Home / Financial Firm (Unknown - Insurer) / Determination 235199
Determination 235199
Claim denied for waterproofing membrane storm damage and related costs
Summary
The owner claimed for a waterproofing membrane, excavation and internal wall repairs after storm water ingress in 2010, which the FSP denied. AFCA found storm damage to the membrane most likely, ordered the FSP to repair or replace the membrane and share excavation costs if a membrane is found, and ordered reimbursement of the $1,430 engineering report.
The exclusions for structural fault, faulty workmanship and lack of maintenance were not established, and the storm events likely damaged the membrane.
Subjects and remedies
natural disasterpay claimrepair or rectify
Text of the determination
Case No: 235199 Determination Page 1 of 7
Case number: 235199
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of Claim
13 October 2011
Background
1. The Applicant held a home building insurance policy with the Financial Services
Provider (FSP) from 23 April 2010 to 23 April 2011 and the policy was current
at the time of loss.
2. The Applicant lodged a claim with the FSP on 11 October 2010 for water
damage sustained to the garage and bedroom walls of his property, the cost of
installing/repairing the waterproofing membrane on the external face of the
block and the installation of an external drainage system.
3. The storm activities occurred on 11 August 2010, 11 October 2010 and 24
October 2010.
4. It has been established that over 300ml of rain fell on these dates.
5. The FSP appointed an assessor F and engineer C to investigate the
circumstances and cause of the loss.
6. The FSP accepted the Applicant‟s claim for inte rnal water damage to the
property. However, based on the expert evidence, it denied the rest of his
claim.
7. The Applicant sought his own expert evidence and is of the view that the storm
event(s) caused the water proofing membrane to fail and thereby expects the
FSP to replace/repair the existing failed waterproof membrane. However, he
accepts that the installation of the external drainage does not fall within the
scope of the policy.
Summary of Applicant’s Position
8. The Applicant, based on F‟s recommendation, appointed engineer NJ to
reassess and investigate the cause of loss.
9. The Applicant refers to NJ ‟s report as below:
Determination
Case No: 235199 Determination Page 2 of 7
“ Conclusions
...
Despite significant inadequacies in the site drainage provisions and the
waterproofing provisions to the lower floor are highlighted above the
waterproofing provisions have proved sufficient to prevent water ingress into the
lower floor level over the period or(sic) your ownership of the house up until the
three recent significant water ingress events.
The installation of the drainage outlets and the landscaping works on Properties
„E‟ and „F‟ pr ior to Event 1 has resulted in significant increase in both the
quantities of surface water flows reaching the site, the speed at which they reach
the site.
On the basis it appears highly likely that the increase in the quantities and the
patterns of surface water flow reaching the site following installation of the
drainage outlets and the landscaping works on P roperties „E‟ and „F‟ is a direct
contributing factor to the spate of recent water ingress problems ”
10. The Applicant says that C failed to record the accurate rainfall from a site closer
to his residence and to comment on whether the building had an existing
waterproofing membrane on the outside wall of the inhabitable areas.
11. The Applicant states that C also failed to indentify that the increased volumes of
water during the initial storm event caused the existing waterproofing
membrane to fail, as it was working adequately prior to this event and that the
pre-existing defence barrier was damaged as a result of this event.
12. The Applicant believes that the damage to the building was caused by the
storm events and that both expert reports from C and NJ did not indicate that
there was structural damage or signs of long term damage caused by drainage
issues.
13. The Applicant says that since the FSP had accepted the claim for the damage
sustained to the pool and the internal wall repairs, it is obliged to accept the
cost of repairing the existing waterproofing membrane which has failed due to
the same storm event.
14. The Applicant reiterates that he requested the FSP to repair or replace the
existing waterproofing membrane which was impacted by storm and that he
does not expect the FSP to install waterproofing membrane to parts of the
building which were never water proofed.
15. The Applicant expects the FSP to accept the following expenses:
Cost of NJ ‟s report - $1,430;
Excavation and construction of waterproofing membrane $7,755;
Internal wall repairs - $1,158; and
Internal wall repairs due to on ongoing water damage $1,500.
Case No: 235199 Determination Page 3 of 7
Summary of FSP’s Position
16. The FSP reiterates that the dispute relates to whether there was a ny physical
damage caused to the waterproofing membrane of the Applicant‟s property by
storm activities.
17. The FSP explains that the Applicant‟s claim for internal water damage was
accepted as the Applicant was not aware of the inadequacies of the structure
until this event and because the FSP has already accepted and a uthorised
repairs to the internal walls.
