Text of the determination
Case No: 232268 Determination Page 1 of 14
Case number: 232268
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of Claim - Insured Event - Liquid Escaping Suddently and Unexpectedly
- Leaking Pipe - Policy Exclusion - Soil Movement or Settlement - Drought and
Rains - Quality of Repairs
31 August 2011
Background
1. The Applicants hold a home building insurance policy with the Financial
Services Provider (FSP).
2. On 10 July 2007, the Applicants lodged a claim with the FSP who recorded the
following claim description:
“THIS AFTERNOON, A PIPE IN OUR NATURE STRIP, (SIC) B URST AND THE
WATER GUSHED INTO OUR HOUSE. THE WATER WENT THROUGH OUR
SIDE AND FRONT WINDOWS AND ALSO THROUGH A VENT IN THE ROOF.
THE PIPE IS THE PROPERTY OF [XYZ]…”
3. The FSP accepted the claim and arranged for the repair of the insured building.
4. The repairs were completed on or about 19 June 2008.
5. On 5 August 2008, the Applicants contacted the FSP and advised that cracks
appeared on the areas repaired. The FSP attended to the new cracks.
6. On 29 December 2008, the Applicants informed the FSP that further cracking
has occurred. The FSP authorised rectification works on or about 6 May 2009.
The rectification works were completed sometime in August 2009.
7. On 6 May 2010, the Applicants contacted the FSP regarding the re-appearance
of cracks on the same areas previously repaired by the FSP.
8. This time, the FSP denied the claim on ground of the policy exclusion of loss or
damage caused by soil movement or settlement. In its 30 November 2010
letter to the Applicants, the FSP, relying on its expert report, stated that “(t)he
cracking is in relation to the drought in the Melbourne area over the years
combined with the normal rains in 2010.”
9. The Applicants are not satisfied with the FSP’s decision, hence this dispute.
Determination
Case No: 232268 Determination Page 2 of 14
Summary of Applicant’s Position
10. The Applicants say that the FSP should carry out repairs to their house “where
it has cracked again in the areas that have supposedly been fixed twice
before”, including the living area, family room, two bedrooms, kitchen,
passageway and the bathroom. The FSP should also repair the doors that do
not close, and “a wardrobe which is coming away from the wall”. They assert
that (a)ll these cracks are in the exact areas that occurred when the water from
the nature strip flooded under [their] home.” The rest of the house do not have
cracks.
11. The y also say that the floor boards now squeak whereas prior to the FSP’s
repairs to the stumps the floor boards did not squeak.
12. They also allege that the FSP’s assessor inspected the insured property on 11
May 2010. During the inspection of the kitchen/family areas, the assessor said
that the kitchen/family area “has not been fixed properly in the first instance and
the bulging was due to faulty workmanship.” The assessor said that it should be
repaired again. When the Applicants informed the FSP about this, they were
told that this assessor did not know what he was talking about because he did
not know the history of the case.
13. To refute the FSP ’s conclusions, the Applicants have organised an inspection
by their own expert . Their “Engineer’s Report” dated 5 June 2011 states that
“ the majority of damage observed with this building is associated with the
leaking and (2) burst water pipe events ” and “[they] do not agree that the
building movements are related to the drought. ”
Summary of FSP’s Position
14. The FSP contends that the “continuing movement” of the insured building “is no
longer the result of an insured event such as the burst water main on 10 July
2007”. Rather, it “is now and has been since January 2009 due to climati c
conditions and resultant settlement, shrinkage, and expansion” which are
excluded under the policy.
15. The FSP alleges that as early as September 2007, there was doubt as to the
genesis of the damage sustained to the building.
16. It further alleges that the floor problems more recently experienced by the
Applicants were a result of a pre-existing defect on the subfloor area. The
Applicants have “candidly admitted to pre -existing issues in respect of the need
to re- level the building”.
