Text of the determination
Case No: 236077 Determination Page 1 of 10
Case number: 236077
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
29 June 2011
Background
1. The Applicant is the executor of the estate of his late mother and held a home
insurance policy in this capacity with the Financial Services Provider (FSP).
The policy insured the building for $225,000 and the contents for $200,000. A
standard excess of $100 applied.
2. The Applicant inherited the property from his late mother in 2006 and aimed to
put it on the market as soon as possible. He obtained a valuation report dated 3
October 2006 where it was commented that there was subsidence. However,
he did not lodge a claim as he believed the policy would not cover subsidence.
3. In 2007, he had discovered a hole in the ground on the southern side of the
house above where he understood the stormwater drain to run. At first, this
hole was small but it continued to increase in size. Finally, it was a metre
across and he could see the bottom of the drain, which was about two metres
below ground level.
4. The Applicant reported this to the council and sometime later, the council
workers excavated and exposed the drain. It was then apparent that a large
hole had formed at the bottom of the drain and he suspected this was
contributing to the subsidence the property had been experiencing. In his
opinion, he believed this issue was the council‟s responsibility and he engaged
a solicitor and engineer to advise him regarding this as well as the likely cost of
repair.
5. Some correspondence passed between the Applicant and the council where
the outcome was the council would not repair the drain until remedial action
was taken by him to repair the property. He could not afford the necessary
repairs and attempted to sell it instead. Howe ver, the movement continued to
worsen and when a builder acting for a prospective buyer inspected it in early
2010, he commented that he thought the home was unsafe. This was later
corroborated by an engineer he engaged as well as one of the council‟s
engineers.
6. Based on this, he decided to have the tenants vacate the property and to
subsequently demolish it. At this point, he still had not considered the possibility
that he had an entitlement to claim but notified the FSP of the situation given
the change in the risk.
Determination
Case No: 236077 Determination Page 2 of 10
7. It was following this notification that a claim was subsequently lodged. A claim
was recorded on the policy on 7 April 2010 and on the same day, the FSP
appointed a loss adjuster to inspect the property and begin assessing the loss.
Following the loss adjuster‟s inspection, the FSP intended to have an engineer
inspect the property to report on the cause of damage. However, some period
of time lapsed and in the process, the Applicant demolished the property.
8. The FSP continued with reviewing the claim and ultimately attempted to resolve
it by offering payment of $50,000. The Applicant has rejected this and is
seeking payment for $159,629.
Summary of Applicant ’s Position
9. The Applicant‟s claim for $159,629 is based on the following breakdown:
Loss on property $100,000
Demolition cost $24,750
Engineer‟s fee $2,002
Building permit $370
Removal of phone line $278
Lost interest $32,229
TOTAL $159,629
10. The calculation behind the loss on property is based on the fact the FSP
obtained a valuation of the land for $175,000. If the house had not been
damaged, his reasonable expectation of its sale price around the time of the
claim would have been $275,000. This results in the property loss of $100,000.
11. He has also allowed for loss of interest on the capital at 5% per annum,
compounding for three and a half years, less net rent. This equals $32,229.
12. The building was unsafe and required demolishment. He had informed the FSP
of this intention after the loss adjuster first inspected the property. As no one
responded to this comment, he proceeded with demolishing the home in the
three months between the loss adjuster‟s first inspection and the engineer‟s site
insp ection. Further, the decision to demolish was in everyone‟s best interests
given it had been declared unsafe by a builder and a couple of engineers. Not
demolishing the building would have resulted in higher costs.
13. He was not aware of any issue with the drain until early 2007 when he
observed a hole in the ground where the drain was. Further, he did not discover
a hole in the drain until the council investigated the issue a number of months
later.
