Determination 237203
Cyclone claim delays; six months premium refund sought
Summary
The insured's cyclone damage claim was settled after significant delays, and she sought six months of premium back. AFCA found the handling delayed and poor, and ordered $250 for non-financial loss, but no premium refund.
Catastrophe pressure explains some delay, but the insurer's poor communication and the unusual inconvenience justify only modest compensation under clause 9.3(b) of the Terms of Reference.
Issues
- Delay primary · upheld“There was a gap of 7 weeks between the inspection of the property by the adjusters, and any response to the Applicant.”
- Poor communication secondary · upheld“After several calls from the Applicant to the FSP, the Applicant was apparently told to contact the adjusters herself. This is bad practice.”
Subjects and remedies
home or building damagenatural disasterpay non financial loss
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Case No: 237203 Determination Page 1 of 4
Case number: 237203
General Insurance - Domestic Insurance - Home Building - Service - Delay in
claim handling
22 March 2012
Background
1. The Applicant and her husband are insured with the Financial Services
Provider (FSP) in respect of a home building and contents insurance policy.
The relevant period of insurance is 26 November 2010 to 26 November
2011.
2. The Applicant lodged a claim under the policy as a result of damage caused
by Cyclone Yasi on or around 2 February 2011. The FSP appointed a loss
adjuster to attended the property and report on the damage. The inspection
took place on 18 February 2011.
3. It was noted there was some damage to contents and damage to the
building which included a shed and fencing. The loss adjuster estimated the
total damage to be $10,610.
4. On 18 March 2011, the Applicant registered a dispute with the Service
regarding the delay in the settlement of her claim.
5. On 26 May 2011 the loss adjuster confirmed that repairs to the building and
payment of contents finalised. However the fence had not been repaired at
that time. The FSP then cash settled the Applicant for the cost of repairing
the fence in July 2011.
6. The Applicant has referred this matter to the Service as she was dissatisfied
with the FSP’s service and handling of the claim.
Summary of Applicant’s position
7. The Applicant says there was a time delay in the assessment notification to
the FSP, a lack of communication as well as a disinterest in effecting repairs
in a timely fashion.
8. The Applicant says she believes the delays in the processing of her claim
were unreasonable due to the FSP and its representatives ’ failure to
effectively manage the claim.
Determination
Case No: 237203 Determination Page 2 of 4
9. The Applicant has asked that the FSP make available customer service
guidelines available that indicate what is expected for information exchange
and outcomes of decisions and timeframes.
10. The Applicant has asked for compensation by way of reimbursement of 6
months of the insurance premium to cover the time delay in the rectification
of the property.
Summary of FSP’s position
11. The FSP does not dispute there were delays in the settlement of the claim.
12. It says at the time the Applicant’s claim was lodged, resource s were
stretched not only across Queensland but other states.
13. The FSP apologises to the Applicant for the delays and says it will provide a
letter addressed directly to her.
14. It says it is currently reviewing its response to catastrophes and how best to
respond to high numbers of claim, heavy demands of recourses and lack of
service providers.
15. The FSP says the Applicant paid a premium which provides for the repair or
replacement and that it has responded accordingly in this claim. It does not
believe the Applicant has suffered a loss that would warrant a return of six
months premium.
Issues
16. Whether the FSP is obliged to refund the Applicant any insurance premium
due to its handling of the claim.
Reasons for Decision
17. FOS has considered it is appropriate to expedite the dispute in accordance
with clause 8.6 of the FOS Terms of Reference. This is because of the
issues in dispute. This dispute has not been the subject of a FOS
Recommendation and has proceeded directly to Determination.
18. There has been an exchange of material between the parties. It therefore is
not intended to recite details of the various reports in this Determination
except where considered relevant.
19. The Applicant has provided a time line of the claims process. The Applicant
accepts that delays in assessment and repairs were inevitable under the
circumstances of the combined flood and cyclone disasters in Queensland.
Case No: 237203 Determination Page 3 of 4
20. The Applicant submits the FSP did not have adequate plans in place to deal
with the very disasters that it offers protection for.
21. I note the Applicant is seeking customer service level statements that would
outline expectations. The Applicant is also seeking compensation in the form
of the return of six months premium for delays during the claims process.
22. The Services’ Terms of Refe rence allow for compensation to be awarded for
both direct financial loss and non-financial loss but this is restricted to
$3,000. Under clause 9.3(b) non-financial loss will only be awarded where:
(i) an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant’s expectation of
enjoyment or peace of mind has occurred; or
In the case of a Dispute pertaining to an individual’s privacy rights –
injury has occurred to the Applicant’s feelings or humiliation has been
suffered by the Applicant.
23. The FSP does not dispute there was a delay and that its normal service
timeframes which accord with the General Insurance Code of Practice were
not met. However, it says this does not warrant the return of six months
premium as it has ultimately responded to and settled the claim.
24. I acknowledge that the catastrophes that impacted Queensland and other
states affected the whole insurance industry. The catastrophes put a great
deal of pressure on insurer’s claim s handling processes and resources.
25. Under the General Insurance Code of Practice, section 4 sets out an
insurer’s obligations regarding responding to catastrophes and disasters. I
note clause 4.3 indicates insurers may not be able to meet all standards of
the Code following a catastrophe and disaster.
26. There are however several issues which require comment.
27. There was a gap of 7 weeks between the inspection of the property by the
adjusters, and any response to the Applicant as to the outcome from that
inspection.
28. After several calls from the Applicant to the FSP, the Applicant was
apparently told to contact the adjusters herself.
29. This is bad practice and even under the pressures imposed upon the FSP
and other insurers it should never have happened.
30. I also note that from the date of the inspection by the adjusters until the
repairs for the fence were completed, some five months elapsed. The fence
was of vital importance because the Applicant and her husband had two
dogs which had to be kept within boundaries.
31. As a result the Applicant and her husband spent many hours, and no doubt,
some monetary expense in erecting a temporary fence.
Case No: 237203 Determination Page 4 of 4
32. Although there was some delay with the claim, which I do not consider to be
unexpected due to the number of claims lodged with insurers resulting from
the catastrophe events, the FSP did meet its obligations to the Applicant
under the terms and conditions of the policy, save as to the matters I have
referred to in the preceding paragraphs.
33. Taken into account the circumstances of events that occurred, as well as
considering the extent of the Applicant’s loss I am satisfied tha t
compensation should be awarded to the Applicant, in the sum of $250
pursuant to clause 9.3(b).
Determination
34. On the basis of the available information I determine the FSP is obliged to
pay to the Applicant the sum of $250.