17. The FSP relies on the expert reports by SS, H, and SR. It says that based on
SS and H’s reports, the cracking and movement in the building is attributable to
the result of the following uninsured events :
movement of the property due to reactive clay foundations;
differential movement attributed to the footing foundation;
Case No: 232268 Determination Page 3 of 14
the relatively wide footing present beneath the existing dwelling being
particularly susceptible to heave related movement of the clay soil profile;
generally poor site drainage and a lack of surface sealing around the
building;
potential problems that may be occurring with the stormwater drains
around the house;
seasonal changes in moisture content of the foundation material related to
the recent drought; and
seasonal wetting and drying of the foundation zone soil profile.
18. The FSP relies on the following policy provision contained in the Product
Disclosure Statement (PDS):
“ What we do not cover
- general exclusions
You are not covered under any section of the policy for damage, loss, cost or
liability caused by or arising from or involving:
…
soil movement or settlement” .
Issues
19. The cause of the continuous cracks and movements on the insured building.
20. Whether the FSP must again perform rectification works on the insured
building.
Reasons for Decision
21. Due to the nature of the dispute, the Financial Ombudsman Service (FOS) has
considered it appropriate to expedite the dispute in accordance with the
Operational Guidelines to the FOS Terms of Reference. Thus, this dispute has
not been the subject of a FOS Recommendation and has proceeded directly to
Determination. The parties have been previously advised that a Determination
will be issued in this case.
The FSP’s evide nce
22. The FSP has provided the following expert reports.
Geotechnical Reports/Advice by SS
23. The FSP has submitted a geotechnical investigation report by SS dated 25
September 2007. The report relevantly reads:
“ 6.0 OPINION
Case No: 232268 Determination Page 4 of 14
…
It is likely that the water main, which we are informed burst approximately 2
months, is responsible for the observed wetting of the upper portion of the clay
profile in both borehole and the footing probe. Such wetting will be accompanied
by volumetric swell.
The relatively wide footing present beneath the existing dwelling will be
particularly susceptible to heave related movement of the clay soil profile. It is
likely that heave of the clay resultant from the wetting has lifted the footings.
We note the surface gradient falling towards the front of the dwelling, and the
lack of surface sealing around large portions of the front (northern and southern)
sides. These factors could contribute to a seasonal wetting and drying of the
foundation soil profile.
It is therefore debatable whether the single flooding event has been responsible
for the damage, or rather observed damage is the combination of many cycles of
seasonal wetting and drying of the foundation zone clay soil profile, caused by
generally poor site drainage and a lack of sur face sealing around the dwelling.”
24. SS prepared a geotechnical advice dated 4 March 2008 following a further
investigation on the insured property on 21 January 2008. According to SS:
“ 4.0 COMMENTS
In a comparison with the results of the previous investigation (dated 25
September 2007), the soil moisture content in borehole 1 has decreased
noticeably at 0.6m depth (from 34.7% to 26.47), but increased marginally at 0.8m
and 1.0m depth. The soil moisture content beneath the existing footings has
decreased significantly at 0.7 depth (from 40.3% to 22.90%).
Soil moisture conditions as measured in this site visit (21.1.2008) are considered
to be within a „normal‟ range considering the site geology plus current seasonal
and overall climate (drought) conditions.”
25. Another geotechnical advised was prepared by SS on 18 October 2010 after a
further investigation on 6 October 2010. SS wrote:
“In a comparison with the results of the two previous investigations, the overall
trend is an increase in soil moisture content.
At 0.6m and 0.8m depth in borehole 1 the soil moisture content has increased
significantly at the same location in the previous investigation; and at 1.0m depth
has remained relatively consistent.
In borehole 2 there has been a significant increase compared with the
investigation dated 04-03-2008.
With the exception of 1.0m depth in borehole 1 the soil moisture contents are
s[t]ill considered to be higher than normal.
This overall increase in soil moisture content during this investigation (dated 06-
10-2010) is a similar trend to the initial investigation (dated 25-09-2007) both of
which were conducted during spring where relatively higher rainfall would be
occurring, compared with the second investigation (dated 04-03-2008) which
was conducted at the beginning of autumn.”