14. The FSP has indicated that issues with the drain has been p re-existing for
some time. This is based on a couple of letters sent by his step father and a
neighbour to the council in 1986 regarding flooding to their premises due to the
Case No: 236077 Determination Page 3 of 10
drain being blocked. He was unaware of this issue at the time he took
possession of the property. Further, as far as he was aware, this flooding did
not cause any structural damage.
15. He also notes the apparent mechanism of the current subject damage is water
leaking out of the bottom of the storm water drain. There is nothing to indicate
this issue and the flooding in 1986 are related.
16. In relation to the failed sewer line, the FSP has indicated that this may have
been pre-existing as well because this was identified by his parents when they
purchased the property in 1983/84. However, he notes that when his parents
purchased the property, the downstairs toilet was not used because it was
understood that the sewer line had parted somewhere below ground level and
this was the area of the problem. As a result, the cistern was turned off and t he
water trap was dry. As his parents were not plumbers and there was no
evidence of any further issues once these measures were taken, nothing
further was done. In his opinion, this was reasonable in the circumstances.
17. He denies he ever installed laser equipment to monitor the subsidence on the
property. The FSP‟s comments in this regard were likely in reference to a
government funded review of the landslip in the area.
18. He did not notify the FSP of the property damage until much later as he
believed the policy did not cover subsidence. Further, there was evidence of
landslip in the area, which he also felt would likely result in the claim being
outside of the cover. In relation to how this prejudiced the FSP, he does not
consider this is significant given the damage did not deteriorate greatly once
the damage first became evident.
Summary of FSP’s Position
19. The FSP appointed an engineer (HS) to inspect the Applicant‟s property and
review the likely cause of the foundation movement. HS conducted a structural
inspection on 21 July 2010 and made further visits on 22 July 2010 and 26 July
2010 to gauge the likely flow through the council storm water pipe. During the
site inspection, the property was in the process of being demolished.
20. HS provided a report dated 26 July 2010 which stated in the conclusion:
“Water soaking into the soil from both the broken earthen ware sewer line
located under the building and the broken concrete Council owned Storm Water
line would undoubtedly have been significant contributors to the loss of soil
bearing capacitates at the front of the house. The fact that the adjacent house to
the South of the property is also near the broken Council Storm Water line, albeit
not as close, and has not suffered inordinate settlement problems to date would
suggest that the sewer line is the larger of the contributing factors. This is
supported further by the locality of the break in the sewer line with respect to the
two front pillars which had suffered the most from settlement. It is not possible to
be absolutely definitive with regard to percentages to which each broken pipe
would have contributed but I suggest that they would be in the order of one third
Council Storm Water and two thirds domestic sewer line.”
Case No: 236077 Determination Page 4 of 10
21. The FSP subsequently appointed another engineer (SBC) to carry out further
enquires in conjunction with its loss adjuster. The following relevant information
was gathered by SBC‟s consultant:
The Applicant advised him that his parents purchased the home in 1983
or 1984 and that as early as 1986, there had been a situation with the
storm water drain;
The Applicant also advised that the sewer line had been disconnected
since before his parent‟s purchase of the property and that this line could
not have contributed to the escape of liquid;
He discussed the sewer line disconnection with the engineer from HS.
This engineer advised him he found one domestic sewer line servicing the
risk address and this was fractured. In regards to the Applicant‟s
contention that the line was disconnected, he did not agree and believed it
was more likely disused;
He discussed a quote provided by a builder, DC, who estimated the cost
of repairs to be $74,000 plus GST. DC confirmed the estimate was based
on works necessary to rectify the damage resulting from the water leak.
However, it did not involve an in-depth assessment of the building to
enable the presentation of a more detailed quotation. It also did not factor
into consideration depreciation; and
The Applicant indicated that he had some ten years ago installed laser
measuring equipment for a period of several months in order to determine
if subsidence or earth movement was in place.
22. The FSP contends that given the engineer reports and the history of the claim,
its offer of settlement was reasonable. This is taking into consideration that the
property has had ongoing problems over an extended period of time, the
Applicant‟s failure to take corrective action to rectify the problem, the property
not being maintained in good repair and the Applicant‟s decision to demolish
the building before the extent of claimable damage could be ascertained.
