Determination 231663
Defective repairs to wrought iron gate and door and delayed claims handling
Summary
The applicant disputed defective repairs to her front gate, sandstone step and rear wrought iron door and delays in claims handling. AFCA ordered the rear door replaced, cash settlement of the front repairs on a quote, and $2,000 non-financial loss compensation.
The FSP's repairs had not been completed to an acceptable standard after repeated attempts, and the delay was an unusual degree of physical inconvenience under clause 9.3(b) of the Terms of Reference.
Issues
- Repairs or contractors primary · upheld
“I determine that the FSP is to replace, as opposed to attempt to repair, the damaged wrought iron door with one of like quality.”
- Delay secondary · upheld
“the FSP has failed to (within a reasonable timeframe) fulfil its obligations under the policy.”
- Misleading conduct secondary · unclear
“The Applicant's concerns in this respect have been noted and the dispute will be referred to the Code Manager.”
Subjects and remedies
home or building damagepay claimpay non financial lossrepair or rectify
Text of the determination
Case No: 231663 Determination Page 1 of 7
Case number: 231663
General Insurance - Domestic Insurance - Home Contents - Service - Defective
Repairwork - Personal Injury - Delay in complaint handling
22 July 2011
Background
1. The Applicant holds a Home Building and Contents Insurance policy (the
policy) with the Financial Services Provider (FSP).
2. The Applicant lodged two claims (44 and 45) with the FSP seeking indemnity
for the cost of repairs associated with two separate insured events.
3. The FSP accepted the claims and proceeded to authorise repairs in line with
the terms of the policy.
4. The Applicant remains dissatisfied with the quality of repairs authorised by the
FSP and the management of her complaints by the FSP during the course of
the claims.
Summary of Applicant’s Position
5. The first of the two claims in dispute is in relation to damage to the front fence
and wrought iron gate of the insured property, due to constructions works
carried out by the municipal council in the area.
6. The second claim is in relation to damage to a wrought iron door at the rear of
the property, which occurred as a result of an attempted break in.
7. The Applicant has faced significant difficulty in dealing with the FSP and its
appointed builders “S” in relation to the management of the claim s.
8. Not only have the authorised repairs not been completed but whilst carrying out
the defective repairs, further damage has been done to the insured property.
9. The entire management of the claims has been riddled with false promises and
mistakes by the FSP and its appointed builders.
10. The Applicant has made herself available on many occasions at short notice for
repairs to be undertaken at her home, including assisting the builders due to a
shortage of hands at the time and yet the repairs have not been completed to
an appropriate standard.
Determination
Case No: 231663 Determination Page 2 of 7
11. Although the FSP has informed the Service that the Applicant’s concerns have
been addressed, this is not the case.
12. The Applicant has sent several letters to the Chief Executive Officer (CEO) of
the FSP outlining her concerns with the claims, however, she has not received
a response to her concerns.
13. The FSP has informed the Applicant’s local Member’s office that the repairs are
well under way to completion. Once again, this advice is misleading and
therefore obstructive.
14. As a result of the physical force required to open and close the front wrought
iron gate and rear wrought iron door, the Applicant has injured her left wrist.
15. The FSP is aware of the Applicant’s resultant injury , however, the FSP has
failed to address the problems with the faulty repairs.
16. Despite the FSP reassuring the Applicant that it would provide her with a copy
of its assessor’s report, the FSP has failed to do so.
Summary of FSP’s Position
17. The Service has not received a Notice of Response from the FSP in relation to
the concerns raised by the Applicant.
18. Notwithstanding, the Applicant informing the FSP on numerous occasions that
she is not satisfied with the repairs undertaken including but not limited to
contacting the FSP’s CEO, the FSP at last contact informed the Service that
t he Applicant’s concerns had been addressed.
19. The Service has approached the FSP in relation to the Applicant’s dispute and
requested that it submit a Notice of Response (NOR) explaining its position in
this regard. The FSP, however, has advised that due to its continuing efforts to
settle the matter, it is not able to submit the NOR and will await the
determination from the Service.
Issues
20. Whether the FSP has fulfilled its obligations under the policy in relation to the
repairs authorised under the claims lodged by the Applicant.
21. Whether the FSP is liable to make compensatory payments to the Applicant
due to the delays in the claims handling process.
Reasons for Decision
22. I am satisfied that a full exchange of information has taken place between each
party and that each party has had the opportunity to address any issues raised.
Case No: 231663 Determination Page 3 of 7
I have reviewed the submissions of the Applicant in relation to the terms and
conditions of the policy and will only refer to the relevant issues and materials
raised.
23. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with the Operational Guidelines to the FOS Terms of
Reference. This is due to the circumstances of the dispute. This dispute has not
been the subject of a FOS Recommendation and has proceeded directly to
Determination.
Consideration has been given to the evidence submitted by the Applicant and I note
she has the following outstanding concerns regarding her claims:
Claim 44 - Damage located to the front of the insured property
The front wrought iron gate has been set too low and as such she is
unable to open or close it without having to lift the gate with the use of her
entire physical force.
