Home / Financial Firm (Unknown - Insurer) / Determination 232451

Determination 232451

Loss of rent claim denied on basis property was untenantable rather than uninhabitable

FirmFinancial Firm (Unknown - Insurer)
Decided2012-03-21
ProductGeneral Insurance · Landlord
OutcomeFor the complainant
Amount awarded$9,040
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant's rented house was damaged by malicious damage and the FSP denied loss of rent as the property was untenantable rather than uninhabitable. AFCA determined the policy responded, awarding loss of rent of $11,200 less an 8-week deduction for the applicant's delay and the policy excess, plus interest at 8.25 percent.

The dictionary meaning of uninhabitable is not able to be inhabited, and the unrebutted opinion of a senior property manager that the house was unliveable until repaired brought it within the cover.

Issues

Subjects and remedies

pay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 232451 Determination Page 1 of 6 Case number: 232451 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of Claim - Loss of Rent 29 February 2012 Background 1. I have reviewed all the material submitted by the parties and save where I make note specifically, I am satisfied the Background as set out in the Recommendation is accurate and is as follows. 2. The Applicant held a landlord insurance policy with the Financial Services Provider (FSP), which was current at the time of the loss. 3. On 6 April 2010, the Applicant lodged a claim with the FSP for malicious damage occasioned to her property. 4. The FSP accepts malicious damage has occurred and repairs were authorised to the property, which were completed in March 2011. 5. The Applicant seeks loss of rent at $220 per week from the date of the claim until the completion of repairs. 6. The FSP has denied the claim for loss of rent on the grounds that the property was not considered inhabitable but merely “untenantable”. 7. The Applicant did not agree with the F SP‟s decision, hence the dispute, which was the subject of a Recommendation. The Recommendation was in favour of the Applicant and not accepted by the FSP. The Applicant accepted the Recommendation. In the circumstances, the matter has been referred to me for Determination. Summary of Applicant’s Position 8. I have reviewed all the material submitted by the parties and save where I make note specifically, I am satisfied the Applicant's position as set out in the Recommendation is accurate and is as follows. 9. The Applicant says that there were extensive delays before repairs were authorised by the FSP. Determination Case No: 232451 Determination Page 2 of 6 10. She further says the FSP informed her that if she commenced repairs, the policy would not respond. 11. Had repairs been commenced earlier or had she been permitted to undertake the work at an early stage she would have been in a position to tenant the property at a much earlier date. 12. Furthermore, the word “uninhabitable” is ambiguous and open to interpretation. 13. The Applicant accepted the Recommendation and in response to the FSP‟s position sent an email dated 17 January 2012 essentially reiterating her position in more detail. She also provided a letter dated 13 January 2012 from RG a Senior Property Manager at a RW Property Consultants in the relevant town who said: “T his letter is to inform the owner that in my honest opinion and with knowledge and experience in the Real Estate Industry, the above state property located at [subject address] was unliveable. I would and will not put a tenant in the property until the property was brought up to a liveable standard.” Summary of FSP’s Position 14. I have reviewed all the material submitted by the parties and save where I make note specifically, I am satisfied the FSP‟s position as set out in the Recommendation is accurate and is as follows. 15. The FSP says that cover for loss of rent is only if the property is uninhabitable. It describes this as being a property that cannot be lived in. It said a property couldn‟t be lived in without the use of essential services such as water, electricity and gas, and a working kitchen, bathroom and toilet. 16. The FSP says further that the property may have been untenantable for a period while under repair or capable or being rented at a smaller rent but it was habitable and therefore there is no cover for loss of rent. 17. The FSP relies on the following policy provision contained within the Product Disclosure Statement (PDS) which the Applicant does not dispute receiving: “Loss of Rent With this option, if your buildings or sections of your buildings suffer loss or damage and are uninhabitable as a result, we will cover any loss of rent equal to the weekly amount as stated on your rental agreement or periodic tenancy agreement for up to 12 months. ... We will ONLY cover loss of rent while your rental prope rty is uninhabitable.” Case No: 232451 Determination Page 3 of 6 18. The FSP rejected the Recommendation and in an email dated 23 December 2011 essentially reiterated its position. It said: “We note from the recommendation that the policy wording of uninhabitable has been determined by FOS as meaning – “not able to be inhabited”. Our position is the home was able to be lived in, as we made mention the property would have been undergoing repairs and that the rental amount would have to be adjusted but we consider that the property was in a state that it could have been rented albeit at a lower rate. We are aware the new tenant may have been inconvenienced however the policy wording does stipulate – “we will only cover loss of rent while your rental property is uninhabitable.” We therefore consider that the property was able to be re let and that the property was therefore able to be occupied.” 19. It did not make further comment on the Applicant‟s letter dated 17 January 2012 or the letter from RG dated 13 January 2012. Issue 20. Whether the FSP is entitled to deny the claim on the grounds that the property was uninhabitable. Reasons for Decision 21. There has been an exchange of material between each party, and I am satisfied each party has had an opportunity to reply to the issues raised. 22. Each FOS case is decided on its merits, taking into account the facts of the case. I have reviewed all the material submitted by the parties both before and after the Recommendation was issued, in order to reach my decision. I will only refer to the relevant submissions and materials raised. 