Home / Financial Firm (Unknown - Insurer) / Determination 237452

Determination 237452

Home destroyed by ground movement after heavy rain, claim denied under landslip exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2011-10-10
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$280,000
Non-financial loss—
Amount claimed$562,410
SourceAFCA PDF

Summary

The applicant's home was rendered unrepairable by ground movement after heavy December 2010 rain, and the FSP denied the claim under the landslip exclusion. The Panel found the rain fell within the storm and flash flood cover, split the loss equally as fair in all the circumstances, and ordered the FSP to indemnify up to the $280,000 Terms of Reference limit with interest under section 57 of the Insurance Contracts Act.

Applying the FOS Terms of Reference 8.2 fairness discretion, the Panel treated the rain-triggered flash flood and the pre-existing slope predisposition as consecutive rather than concurrent causes and so split the loss equally, capped at the $280,000 limit.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 237452 Determination Page 1 of 8 Case number: 237452 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim – Landslip – Storm – Proximate cause 23 September 2011 Background 1. On 20 December 2010 the Applicant lodged a claim under his household insurance policy for damage to his home. The Applicant had woken on the morning of 20 December after heavy rain to discover decking between the house and the garage had shifted and was out of alignment. 2. The house continued to move to the extent that it became uninhabitable and eventually was to be demolished. The Applicant‟s claim is for $562,410. 3. The Financial Services Provider (FSP) denied liability for the claim on the ground that the damage was caused by landslip which is specifically excluded from cover provided by the policy. Summary of Applicant’s Position 4. The Applicant contends that the cause for the damage was storms in the area which is covered by the terms of the policy. 5. The total amount of rainfall from 1 to 20 December was 389mm with 155.8mm falling from 17 to 20 December being 40% of the rainfall to 20 December. From 22 to 29 December a further 198mm of rain fell. 6. In his opinion the proximate cause of the loss was either directly or substantially caused by the storms and torrential rainfall experienced during December 2010. The landslip that damaged the home was caused by rainwater and so does not break the chain of causation between the storms or rainfall and his loss. 7. The Applicant draws attention to use of the word „landslip‟ in the expert reports as the cause of the damage and not „landslide‟ which is excluded from the cover provided by the policy. The Applicant argues any ambiguity arising from the meaning of the word used by the experts and the meaning of the word contained in the policy must be read against the FSP. The Applicant notes that landslip is not included within the general exclusion in the policy. Determination Case No: 237452 Determination Page 2 of 8 Summary of FSP’s Position 8. The FSP relies substantially on engineering reports commissioned by it. Engineer “C” was of the opinion that the damage was caused by landslip ultimately caused by ground water. The engineer considered the dominant source of water impacting on ground water and seepage was the natural infiltration and seepage from the rainfall events proceeding and during the slip. 9. The FSP relies on the following policy provisions: “Words/terms with special meanings Storm A violent disturbance of the atmosphere associated with strong winds, including a cyclone, lightning, heavy rain, hail or snow, but not continuous bad weather by itself. … Insured events you are covered for Damage caused by weather … What is covered Storm What is not covered Loss or damage … x caused by rain, hail or snow after it has reached the ground What is covered Flash flood and stormwater run-off A sudden flood caused by heavy rain that fell no more than 24 hours prior to the flash flood or storm water run-off … When you are not covered – general exclusions Exclusions When you are not covered … Erosion, landslide erosion, landslide, subsidence, earth movement (except earthquake), earth shrinkage or expansion no matter how caused. 10. The FSP submits that case law applies in the event the proximate cause for the loss was either by rain, landslip/landslide or a contribution of both. 11. The FSP argues that the rain itself did not cause the damage but the landslip did. As such there is overwhelming argument the rain was not the proximate cause. 12. The FSP submits that the land on which the house was situated had a landslip in 1981. The slope was vulnerable and due to saturation over a lengthy period of time the failure of the slope was a classic example of a landslide and the proximate cause of the damage. 