Case No: 232268 Determination Page 5 of 14
26. All of the above were prepared after investigations by an engineering geologist.
Reports by Engineer H
27. T he FSP submitted a “Site Inspection” report by Engineer H dated 2 February
2009 after an inspection on 7 January 2009. The report relevantly reads:
“ HISTORY
…
A further assessment was carried out in March 2008 and this showed that a
considerable amount of movement was occurring both internally and externally
to the building. It was indicated that these repairs were completed around June
2008. These works form part of what is known as secondary damage.
It was indicated that since the repairs in June 2008, further cracking and
movement has been occurring in the house, particularly in areas where previous
repair were carried out to the interior plasters walls. It was indicated that these
problems became evident around September last year [2008]. This additional
movement, which has occurred since September 2007, is known as the third
area of damage.
…
CONCLUSIONS
...
The third area of damage, which has only been reported recently, has resulted
due to minor movement occurring in the concrete stumps to the house. All of the
cracking and movement is occurring in the same areas where repairs were
carried out for the secondary damage. As mentioned previously, it is possible
that water could have ponded underneath the house for some time following the
burst in the water main and it is possible that a further monitoring should have
been left before repairs were carried out to the interior of the house.
It would appear that only nine months was allowed for the monitoring time and in
our opinion, a period in excess of twelve months should have been given before
repairs were carried out to the house.”
Therefore, in our opinion, the movement now evident in the third area of damage
has resulted due to the house not being left for sufficient time for the foundation
material to dry out, due to the burst in the water main, before repairs were
carried out to the house.
In our opinion, a full twelve months has now occurred since the burst in the water
main and in our opinion, any effects of the water due to the burst in the water
main would have dissipated by now.
Therefore, in our opinion, if any further movement occurs in the house in the
future, particularly to the interior walls, then this movement would be related to
the recent drought and not related to the burst that occurred in the water main.
Minor cracking is occurring to the new brickwork, particularly around the south
west corner and in our opinion, this cracking and movement is related still to the
recent drought and possibly problems with storm water drains and this problem
is not related to the burst in the water main.”
Case No: 232268 Determination Page 6 of 14
28. A “Second Site Inspection” report was prepared by H on 26 November 2010.
The report noted the following damaged areas during the site inspection on 10
November 2010:
front entrance passageway - cracking around the archway leading to the
lounge room area;
main bedroom at the front of the house - door does not close properly and
there is a gap between the built in wardrobes and the south wall;
second bedroom – door is binding and there is hairline cracking around
the door area;
lounge room area – there is hairline cracking around the window in the
east wall and the door leading to the kitchen meals area does not close
properly;
meals area – lifting of the plaster area around a previously repaired crack
around the door leading to the lounge room area;
bathroom – door does not close properly and there is a hairline cracking
around the door on the passageway side;
sub floor area – very dry at the time of inspection with evidence of
previous packing of the stumps;
29. The report noted that “generally all of the cracking and movement reported
were in areas observed during [the] initial site inspection” on 7 January 2009.
“No other problems were reported or observed at the time of [the second]
inspection”.
30. It then concludes as follows:
“ CONCLUSIONS
From our recent site inspection it would appear that similar movement is
occurring around the areas where previous repairs were carried out following
initial site inspection.
A burst occurred in the water main around 10 July 2007. In our opinion, any
[e]ffects of the moisture from this burst water main would have dissipated by now
as it is over three years since the burst occurred.
Therefore, in our opinion, any [e]ffects of the burst water main would no longer
be affecting the moisture contents of the foundation material for a period of up to
12 to 18 months depending on the type of leak.
From the recent moisture readings taken of the foundation material it would
appear that a general increase has occurred in the moisture content of the
moisture material in Bore Hole 1 and a reduction has occurred in Bore Hole 2
over the spring period. Relatively normal rains have been occurring over 2010. It
should be noted that when the burst in the water main occurred a drought was
affecting the Melbourne area and therefore, the moisture content of the
foundation material could have been lower than would normally be expected.
Repairs have been carried out to the building while the moisture content was low
over the drought period.
