their loss is what they had to contribute over and above what they had
originally agreed to contribute. They believe they should be placed in
the same financial position they had committed to being in. They
committed to spending $26,000 and, therefore, believe that at the very
least the additional amount they paid over and above that amount
should be reimbursed to them by the FSP.
Case No: 237897 Determination Page 5 of 12
Ombudsman’s consideration
13. I have decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous FOS decisions. I have
taken into account all the material submitted by the parties, both before and
after the Recommendation. I am satisfied that the documentation I have
relied on has been provided to both parties.
14. I have carefully considered the case manager ’s Recommendation, together
with the Applicants’ further submissions.
15. I am satisfied that the case manager’s Recommendation contains an
accurate summary of the background to this dispute, the parties’ positions,
the issues to be determined, any applicable paragraphs of the Terms of
Reference and any relevant law.
16. I agree with the case manager’s reasons for the Recommendation and the
recommended outcome.
17. Following my review of the Applicants’ response to the Recommendat ion, I
will address the following issues in this Determination:
a. Whether the Applicants suffered loss because they were misinformed
by the FSP about the funds they would need to borrow or, alternatively,
to contribute to enable their purchase of land and the construction of a
house on that land; and
b. Whether the FSP caused a delay in the construction of the house.
Whether the Applicants suffered loss because of a misrepresentation by the
FSP
18. The Applicants met with the FSP in July 2010. They were trying to work out
how much they could borrow to purchase a block of land and then build a
house. Following on from this discussion, there was a chain of emails
between the FSP and the customer.
19. The parties have provided emails between the FSP’s officer Mr SC and the
Applicants for the period 22 July 2010 to 8 October 2010. An email chain
dated 22 July 2010, contains the following exchanges:
a. At 14.41pm Mr SC sent the following email to Miss R:
“As discussed, below are approximate cost[s] for construction. Also, I would
only proceed with this loan if I can achieve a rate discount of .85% which
based on the standard variable of 7.51% = 6.66%.
In terms of Bank Fees in relation to the mortgage.
$395 annual package fee
$300 progress draw fee to cover the 5 payments to the builder.
Based on a loan amount of $315,000 and security value of $353,500 the
lenders mortgage insurance would be approximately $4,756.50 (this includes
gov[ernment] stamp duty).
Case No: 237897 Determination Page 6 of 12
Separate government fees will apply which I have already provided you with
such as registration and stamp duty”.
b. At 14.51pm, Miss R responded to Mr SC as follows:
“Hi [Mr SC]
Have you absorbed the stamp duty and the mortgage insurance into our
loan?”
c. At 15 .07pm, Mr SC replied saying, “ yes I have ”.
d. At 15.18pm, Miss R responded:
“So just confirming that total loan amount is $315,000”.
e. At 15.25pm, Mr SC replied saying, “ That’s correct ”.
20. The parties agree that there would need to be a valuation and while the FSP
says that it informed the Applicants of the likelihood of a low valuation, there
is no record of it.
21. In cases where an FSP is giving ‘pre - approval’ for a loan, it needs to take
great care in ensuring that their customers understand that the approval is
subject to change. I would expect this to be communicated in the written pre-
approval notification. For example, the written confirmation should include
caveats to the effect that it is guaranteed and is subject to the FSP’s credit
assessment and that the loan amount was dependent on a satisfactory
valuation of a specified amount. The emails in this dispute did not contain
any such caveat.
22. The FSP knew that the Applicants were seeking to buy land and build and it
is reasonably foreseeable that having obtained the pre-approval, the
Applicants would enter into contracts to purchase the land. In my view the
FSP has misled the Applicants.
23. The next question is how much compensation, if any, the Applicants are
entitled to. The aim of compensation for misleading conduct is not the make
the promise come true. That is, it is not to put the Applicants in the position
whereby they have a $315,000 loan and a house. It is often thought that this
should be the remedy but the courts have not agreed with this approach.
Rather the courts have said that the relevant question to be asked is what
could the Applicant have done differently if they were not misled and if they
are worse off because they effectively missed out on the opportunity to do
something different, then they will be entitled to be compensated to the
extent that they are worse off.
24. I appreciate that this is a difficult concept to understand but it is a relevant
legal principle to which I must have regard.