13. The FSP refers to Brighwall Home Units Pty Ltd v United Insurance Co Limited, the United States High Court of Appeals Fifth Circuit in West v Harriss and Case No: 237452 Determination Page 3 of 8 Stewart & Anor v Preferred Fire Insurance Company Kan 477 2d 966 to argue that the exclusion concerning landslip operated to preclude the Applicant from an entitlement to indemnity under the policy. Issue 14. Whether the FSP was entitled to deny the claim on the ground that the damage was caused by landslip. Reasons for Decision Jurisdiction 15. The FOS Terms of Reference provide: “3.2 Disputes lodged with FOS between 1 January 2010 and 31 December 2011 Where a Dispute is lodged with FOS between 1 January 2010 and 31 December 2011: a) the amount that may be awarded by FOS in relation to a claim made in the Dispute will be determined in accordance with Schedule 1, … 5.1 Exclusions from FOS‟s jurisdiction The Service may not consider a Dispute: … o) where the value of the Applicant‟s claim in the Dispute exceeds $500,000 … Schedule 1 … Type of claim Amount of claim … 5. Other $280,000” 16. Notwithstanding the financial limits set out in the Terms of Reference, the FSP has agreed that the Applicant may refer his dispute to FOS subject to FOS not exceeding the $280,000 limit imposed by the Terms of Reference. The Applicant has agreed to FOS considering the dispute on these terms. 17. As advised to the Parties, FOS has considered it appropriate to expedite the dispute in accordance with the FOS Operational Guidelines to the FOS Terms of Reference. This is because of the complex nature of the issues. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. Case No: 237452 Determination Page 4 of 8 18. This decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in insurance industry matters and a representative with extensive experience in consumer claims. 19. The Panel is satisfied that there has been an exchange of material between the parties. Each party therefore has had the opportunity to comment on the issues presented to FOS. 20. When making a claim under an insurance policy the responsibility rests with the policyholder to establish on the balance of probabilities that the cause for the loss falls within the cover provided by the policy. An FSP relying on a clause in the policy to deny the claim then has the burden of establishing on the balance of probabilities that the terms of the relevant clause apply to defeat the claim. 21. Prior to arriving at a Determination the Panel has read and considered the material submitted by both parties. 22. The circumstances of the Applicant‟s loss are clearly documented and not in dispute. The house suffered damage to the extent that it is unrepairable as a result of movement of the house after heavy rains had been experienced in the area over a period of time. 23. The evidence presented refers at various times to “landslide” and “landslip” . However for the sake of clarity it is noted that a consultant engineer involved in assessing the cause confirmed that the terms “landslip” and “ landslide ” are interchangeable. The consultant is a qualified geotechnical engineer. As such to the extent that these terms are relevant to this dispute, the Panel considers the terms “landslide” and “landslip” to be interchangeable for the purposes of the application of the policy. 24. The rain fall charts produced by the Bureau of Meteorology confirm that for the month of December 2010 the mean rainfall for the Sunshine Coast Airport site was 157.9mm and for Maroochydore rainfall for 17, 18 and 19 December 2010 was respectively 73.6mm, 5.4mm and 51.8mm. 25. The policy defines „storm‟ to include „heavy rain‟ . It does not limit the period of heavy rain to a specific period. The policy then goes on to exclude “ continuous bad weather by itself”. The Panel finds the term „bad weather by itself‟ to be unclear and confusing. “Bad weather” may reasonably be regarded to include all the elements of weather specified in the preamble of the definition so that bad weather may include strong winds, cyclones, lightning, heavy rains, snow and hail either individually or collectively. The very nature of heavy rain may reasonably be regarded as bad weather. 26. The intensity of rainfall over the southern and south western area of the State during the December 2010/ January 2011 period has been well documented by the media and was responsible for widespread flooding causing extensive damage to infrastructure and property. Case No: 237452 Determination Page 5 of 8 27. The Panel therefore is of the opinion that the heavy rainfalls experienced in the area of the Applicant‟s home during December 2010 fall within the definition given by the policy to „storm‟. 28. Further, while the policy states that loss or damage caused by rain after it reaches the ground is not covered, the FSP in considering the proximate cause for the damage included rain in its deliberations as a contributing factor. 29. However, the Panel also notes that the event “Flash flood and stormwater run - off” is covered by the policy, which is defined as “a sudden flood caused by heavy rain that fell no more than 24 hours prior to the flash flood or stormwater run- off”. By its very nature this provides cover for stormwater run -off after the rain has reached the ground. 