Case No: 232268 Determination Page 7 of 14
Normal rains have been occurring in the 2010 period which can be increasing
the moisture content back to normal levels prior to the drought. Therefore, this
adjustment in the moisture levels can result in further movement occurring of the
foundation material particularly around areas where previous repairs have been
carried out.
Therefore, in our opinion, the additional cracking occurring in the house has
resulted due to further movement in the foundation material related to the
stabilising of the foundation material between the drought and the normal rains
that have been occurring this year. In our opinion, the movement is not related to
the moisture from the burst in the water main as this occurred over 3 years ago.”
Report Regarding Sub-Floor Area by SR
31. The FSP also submitted a report by SR dated 20 July 2009. The report reads:
“We are advising [the FSP] that when we entered the sub floor area at the
[insured] property to glue and wedge floor boards to joists we found several joists
that are over spaced. The joists should be spaced at 450 centres, however, we
found several that were spaced over 500mm. In some areas the floor boards
were not nailed, the nails having missed the joist. We have fitted some extra
joists where spacing was extreme and have glued in place. We have not top
nailed as this will require extra time and require removal of furniture and carpet.
We have been able to eliminate some of the bounce and squeaks, but not all.
The floor requires more joists in other areas and top nailing to floors. We have
advised owner of problems and that problem caused when home was first built.
Owner states that these problems were not there prior to water leak and wants
[the FSP] to repair. ”
The Applicants’ Evidence
32. The Applicants submitted B’s Engineer’s Report dated 5 June 2011 . B
inspected the insured property on 24 May 2011.
33. B stated that according to the Applicants, there have been two burst events:
“ 1. Brief Background
…
The owner informed us that on 2 separate occasions, a sub-terrain pipe, (located
on the nature strip of the footpath directly in front if the house), burst. The first
burst was on 20 March 2007 & the second burst was on 10 July 2007. On the
second occasion, a water fountain sprayed water on the front end of the house,
resulting in water damage to various aspects of the house. The majority of the
cosmetic damage had been made good after the second burst pipe event.
The Owners expressed their concerns in relation to continual movements and
cracks/defects in the house…”
34. B noted the following damaged areas:
“ 2. Damage Concerns & observations
We inspected the building both internally and externally (refer to the attached
sketch for a record of floor levels) and noted the following:-
Case No: 232268 Determination Page 8 of 14
I. Externally there were cracks, damage and concerns as follows:
a) The sealant in the articulation joists was not flexible.
b) Many of the subfloor vents were obscured by the timber floor framing. The
vents along the rear parts of the house (which were re-built) were
obscured by insulation in some areas and timber framing in other areas.
c) Bubbling paint was observed along the eaves lining, beside the window
from Bed 1.
II. Internally there were cracks and damage concerns as follows:
a) A 5mm wide crack was located in the archway leading into the living room
area beside the front entry door. The owner informed us that the crack
appeared over 10 years ago, and they had arranged for the stump
beneath the west side if the archway to be strengthened. The crack did
not re-appear until after the burst water pipe.
b) An approximately 10mm wide gap was present between Bed 1 robe and
the south wall;
c) An approximately 300mm ling section of plaster, was building over the
east side of the doorway leading into the living room from the kitchen. A 1
mm wide horizontal crack was located the west side of the door.
d) An approximately 200 mm long section of plaster, was bulging over the
west side of the doorway leading into the passageway from the kitchen.
e) A 1 mm wide horizontal crack was located at the top north side of the front
entry door.
f) A 1 mm diagonal crack was located at the top east side of the door
leading into Bed 2
g) A 1mm wide vertical crack was located at the top west side of the door
leading into Bed 2.
h) The remainder of the house was in good condition, without any signs of
major cracking, however, there were other minor cracks.
III. Floor levels revealed the following:
a) The south-east corner of the dining room/house was the highest point.
b) Both the north-east and north-west corners, were relatively low points,
with the north-west corner being the lowest point of the house.
c) A slope of 20mm down towards the west, was recorded along the north
wall of the living room.
d) The midpoint of the north wall of the living room, was the lowest internal
point for the house.”
