Home / Financial Firm (Unknown - Insurer) / Determination 237015

Determination 237015

Quality and handling of storm repairs; balcony water damage claim denial

FirmFinancial Firm (Unknown - Insurer)
Decided2013-06-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$1,500
Amount claimed—
SourceAFCA PDF

Summary

The executor of a deceased homeowner complained about storm repairs, delays, a balcony claim denial and other items. AFCA ordered the master bedroom ceiling restored to its original height, paid $427.50 interest and $1,500 non-financial loss, and upheld the balcony denial.

The insurer must restore the home to its pre-loss condition, but the balcony damage was gradual deterioration and a structural defect excluded under the policy, and hospital co-payments were not alternative accommodation.

Issues

Subjects and remedies

deceased estatehealth or medicalpay interestpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 237015 Determination Page 1 of 16 Case number: 237015 General Insurance - Domestic Insurance - Home Contents - Service - Delay in Claim Handling - Dispute Over Handling of Claim and Repairs 30 May 2013 Background 1. The Applicant is the estate of the late “JB”, represented by JB’s daughter “AR” as executor. JB held a home and contents insurance policy with the Financial Services Provider (FSP) from 17 September 2008. 2. On 4 February 2011, JB’s home was damaged as a result of a storm and she subsequently lodged a cl aim with the FSP (the “initial claim”). The FSP accepted the initial claim and made arrangements for repairs to the building and repair/replacement of damaged contents. 3. JB was seriously ill at the time of the storm, her health subsequently worsened and she passed away in early March 2012. AR assisted her mother in dealing with the initial claim during JB’s illness and has continued to handle it as executor of JB’s estate. 4. Both JB and AR were dissatisfied with a number of aspects of the FSP’s handling of the initial claim. 5. The FSP has acknowledged that JB and AR experienced some difficulties in the course of its handling of the initial claim, but is of the view that the initial claim has now been satisfactorily resolved. However, AR remains dissatisfied with both the handling and the resolution of the initial claim. 6. In May 2012, the Applicant sought indemnity from the FSP in relation to water damage to the balcony of the home (the “balcony claim”). The balcony claim was denied by the FSP and the Applicant has disputed the denial. The parties have agreed that the denial of the balcony claim should be dealt with as part of the current dispute. Summary of Applicant’ s position 7. As outlined above, AR is JB’s daughter and the executor of her estate. For the sake of brevity, JB and AR will hereafter be referred to as “the Applicant”, except where it is necessary to distinguish between them for the purpose of clarifying certain factual matters. Determination Case No: 237015 Determination Page 2 of 16 8. The Applicant says that the FSP has made innumerable errors in the handling of the initial claim through its actions and the actions of its agents, which it has failed to satisfactorily address. 9. The issues raised by the Applicant include the quality of repairs, the approach taken in relation to damaged contents, repeated delays in progressing outstanding issues, an inadequate level of service by the FSP and its agents and the unsatisfactory management of complaints by the FSP. Overall, the Applicant contends that the handling of the initial claim by the FSP has not been of a standard commensurate with reasonable expectations. 10. In relation to the balcony claim, the Applicant considers that the damage was caused by the water overflowing from roof gutters during periods of heavy rainfall, and disputes the FSP’s denial of the claim. 11. The Applicant seeks:  full reinstatement of the home to the condition it was in prior to the loss (including indemnity for damage to the balcony discovered in May 2012);  full reimbursement of temporary accommodation expenses and interest for delayed reimbursement of other expenses; and  compensation for the excessive and repeated delays and other difficulties encountered during the claim process. 12. The Applicant has repeatedly sought a full investigation by the FSP into its management of the claim, but acknowledges that this is outside the scope of the remedies currently sought from the Service. Summary of FSP’s position 13. The FSP accepts that the handling of the claim has been less than ideal and that JB and AR have experienced some difficulties, delays and inconvenience, particularly as a result of the initial repair work not being completed to the required standard. 