Determination 234552
Fire claim: delayed building repairs, contents settlement and temporary accommodation rent
Summary
After a fire, the applicant complained about delayed building repairs, slow contents settlement and late rent payments for temporary accommodation. AFCA ordered a building project manager appointed, payment of the contents offer and rent balance, a legal cost contribution and $2,000 non-financial loss.
Having elected to settle the building claim by repair, the FSP assumed responsibility to progress the repairs in a timely manner under the General Insurance Code standard of fair, transparent and timely claims handling.
Issues
- Delay primary · upheld
“The Panel finds the tardy progress in obtaining quotes, and perception of the absence of urgency on the part of the loss adjuster ... unacceptable.”
- Poor claim handling secondary · upheld
“There appears to have been little if any supervision of the work; the builder's lack of progress went unnoticed and unmanaged.”
Subjects and remedies
home or building damagepay claimpay compensationpay non financial lossrepair or rectify
Text of the determination
Case No: 234552 Determination Page 1 of 9
Case number: 234552
General Insurance – Home Building and Contents – Rectification of damaged
building – Settlement of contents claim – Outstanding Rental payments
28 September 2011
Background
1. The Applicant is being assisted by a lawyer in the handling of his dispute with
the Financial Services Provider (FSP) and will be referred to as the Applicant in
this determination.
2. The Applicant insured his home and contents under a Home Insurance Policy
for $637,000 and $153,153 respectively with a $200 policy excess. The policy
commenced on 5 December 2005 and had been renewed to 5 December 2011.
3. On 15 September 2010, the insured building and contents were badly damaged
by fire. After preliminary investigations were completed by the FSP, it agreed to
accept the claims for the cost of repairs to the building and repairs and
replacement of contents items damaged in the fire.
4. However, due to the unacceptable delay in commencing repairs to the building,
settlement of his contents claim and delays in meeting his temporary
accommodation costs, the Applicant has submitted a notice of dispute with the
Financial Ombudsman Service (FSP).
Building Dispute
5. The following is a chronology of activity with the claim:
Date Comments
15/09/10 Fire damages insured property;
16/09/10 Loss adjuster inspects site;
20/09/10 First adjuster’s report
05/10/10 Scope of Works for repairs to the building submitted to the
adjuster
16/10/10 Second adjuster’s report to the FSP enclosing copy of the
Scope of Works;
19/10/10 Copy of Scope of Works submitted to builders B, P and
Applicant’s preferred builder L;
27/10/10 Third adjuster’s report – pursuing quotes from builders;
Determination
Case No: 234552 Determination Page 2 of 9
26/11/10 Fourth adjuster’s report – quote for $169,400 received from
builder B; still pursuing quotes from P and L;
17/12/10 Fifth adjuster’s report – quote for $208,010 received from
builder P’
14/02/11 Sixth adjuster’s report still pursuing quote from builder L;
21/02/11 Seventh adjuster’s report – Still no quote from builder L,
adjust er reports failure of L to submit quote has resulted in
significant delays in commencement of building repairs;
16/03/11 Email from FSP to adjuster – FSP wanted clarification as to
whether rebuilding had commenced or if the Applicant still
wanted a cash s ettlement;
22/03/11 Adjusted received written confirmation from Applicant’s
lawyer that Applicant wants building repairs completed by
builder B and had signed a contract with the builder;
19/04/11 Ninth adjuster’s report – Builder B is currently underta king
repairs and adjuster is monitoring progress
Contents
Total claimed amount estimated to be $115,000
19/10/10 Loss adjuster reports ‘L’ a Contents Service company was
in the process of providing an inventory of items they have
cleaned and salvaged and identifying items not
salvageable;
27/10/10 Adjuster reports L completed inventory. Adjuster in process
of obtaining quotes;
17/12/10 Applicant provides a further list of items not noted on the
inventory provided by L;
14/02/11 Adjuster received an upda ted inventory of claimed items.