35. B gave the opinion that “the majority of damage observed with this building, is
associated with the leaking and (2) burst water pipe events”, thus:
“3. [B] Assessment
The movement and cracks in this building are most likely related to the
changed soil moisture content and surrounding site conditions, which have
resulted in differential movements in the building. The site has „H‟ soil type
present… In brief, clay expands when it is moist and shrinks when it dries.
The net result associated with changes in soil moisture content, is that the
ground surface level fluctuates (up and down). In a class H soil, the ground
Case No: 232268 Determination Page 9 of 14
surface level can be expected to fluctuate from 40 to 70mm. These
fluctuations occur under normal seasonal weather patterns (i.e. dry season to
wet season) and do not take into consideration abnormal conditions, such as
drought or floods, which can result in larger ground surface level movements.
For this reason it is important to minimize soil moisture content fluctuations
both around and beneath the building. It is our opinion that the following
factors have contributed to the movements:
Footings
The footings are not adequate, by modern standards, for this type of building,
however they would have complied with the relevant regulations at the time of
construction. The existing footings are approximately 400 mm deep founded
700mm below ground level…. We note however that since the building was
performing well prior to the burst water pipe, it is our opinion that the footing
size/depth is not the cause of the building movements, however it means that
the footings are more sensitive to soil moisture content changes and in
particular events (i.e. flooding/burst pipes).
…
Trees
…
Water
A leaking pipe can contribute to the movement of the footings and hence the
building. Clay expands when it is moist and shrinks when it dries. A water
source can saturate the clay, and hence cause it to swell. As the clay swells,
the building moves up (heaves) in the area beside the leak/excessive
moisture, whilst the dry areas of the bu ilding remain relatively low…
It is our opinion that the majority of damage observed with this building, is
associated with the leaking and (2) burst water pipe events. The direct
damage caused by water (i.e. carpets, paintwork etc) does not require further
works, however the building movements (and associated damage) are still an
issue.
The soil moisture content readings carried out by the soil tester, confirm that
soil moisture content at the base of the footings was excessively high in
September 2007, ha d reduced down to „excepted‟ levels in 2008 and
increased slightly in October 2010. The soil moisture content results suggest
that the soil moisture content at the front of the house, (i.e. for the strip
footings) seems to have returned to the „pre -burst p ipe‟ condition…
We express our concerns in relation to the soil moisture content readings,
which were only taken at the front of the house, as follows:
No readings were taken at the rear of the house (downhill).
No readings were taken under the house.
…
…Without a soil moisture content reading under the house, (and in particular
at the base of the stump footings), it is difficult to confirm if the soil moisture
content has stabilized. We also note that changes to soil moisture content
beneath the house, t ake longer to return back to „pre - event‟ condition, due to
the „protection‟ offered by the building and perimeter footings. For this reason
it is our opinion that the internal damage observed during ou[r] site visit, is as
Case No: 232268 Determination Page 10 of 14
a result of the stumps settling as the soil dehydrates from the effects of the
leaking/burst pipe/s.
Sub-floor Ventilation
…
Articulation joints
… ”
36. B also provided comments on the FSP’s various expert reports. B disagreed
with some of SS and H’s opinions. I note in particular the following comments.
“II. The writer of [the SS] report [dated 25 September 2007] provides their
opinion, that the reason for the high soil moisture content at the footing, is most
likely related to seasonal fluctuations in weather, as opposed to the single event
of a burst pipe.
We do not agree with his opinion, for the following reasons:
There was not just „one‟ burst pipe event. In fact there were 2 burst pipe
events.
The period (i.e. time) and quantity of water released into the ground, is not
known. The burst pipe is quite often the final event of pipe failure. Prior to the
actual burst, a leak is often present, which constantly discharges water into
the surrounding soil.
The two burst pipe events were observed during the dry season, and during
the drought, which could not account for the excessively high soil moisture
readings.
Apart from the crack in the archway, the owners confirmed that the building
was performing very well until the burst pipe events.