14. The FSP suggests that it has taken steps to accommodate JB’s illness throughout the claim process (within the scope of the policy) and has addressed any issues raised in a timely manner. It is of the view that, following rectification of the initial repair work, and settlement of certain other outstanding issues, the matter has been appropriately resolved. 15. The FSP relies on the following policy provisions: Page 9 of the Product Disclosure Statement (PDS) “ How much we will pay ... Case No: 237015 Determination Page 3 of 16 If your buildings are damaged or are a total loss, the amount we will pay will be the total amount required to repair or rebuild your home to the condition it was in just before the loss or damage occurred, but not better, and this will not be limited to the sum insured. ” Pages 11-14 of the PDS “ When your buildings are protected (continued) ... Event We will cover We won’t cover Storm, rainwater, flood or wind Loss or damage as a result of:  storm (including named cyclone)  rainwater  flood, or  wind Water entering your buildings:  through an opening made for any building, renovation or repair work  because of a structural defect, faulty design or faulty workmanship. ... ... Water or liquid damage Loss or damage caused by water or liquid escaping from:  a fixed pipe or an object attached to a pipe, fixed gutter, fixed tank or a drain  ... Your buildings for loss or damage caused by water or liquid entering your buildings:  through an opening made for any building, renovation o r repair work  because of a structural defect, faulty design or faulty workmanship. ...” Page 15 of the PDS “ Additional buildings benefits ... Additional Benefits We will cover We won’t cover Alternative temporary accommodation (including for pets) Costs for alternative accommodation for up to 12 months if your buildings suffer loss or damage and you are We will not cover this, if you do not need to pay for alternative accommodation. Case No: 237015 Determination Page 4 of 16 unable to live in your home as a result. The loss or damage must occur as a result of an event we have agreed to cover. We will pay:  up to an amount that is equal to the weekly rental value of your buildings before the event occurred, and  the reasonable costs of alternative accommodation for your pets. The maximum amount we will pay is up to 10% of the buildings sum insured, as shown in your Schedule. ...” Page 30 of the PDS “ When your contents are protected (continued) Event We will cover We won’t cover Storm, rainwater, flood or wind Loss or damage as a result of:  storm (including named cyclone)  rainwater  flood, or  wind. Water entering your buildings:  through an opening made for any building, renovation or repair work  because of a structural defect, faulty design or faulty workmanship. ... ...” Pages 50-51 of the PDS “ How we settle a contents claim We will decide how we settle your claim If your contents suffer loss or damage, we will decide whether to:  repair an item Case No: 237015 Determination Page 5 of 16  replace an item or  pay you the cost to replace or repair the item. ... If we decide to replace your contents We will replace the item with the nearest equivalent new item. If the item we are replacing is part of a pair, set, collection or system of items, we will only replace the damaged or lost item itself. ... If we decide to pay you the cost to repair or replace your contents We will pay you the fair and reasonable cost we would have incurred to repair or replace the damaged or lost item...” Issues 16. Whether the FSP has settled the Applicant’s claims appropriately. 17. If not, to what extent the FSP should make any further payment or undertake any further work in order to settle the Applicant’s claims appropriately. 18. Whether the Applicant is entitled to compensation for non-financial loss incurred as a result of the FSP’ s handling of the matter. Reasons for decision 19. I am satisfied that a full exchange of the relevant information has taken place between the respective parties and that each party has had the opportunity of addressing any issues raised. 20. Due to the nature of the dispute, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. Therefore, this dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. The parties have been previously advised that a Determination will be issued in this case. 21. The parties have made multiple, lengthy submissions to the Service addressing numerous issues. Many of the issues that were originally part of the dispute have since been resolved and others are not directly relevant to the outcome. Accordingly, only those issues which remain outstanding and which are directly relevant to the outcome will be addressed in this Determination. 22. I accept that the standard of the initial repairs, the time taken to rectify them, the level of service and the general management of the initial claim by the FSP has been less than ideal. I do not intend to itemise each instance where such problems occurred except where directly relevant for the purposes of Case No: 237015 Determination Page 6 of 16 this Determination. However, it is clear that both JB and AR were distressed by these difficulties, particularly given JB’s serious health issues. 