18. However, in regards to the installation/repair of the waterproofing membrane
the FSP relies on C‟s report as below:
“We conclude that the proximate cause of the damage to the ground floor of the
residence is not the result of storm activity but from water seepage that has
occurred as the result of the following causes:
1. Lack of drainage and waterproofing;
2. Poor building practice;
3. Excess water caused by runoff from surrounding grounds, not necessarily
from the pipe located on the neighbours property;
...
We recommend that a waterproof membrane [tanking] be installed on the
external face of the block along the LHS of the property from existing ground
level to below the first course of block work. ”
19. The FSP says that the policy insures the Applicant against physical loss of or
physical damage to the building when the loss or damage is directly caused by
any of the events specified in the policy, in this case by a storm.
20. The FSP is of the view that whilst storm is a specified event under the policy,
the policy specifically excludes cover for loss or damage directly or indirectly
caused by or arising out of faulty design, faulty workmanship and lack of
maintenance.
21. The FSP relies on the following policy provisions:
“ What You are insured against if Your Home is not a caravan
This policy insured You against physical loss of or physical damage to:
Your Home if „Building‟ is shown on the certificate of insurance
...
If the loss or damage is directly caused by any of the following events occurring during
the Period of Insurance.
...
10 Storm
but not loss or damage directly or indirectly caused by or arising out of:
Case No: 235199 Determination Page 4 of 7
a structural fault, faulty design or faulty workmanship
lack of maintenance (e.g. failure to clean out gutters). ”
22. The FSP says that both engineers C and NJ have concluded that the water had
seeped into the lower level of the building as a result of inadequate drainage,
inadequate waterproofing and general water runoff. Further, it refers to NJ ‟s
report which specifically states that the existing waterproofing membrane did
not sustain any physical damage as a result of this event.
23. The FSP disputes liability for the Applicant‟s claim for the cost of excavation
and installation/repair of the waterproofing membrane for the reasons listed
above.
Issue
24. Whether the FSP is liable to indemnify the Applicant for the cost of replacing
the existing waterproofing membrane and the cost of NJ ‟s report.
Reasons for Decision
25. Due to the nature of this dispute, FOS has considered it appropriate to expedite
the dispute in accordance with the Operational Guidelines to the FOS Terms of
Reference. This dispute has not been the subject of a FOS Recommendation
and has proceeded directly to Determination.
26. I am satisfied that a full exchange of information has taken place between each
party and that each party has had the opportunity to address any issues raised.
27. The onus of proof rests on the Applicant to establish that, on the balance of
probabilities, he has suffered a loss caused by an insured risk. Once the
Applicant has established that the loss was caused by a risk insured under his
policy, the onus then shifts to the FSP to show that, on the balance of
probabilities, the loss falls within a n exclusion clause in the policy.
28. The FSP‟s policy excludes cover for storm damage, if the damage results from
a structural fault, faulty design, faulty workmanship or a lack of maintenance.
29. Accordingly it is necessary to consider whether any of these exclusions are
applicable to this matter.
30. I am unable to conclude that they are. The undisputed evidence of the
Applicant is that at the time of the three storms (which I call the storm event for
simplicity), he had lived at the property for two and a half years. The undisputed
claim is that there had been no ingress of water prior to the storm event.
31. This is extremely significant because of the investigations conducted by the
Applicant‟s engineer “NJ”, who has carefully documented all the incidences of
heavy rain from the time that the Applicant acquired the property. Over 40mm
Case No: 235199 Determination Page 5 of 7
of rain fell on 15 occasions during the time that the Applicant was in possession
of the property, up until the first of the storm events in August 2010. The
maximum daily rainfall recorded over this period was 110mm on 20 May 2009.
It should be noted that on that occasion, 85mm had fallen on 19 May and
95mm was recorded the following day. 290mm of rain in three days is an
extraordinary rainfall, yet according to un-contradicted evidence, no water
entered the property at that time.
32. In these circumstances I find it hard to accept an argument from the FSP that
when the rain has entered the property during the storm events of 2010, it has
been due to structural faults or faulty design. Put quite bluntly, there cannot
have been too much wrong with the design if rain had not been able to enter in
the extraordinary rain events of 2009.
33. I consider that the 2009 rain events are also important for another reason. In
both the engineering reports of “C”, and NJ, the possibility is contemplated that
at the relevant part of the Applicant‟s property there might not have been any
water proofing membrane in place. Having regard to the reported rainfall as
listed in the NJ report, I consider that on the bala nce of probabilities this
possibility cannot be seriously contemplated.
34. In these circumstances the contention of the Applicant is that in some manner
which he is unable to more accurately describe, the water membrane has been
compromised by the storm event of 2010.
35. In this context the earlier rain events of 2009 are something of a twin-edged
sword from the Applicant‟s viewpoint. A question may well arise, why did the
2010 storm events lead to a compromising of the water membrane, if the
heavier rain in 2009 had not.