Report sent to FSP for review;
21/02/11 Applicant to review updated list and to advise amount he
would be satisfied to settle for; when response received
from Applicant, adjuster will make a recommendation re
settlement of contents claim;
22/03/11 Adjuster reports the Applicant is still updating list; ( However
Applicant’s lawyer had submitted list of claimed items to the
FSP, letter was dated 01/03/11 and apparently received by
the FSP on 10/03/11).
07/04/11 Letter from lawyer to FSP – advising claimed list of contents
sent to the FSP on two occasions and still waiting for cash
settlement offer;
19/04/11 Adjuster advises he has sent a final list of claimed items to
the Applicant for checking.
Case No: 234552 Determination Page 3 of 9
Rental payments
6. In addition, the Applicant reports the FSP has not been paying his rental in a
timely manner resulting in demands from the rental property manager.
Summary of Applicant’s Position
Building
7. He is not satisfied with the progress of the building works at the insured
property. He seeks authority to take control of the building process and appoint
a builder to commence construction to the damage caused to his house without
delay.
8. He is frustrated at the number of telephone calls he has made to the FSP to
progress his claim. He states that construction of his house was due to be
completed within six months of the fire but finalisation of repairs is still to be
resolved.
Contents
9. His claim for damage to his contents has been delayed by the FSP because it
has not made payment for the purchase of replacement contents except for a
lump sum payment of $10,000 which was totally inadequate and insufficient to
properly meet his claim.
10. The Applicant had numerous items of contents and furniture with a list being
collated by the FSP which was not provided to him for some significant time
after which he had to re-purchase some contents from his own funds to at least
accommodate himself to a minimum standard.
11. He is short of finance and continues to experience financial difficulties and the
delays caused by the FSP in not progressing his claim in a timely fashion is
causing him loss and extreme distress. He has not received sufficient funds to
reimburse him for the loss of his contents and this has continued to be ignored
by the FSP.
12. He has asked the FSP on numerous occasions as to when he can expect
payment due to him in relation to the contents destroyed in the fire and he has
not received a response.
13. A detailed list of contents was collated by the FSP and finalised by him
allocating values for the contents but the issue has not been addressed by the
FSP.
Payment of Rental for Temporary Accommodation
14. The FSP has not met his rental payments in a timely fashion resulting in him
falling into arrears with his rent. This has resulted in his rent remaining unpaid
Case No: 234552 Determination Page 4 of 9
for two months at a time and has left him having to pay the rent from his own
funds.
15. He has requested the FSP make sure the rent is paid one month in advance
but it has not offered any response to his request.
16. He advises that the FSP continues to fall behind in the payment of his rent.
Summary of FSP’s Position
Building
17. The delays experienced in authorising builder B to proceed with repairs to the
fire damaged insured building were the direct result of the failure of the
Applicant’ s preferred builder to submit a quote, as requested by the Applicant,
in a reasonable period of time.
18. On receiving advice the Applicant did not wish to pursue the quotation,
authority was given to builder B to proceed with repairs.
19. Further, a letter dated 24 February 2011from the Applicant’s lawyer noted that
the Applicant was considering a cash settlement for the building aspect of the
claim rather than employing the services of builder B. This contributed to further
delays as, although already authorised by the FSP, builder B was not allowed
to commence works.
20. On 22 March 2011, the loss adjuster informed the FSP that the Applicant had
signed the necessary contracts and demolition work had commenced. The FSP
was also advised that repairs would take four or five months to complete due to
the amount of work required to reinstate the property.
Contents
21. As at 2 May 2011, the FSP had not received a list of the contents signed off by
the Applicant.
22. The FSP’s latest information is that the contents aspect of the c laim is in its
final stages before settlement with the Applicant to formally sign off on the final
list.
23. Upon receipt of the returned signed list, the loss adjuster advises they will be in
a position to recommend full and final settlement of the contents deemed non-
restorable.
Payment of Rental for Temporary Accommodation
24. The FSP maintains that it has maintained regular rental payments as evidence
by the recommendations contained in the loss adjuster’s various reports.