23. In light of these issues, the handling of the Applican t’s claim has been difficult for those involved, particularly AR, given that JB passed away while repairs were still being completed and the parties remained in dispute. 24. I will now consider in turn each of the issues which remain outstanding between the parties, based on their submissions to the Service. Master bedroom ceiling 25. The ceiling in the master bedroom was damaged by water entering the property as a result of the storm and needed to be replaced. 26. The Applicant says that a replacement ceiling was constructed out of plasterboard (rather than the original lathe and plaster) and installed at a lower height than the original ceiling. Based on advice from AS’s architect, this is detrimental because the ceiling is now lower than the ceilings of neighbouring rooms and will need to be restored to its previous height before renovations can be undertaken. 27. The Applicant submits that the repair was not carried out properly as the ceiling was not restored to its pre-loss condition, as required under the policy. T he Applicant’s primary concern is the height of the replacement ceiling. 28. The FSP does not deny that the replacement ceiling has been installed at a lower height than the original but contends that JB did not raise any issue with the position or construction of the replacement ceiling at the time it was installed. The FSP argues that the installation of a lower replacement ceiling is an accepted repair method in the building industry. Further, the FSP states that JB made no complaint at the time the ceiling repair was completed and therefore it is not appropriate for this to be revisited. 29. In response, AR says that she only noticed the issue with the ceiling when she engaged an architect to advise on planned renovations in May 2012 and that, to the best of her knowledge, her mother wasn’t aware of it. 30. I consider that regardless of whether the problem was noticed by JB or not, under the policy the FSP is required to repair the ceiling to the condition it was in just before the loss occurred. This includes restoring the ceiling at its original height. 31. There is no evidence before me confirming the difference between the height of the original and the replacement ceilings, or that the replacement ceiling is not in an appropriate position. However, AR has offered to provide copies of her architect’s plans confirming that the ceiling would need to be restored to the height of the ceilings in the neighbouring rooms before the planned renovations can occur, resulting in additional costs. Subject to AR providing Case No: 237015 Determination Page 7 of 16 such evidence, the FSP should arrange to have the ceiling corrected (i.e. by repairing the original ceiling or replacing it at the original height). Ceiling rose 32. The ceiling of the master bedroom included a central ceiling rose of the kind often found in period homes, which also had to be replaced as part of the repair. The FSP’s builders discarded the damaged ceiling rose on the basis that it was irreparable. 33. JB and AR were dissatisfied with the replacement ceiling rose installed as part of the initial repair works, on the basis that it was too dissimilar to the original design. At their request, this ceiling rose was removed and replaced by an alternative ceiling rose, which was closer in design to the original. 34. Although the alternative ceiling rose was approved by JB, AR says this rose was only accepted as a suitable substitute because the FSP’s builder said that the original ceiling rose design was not available, which was later discovered to be incorrect. AR also argues that the FSP’s builders should have attempted to repair the original ceiling rose or should at least have taken a mould from it to enable a replica to be produced. 35. AR remains dissatisfied with the second replacement ceiling rose which she considers to be a “poor substitute” for the original, and se eks to have this replaced with a ceiling rose moulded from one of the ceiling roses in the neighbouring terrace houses. 