Denial of claim - flood total loss of stolen and repaired vehicle

FirmFinancial Firm (Unknown - Insurer)
Decided2011-09-23
ProductGeneral Insurance · Motor
OutcomeFor the complainant in part
Amount awarded$12,620
Non-financial loss—
Amount claimed$47,923
SourceAFCA PDF

Summary

The Applicant's stolen and recovered vehicle was damaged while stored under the FSP's care and was later declared a total loss in the January 2011 floods. The FSP denied the flood loss as outside the expired policy, but AFCA ordered payment of the $12,500 agreed value, interest and the registration balance, and rejected the repair costs claim.

The FSP failed to return the vehicle to pre-loss condition after the theft and was responsible for damage while in its care, so it must indemnify the agreed value, but the repair costs incurred were a lost cost.

Issues

Subjects and remedies

natural disastertheft or burglarypay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 234526 Determination Page 1 of 9 Case number: 234526 General Insurance - Domestic Insurance - Motor Vehicle - Comprehensive - FSP Decision - Denial of Claim 16 September 2011 Background 1. The Applicant held a comprehensive agreed value motor vehicle insurance policy with the Financial Service Provider (FSP) from 26 August 2005 to 26 August 2006 and the policy was current at the time of loss. The agreed value of the vehicle, a Nissan 300ZX was $12,500 with a basic excess of $750 and a theft excess of $2,000. 2. The insured vehicle was stolen but recovered in a damaged state. 3. The Applicant lodged a claim for the theft of the vehicle on 19 September 2005. The claim was accepted by the FSP and the vehicle damage repaired except for the dispute in relation to the damage to the engine of the vehicle. 4. The dispute was referred to the Service to determine whether the FSP was liable to investigate the damage to the engine and whether that damage related to the theft of the vehicle. The Service determined that the FSP was liable to assess the engine and repair the damage. 5. Following the Service’s D etermination the Applicant’s vehicle engine was assessed and found to be damaged. The FSP was to attend to the repairs of the engine. 6. However, whilst the vehicle was stored at F (under the FSP’s care) , the period during which the Applicant’s dispute was being reviewed by the FSP and the Service, the vehicle sustained extensive damage and had some parts stolen. 7. Further assessment of the vehicle revealed that it required extensive mechanical and panel repairs. 8. The FSP then decided to consider the vehicle a total loss, as the cost of repairs may have outweighed the agreed sum insured under the policy. However, the Applicant referred this decision back to the Service and the FSP was required to repair the vehicle and bring it to its pre -loss condition. Determination Case No: 234526 Determination Page 2 of 9 9. The vehicle was initially transferred to the FSP’s repairer BL. However, when it was noted that there were considerable delays in repair works experienced with BL, the vehicle was then transferred to BR which was the Applicant’s preferred repairer and closer to his place of residence. 10. The vehicle was being repaired and the repairs were being monitored by the Applicant and the FSP’s assessor from September 2007 to January 2011. 11. Whilst the vehicle was being repaired at BR, the vehicle sustained flood damage in January 2011 and was deemed a total loss. 12. The FSP denied liability for this loss and is of the view that it has fulfilled its obligations under the policy by attempting to repair the damage sustained as a result of the theft and says that the flood damage is a new event which falls outside the Applicant’s policy period. 13. The Applicant is of the view that flood damage to the vehicle should be cove red by his comprehensive motor insurance policy which expired in August 2006. He states that the policy should be considered active as the initial claim was still open with ongoing repairs. Summary of Applicant’s Position 14. The Applicant holds the FSP responsible for the additional and extensive damage sustained to his vehicle whilst at F as it was under the FSP’s care and because it was the FSP ’s decision to store the vehicle at F. 15. The Applicant says that the initial vehicle damage caused by the theft was repaired by the FSP except for the dispute relating to the engine of the vehicle and that the vehicle was in a repaired condition until it sustained additional damage whilst at F. 16. The Applicant is of the view that the damage sustained at F cannot be related to the initial damage caused by the theft. 