Fire claim: delayed building repairs, contents settlement and temporary accommodation rent

FirmFinancial Firm (Unknown - Insurer)
Decided2011-11-22
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$59,038
Non-financial loss$2,000
Amount claimed$115,000
SourceAFCA PDF

Summary

After a fire, the applicant complained about delayed building repairs, slow contents settlement and late rent payments for temporary accommodation. AFCA ordered a building project manager appointed, payment of the contents offer and rent balance, a legal cost contribution and $2,000 non-financial loss.

Having elected to settle the building claim by repair, the FSP assumed responsibility to progress the repairs in a timely manner under the General Insurance Code standard of fair, transparent and timely claims handling.

Issues

Subjects and remedies

home or building damagepay claimpay compensationpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 234552 Determination Page 1 of 9 Case number: 234552 General Insurance – Home Building and Contents – Rectification of damaged building – Settlement of contents claim – Outstanding Rental payments 28 September 2011 Background 1. The Applicant is being assisted by a lawyer in the handling of his dispute with the Financial Services Provider (FSP) and will be referred to as the Applicant in this determination. 2. The Applicant insured his home and contents under a Home Insurance Policy for $637,000 and $153,153 respectively with a $200 policy excess. The policy commenced on 5 December 2005 and had been renewed to 5 December 2011. 3. On 15 September 2010, the insured building and contents were badly damaged by fire. After preliminary investigations were completed by the FSP, it agreed to accept the claims for the cost of repairs to the building and repairs and replacement of contents items damaged in the fire. 4. However, due to the unacceptable delay in commencing repairs to the building, settlement of his contents claim and delays in meeting his temporary accommodation costs, the Applicant has submitted a notice of dispute with the Financial Ombudsman Service (FSP). Building Dispute 5. The following is a chronology of activity with the claim: Date Comments 15/09/10 Fire damages insured property; 16/09/10 Loss adjuster inspects site; 20/09/10 First adjuster’s report 05/10/10 Scope of Works for repairs to the building submitted to the adjuster 16/10/10 Second adjuster’s report to the FSP enclosing copy of the Scope of Works; 19/10/10 Copy of Scope of Works submitted to builders B, P and Applicant’s preferred builder L; 27/10/10 Third adjuster’s report – pursuing quotes from builders; Determination Case No: 234552 Determination Page 2 of 9 26/11/10 Fourth adjuster’s report – quote for $169,400 received from builder B; still pursuing quotes from P and L; 17/12/10 Fifth adjuster’s report – quote for $208,010 received from builder P’ 14/02/11 Sixth adjuster’s report still pursuing quote from builder L; 21/02/11 Seventh adjuster’s report – Still no quote from builder L, adjust er reports failure of L to submit quote has resulted in significant delays in commencement of building repairs; 16/03/11 Email from FSP to adjuster – FSP wanted clarification as to whether rebuilding had commenced or if the Applicant still wanted a cash s ettlement; 22/03/11 Adjusted received written confirmation from Applicant’s lawyer that Applicant wants building repairs completed by builder B and had signed a contract with the builder; 19/04/11 Ninth adjuster’s report – Builder B is currently underta king repairs and adjuster is monitoring progress Contents Total claimed amount estimated to be $115,000 19/10/10 Loss adjuster reports ‘L’ a Contents Service company was in the process of providing an inventory of items they have cleaned and salvaged and identifying items not salvageable; 27/10/10 Adjuster reports L completed inventory. Adjuster in process of obtaining quotes; 17/12/10 Applicant provides a further list of items not noted on the inventory provided by L; 14/02/11 Adjuster received an upda ted inventory of claimed items. Report sent to FSP for review; 21/02/11 Applicant to review updated list and to advise amount he would be satisfied to settle for; when response received from Applicant, adjuster will make a recommendation re settlement of contents claim; 22/03/11 Adjuster reports the Applicant is still updating list; ( However Applicant’s lawyer had submitted list of claimed items to the FSP, letter was dated 01/03/11 and apparently received by the FSP on 10/03/11). 07/04/11 Letter from lawyer to FSP – advising claimed list of contents sent to the FSP on two occasions and still waiting for cash settlement offer; 19/04/11 Adjuster advises he has sent a final list of claimed items to the Applicant for checking. Case No: 234552 Determination Page 3 of 9 Rental payments 6. In addition, the Applicant reports the FSP has not been paying his rental in a timely manner resulting in demands from the rental property manager. Summary of Applicant’s Position Building 7. He is not satisfied with the progress of the building works at the insured property. He seeks authority to take control of the building process and appoint a builder to commence construction to the damage caused to his house without delay. 8. He is frustrated at the number of telephone calls he has made to the FSP to progress his claim. He states that construction of his house was due to be completed within six months of the fire but finalisation of repairs is still to be resolved. Contents 9. His claim for damage to his contents has been delayed by the FSP because it has not made payment for the purchase of replacement contents except for a lump sum payment of $10,000 which was totally inadequate and insufficient to properly meet his claim. 10. The Applicant had numerous items of contents and furniture with a list being collated by the FSP which was not provided to him for some significant time after which he had to re-purchase some contents from his own funds to at least accommodate himself to a minimum standard. 