36. The FSP states that the alternative ceiling rose was chosen in consultation with JB and AR, following which AR signed a Certificate of Satisfaction for the repair works. Accordingly, it should be inferred that the alternative rose was of sufficient quality for its purpose and AR should not be able to revisit this decision after the fact. AR acknowledges that she did not continue to pursue her requests to have a mould of the original ceiling rose taken and that JB ultimately relented to the alternative design chosen, but states that this was due to JB’s health issues at the time. AR has also argued that she felt under pressure from the builder to sign the Certificate of Satisfaction which at the time she mistakenly understood related to the painting work only. 37. Under the policy, the FSP agrees to try to match any material used to repair the home with the original materials or “nearest equivalent available ”. Given that the alternative ceiling rose was sourced in consultation with AR and JB, and that AR subsequently signed the Certificate of Satisfaction, I consider that the FSP acted reasonably in the circumstances. Paintwork 38. It was accepted that the painting work undertaken by the first builder engaged by the FSP (“BB”) was not completed to an acceptable standar d. Case No: 237015 Determination Page 8 of 16 An alternative builder (“LB”) was subsequently engaged to rectify BB’s work, including repainting areas of the home previously painted by BB. 39. Following repainting by LB, the Applicant remains unhappy with some of the paintwork. The Applicant claims that not all surfaces painted by BB were rectified by LB and therefore some poor quality paintwork is still apparent, as well as areas where repainted areas do not colour-match undamaged areas and high gloss paint has been used which is not consistent with the matte paint used in the remainder of the house). 40. The FSP claims that the scope of the rectification work was agreed with JB and completed whilst she still resided in the home. This included the areas to be painted and the paint type and colour to be used. The FSP was given no reason to suspect that JB was dissatisfied with the final result. The FSP also notes that AR signed a Certificate of Satisfaction on 15 February 2012 for the work completed by LB, including repainting (see above). It is the FSP’s position that this matter should not be revisited retrospectively by AR. 41. The FSP notes that the policy provides for the repair of only those parts of the building that actually sustained damage, and contends that the Applicant has sought the repainting of undamaged areas. The Applicant disputes this. 42. The FSP argues that LB took pains to ensure that rectification of the paintwork was undertaken to JB’s satisfaction including undertaking the painting room by room while JB remained in the house and using an acrylic sealer instead of an oil-based sealer at her request, so as to minimise discomfort to her from the resulting fumes. AR has also confirmed on several occasions that she is generally happy with the quality of the painting works carried out by LB. 43. No persuasive evidence has been provided to demonstrate substandard paintwork completed by the FSP’s agents . Given that both JB and AR appear to have been satisfied with the work at the time it was completed by LB and that AR signed the Certificate of Satisfaction, I am of the view that the FSP should not be required to take any further action in this respect. CD player 44. The parties could not reach agreement on the appropriate settlement for a JVC CD player that sustained rust damage as a result of the storm and/or while in storage with the FSP’s agent. The FSP’s agents attempted to repair the damage, but this proved unsuccessful. 45. The FSP ultimately chose to cash settle JB for $263, being the amount quoted by its supplier as the price of an equivalent replacement model. The FSP also permitted JB to retain the original unit, so that she could attempt further repairs, given that the item had sentimental value. 46. AR considers that the model on which the cash settlement was based does not adequately reflect the aesthetics of the original player, which fitted better Case No: 237015 Determination Page 9 of 16 within the decor of the home. She seeks an alternative replacement model, which she has confirmed can be obtained for $450. 47. The FSP did not consider the alternative model proposed by AR to be a “like for like ” replacement. It relied upon evidence from its supplier to attest that the alternative proposed by AR represented a superior model, while a comparative product to the damaged model (with some additional features) could be purchased for the proposed settlement amount of $263. 48. On the balance of the material provided, I consider that the settlement amount offered by the FSP is reasonable and that the FSP should not be obliged to pay any further amount for the CD player. Reimbursement for wardrobes 49. BB (the first builder engaged by the FSP) did not install replacement wardrobes in the master bedroom, as provided for in the initial scope of works. As a result, the FSP cash settled JB for the amount of $2,500 to fund the purchase of replacement wardrobes. However, replacement wardrobes were subsequently installed by LB (the builder engaged to rectify BB’s work), at no cost to the Applicant. 