17. The Applicant says that following the reassessment of the vehicle (after it was found that it had sustained extensive damage whilst at F) the FSP attempted to write off the vehicle. 18. However, he sought further assistance from the Service in this regard and it was determined that the FSP should repair the vehicle to its pre -loss condition. 19. The Applicant says that the wheels of the vehicle were stolen whilst stored at F and that he was unable to replace them for $800 as authorised by the FSP and therefore requested the FSP to revise this amount to $1,200. 20. Further, the Applicant acknowledges that he offered to purchase aftermarket parts for the brakes and engine parts (the Applicant preferred to upgrade the performance of the engine) and that this cost fell within the approved limits of Case No: 234526 Determination Page 3 of 9 the FSP. He also accepted that (as advised by the FSP) a life time guarantee will not be extended on these parts. 21. The Applicant confirms that he accepted a cash settlement for part of the repair work relating to the engine and that at no time was he advised that it was in full and final settlement of the claim. 22. The Applicant lists the following outstanding repair works which were to be completed but for the floods in January 2011:  Brakes  Interior work  Gearbox and differential not inspected  Exhaust not replaced  Suspension not replaced  Front flight inserts not completed  Mash insert over vents  Third brake light  Cylinder heads  Intercooler  Seat frames 23. The Applicant says that he was not informed by the FSP that he was responsible for the completion of the repairs and that the Applicant was not privy to this discussion between the repairer and the assessor. 24. The Applicant also confirms that he was not aware that his claim was closed by the FSP. 25. The Applicant say s that the FSP failed to act on the Service’s previous Determination to pay the interest awarded and to pay the cost of six months vehicle registration and that at no time did he enter into any agreement with the FSP which forfeited his rights under the previous Determination. 26. The Applicant is of the view that the FSP’s negligence caused extensive damage to his vehicle, which in turn delayed the repairs until the floods in January 2011. 27. Since the repairs were not completed, the Applicant is of the view that the FSP is responsible for the loss and that his claim should be covered under his policy which expired in August 2006. 28. The Applicant says that six months vehicle registration amounts to $420 and not $300 as reimbursed by the FSP and questions how the FSP has calculated the recent payment of interest amounting to $3,000. Case No: 234526 Determination Page 4 of 9 29. The Applicant is of the view that the FSP never returned his vehicle in its pre- loss condition subsequent to the theft and expects the FSP to reimburse the agreed value of the vehicle amounting to $12,500 and the cost of repairs spent on the vehicle amounting to $35,423 as the full and final settlement of the claim. Summary of FSP’s Position 30. The FSP, in its notice of response, says that even though there was an initial delay in attending to the engine repairs, the rest of the repairs to the vehicle were completed by way of an agreement with the Applicant and therefore it was not bound to pay interest from January 2007 to date as requested by the Applicant. 31. Since then, the FSP has agreed to pay interest as determined by the Service in 2007 amounting to $3,000 (not supported by calculation). 32. Further, the FSP acknowledges the delays experienced in completion of repairs and that the assessor had not followed up the repairer consistently so that the repairs could be progressed. The FSP has awarded compensation of $3,000 for the delays and inconvenience caused to the Applicant whilst the vehicle was being repaired. 33. Following the previous Determination, the FSP has now settled $300 for the cost of six months vehicle registration fees. 34. The FSP lists the cost of repairs and cash settlements incurred and says that had the vehicle been considered a total loss in September 2007, it would have incurred the agreed value sum insured of $12,500 with interest of $740.83. 35. The following expenses and payments have been incurred by the FSP: Item Amount Date Repairs JJ $5,500. 03/12/2008 BL $11,999. 21/02/2009 BL $1,509. 07/09/2009 S $800 24/03/2009 Towing $110 13/10/2009 BP $1182. 