30. The Panel is somewhat perplexed by the contradictory nature of these two insured events, firstly that „rain‟ is covered as storm, although rain „after it has reached the ground‟ is excluded, but then, stormwater (including rain) is covered on the ground when it has resulted in flooding (within 24 hours). 31. In the Panel‟s view, this could give rise to confusion for policyholders a nd brings into question whether, in certain circumstances, the FSP has fully discharged its „clearly inform‟ mandate. 32. However, the Panel will consider this dispute on the merits of the evidence and reasonable interpretation of the cover provided by these i nsured events. 33. The first issue for the Panel to consider is the proximate cause of the damage and whether such cause is provided for under the policy or whether it is excluded under the policy. 34. In this regard consultant engineer “C” commissioned by the FSP to provide an opinion on the cause for the distress to the building provided the following information: Report dated 4 January 2011  a report by that company in 1981 included plans showing an existing landslip on the site at that time.  the site was in a previously identified slip.  there were indications of previous distress in the roadway above the site.  seepage was evident above the site as well as below.  the slip occurred following a period of prolonged rainfall. Report dated 21 January 2011  the slip at the Applicant‟s site was a textbook rotational slip failure.  rotational slips are associated with ground water and the pressures exerted by ground water in the pores in the soil. Case No: 237452 Determination Page 6 of 8  the cause for the landslip was complex involving a number of factors. These include soil strength, drainage conditions, antecedent soil moisture conditions and the volume and intensity of particular rainfall events.  there was little doubt while the antecedent conditions allowed the slip to occur the high rainfalls in the few days immediately preceding the slip resulted in increased soil moisture and pore pressure and ultimately caused the soils to slip. 35. The engineer was of the opinion that  “the site was predisposed to slip due to its slope, topography, soil type and previous history  The antecedent rainfall conditions had led to high soil moisture prior to the slip  The increase in soil moisture and soil pore water pressures triggered the slip  The dominant source of water impacting on soil water conditions was infiltration of heavy rainfall immediately preceding the slip  The damage may have been less had an appropriate geotechnical investigation and footing design been undertaken” 36. Engineer “JC” commissioned by the FSP to comment on the likely cause for the damage noted the cause for the damage was landslip resulting in the supporting timber poles moving down the slope with the soil mass. The engineer referred to engineer “C‟s” reports in relation to the failure of the ground. 37. The Applicant states the property was purchased by him in 1997 and that it was about seven years old at that time. He had lived there since that time. It had not been subject to any extensions or renovations and had been well maintained. He did not report any evidence of landslip during that time. 38. It is not disputed that the predisposition of the ground on which the home was constructed was a factor in causing the landslip and in turn the damage claimed by the Applicant. It is important to note however that there was no evidence of slip in approximately the 20 years since the house was constructed or indeed since the engineer‟s 1981 report (being approximately 29 years ago) until about 20 December 2010 when the damage occurred. 39. Of particular note is that “ C ” reported “the site was predisposed to slip due to its slope, topography, soil type and previous history ” however it is not disputed that there was no history of landslip since the house was constructed. 40. Further, he noted that “ The antecedent rainfall conditions had led to high soil moisture prior to the slip ”, w hich seems to refer to the storm conditions during December 2010. Therefore it appears the event of “storm” was a significant factor in that it resulted in the property being immediately predisposed to damage. 41. Importantly engineer “ C ” considered “ The dominant source of water impacting on soil water conditions was infiltration of heavy rainfall immediately preceding the slip” . Case No: 237452 Determination Page 7 of 8 42. In considering the application of the policy terms, the Panel is of the view that there is no evidence that the underlying predisposition of the site has caused the loss, that is, there was no spontaneous landslip. Clearly there has been an intervening cause(s). 43. It is noted that “Storm” was a contributing factor, although the FSP seeks to rely on its exclusion, insofar as rain is no longer covered once it has reached the ground. 