50. The FSP argues that it should be entitled to a refund of the initial payment of $2,500 otherwise the Applicant will obtain a windfall gain. 51. The Applicant does not dispute the obligation to reimburse the payment of $2,500 but considers that, because of the delays and other problems with the repairs, this payment should not be required until the matter is fully resolved. 52. Although the FSP has confirmed that the money should be reimbursed directly to LB, the Applicant has expressed a preference to make the payment to the FSP. 53. The Applicant cannot keep the benefit of both the replacement wardrobes and the cash payment and therefore I consider that the Applicant should reimburse the amount of $2,500 to the FSP, which can then attend to payment to LB. Hospital costs 54. The Applicant seeks reimbursement under the “alternative accommodation” provision of the policy for expenses incurred in May and June 2012, when JB was in hospital undergoing treatment for her illness and repair work was being undertaken at her home. The amount sought to be reimbursed is $1,815, being the hospital co-payment amount of $55 per day for a period of 33 days. The Applicant contends that this represents the “accommodation” component of the hospital expenses. 55. The Applicant argues that it was agreed between the parties that, for the convenience of all concerned, repair works would be carried out during the Case No: 237015 Determination Page 10 of 16 period JB was in hospital undergoing surgery. The Applicant argues that, as the FSP would otherwise have been required to fund temporary accommodation, it should reimburse the amount of the hospital co-payment. 56. The FSP says that under the terms of the policy it is not obliged to pay any component of the hospital costs and to do so would result in a breach of the Private Health Insurance Act 2007 (the Act), which makes it an offence to operate as a “health insurance business”. The FSP acknowledges that one of its loss adjusters initially advised AR that part of JB’s hospital costs would be reimbursed as alternative accommodation. 57. For the purposes of this Determination, it is not necessary to reach a view as to whether reimbursement of the amount claimed by the Applicant would place the FSP in breach of the Act. 58. The policy provides indemnity for the costs of alternative accommodation where the insured is unable to live in their home as the result of damage resulting from an insured event. However, cover is not provided where the insured does “not need to pay for alternative accommodation”. 59. The underlying issue is whether the hospital co-payment was incurred because JB was unable to live in her home, as a result of the storm damage and/or the FSP’s conduct of repair work s. 60. JB did not move to alternative accommodation immediately following the storm (although it was arguable that her home was not then in a liveable condition) as she preferred to remain in her own home. There were times during the period when repairs were being carried out when it was necessary for JB to move into alternative accommodation, and the FSP has reimbursed the Applicant for the costs incurred in doing so. 61. JB’s hospital stay was primarily related to her need for treatment for her serious illness and therefore she would have incurred the hospital costs regardless of the FSP’s need for access to the home to carry out repairs. Given that JB was in hospital for treatment during this period, I consider that she did not have a need for “alternative accommodation” within the terms of the policy. 62. I have considered whether JB has relied to her detriment on the advice given by the loss adjuster that a component of her hospital costs would be reimbursed under th e policy. However, I am satisfied that JB’s decision to undergo surgery at this time was made primarily for health-related reasons. 63. The timing of JB’s hospital treatment was no doubt fortunate for the FSP as it might otherwise have incurred a payout for accommodation costs under the policy. However, I do not consider that this in itself entitles the Applicant to reimbursement of the hospital co-payment as alternative accommodation costs. Case No: 237015 Determination Page 11 of 16 Interest 64. The Applicant seeks payment of interest to compensate for delays in reimbursement by the FSP of certain expenses incurred by the Applicant with respect to the initial claim. 65. The FSP has agreed that it will pay interest in the amount of $427.50 as requested by the Applicant. However, the FSP considers that this amount should be deducted from the amount of $2,500 to be reimbursed by the Applicant in respect of the wardrobes (see paragraphs 49 to 53 above). 66. I do not consider that these issues should be linked and am of the view that the FSP should attend to payment of the interest owed to the Applicant as a separate matter. Disputed invoice 67. During the course of the Applicant’s dealings with the FSP in relation to the initial claim, it became apparent that an invoice tendered by a repairer had been authorised for payment by an employee (“CW”) of a loss adjust er agent of the FSP (“CC”), in circumstances where the work which was the subject of the invoice had not been carried out at the Applicant’s property. On being notified of this by the Applicant, the FSP undertook further investigations and referred the matter to a solicitor. 