23. As a result, it submits that the Applicant‟s entitlement under the policy is likely
between the sums of $25,000 and $50,000. In providing this figure, it is relying
on the following policy provision as the Applicant had no intention of allowing it
the option to repair the damage given he demolished the property:
“If we have chosen to repair or rebuild your damaged buildings and you do not wish to
repair or rebuild them, we will at our option:
a. pay you the reasonable cost to repair or rebuild your damaged buildings less an
amount for depreciation based on the age and condition of the buildings …”
24. In providing this estimate, the FSP relies on the following:
In the valuation report provided to the Applicant dated 3 October 2006, the
author estimated the likely repair cost to be between $25,000 and
$50,000. However, the Applicant did not undertake any steps to rectify the
damage back then or later. As a result, the costs undoubtedly escalated;
Case No: 236077 Determination Page 5 of 10
In December 2007, the Applicant obtained some written estimates, one
from DC for $74,000 plus GST and the other from an engineer for
$116,000. There is nothing to suggest the engineer‟s estimate was limited
to the cost to rectify the water damage. DC‟s estimate was apparently
limited to repairing the water damage, but did not take into consideration
depreciation; and
In the Applicant‟s letter to the council dated 6 August 2009, he advised the
cost of repairs to be between $50,000 and $100,000.
Issues
25. Whether the Applicant is entitled to the amount sought regarding this claim.
Reasons for Decision
26. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with clause 8.6 of the FOS Terms of Reference. This is
due to the circumstances, quantum and complexity of the dispute. This dispute
has not been the subject of a FOS Recommendation and has proceeded
directly to Determination.
27. This decision has been made by a Panel consisting of an Ombudsman, a
representative with extensive experience in the insurance industry and a
representative with extensive experience in consumer claims.
28. Prior to arriving at this decision, the Panel confirms it has considered all the
material submitted by the parties.
Is the claim covered?
29. The onus is on the Applicant to establish, on the balance of probabilities, that
he suffered a loss caused by a risk insured against (in this case, water or other
liquid damage). Once this has been established on the face of the facts, the
onus shifts to the FSP to show, on the balance of probabilities, the claim falls
within an exclusion of the contract of insurance.
30. Upon reviewing the FSP‟s materials, it appears it has accepted liability of the
claim although this has not been made clear. In the FSP‟s Notice of Response,
it makes reference to a number of issues that entitle it to deny the claim, such
as the fact the damage was pre-existing for a long period of time or that the
policy does not cover gradual escape of liquid. It has also referred to numerous
other exclusion clauses in its policy that, if applicable, would have entitled it to
deny the claim.
31. However, it has made a number of attempts to resolve the Applicant‟s claim by
way of cash payment, which would indicate that it accepts the claim falls within
the cover provided by the policy. This therefore makes for a somewhat
confusing submission.
Case No: 236077 Determination Page 6 of 10
32. Regardless of th is, the Panel finds HS‟s report dated 26 July 2010 to be
persuasive. This report has clearly identified a leaking stormwater drain and a
sewer line being the main contributing factors to the foundation movement
causing damage to the home. This was also cor roborated by the Applicant‟s
engineers.
33. The Panel therefore accepts the dominant cause to the Applicant‟s property
damage was the escape of liquid from the stormwater drain pipe and the sewer
line. This falls within the following insuring provision:
“ Water or other liquid damage
We will pay for loss or damage which results directly from the bursting, leaking,
discharging or overflowing of:
…
fixed pipes.”
34. The FSP has referred to letters sent by the Applicant‟s step -father and a
neighbour that made reference to a blocked drainage causing damage to the
property. It has attempted to infer that there is a connection between this event
and the current leak.