Case No: 237897 Determination Page 7 of 12
25. During the course of this dispute the Applicants have indicated that if they
had known the correct information, they could have done one of two things
differently. They could have decided not to proceed with the purchase or
construction or, alternatively, they would have obtained funding from the
other lender. In their most recent correspondence, the Applicants have
indicated that they would not have proceeded, but it is my view that it is more
likely than not that they would have proceeded using the other lender
because I think they were keen to have their first home. I reach this view
because:
Their alternative was to continue paying rent;
At the time they were entitled to a $20,000 FHOG. It was not known at
that time how long that grant would remain available at that level. In
my view the availability of the grant placed some pressure on first home
buyers to commit to purchasing sooner rather than later;
They were informed at the outset by the FSP that they had a borrowing
capacity of $400,000. Therefore, they knew they could afford to repay
a loan of $322,000;
The Applicants decided to change builders in September 2010 thereby
forfeiting the $3,000 deposit they paid to their first builder. This action
is not consistent with a borrower who is concerned about increasing
their liability by a relatively small amount; and
They initially informed FOS that if they had been provided with accurate
figures by the FSP they would have borrowed funds from the other
lender rather than the FSP.
26. So the Applicant’s loss is worked out by comparing the position they were in
with the FSP with the position they would have been in if they proceeded
using the other lender. In making this comparison however, I will not take
into account the $3,000 the Applicants lost when they moved to the other
builder because I do not regard this cost as one that a person under an
obligation to minimise their losses would reasonably incur.
27. I requested the assistance of the Financial Calculations Specialist in making
this comparison. I note that during the investigation of this dispute the
Applicants provided to this office a quotation that had been provided to them
by the other lender on 21 July 2010. That quotation was for an amount of
$318,000 rather than the $312,062 provided by the FSP. In these
circumstances the Financial Calculations Specialist was asked to use the
figure of $318,000 when calculating whether the Applicants would have been
better or worse off moving to the other lender.
28. The FSP charged the following for Land Loan:
Registration Charges $ 692.10
Stamping Charges $6,584.00
Bank Cheque $ 10.00
Case No: 237897 Determination Page 8 of 12
Annual Package Fee $ 395.00
LMI $3,869.73
$11,550.83
29. In addition the FSP charges for Combined Loan were:
LMI $670.34
Bank Cheque $ 10.00
Progressive Drawdown $300.00
$ 980.30
$12,531.17
less
Refund Stamp Duty 08/10/2010 $ 619.00
Refund LMI 16/12/10 $ 670.34
Net overall amount charged by FSP $11,241.83
30. If the Applicants had decided to proceed with the other lender, then the
following charges would have been incurred:
Stamp Duty $5,920.00 1
Registration Charges $ 792.20
Title Search $ 9.84
Annual Package Fee $ 395.00
Progressive Drawdown say $ 300.00
LMI (based on loan of $318,000) $4,495.22
$11,912.26
31. The App licants’ decision to proceed with the FSP resulted in lower charges
and they saved $670.43.
32. The Banking Specialist also provided an updated table showing a
comparison of the FSP interest rate actually charged on the loans and what
the other lender may have charged , using the other lender’s standard
variable rate less the discount of 0.07%. that the Applicants say they were
offered by the other lender.
1 The other lender ’s calculation indicates a stamp duty on the Transfer of Land of $6,530. However
based on the State Revenue Office calculator for the relevant State, an amount of $5,920 is due on a
purchase price of $191,000.
Case No: 237897 Determination Page 9 of 12
Date FSP Other
Lender
Change RBA CASH RATE MOVEMENTS
Land Loan 05/05/2010 4.5 +0.25
27/08/2010 6.66 6. 54
15/11/2010 6.97 +0.43 03/11/2010 4.75 +0.25
16/11/2010 7.01 +0.35
Combined Loan
15/12/2010 7.01 6.97
07/11/2011 6.7 7 - 0.2 02/11/2011 4.5 - 0.25
14/11/2011 6.76 - 0.25
19/12/2011 6. 52 - 0.25 0712/2011 4.25 - 0.25
19/12/2011 6.51 - 0.25
20/2/2012 6.61 6.6 1 +0.1 / +0.09
14/5/2012 6.24 6.2 9 - 0.37 / - 0 .32 02/05/2012 3.75 - 0.5
18/06/2012
08/10/2012
10/12/2012
13/05/2013
20/05/2013
6.04
5.86
5.66
5.41
6.0 8
5.88
5.68
5.43
- 0.2 / - 0.21
- 0.18 / - 0.2
- 0.2 / - 0.2
- 0.25
- 0.25
06/06/2012
03/10/2012
05/12/2012
08/05/2013
3.5
3.25
3.00
2.75
- 0.25
- 0.25
- 0.25
- 0.25
33. Therefore, the overall position of the Applicants accepting the FSP loan
compared to accepting the other lender’s loan can be summarised as
follows:
FSP loan Establishment charges $11,241.83
Estimated other lender charges $11,912.26
Benefit by choosing the FSP $ 670.43
Less
Interest differential to February 2012 $ 154.52
Net benefit for choosing FSP $ 515.91
34. On a simple calculation basis, since February 2012, the difference between
FSP and other lender’s interest rates is approximately 0.02%. Based on a
loan amount of $318,000 this equates to $63.60 per annum
Case No: 237897 Determination Page 10 of 12
35. In other words, if the Applicants had decided to proceed with the other lender
in preference to the FSP then they would have been worse off. It follows
that when assessing compensation for misleading conduct and having
regard to the legal principle that you ask what would the Applicants have
done differently if they were in possession of the correct information and how
much better or worse off were they as a result, then the answer is that the
Applicants have not in fact suffered any loss as a result of the
misrepresentation.