11. He is short of finance and continues to experience financial difficulties and the delays caused by the FSP in not progressing his claim in a timely fashion is causing him loss and extreme distress. He has not received sufficient funds to reimburse him for the loss of his contents and this has continued to be ignored by the FSP. 12. He has asked the FSP on numerous occasions as to when he can expect payment due to him in relation to the contents destroyed in the fire and he has not received a response. 13. A detailed list of contents was collated by the FSP and finalised by him allocating values for the contents but the issue has not been addressed by the FSP. Payment of Rental for Temporary Accommodation 14. The FSP has not met his rental payments in a timely fashion resulting in him falling into arrears with his rent. This has resulted in his rent remaining unpaid Case No: 234552 Determination Page 4 of 9 for two months at a time and has left him having to pay the rent from his own funds. 15. He has requested the FSP make sure the rent is paid one month in advance but it has not offered any response to his request. 16. He advises that the FSP continues to fall behind in the payment of his rent. Summary of FSP’s Position Building 17. The delays experienced in authorising builder B to proceed with repairs to the fire damaged insured building were the direct result of the failure of the Applicant’ s preferred builder to submit a quote, as requested by the Applicant, in a reasonable period of time. 18. On receiving advice the Applicant did not wish to pursue the quotation, authority was given to builder B to proceed with repairs. 19. Further, a letter dated 24 February 2011from the Applicant’s lawyer noted that the Applicant was considering a cash settlement for the building aspect of the claim rather than employing the services of builder B. This contributed to further delays as, although already authorised by the FSP, builder B was not allowed to commence works. 20. On 22 March 2011, the loss adjuster informed the FSP that the Applicant had signed the necessary contracts and demolition work had commenced. The FSP was also advised that repairs would take four or five months to complete due to the amount of work required to reinstate the property. Contents 21. As at 2 May 2011, the FSP had not received a list of the contents signed off by the Applicant. 22. The FSP’s latest information is that the contents aspect of the c laim is in its final stages before settlement with the Applicant to formally sign off on the final list. 23. Upon receipt of the returned signed list, the loss adjuster advises they will be in a position to recommend full and final settlement of the contents deemed non- restorable. Payment of Rental for Temporary Accommodation 24. The FSP maintains that it has maintained regular rental payments as evidence by the recommendations contained in the loss adjuster’s various reports. Case No: 234552 Determination Page 5 of 9 25. The Applicant has the opportunity to take up temporary accommodation in accordance with the terms of his policy for the duration of repairs or the remainder available under the policy limit, whichever is the lesser. 26. The FSP relies on the following policy/contract provisions: ‘Other benefits w e will provide 1. Additional cost of temporary accommodation (Applicable only when you have contents cover) ‘additional costs’ mean those rental and other related costs which you have to incur at the location of your temporary accommodation which are in addition to the costs you would have had to incur if you continued to live at your risk address. ... We will pay for temporary accommodation for: the period which we agree is reasonably necessary, or 12 months, Whichever period of time is the lesser. ... ‘What happens after you make a claim 1. Assist us with your claim You must assist us with your claim. This means you give us all the information and assistance with your claim which we may reasonably require. If you do not we may not pay your claim or provide cove r.’ Issues 27. Whether the FSP has managed the A pplicant’s claim in accordance with good insurance practice and the General Insurance Code of Practice. Reasons for Decision Building 28. The Applicant’s house was damaged by fire on 15 September 2010. Key activities after that date were: • 15 October Scope of Works (SOW) provided to loss adjuster; • 19 October Copy of SOW provided to builders B, P and L; • 26 November Quote received from builder B; • 17 December Quote received from builder P; • 21 February 2011 Loss adjuster informs FSP it is still seeking a quotation from Applicant’s preferred builder L. Applicant advises loss adjuster he no longer wants builder L to quote; • 22 March Applicant signs contract with builder B to commence repairs. Case No: 234552 Determination Page 6 of 9 29. The Applicant’s house was severely damaged by fire as evidenced from the two quotes to carry out repairs that is, $169,400 and $208,010. The last quote was received on or about 17 December 2010, three months after the fire. 30. However, it appears that very little was done to progress the repairs other than the loss adjuster still pursuing a quote from builder L. This was five months after the fire. 31. The Panel is mindful that the Applicant’s inability to source a quote from his builder would have contributed to the delay in commencing repairs at his property. However, the FSP, having elected to settle the building claim by way of repair, assumes a responsibility to undertake the repairs in a timely manner. 