…
We reviewed the engineering report prepared by [H Engineers] dated 2 February
2009, and note the following:
…
III. We agree that further time should have been allowed prior to jacking and
packing the timber floor for the house (and repairing all subsequent internal
cosmetic damage). It is our opinion however, that 12 months is inadequate, due
to the fact that we do not know how long the leaking pipe has been present (prior
to the 2 burst events), and the fact that the floor level reveal a dishing of the
floor, which could be expected if the subfloor soil, dried out at a slower rate than
the perimeter walls, after the re-levelling works.
IV. In addition to the above point, we do not agree that the building movements
are related to the drought. Simply put, the drought cannot affect only part of the
property, and if the drought was the cause of the stump movements, then we
would have expected to record the exact opposite type of floor levels.”
…
We reviewed the engineering report prepared by [H Engineers] dated 26
November 2010 and note the following:
…
Case No: 232268 Determination Page 11 of 14
II. [H] states, „normal rains have been occurring over 2010. It should be noted
that when the burst in the water main occurred a drought was affecting the
Melbourne area and therefore, the moisture content of the foundation material
could have been lower than would normally be expected. Repairs have been
carried out to the building while the moisture content was low over the drought
period.
We agree that for the past 9 months the drought has been broken, and we are
now again experiencing normal rainfall. However, if the rains were affecting the
subfloor area of the house, then one would expect to see the stumps heaving
(i.e. lift), causing the central areas of the house to be higher, however this is not
the case, as our floor levels have confirmed, and the floor is actually dishing,
even though it has been re-levelled in the past.. For this reason we do not agree
with [H‟s] opinion that the floor movements are not related to the bust/leaking
pipe.” (sic)
37. B then made the following recommendations:
“We re commend that the most suitable solution to the movement problems
observed with this building, is to allow for the soil to dehydrate for another 6
months, then carry out the works as listed below. Dehydration under the house,
usually takes a number of years, and since it has almost been 4 years since the
events, it is our opinion that the majority of the building movements related to the
events, would have occurred, hence, re-levelling works may be carried out.
We recommend the following works be carried out immediately .
a) Agricultural drain
…
b) Moisture barrier
…
c) Sub-floor vents
…
d) Articulation Joints – brickwork
…
e) [XYZ] water pipe
…
We recommend that the following works be carried out at least 6 months after
the above works have been carried out.
f) Jack & Packing
The floor for the entire building should be jacked and packed so that it is
level.
g) Patch & painting internally
All cracks and damage to the house should be patched and painted after all
of the structural works (i.e. jacking & packing) have been completed.
h) Doors and windows
Doors and windows, which do not function properly, should be adjusted/made
operable, after all the structural works have been completed. Seal all window
& door gaps with maximum 5mm thick flexible sealant.
Case No: 232268 Determination Page 12 of 14
i) Monitor
Floor levels (similar to the attached sketch), should be recorded after the
house has been levelled, and issued to the owner. Floor level should be
taken at least 1 year later to assess if further building movements have
occurred, which may require additional works ”.
38. The FSP submitted its comments to B’s report on 13 July 2011. It is noted that
the comments were made by the FSP’s case manager, rather than SS or H.
The Applicant’s expert B then replied to the FSP’s comments on 2 Aug ust
2011.
Analysis/Conclusion
39. It is common ground that the Applicants’ claim on 10 July 2007 was covered
under the insured event of “Liquid escaping suddenly and unexpectedly from a
… fixed pipe”. Repairs were completed and rectification works were performed
twice by the FSP.
40. The Applicants now claim that cracks have again re-appeared and the floors
have moved in the same areas supposedly already repaired and rectified by the
FSP.
41. After a careful consideration of all the expert reports, I am of the opinion that
the FSP must again rectify the cracks and movements . My reasons are as
follows:
42. The FSP’s own expert, H, admits that “generally all of the cracking and
movement reported [on 10 November 2010] were in areas observed during
[the] initial site insp ection” on 7 January 2009. “No other problems were
reported or observed” on 10 November 2010.