36. It is at this point that the careful report by NJ again becomes quite vital. What
NJ has highlighted is the extent to which excavation and changes to the
topography of adjoining properties have increased the flow of water between
those properties at times of heavy rain. Ultimately a great deal of this water has
found its way to the Applicant‟s property. In these circumstances I find it quite
reasonable to accept that the rain which fell in the storm events was sufficient
to cause damage to the water membrane because of the increased volume of
water coming from the adjoining properties.
37. The problem which, however, still confronts the Applicant is that the expert
engaged on behalf of the FSP, C, expresses the view that the storm event
could not have damaged the water membrane. In the report of NJ, after
highlighting obvious inadequacies in the site drainage provision the author of
the report then includes the following:
“the fact that three instances of serious water ingress have then occurred over a
period of less than three months strongly suggests some change either in the
water proofing performance or alternatively in the volumes of surface water flows
reaching the property.”
38. NJ also commented that:
Case No: 235199 Determination Page 6 of 7
“ Clearly the water ingress through the rear wall of the bedroom in the south
western corner of the lower floor area indicates that whatever membrane might
have been installed to the earth face of the wall has failed. As we did not observe
any indications of significant movement of the retaining walls or slabs in the
lower floor area in the course of our inspection which might have caused
physical damage to the installed membrane, it appears that the failure is most
probably the result of some inadequacy in the installed membrane, and/or of
water overtoppi ng the area of the wall to which the membrane has been applied.”
39. It is therefore necessary to consider the suggestion that because there has
been no obvious evidence of physical damage to the membrane, any failure of
the membrane must be the result of “som e inadequacy in the installed
membrane”.
40. These comments make good sense but it is important to acknowledge that the
writer of the comments is making them in reference to an invisible object. He
has to speculate as to how this object, a water membrane hidden below the
surface, may have been damaged.
41. One must make the obvious observation, that if the water membrane was
inadequate or had been inadequately installed, one would have thought that
the problem would have manifested itself a good deal earlier and certainly in
the calamitous 2009 rain events. One would have thought that if, for example, a
claim had been brought against the installer of the water membrane and the
installer had been aware that the membrane had withstood the 2009 rainfall, he
would have strenuously resisted any suggestion that his work had been
inadequate.
Conclusion
42. We are therefore left with the certain knowledge that there had been huge rain
falling upon the Applicant‟s property in 2009 but no ingress of water. There
have been significant alterations to the topography of the neighbouring
properties leading to an increased probability that more water than previously
would flow from those properties into adjoining properties and ultimately
affecting the Applicant‟s property. There ar e then the storm events in August
and October 2010, and for the first time, significant water enters the property.
43. In the circumstances I consider that the most likely cause of the ingress of
water is damage (the details of which cannot be more accurately specified), to
the water membrane in the 2010 storm events.
44. The question then arises as to the form of any redress to which the Applicant
should be entitled from the FSP. There has been some confusion as to the
precise relief sought by the Applicant. Ultimately, however, I am satisfied that
what he is seeking is reasonable. It is the repair, or alternatively replacement,
of the existing membrane. In order that this can be affected, excavations have
to be carried out.
45. Whilst I have concluded that it is overwhelmingly probable that there must be
an existing water membrane at the point at which this water has entered, it will
Case No: 235199 Determination Page 7 of 7
not be known until the excavations are carried out as to whether this is the
case. The material adduced by the Applicant has satisfied me that, at least, the
FSP should contribute to the costs of excavation which will be required.
46. I think the appropriate course is that if, after the excavations have been carried
out, the existence of a water membrane is confirmed, then the FSP should
attend to the repair, or if necessary, replacement of that water membrane and
shall bear the costs of the excavation. If, on the other hand, there is no water
membrane in place, then the costs of the replacement of the membrane must
be borne by the Applicant.
47. Finally, as I consider that the report of NJ has added significantly to the
investigation of this matter and my ability to make a Determination, the
Applicant should be reimbursed for the costs of the NJ report.
Determination
48. I determine that provided the Applicant accepts this Determination, the area of
the dwelling on which the water entry has occurred be excavated in order that
the water membrane (if any) may be inspected. I determine that the Applicant
and the FSP shall be initially equally responsible for the costs of the excavation.
49. In the event that a water membrane is identified, I determine that the FSP shall
meet the costs of repairs or replacement of the water membrane together with
all the costs of the excavation.
50. If upon examination there is no water membrane in situ, the Applicant shall
meet the costs of installation of any new water membrane.
51. I determine that the FSP shall reimburse the Applicant for the costs of the NJ
report.
52. I determine that if he is available for this purpose NM of NJ shall determine the
area to be excavated and whether there is a water membrane in situ.