68. This event did not directly impact the Applicant as the relevant invoice was paid by the FSP and the relevant employee is no longer employed by CC. However, the experience perhaps (not unreasonably) affected AR’s confidence in the hone sty and good faith of the FSP’s agents. 69. As a result of this development, the Applicant sought to have CC removed from any further involvement in the claim. Notwithstanding this, the FSP later retained CC (without the involvement of CW) to engage an independent expert to report on whether the invoiced work had in fact been undertaken. However, there is no evidence that the Applicant was disadvantaged as a result. 70. The Applicant sought to have the Service investigate the initial invoicing issue and the conduct of the FSP’s subsequent investigation. Ultimately, any dispute over whether or not the work was done and/or should have been paid for is properly between the loss adjuster, the repairer and the FSP. Given that there is no evidence that the Applicant was adversely affected, I am of the view that this falls outside the Service’s jurisdiction. Balcony claim 71. The Applicant notified the FSP’s assessor (“PC”) of a claim for damage to the front balcony of the home on 16 May 2012, when PC attended the property to investigate damage relating to a separate, unrelated claim. Case No: 237015 Determination Page 12 of 16 72. The Applicant advised that damage to the main structural beam of the balcony was identified by her tradespeople (“WM”) on 14 May 2012 and the balcony was immediately demolished due to safety concerns. WM have provided a brief report confirming that both the fascia board and the main structural beam of the balcony were completely rotten and that “there was structural damage affected by rainwater”. 73. PC was not able to inspect the damaged balcony when he attended the property on 16 May 2012 as it had already been demolished, but was able to observe and photograph wood removed from the balcony. PC stated that he “could see the wood was quite rotted” and, based on his previous experience, believed th at the damage had “occurred over a long period of time”. 74. Both the FSP and the Applicant provided photographic and other evidence which sought to establish the condition of the balcony prior to May 2012. The FSP also referred to evidence from “GM” (a build ing supervisor employed by LB) that JB had told him in late 2011 that the balcony was in a state of disrepair. However, I do not find this particularly persuasive as it is unlikely that JB had any knowledge as to whether or not the balcony was structurally sound. 75. The FSP also provided a report from GM who stated that, in his experience, the fascia timber would need to have been saturated continuously for 10 to 15 years to get to the stage of removal and that it would have taken a similar amount of time for the beam to rot. In light of the drought conditions experienced in Melbourne over the preceding period, he considered that it was impossible for the damage to have occurred in a short period of time. GM has suggested that water entered the underlying structure either through splits in the unsealed boards on the balcony deck or as a result of the fascia not being painted. GM ’s report was prepared based on incidental observations of the balcony made in the course of inspecting the paintwork in the adjoining room in late 2011. 76. The FSP considers that the damage to the balcony is not the result of an insured event but rather has been sustained over a significant period of time. The FSP claims that the damage is excluded under the policy either because:  it is due to “long term lack of maintenance” (and therefore falls within the exclusion for damage “caused directly or indirectly by... rust, corrosion, gradual deterioration... wear or tear” ); or  it falls within the exclusion for water entering “because of a struc tural defect, faulty design or faulty workmanship” . 77. The Applicant considers that the damage to the balcony arises from the same “root cause” as the initial claim, being a problem with the operation of the box gutter roofing system which was originally identified by the FSP ’ s experts. The Applicant acknowledges that the balcony was “old and weathered”, but states that the boards were in relatively good condition and the fascia was painted. The Applicant also questions what maintenance Case No: 237015 Determination Page 13 of 16 could have been undertaken in relation to the structural beam, given that it was entirely concealed by the fascia boards and therefore no damage was apparent. 