11/04/2006 Cash settlements Car seats $900 18/02/2009 Engine work $13,000 19/08/2009 Floor mats, carjack & wheel brace $423 16/03/2006 Interest $3,000 07/07/2011 Compensation $3,000 07/07/2011 Case No: 234526 Determination Page 5 of 9 Six months registration $300 07/07/2011 A total of $41,723 has been incurred to date in relation to this claim. 36. The FSP says that it paid $13,000.53 for the remaining repairs to the engine so that the Applicant could attend to the additional modifications he wished to upgrade the engine with. 37. The FSP is of the vie w that since the Applicant’s vehicle is now considered a total loss as a result of the January 2011 floods, its life time repair guarantee on the works completed to date will cease and be no longer valid as the vehicle has reached the end of its serviceable life. 38. The FSP says that the loss caused by the floods falls outside the scope of the Applicant’ s policy which expired in August 2006 and will not be covered. 39. The FSP relies on the following policy provisions: “ WHAT IS COVERED ... Partial loss If we agree to pay your claim for partial loss or damage we may chose to:  repair your vehicle , or any part of it, or  replace any part of your vehicle , or  pay you the cost of repairing or replacing your vehicle , or any part of it. ... WHAT IS NOT COVERED If we agree to pay your claim under this policy we will not pay you more than:  The quote from the repairer you choose as adjusted by our assessor, or  The agreed value of your vehicle, whichever is lesser.” 40. The FSP acknowledges that there were outstanding repairs to the Applicant’s vehicle, but states that it is not obliged to complete these repairs now, as the vehicle has been deemed a total loss as a result of an unrelated incident, which is the flood. 41. Therefore, the FSP is of the view that it is not entitled to reimburse the Applicant for the total loss of the vehicle as a result of the flood event nor the repair costs incurred to date. Issues 42. Whether the FSP is entitled to deny the Applicant’s claim for the agreed value of the vehicle of $12,500 caused by a flood. Case No: 234526 Determination Page 6 of 9 43. Whether the FSP is liable to indemnify the Applicant for the cost of repairs incurred amounting to $35,423. 44. Whether the FSP’s settlement for interest is in accordance with the previous Determination of the Service. 45. Whether the FSP’s payment of $300 towards the six months vehicle registration is correct. Reasons for Decision 46. Due to the nature of this dispute, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 47. I am satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. 48. I understand the FSP’s position that the current damage caused by the flood occured well ou tside the policy period of the Applicant’s policy which expired in August 2006. 49. However, it should be noted that the majority of the damage sustained to the vehicle which caused the delay in completing the repairs was related to the extensive damage which occurred whilst in the care of the FSP and stored at F. It is also noted that some parts of the vehicle were stolen whilst at F. 50. At the Service’s request, the FSP has commented on the outstanding repairs as below; “ Brakes: We paid $5500.00 on the 27/11/08 for the supply of a full brake kit for the vehicle as per insured’s request to his supplier. (fitment is still yet to be done) Interior: We paid Bodyworks Unlimited $1509.20 for interior 07/09/09. Gearbox & differential: Unable to report anything until checked by mechanic when car drivable (sic) & can be road tested. (no visible damage) Exhaust: Waiting for engine rebuild before getting a report on what’s required to fix exhaust. Suspension: Unable to report anything until checked by mechanic when car drivable(sic) & can be road tested. (no visible damage) Front Light insert not completed: Don’t know anything about this, should have been done by original repairer Bodyworks Unlimited. Mesh insert over vents: Waiting on insured to supply a quote. Third brake light: Don’t know anything about this. Cylinder heads: These items are included in the engine quote which insured was cash settled for totalling:$13000.53. Intercooler: We were waiting on quote from insured’s mechanic. Case No: 234526 Determination Page 7 of 9 Seat Frames: We have already cash settled insured for new aftermarket seats totalling:$900.00 on the 18/02/09.” 