Whether the FSP caused a delay in the construction of the house
36. The Applicants say that they lost their place in the construction schedule
after they were informed they would have to pay an $8,000 LMI top up when
they added the construction funding to the Land Loan and they could not
afford that cost. They say that it was because of the quoted cost of LMI they
changed builders in an effort to increase the valuation of their property and,
consequently reduce the cost of LMI.
37. I have reviewed the documentation and note the following sequence of
events took place in relation to the Applicants ’ dealings with their new
builder:
The Applicants obtained a quotation for construction of the house from
the new builder on 26 September 2010;
On 30 September 2010 a $2,000 debit in favour of the new builder
appears on their credit card; and
On 30 October 2010 they entered into a contract with the new builder.
38. My review of the documentation in relation to a LMI cost of $8,000 discloses:
On 7 October 2010 the female Applicant sent an email to the FSP’s
officer with whom she had been dealing saying that she “had a call
from [the FSP’s mortgage area] yesterday . . . they also said our
mortgage insurance would be $8,000. That is not right.”
In his response email on the same day the FSP’s officer said:
“With regards to your conversation with the [mortgage area] y esterday,
the total mortgage insurance premium was in fact approx $8000
however what they may not have told you was the actual Top Up
premium was only approx just over $4000 (remember you have already
paid approx $3750 )” .
39. These records indicate that the Applicants committed to the new builder by
paying a $2,000 deposit prior to being quoted an LMI cost of $8,000. In
these circumstances, I do not accept that they changed builders because
they were informed they would be required to pay a top up premium of
$8,000.
40. I am further persuaded in this view by the following:
Case No: 237897 Determination Page 11 of 12
In the male Applicant’s email to the FSP on 7 October 2010 he stated
that they had change builders because the first builder had “made
variations to [their] initial agreement which [they] were unable to
resolve”;
In an email to the FSP on the same day the female Applicant said that
the new valuation “should not come back lower than the valuation done
for the [initial building contract]”. This comment does not indicate an
expectation that the new valuation would be for a higher amount; and
They forfeited a $3,000 deposit paid to their first builder without any
basis for an expectation that the new valuation would be higher,
particularly given the price of both building contracts was almost the
same.
41. I also note in relation to LMI that on 22 October 2010 the FSP informed the
Applicants in an email that the actual top up fee of $670.04 for LMI (which
appears to have been revised down from the earlier figure quoted) would be
refunded to them “as a gesture of goodwill ”.
42. The documentation indicates that the Applicants signed the contract with
their new builder on 30 October 2010. It seems to me that the delay in
commencement of construction arose primarily because of the Applicant’s
decision to change builders. As indicated above, I am not satisfied that
decision arose because of any errors made by the FSP.
43. In regard to the Applicants’ contention that the female Applicant was referred
to in the initial documentation as ‘Mrs’ rather than ‘Miss’ and the need to
have new documents prepared caused delay, I have reviewed the
documents and note that on the application form the Applicants signed on 18
July 2010, the female Applicant was described as being ‘Mrs’. I also not that
on the initial FHOG application the Applicants signed on 1 November, 2010.
the female applicant crossed out and initialled where she had originally
noted her status as ‘Miss’ and recorded her status as ‘Mrs’. In these
circumstances, I consider that the Applicants must take responsibility for
failing to correct any errors in the recording of the female A pplicant’s marital
status and any delay that resulted from that.
Conclusion
44. I have considered the further information, but it does not change my view
that the case manager’s Recommendation was correct.
Case No: 237897 Determination Page 12 of 12
Determination
45. I determine in favour of the FSP.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.