78. The Applicant argues that photographs provided by her demonstrate that only one section of the structural beam was damaged and therefore it is probable that this occurred as a direct result of water overflowing from the gutters (rather than through gradual deterioration). The Applicant has provided a statement from WM confirming that there was damage to one part of the beam only and that this resulted from overflowing gutters. WM also agrees with the view expressed by GM that the damage would have occurred over a number of years. 79. In his report dated 10 October 2012, the FSP’s roofing expert (“RC) confirmed that the design of the box gutter system resulted in rainfall from neighbouring terraces draining to the outlet on the roof of the Applicant’s property. Further, prior to work being undertaken on behalf of AR in or around July 2012, the box gutter system did not have any overflow mechanism allowing it to drain effectively. The box gutter system was also liable to become blocked by leaf debris from the large trees located in close proximity to it. The cumulative effect of these features of the box gutter system was that it was prone to overflow during periods of heavy rainfall. 80. The Applicant argues that the design of the box gutter system cannot be considered to be a structural defect given that the FSP has previously accepted claims for damage resulting from water overflowing from the box gutter. The Applicant notes that the box gutter system has generally proved adequate, but was simply not designed for the kinds of storms that occurred during 2010 and 2011. 81. The Applicant’s policy is a defined events policy which provides cover for loss or damage as a result of events including:  storm;  rainwater; and  water escaping from a fixed pipe or an object attached to a fixed pipe, fixed gutter, fixed tank or a drain, subject to the exclusions identified in paragraph 76 above. 82. It is an accepted principal of general insurance law that an insured bears the onus to establish that they have suffered a loss caused by an event to which the policy responds. Once a prima facie claim has been established, the onus shifts to the insurer to prove that an exclusion applies if it seeks to deny or limit its liability for loss. 83. The evidence provided by both the Applicant and the FSP suggests that the damage to the balcony was caused by rainwater, although there is a difference of opinion as to the method of ingress (i.e. whether through unsealed surfaces or as a result of overflow from the box gutter). Accordingly, I accept that the Applicant has established a prima facie claim. Case No: 237015 Determination Page 14 of 16 84. Statements by both the FSP’s and the Applicant’s experts indicate that the damage to the balcony occurred over a number of years. Accordingly, I consider that this damage is in the nature of gradual deterioration, and therefore excluded under the policy. I note that the wording of the relevant exclusion does not distinguish between whether or not the defect was (or should have been) apparent to the insured. 85. If, as claimed by the Applicant, the damage arose as a result of overflow from the box gutter system, then I consider that it would also fall within the exclusion for “structural defect, faulty design or faulty workmanship” due to the defects identified in RC’s report. In these circumstances, section 46 of the Insurance Contracts Act would have no application. Section 46 provides that if a claim is made in respect of a loss that occurred in whole or in part as a result of a defect or imperfection in a thing and the insured was not aware of the defect or a reasonable person in the circumstances could not be expected to have been aware of the defect or imperfection, then the insurer may not rely on an exclusion clause that refers to the condition of the thing before the contract was entered into. However, judicial authority has confirmed that this section does not apply to an exclusion of an event which makes no reference to when the event occurs. 86. Accordingly, the FSP is entitled to deny the Applicant’s claim for damage to the balcony. Compensation 87. The Applicant seeks compensation from the FSP for the stress and inconvenience caused as a result of its poor handling of the initial claim. 88. On 23 March 2012, as part of its proposed settlement of the claim, the FSP offered $3,000 compensation for the stress caused to JB during the claim process. The offer was rejected by AR and it was later withdrawn. 89. With hindsight, the FSP has suggested that it would not have made the offer had it known that JB had already passed away at the time the offer was made. 90. The FSP further considers that no compensation should be payable to AR for stress or delays encountered with the handling of the claim as AR is not the insured party under the policy. 