35. However, the Panel is not satisfied such a connection exists. The letters made
reference to the drain being blocked and causing water to overflow into the
property. The issue in this claim is for a significant hole in the drain pipe
causing water to seep into the soil beneath the home, resulting in significant
damage. In the Panel‟s opinion, the FSP has not est ablished that the issues
experienced by the Applicant‟s step -father resulted because of this hole. It
appears more likely this is isolated to the one event given it has not occurred
again and the large amount of years which lapsed since.
36. The FSP has also referred to the sewer pipe issue being in existence since
1983 which the Applicant was allegedly aware of through his parents. However,
as the Applicant correctly pointed out, he was not aware of same until after the
claim occurred given the property was owned by his parents.
37. Further, according to the Applicant, even if his parents may have been aware of
an issue with the sewer pipe, they felt they were undertaking appropriate
measures to protect the property given the lack of issues experienced
afterwards. The Panel also notes the FSP has provided no substantive
evidence to indicate that the issue with the sewer pipe back in 1983 is the same
as the one identified by its engineer.
38. Given this, the Panel accepts that the Applicant has established an insured
event occurred which caused damage to the property.
Quantum
Applicant’s claim
Case No: 236077 Determination Page 7 of 10
39. One of the significant issues in dispute between the parties is the amount the
FSP should pay towards the claim. The Panel does not find the Applicant‟s
amount of $100,000 plus interest to be persuasive for the following reasons:
He has provided no direct evidence to support the contention that the
property needed to be demolished. He has noted a number of people told
him the property was unsafe but there was nothing to indicate that being
unsafe meant the whole structure needed to be demolished;
He referred to an engineer‟s email sent to him dated 16 March 2010 that
made reference to demolishment. However, this email stated “ I believe
the best course of action is to make the building safe by demolishing any
structures that are susceptible to imminent collapse ”. This clearly does not
state that the whole property needed to be demolished;
The Applicant is seeking three and a half years worth of interest due to
lost capital. This is unreasonable given he did not notify the FSP of the
claim for three of those years; and
The available evidence indicates the damage to the property was
repairable. There is no engineering or other expert evidence that states
the property needed to be completely demolished and rebuilt.
40. The Panel therefore does not accept the Applicant‟s method of measuring his
loss to be appropriate or in accordance with the cover provided by the policy.
41. The Applicant has also sought the costs he has incurred in demolishing the
building. The policy provides for these costs under the following policy
provision:
“ Removal of debris, professional fees and extra costs
… When the buildings have been destroyed or damaged by an insured event and we
have agreed to pay your claim, we will also pay the reasonable and necessary costs
of:
a. demolition and removing debris from your risk address;
b. architects‟, engineers‟, surveyors‟ and solicitors‟ fees; and
c. meeting the requirements of any statutory authority.
We will only pay these costs if they relate directly to the destroyed or damaged part of
the buildings and we have agreed to do so before they are incurred.”
42. In this instance, the Applicant has clearly incurred these fees without the FSP‟s
permission given the FSP did not instruct him to demolish the building.
Although he states he informed the FSP or one of its agents that he intended to
demolish the building, there is no evidence the FSP agreed to this. The fact the
FSP did not respond to his comment does not, in the Panel‟s op inion, imply
consent, especially given the FSP did not have an opportunity to properly
assess the extent of damage.
43. The Applicant being a professional loss adjuster, albeit in another area of
insurance, should have at least been aware that it is general insurance practice
to assess the extent of a loss when reviewing the claim. As such, it is unclear
why he felt it was appropriate to demolish the building given he was aware the
Case No: 236077 Determination Page 8 of 10
costing assessments was yet to be completed. Although the Panel accepts
there was some delay in the FSP arranging a site inspection from the loss
adjuster‟s initial inspection, it does not accept that the Applicant was entitled to
infer the FSP‟s consent to the property‟s demolishment.
44. Further, the Panel accepts the available evidence indicates demolishing the
building was not necessary in the circumstances.