23. In reaching a decision, it is appropriate to consider the Terms of Reference under which FOS operates. The Terms of Reference require that I consider what is fair in all the circumstance having regard to the relevant legal principles, the terms of the relevant policy and good industry practice. Regard should also be had to prior Determinations, although such Determinations are not binding or precedents. 24. The salient facts appear to be that when last inspected on 23 December 2008, the house w as “maintained to an acceptable standard however there were some items of maintenance noted which should be considered” – see report from H Real Estate dated 23 December 2008. Case No: 232451 Determination Page 4 of 6 25. The house was rented at $220 a week, which was to increase to $250 a week. I assume it did not increase to $250 as the Applicant has claimed always at the rate of $220 per week. 26. The tenants vacated the house and the house was inspected on or about 23 March 2010 at which time the state of the property had deteriorated considerably. 27. Th e FSP‟s assessor refers to a police report (which I have not seen) which refers to a break in at some time between 14 April and 6 May 2010 during which break in further damage was done. 28. In any event, the Applicant says a claim was made on 6 April 2010 (this date is not disputed by the FSP) and the FSP‟s assessor attended the property on 5 July 2010. It is not clear to me why there was such a delay between the claim made and that first attendance. 29. I have read carefully the several reports of the FSP‟s assess or and in all the circumstances of a claim with the many items for repair and many causes of the damage, I do not find there has been inordinate delay in assessing the claim. The assessor appears to have waited for some time for a detailed statement from the Applicant outlining the events leading to the claim. This was to hand on 28 0ctober even though it had been requested sometime in July. After assessing and adjusting the claim and receiving instructions from the FSP, the builders were instructed to commence repairs on 2 December 2010 save for the provision of the excess which was to hand on 18 January 2011 and the building works were then scheduled to commence 7 to 10 days thereafter and were completed on or about 29 March 2011. 30. It is not in dispute that the Applicant‟s property was maliciously damaged and otherwise damaged and that it required extensive repairs, which were undertaken by the FSP and completed on or before 29 March 2011. 31. It is also not in dispute that the FSP, or its attending loss assessor, informed the Applicant that she was unable to undertake any of the repair work. The PDS says: “ You must ... not repair or replace any damaged buildings or contents without our consent.” 32. What is in dispute is whether the house was “uninhabitable” as a r esult of the damage and therefore could not be rented. 33. The key word is not defined in the policy. However, the Macquarie Dictionary describes “uninhabitable” as being “not able to be inhabited.” The Collins Dictionary describes the word to mean “ unsuitable for living in”. Case No: 232451 Determination Page 5 of 6 34. The FSP also contends this to mean a property that cannot be lived in. It said a property couldn‟t be lived in without the use of essential services such as water, electricity and gas, and a working kitchen, bathroom and toilet. It says this property still had those features. 35. The FSP says that it could have been rented out albeit at a significant cheaper rental but this does not mean it is “uninhabitable” as described but just “untenantable.” 36. I have considered carefully the photographs tak en by the FSP‟s assessor. I have also considered carefully the extensive description of works that had to be done and the cost of those works. 37. I have also considered the opinion of RG who is described as a Senior Property Manager. She says the property was “unliveable” and that she wouldn‟t put a tenant in it “until it was brought up to a liveable standard”. 38. This statement from RG was not rebutted by the FSP. I place great weight on it as RG is in the business of putting tenants into property and she says it is not only untenantable but also unliveable. Because of the Dictionary definitions, I am of the view that the words “unliveable” (RG‟s word) and “uninhabitable” mean the same thing. 39. Accordingly, in my view, for the reasons stated above, I determine that the policy responds as the house was damaged and was uninhabitable until it was repaired. 40. The house was without tenants for over a year. The most that can be claimed under the policy is $11,200 for this head of damage. Policy excesses apply. 41. In the FSP„s assessor‟s report of 2 December 2010, the FSP has instructed the policy excess to be $400. 42. However, I am of the view that it is fair in all the circumstances that the FSP does not have to pay the loss of rent for all of that period, as there was an unexplained delay by the Applicant in providing a detailed statement regarding the claim and relevant documentation. The assessor first inspected the property on 5 July. I presume he asked for this documentation at or about that time or the time of his first report, which is dated 20 July. The material was provided on 28 October. In my view, it would have been reasonable to provide this within say 4 weeks of request. – say by the end of August, at the latest. Accordingly, in my view, it is reasonable in all the circumstances and in view of the policy condition that requires an insured to “give us any information ….we require to investigate and process your claim”, to reduce the amount payable by 8 weeks for the delay in providing the relevant information. I calculate this amount to be $1,760. Case No: 232451 Determination Page 6 of 6 Determination 43. On the basis of the available information, and for the reasons stated above, I determine that the FSP is required to pay the Applicant for the loss of rent in the amount of $11,200 less $1,760 less any relevant policy excesses. 44. I further determine that the FSP pay interest of 8.25% per annum on the sum ultimately payable to the Applicant from the date of the IDR letter dated 16 February 2011 at which time it had all relevant information to make its decision.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.