Case No: 234552 Determination Page 5 of 9
25. The Applicant has the opportunity to take up temporary accommodation in
accordance with the terms of his policy for the duration of repairs or the
remainder available under the policy limit, whichever is the lesser.
26. The FSP relies on the following policy/contract provisions:
‘Other benefits w e will provide
1. Additional cost of temporary accommodation (Applicable only when you
have contents cover)
‘additional costs’ mean those rental and other related costs which you have to
incur at the location of your temporary accommodation which are in addition to the
costs you would have had to incur if you continued to live at your risk address.
...
We will pay for temporary accommodation for:
the period which we agree is reasonably necessary, or
12 months,
Whichever period of time is the lesser.
...
‘What happens after you make a claim
1. Assist us with your claim
You must assist us with your claim. This means you give us all the information and
assistance with your claim which we may reasonably require. If you do not we may
not pay your claim or provide cove r.’
Issues
27. Whether the FSP has managed the A pplicant’s claim in accordance with good
insurance practice and the General Insurance Code of Practice.
Reasons for Decision
Building
28. The Applicant’s house was damaged by fire on 15 September 2010. Key
activities after that date were:
• 15 October Scope of Works (SOW) provided to loss adjuster;
• 19 October Copy of SOW provided to builders B, P and L;
• 26 November Quote received from builder B;
• 17 December Quote received from builder P;
• 21 February 2011 Loss adjuster informs FSP it is still seeking a
quotation from Applicant’s preferred builder L.
Applicant advises loss adjuster he no longer wants
builder L to quote;
• 22 March Applicant signs contract with builder B to commence
repairs.
Case No: 234552 Determination Page 6 of 9
29. The Applicant’s house was severely damaged by fire as evidenced from the
two quotes to carry out repairs that is, $169,400 and $208,010. The last quote
was received on or about 17 December 2010, three months after the fire.
30. However, it appears that very little was done to progress the repairs other than
the loss adjuster still pursuing a quote from builder L. This was five months
after the fire.
31. The Panel is mindful that the Applicant’s inability to source a quote from his
builder would have contributed to the delay in commencing repairs at his
property. However, the FSP, having elected to settle the building claim by way
of repair, assumes a responsibility to undertake the repairs in a timely manner.
32. The FSP, through its loss adjusters and building panels has the experience and
resources to ensure the Applicant is returned to his pre-loss situation as soon
as possible. It appears that the Applicant is inexperienced in such matters and
the FSP has a responsibility to assist him in meeting his responsibilities, rather
than simply awaiting his responses to occasional requests from the adjuster,
who appears to have taken a passive approach to the progress of this matter.
33. Even though the matter did progress to the stage where some repair work
commenced, it appears there has been little if any supervision of the work, and
the builder’s lack of progress appears to have gone un -noticed and
unmanaged. Even if the lack of management falls to the adjuster, the FSP must
accept responsibility for his actions (or lack of).
34. The Panel finds the tardy progress in obtaining quotes, and perception of the
absence of urgency on the part of the loss adjuster to progress repairs as being
unacceptable. The Panel’s opinion is supported by a Scope of Works being
submitted to the loss adjuster on or about 15 October 2010.
35. Accordingly, the Panel determines in accordance with Clause 8.3 of the Terms
of Reference an independent experienced Building Project Manager be
appointed as a matter of urgency to oversee the completion of the building
repairs.
36. Therefore, the Applicant and FSP are invited to submit the names of two
independent experienced Building Project Managers to the Panel. The Panel
will appoint a Project Manager from the names submitted.
37. The parties are to submit their nominees by 2 September 2011.
Contents
38. In response to an email from the Financial Ombudsman Service (FOS) dated
10 August 2011 to the FSP, on 15 August 2011, the FSP informed FOS that on
or about 8 August 2011 it had made a final settlement offer for the A pplicant’s
contents claim for the amount of $56,038.14.