43. It is my view that because the cracking and movements are in the exact areas
repaired by the FSP and no other cracks and movements have been observed
in the other areas of the building, there arises a rebuttable presumption that the
repairs were poorly made or were made prematurely having regard to the need
to allow the affected area to stabilize.
44. The onus therefore is on the FSP to prove that the continuous cracks and
movements were not due to poor repairs.
45. There is no dispute that the initial repairs were made earlier than it should have
been. H wrote in its 2 February 2009 report:
“It would appear that only nine months was allowed for the monitoring time and
in our opinion, a period in excess of twelve months should have been given
before repairs were carried out to the house.”
46. On the other hand, B said that:
“We agree that further time should have been allowed prior to jacking and
packing the timber floor for the house (and repairing all subsequent internal
cosmetic damage). It is our opinion however, that 12 months is inadequate, due
to the fact that we do not know how long the leaking pipe has been present (prior
Case No: 232268 Determination Page 13 of 14
to the 2 burst events), and the fact that the floor level reveal a dishing of the
floor, which could be expected if the subfloor soil, dried out at a slower rate than
the perimeter walls, after the re- levelling works”.
47. B also noted that the FSP/SS did not conduct a soil moisture content reading
under the house/at the base of the stump footings before repairs commenced.
Without this, “it is difficult to confirm if the soil moisture content has stabili zed” .
48. The FSP has submitted expert reports which essentially state that “the drought
and the normal rains” have caused the continuous cracks and movement s in
2010.
49. By way of rebuttal, the Applicant has submitted B’s report which concluded that
“the major ity of damage observed with this building, is associated with the
leaking and (2) burst water pipe events” in 2007.
50. In my opinion, B has successfully rebutted the FSP’s expert reports. I am
satisfied with B’s explanations as noted in paragraph 36 above. In particular, I
agree with the following points raised by B:
the drought cannot affect only part of the property;
if the drought was the cause of the stump movements, then the exact
opposite type of floor levels should have been recorded;
if the rains were affecting the subfloor area of the house, then the stumps
should have been heaving (i.e. lift), causing the central areas of the house
to be higher. However in this case, the floor is actually dishing, even
though it has been re-levelled in the past.
51. It is noted that the FSP has not submitted further expert reports to address or
rebut B’s report.
52. Therefore, I am satisfied that the continuous cracks and movements can be
attributed to the FSP’s poor repairs and are also necessarily related or linked to
the insured event of burst/leaking pipe in 2007.
53. With regard to the FSP’s submission that the “floor problems more recently
experienced by the Applicants were as a result of pre- existing defect”, I am of
the opinion that the FSP cannot now seek denial of the claim on the ground of
pre-existing defects because:
this ground was not included in the FSP’s denial letter dated 30 November
2010; and
the FSP’s expert SR has stated that the sub - floor problems were “caused
when [the] home was first built”. The Applicants say that the floor boards
did not squeak prior to the FSP’s repairs. In my opinion, the Applicants
would not have known about the alleged over spacing of joists or joists
missing nails. Section 46 of the Insurance Contracts Act (1984) provides
that if a claim is made in respect of a loss that occurred in whole or in part
as a result of a defect or imperfection in a thing and the insured was not
aware of the defect or a reasonable person in the circumstances could not
be expected to have been aware of the defect or imperfection the insurer
Case No: 232268 Determination Page 14 of 14
may not rely on an exclusion clause that refers to the condition of the
thing before the contract was entered into.
Determination
54. On the basis of the available information and the reasons stated above, I
determine that:
the FSP must rectify the cracks and movements on the insured building
as noted in H’s report dated 26 November 2010 and B’s report dated 5
June 2011 and which have been outlined above in paragraphs 28 and 34
above;
pursuant to 9.4 of the FOS Terms of Reference, the Applicants are
entitled to reimbursement of professional costs incurred in seeking the
expert reports from B. This entitlement is subject to the maximum limit of
$3,000 and to the Applicants’ proof of pay ment of professional fees to B.