45. Accordingly, the Panel does not accept the FSP is liable for these costs.
Amount
46. The policy provides for the following benefit in the situation when the FSP has
chosen to repair the damage but the Applicant is seeking a cash settlement
instead:
“If we have chosen to repair or rebuild your damaged buildings and you do not wish to
repair or rebuild them, we will at our option:
a. pay you the reasonable cost to repair or rebuild your damaged buildings less an
amount for depreciation based on the age and condition of the buildings …”
47. The policy also imposes the following obligation on an insured regarding the
lodgement of a claim:
“ Making a claim
…
5. Contact us as soon as possible
If there is any loss, liability, injury or damage which is likely to result in a claim,
you must give us immediate notice of the full details of any loss, anticipated or
alleged liability, injury or damage.”
48. Based on these provisions, the FSP is liable for the reasonable cost to repair
the damaged building at the time the Applicant should have lodged the claim
less depreciation. The Panel considers this approach is also fair in all the
circumstances given it would account for the prejudice the FSP would have
incurred in the delay in lodging the claim and the Applicant demolishing the
home.
49. As articulated by the FSP though, there is minimal information available
regarding what the cost of repairs would have been. The only available
evidence is from a builder engaged by the Applicant, DC, who stated to SBC
that his estimate of $74,000 plus GST was to repair the damage resulting from
the water leak. However, DC acknowledged this amount did not account for
depreciation. Further, DC acknowledged his estimate did not i nvolve an in-
depth assessment of the building to allow the presentation of a detailed
quotation.
50. The FSP has referred to a valuation report provided by the Applicant where the
valuer estimated the cost of repairs to be between $25,000 and $50,000.
However, the Panel does not consider a valuer has the appropriate expertise to
Case No: 236077 Determination Page 9 of 10
provide an estimate of cost of repairs to building damage. Such an issue is
more appropriately commented on by a builder.
51. As the Applicant demolished the building before the FSP could engage
appropriate experts to review the damage, there has been no opportunity for a
scope of works or detailed quotes to be compiled.
52. The Panel is therefore left in the situation of having to provide a figure that is
fair in all the circumstances pursuant to clause 8.2 of the Terms of Reference
given the limited information available. Clause 8.2 of the Terms of Reference
state the following:
“Subject to paragraph 8.1, when deciding a Dispute and whether a remedy should be
provided in accordance with paragraph 9, FOS will do what in its opinion is fair in all
the circumstances, having regard to each of the following:
a) legal principles;
b) applicable industry codes or guidance as to practice;
c) good industry practice; and
d) previous relevant decisions of FOS or a Predecessor Scheme (although FOS will
not be bound by these)”
53. In this instance, the FSP has offered to settle the Applicant‟s claim by way of
payment of $50,000. In the Panel‟s opinion, this seems low given the foll owing:
The only estimate available from an appropriately qualified expert
provided an estimate of $81,400;
It is common for substantive building costs to exceed the initial estimates.
As such, it is often appropriate to apply a builder‟s margin on the init ial
estimate; and
There is no evidence to suggest the depreciation was so significant that it
should account for more than 40% of the actual cost, especially given the
policy normally allows new for old if the FSP had the option to repair the
home.
54. As the FSP was aware, the Applicant‟s qualified expert provided an estimate of
$81,400. Should the FSP have wished it could have led evidence
demonstrating why that figure should not be accepted; it has not done so and
accordingly, pursuant to the Panel‟s „fair a nd reasonable‟ mandate , it now
determines that is the quantum for cash settlement.
Determination
55. On the basis of the available information the Panel determines that the FSP
pay the Applicant the sum of $81,400 in full and final settlement of the claim.
Case No: 236077 Determination Page 10 of 10
56. In the event the Applicant accepts the Determination, the FSP is to pay this
amount within 21 days of being notified of his acceptance.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.