32. The FSP, through its loss adjusters and building panels has the experience and resources to ensure the Applicant is returned to his pre-loss situation as soon as possible. It appears that the Applicant is inexperienced in such matters and the FSP has a responsibility to assist him in meeting his responsibilities, rather than simply awaiting his responses to occasional requests from the adjuster, who appears to have taken a passive approach to the progress of this matter. 33. Even though the matter did progress to the stage where some repair work commenced, it appears there has been little if any supervision of the work, and the builder’s lack of progress appears to have gone un -noticed and unmanaged. Even if the lack of management falls to the adjuster, the FSP must accept responsibility for his actions (or lack of). 34. The Panel finds the tardy progress in obtaining quotes, and perception of the absence of urgency on the part of the loss adjuster to progress repairs as being unacceptable. The Panel’s opinion is supported by a Scope of Works being submitted to the loss adjuster on or about 15 October 2010. 35. Accordingly, the Panel determines in accordance with Clause 8.3 of the Terms of Reference an independent experienced Building Project Manager be appointed as a matter of urgency to oversee the completion of the building repairs. 36. Therefore, the Applicant and FSP are invited to submit the names of two independent experienced Building Project Managers to the Panel. The Panel will appoint a Project Manager from the names submitted. 37. The parties are to submit their nominees by 2 September 2011. Contents 38. In response to an email from the Financial Ombudsman Service (FOS) dated 10 August 2011 to the FSP, on 15 August 2011, the FSP informed FOS that on or about 8 August 2011 it had made a final settlement offer for the A pplicant’s contents claim for the amount of $56,038.14. 39. The FSP is awaiting a response from the Applicant. Case No: 234552 Determination Page 7 of 9 40. Subject to the Applicant’s acceptance of this offer the FSP is to make payment within 5 working days of receiving the release. Payment of Rental for Temporary Accommodation 41. The Applicant contends that there has been an ongoing problem with the FSP being overdue in paying his rent. 42. The FSP states that it has been making payments in a timely manner. 43. The FSP has submitted copies of only three payment forms for authority to pay the rent. These were: • 16/11/2010 $3,128 Rent period unknown; • 22/12/2010 $1,564 Rent period 24/11/10 to 24/12/10; • 22/2/2011 $3,128 Rent period 26/1/11 to 25/3/11. 44. These payments confirm the FSP had a history of late payments of the A pplicant’s rent. The Applicant states late payments continue to be made. 45. In response to FOS’ email dated 10 August 2011, the FSP responded on 15 August 201 stating: “ With respect to the rental accommodation – our records indicate payment has been arranged for upto (sic) and including the period 26/07/2011 until 25/08/2011 (paid 09/08/2011). We have instructed the loss adjuster to calculate settlement for the balance remaining of the 12 month period available under the policy. Once the adjuster has calculated the amount we will issue the payment to the insured.” 46. The FSP, in its email of 16 August 2011 has agreed to pay to the Applicant the balance available under the Temporary Accommodation benefit and to pay this in advance, in full. 47. The FSP is required to make this payment within 5 working days of acceptance of this determination. Other Matters 48. The Panel considers general Insurance Code of Practice relevant to this dispute is: ‘ 3. INSURANCE CLAIMS 3.4 The following standards apply to all claims. 1. We wil l conduct claims handling in a fair, transparent and timely manner.’ General Insurance Terms of Reference 8.3 Specialist input ... Case No: 234552 Determination Page 8 of 9 b) FOS may also obtain expert advice including from a legal expert, industry expert, medical practitioner or building expert appointed by FOS. FOS may require the Financial Services Provider to pay or contribute to the cost provided that: (i) the fees of the expert are reasonable, having regard to the complexity of the dispute; and (ii) the fees do not deviate significantly from the usual market rate for such advice; and (iii) the person has the necessary expertise. Unless exceptional circumstances apply, FOS will not require the Financial Services Provider to contribute more than $3,000 per Dispute to the cost of expert advice obtained by FOS. ... 1. 9.3 Other compensation 2. ... 3. b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial 4. Services Provider compensate the Applicant for non-financial loss but only where: 5. (i) an usual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind has occurred; 6. ... 7. The maximum amount of compensation for non-financial loss will be $3,000 per claim made 8. in the Dispute. 9. ... 10. 9.4 Applicant’s costs in pursuing the matter 11. FOS may decide that the Financial Services Provider contribute to the legal or other professional costs or travel costs incurred by the Applicant in the course of the Dispute. Unless exceptional circumstances apply, FOS will not require the Financial Services Provider to contribute more than $3,000 to these costs. Determination SUMMARY 12. The Panel determines: as a matter of urgency, a Building Project Manager be appointed to manage the completion of r epairs to the Applicant’s property; Case No: 234552 Determination Page 9 of 9 the FSP to finalise the Applicant’s contents claim within 5 working days of acceptance of its offer; the FSP to pay the balance of the Applicant’s rental benefit within 5 working days of acceptance of this determination; the FSP to pay compensation of $2,000 to the Applicant for the unreasonable delays encountered in the completion of the building repairs and rental payment delays; the FSP is to indemnify the Applicant in the sum of $3,000 towards his legal cost which the Panel notes have been invoiced in the sum of $5,318.93 if paid prior to 21 September 2011.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.