44. A site visit was conducted by the Panel Ombudsman in this matter to assist in determining this dispute. The Applicant advised that at the relevant time the rain was very heavy. The soil was saturated and the water running across the Applicant‟s property from the property acro ss the road and down the road. According to the Applicant the damage to the property occurred as the garage started to move, thereby attempting to disengage itself from the house. The initial assessor had commented that it would be good to get the garage away from the house; however the FSP did not take any action in this regard. The FSP‟s representative advised that structural engineers had stated that the garage could not successfully be disengaged. This representative could not say when this was communicated to either herself or to the Applicant. She merely maintained that she had had a “conversation”. She could not recall when that conversation had taken place. The Panel notes an email dated 12 January approximately 20 days after the event, includes comments by the FSP‟s representative that she was „checking with respect to the garage‟. In view of the content of this email it is reasonable to assume that no conversation took place with the Applicant (as earlier alleged) nor did the FSP‟s representative take any action towards having an assessment conducted as to the feasibility of disengaging the garage from the house prior to that date. Given the seriousness of the Applicant‟s situation, h is expressed concerns and the risk faced, the Panel is of the view the FSP‟s representative has not acted appropriately at that time and this may have contributed to additional damage to the property. 45. Notwithstanding the above finding, the Panel however recognises that the property, no matter what action was taken by the FSP, would of necessity required demolition. 46. However, having carefully considered all of the technical evidence the Panel is inclined to the view that the proximate cause of the damage, on the balance of probabilities was the substantial and heavy rainfall immediately before the slip. 47. In considering this dispute, the Panel must have regard to what is fair in all the circumstances having regard to the terms of the policy, good industry prac tice, relevant legal principles and prior Determinations although not binding. 48. In this respect the Panel notes in a prior Determination 42429 consideration was given to the question of cause and effect. In that dispute landslip occurred and caused damage to a home. Landslip was excluded under the policy. The property had been inundated by an extraordinary downpour of rain immediately prior to the landslip. The Panel noted in that case that the engineer found that the high volumes of rainwater caused the movement of the soil. In that dispute Case No: 237452 Determination Page 8 of 8 the Panel found after applying the principles of cause and effect, that the dominant or proximate cause of the Applicant‟s loss was caused by storm and the high volume of rain produced thereby. 49. In this dispute the period of heavy rainfall is encapsulated by the definition of „flash flood and stormwater run - off‟. The effect of the substantial run -off of water appears to have been the immediate cause of the house movement. From that point on, given the nature and connectedness of the construction, the house was doomed. 50. Although the heavy rainfall in the days leading up to the loss has contributed by predisposing the property to potential loss, it was ultimately the flash flood/stormwater run-off which triggered the damage. I n the Panel‟s view these events could be considered as consecutive rather than concurrent. 51. On this basis the principle of “Wayne Tank” does not apply. Rather the Panel is of the view that such a situation should be properly addressed by use of FOS Terms of Reference 8.2 which requires the Panel to determine an outcome which is „fair in all the circumstances‟. 52. The Panel is of the view that a fair outcome in all the circumstances is that each party bear half the cost of the loss. 53. The Terms of Reference referred to earlier in the determination limit the amount that may be awarded by FOS in relation to a claim made to the sum of $280,000. As half of the cost to reinstate the building is in excess of $280,000, the amount which the Panel may award is limited to $280,000. 54. Given that the estimated cost of this loss is estimated to be in excess of $560,000 the Panel determines that the FSP is required to indemnify the Applicant to the extent of this applicable limit, that is $280,000. Determination 55. Having regard to the available material and to what is fair in all the circumstances the Panel determines that the FSP is responsible to indemnify the Applicant to the extent of the limit of the FOS Terms of Reference, being $280,000 and further the FSP is to pay interest in accordance with section 57 of the Insurance Contracts Act from 18 February 2011 being the date of the FSP's IDR letter, to settlement of the claim.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.