39. The FSP is awaiting a response from the Applicant.
Case No: 234552 Determination Page 7 of 9
40. Subject to the Applicant’s acceptance of this offer the FSP is to make payment
within 5 working days of receiving the release.
Payment of Rental for Temporary Accommodation
41. The Applicant contends that there has been an ongoing problem with the FSP
being overdue in paying his rent.
42. The FSP states that it has been making payments in a timely manner.
43. The FSP has submitted copies of only three payment forms for authority to pay
the rent. These were:
• 16/11/2010 $3,128 Rent period unknown;
• 22/12/2010 $1,564 Rent period 24/11/10 to 24/12/10;
• 22/2/2011 $3,128 Rent period 26/1/11 to 25/3/11.
44. These payments confirm the FSP had a history of late payments of the
A pplicant’s rent. The Applicant states late payments continue to be made.
45. In response to FOS’ email dated 10 August 2011, the FSP responded on 15
August 201 stating:
“ With respect to the rental accommodation – our records indicate payment has
been arranged for upto (sic) and including the period 26/07/2011 until
25/08/2011 (paid 09/08/2011). We have instructed the loss adjuster to calculate
settlement for the balance remaining of the 12 month period available under the
policy. Once the adjuster has calculated the amount we will issue the payment to
the insured.”
46. The FSP, in its email of 16 August 2011 has agreed to pay to the Applicant the
balance available under the Temporary Accommodation benefit and to pay this
in advance, in full.
47. The FSP is required to make this payment within 5 working days of acceptance
of this determination.
Other Matters
48. The Panel considers general Insurance Code of Practice relevant to this
dispute is:
‘ 3. INSURANCE CLAIMS
3.4 The following standards apply to all claims.
1. We wil l conduct claims handling in a fair, transparent and timely manner.’
General Insurance Terms of Reference
8.3 Specialist input
...
Case No: 234552 Determination Page 8 of 9
b) FOS may also obtain expert advice including from a legal expert, industry expert,
medical practitioner or building expert appointed by FOS. FOS may require the
Financial Services Provider to pay or contribute to the cost provided that:
(i) the fees of the expert are reasonable, having regard to the complexity of the
dispute; and
(ii) the fees do not deviate significantly from the usual market rate for such advice;
and
(iii) the person has the necessary expertise.
Unless exceptional circumstances apply, FOS will not require the Financial Services
Provider to contribute more than $3,000 per Dispute to the cost of expert advice
obtained by FOS.
...
1. 9.3 Other compensation
2. ...
3. b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial
4. Services Provider compensate the Applicant for non-financial loss but only
where:
5. (i) an usual degree or extent of physical inconvenience, time taken to resolve the
situation or interference with the Applicant’s expectation of enjoyment or peace of
mind has occurred;
6. ...
7. The maximum amount of compensation for non-financial loss will be $3,000 per
claim made
8. in the Dispute.
9. ...
10. 9.4 Applicant’s costs in pursuing the matter
11. FOS may decide that the Financial Services Provider contribute to the legal or
other professional costs or travel costs incurred by the Applicant in the course of
the Dispute. Unless exceptional circumstances apply, FOS will not require the
Financial Services Provider to contribute more than $3,000 to these costs.
Determination
SUMMARY
12. The Panel determines:
as a matter of urgency, a Building Project Manager be appointed to
manage the completion of r epairs to the Applicant’s property;
Case No: 234552 Determination Page 9 of 9
the FSP to finalise the Applicant’s contents claim within 5 working days of
acceptance of its offer;
the FSP to pay the balance of the Applicant’s rental benefit within 5
working days of acceptance of this determination;
the FSP to pay compensation of $2,000 to the Applicant for the
unreasonable delays encountered in the completion of the building repairs
and rental payment delays;
the FSP is to indemnify the Applicant in the sum of $3,000 towards his
legal cost which the Panel notes have been invoiced in the sum of
$5,318.93 if paid prior to 21 September 2011.