51. Even though the assessor is of the view that the damage to the cylinder heads was included in the payment of $13,000.53 for the engine rebuild, I am of the view that this is not the case. 52. The file notes of the FSP (after the payment for engine rebuild) state: “INSUREDS MECHANIC H AS QUOTED A PRICE TO REBUILD THE STANDARD MOTOR. PLEASE CASH SETTLE INSURED FOR MOTOR REBUILD: $13000.53 ... 27/07/2009 ... SIGHTED CAR AT BR & CYLINDER HEADS CANT (SIC) BE RECONDITIONED AS THEY HAVE BEEN EXPOSED TO OVERHEATING & THE ALUMINIUM HAS GONE SOFT MECHANIC ADVISED TO GET A SET OF SECONDHAND ONES & RECONDITION THEM ALSO INSURED INTERCOOLER ISDAMAGE(SIC) WILL NEED REPLACING. VR ADVISED TO SEND A SUPP QUOTE THOUGH FOR THESE ITEMS SO I CAN ARRANGE TO CASH SETTLE INSURED ... 13/11/2009 CLUTCH IS DAMAGED & NEEDS REPLACING. AWAIT FOR MECHANIC UPDATE 04/03/2010 ... AT THIS STAGE I AM WAITING ON SUPP QUOTE FROM [ APPLICANT’S] MECHANIC FOR HEADS AND GEARBOX REPORT. WHEN THESE ARE RECEIVED I WILL ORGANISE A CHEQUE AND CASH SETTLE [APPLICANT] FOR THESE ITEMS ... 22/12/2010” 53. Based on the above, I am satisfied that the work on the vehicle was not completed as it is quite clear that the assessor was still waiting on quotes for various items just before the flood. 54. I understand that the FSP has accepted that the claim was poorly managed by the assessor and thereby awarded compensatio n of $3,000 to the Applicant in this regard. 55. Both the FSP’s and the Applicant’s repairers have delayed the repair process and therefore, I am not inclined to hold any one person responsible for the overall delays in completing the repairs. Case No: 234526 Determination Page 8 of 9 56. I regard the compensation payment of $3,000 made by the FSP to the Applicant as an ex gratia payment that does not prevent me from considering a further payment of compensation under clause 9.3 of the Terms of Reference (TOR). However, having considered the circumstances of this dispute and the contribution of both parties to the delay, I simply say that it was appropriate for the FSP to make the payment but I do not propose to determine any further payment as regards compensation under clause 9.3 of the TOR. 57. I am of the view that the Applicant was entitled to have his vehicle returned to him in its pre-loss condition after the initial loss and the FSP failed to fulfil its obligations in this regard. 58. Further, I believe that the FSP is responsible for the additional damage caused to the vehicle whilst under its care with its nominated storage or repairer F. 59. I note that the Applicant never received a fully functioning vehicle after the theft and subsequent Determination by the Service on the dispute relating to the engine. The vehicle has been under repairs from the last quarter of 2007 until January 2011 when it was damaged by a flood and declared a total loss. 60. I am of the view that the FSP is liable to indemnify the Applicant for the pre-loss condition by providing a fully functioning vehicle or a financial benefit to the agreed value of the vehicle. 61. Therefore, it is fair and reasonable in all the circumstances that the FSP reimburses the Applicant the agreed value of the vehicle to the amount of $12,500. 62. I note that the Applicant has requested a cash settlement of $35,423 being the repairs costs incurred by the FSP to date. However, the FSP is not required to make any such payment as the repair expenses incurred by the FSP and the Applicant will be considered as lost cost and was nullified when the vehicle was declared a total loss. 63. Further, with regard to the calculation of interest, I am of the view that the interest on the agreed value sum insured of $12,500 is to be calculated (as per the previous Determination) at the rate of 8.5% from 23 January 2007 until the final settlement of this claim is made. The FSP may deduct the initial payment of interest in the amount of $3,000 from this payment. 64. Finally, a Case Manager of the Service has contacted the Quee nsland Department of Transport regarding the registration fees and it was confirmed via a phone call that the six months vehicle registration renewal fee is $420.00. Determination 65. On the basis of the available information, I determine that the FSP is liable to indemnify the Applicant for the agreed value of the motor vehicle amounting to $12,500. However, the Applicant is not entitled to receive any other payments towards the repair expenses incurred by the FSP and himself. Case No: 234526 Determination Page 9 of 9 66. I also determine that the Applicant is entitled to the balance of the interest payment and six months registration fees due as explained above.