91. The Terms of Reference for the Service provide that a payment (capped at $3,000) may b e made to an Applicant to compensate them for “ an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind” . In the present case, to the extent that payment of compensation is warranted, I consider it appropriate that such payment should be made to JB’s estate. 92. There is no question that this was a difficult matter for JB and AR and that it was not handled as well as it should have been. I am satisfied that the Case No: 237015 Determination Page 15 of 16 Applicant has established that a number of issues arose during the handling of the initial claim, including the following:  the repair and rectification of the insured home has taken well over a year, in circumstances where AR specifically requested that the claim be prioritised due to JB’s ill health;  there have been a number of unexplained delays in starting and completing repair work and reimbursing expenses;  numerous aspects of the repair work were not initially of an acceptable standard and much of this work had to be rectified; and  certain of JB’s clothing and other items were further damaged by the FSP’s agent who was engaged to attend to the initial contents damage. 93. I accept that the process has been frustrating for the Applicant, particularly given JB’s ill health. However, I am satisfied that generally the FSP has acted in good faith to attempt to resolve the issues raised including replacing the original loss adjuster and engaging a new builder to rectify the initial repairs, following complaints from AR. The FSP has also attempted to accommodate JB’s ill health and her desire to stay in her own home – for example, by arranging to have the home repainted one room at a time while JB remained in residence. 94. The management of the initial claim has been complicated by the separate involvement of JB, AR and AR’s husband “BR”, together with the numerous experts, loss adjusters and service providers retained by the FSP. This may have resulted in misunderstandings and miscommunications over some issues. While such difficulties added to the frustration experienced by JB and AR, putting to one side the disputed invoice referred to above, I do not consider that the actions of the parties involved were malicious or deliberate. 95. Given the matters outlined above, I am of the view that a compensatory payment is warranted. 96. That said, I am not of the view that the full amount allowable under the Terms of Reference should be provided. I accept that AR and JB were both inconvenienced throughout the course of the initial claim and that it was a difficult experience for them. I also accept that the FSP and its agents have made errors and have not, on the whole, handled the matter as well as they might have done. 97. However, the involvement of more than one p arty on the Applicant’s side has also at times has complicated the matter for the FSP and led to some confusion over settlement of the claim. Additionally, the circumstances of JB’s illness have undoubtedly placed additional pressures on all concerned. As stated previously, I do not blame AR or JB for this but I accept that it added to the difficulty in resolving some aspects of the claim. 98. In accordance with what is fair in all the circumstances, I consider that the FSP should pay compensation for non-financial loss in the amount of $1,500, and that this payment should be made to JB’s estate. Case No: 237015 Determination Page 16 of 16 99. For completeness, I note that the Applicant has also raised concerns about the management of the balcony claim, alleging that the FSP has not acted in good faith and “never had any intention of assessing the claim fairly”. 100. Having reviewed the materials provided, I consider that the FSP has managed the balcony claim reasonably and without excessive delay, particularly given the need to obtain expert reports and the delay in information being provided by the Applicant’s tradespeople. Determination 101. On the basis of the available information, I determine that the FSP should attend to the following:  the FSP should repair or replace the master bedroom ceiling at its original height, subject to AR providing evidence that the ceiling would need to be returned to its original height in order to allow renovations to be undertaken;  the FSP should pay to JB’s estate the amount of $427.50 previously agreed by the parties, as interest for the delayed reimbursement of expenses incurred by JB;  the FSP should pay to JB’s estate the amount of $1,500 as compensation for non-financial loss; and  the Applicant should refund to the FSP the amount of $2,500 paid to JB in respect of the wardrobes, which the FSP should use to satisfy LB’s invoice. 102. In relation to other aspects of the dispute raised by the Applicant throughout the course of the claim, I am satisfied that the FSP is not obliged to take these matters any further.