The damage to the base of the front fence has been repaired with a
concrete render. The person “DP” who was responsible for the repair had
previously informed her that any repairs completed using cement
rendering would break away within a year.
The paintwork carried out to the base of the fence sandstone and
concrete render area has been completed in the incorrect colour.
24. Having considered the available evidence, I am satisfied that the repairs to the
front wrought iron gate, sandstone step and base of the front fence have not
been completed to an acceptable standard.
25. I also note that there is a matter of the Applicant’s home being listed as a
heritage property, which may have been a contributing factor in the FSP not
being able to finalise repairs in this area after making numerous attempts.
26. Therefore, in the absence of any evidence to the contrary, a reasonable
outcome for this aspect of the dispute is for the Applicant to be allowed the
opportunity to obtain a reasonably priced quote from a repairer of her choice.
The FSP is then to cash settle the Applicant for the cost of repairs on the basis
of this quote.
Claim 45 – Damage to the rear of the property
The wrought iron door at the rear of the property has not been replaced.
The repair work ca rried out by the FSP’s appointed builder involved
“yanking out” of the door as opposed to unscrewing it from the fittings. In
this process the door was further damaged.
Case No: 231663 Determination Page 4 of 7
The door was returned, installed and re-soldered without the permission
of the Applicant and without informing her of the additional damage done
to the decorative work (broken).
The door is no longer straight, rather bows towards the lock area, making
it difficult to open and close in its operation as a security door.
S in an attempt to rectify the above mentioned issue, bent the hinges
backwards, however, this has not resolved the problem. The Applicant
maintains that the backward bending of the hinges has further
compromised the structural integrity of the door.
In order to unlock the door, the Applicant is required to use her left arm
and entire body weight to pull the door towards her, while attempting to
unlock it with her right hand.
The painting work, refilling and plasterwork at the rear of the property has
not been completed.
27. In the absence of evidence to the contrary, I am satisfied that the repairs to the
rear wrought iron door have not been addressed to an acceptable standard,
even after the FSP having had numerous opportunities to finalise this matter.
The door has been removed and reinstalled on multiple occasions after
attempts to repair it have been made, only to have it further damaged during
this time.
28. Therefore, I determine that the FSP is to replace as opposed to attempt to
repair, the damaged wrought iron door with one of like quality, standard and
decorative work.
29. In addition to the replacement of the rear wrought iron door, the FSP is also
responsible for the required rectification of paintwork, refilling and plasterwork
related to the original damage and subsequent attempts to repair this area of
the home.
Misleading Information
30. The Applicant maintains that the FSP has provided misleading information
during the course of the claim. The information referred to is:
The FSP informed the Service that all works had been completed and
the dispute stands as resolved. This information is obviously misleading
and obstructive.
The FSP has informed the Applicant’s local Member’s office that the
repairs were well on their way to completion. Once again the Applicant
states this is both misleading and therefore obstructive.
31. The Applicant’s concerns in this respect have been noted and the dispute will
be referred to the Code Manager to determine whether investigation under the
General Insurance Code of Practice is required.
Case No: 231663 Determination Page 5 of 7
Personal Injury
As a result of the physical force required to open and close the front
wrought iron gate and rear wrought iron door, the Applicant has injured
her left wrist.
The injury has been diagnosed to be “teno synovitis of the flexor carpi
radialis on the l eft side”.
The Applicant has had to have acupuncture and physiotherapy to remedy
the effects of the injury. However, both the Applicant’s GP and
physiotherapist have advised her that the injury will not heal until such
time that the cause has been remedied.
32. Consideration has been given to the Applicant’s position and supporting
evidence in respect to the physical injury allegedly sustained as a result of her
having to at great physical inconvenience, deal with the opening and closing of
the respective gate and door over this extended period of time.
33. However, as explained to the Applicant by the Case Manger, the Service
cannot make a determination of compensation in this regard and the Applicant
may need to consider a more appropriate forum to refer her concerns to in this
regard.
Compensation
34. I note the Applicant is seeking compensation for unreasonable delay, loss of
personal time and enjoyment, inconvenience faced, stress and a failure to
resolve her concerns, from the FSP.
35. I consider the FOS Terms of Reference relevant to this dispute are:
“9.3 Other compensation
a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial
Services Provider compensate the Applicant for consequential financial loss or
damage up to a maximum amount of $3,000 per claim made in the Dispute
...
b) Subject to paragraph 9.3c) and paragraph 9.7, FOS may decide that the Financial
Services Provider compensate the Applicant for non-financial loss but only where:
(i) an unusual degree or extent of physical inconvenience, time taken to resolve
the situation or interference with the Applicant’s expectation of enjoyment or
peace of mind has occurred; or
(ii) in the case of a Dispute pertaining to an individual’s privacy rights – injury has
occurred to the Applicant’s feelings or humiliation has been suffered by the
Applicant.
The maximum amount of compensation for non-financial loss will be $3,000 per claim
made in the Dispute.
c) Notwithstanding paragraphs 9.3 a) and b), FOS will not provide compensation for:
(i) consequential financial loss; or
(ii) non-financial loss,
Case No: 231663 Determination Page 6 of 7
in a Dispute arising as a result of a claim on a General Insurance Policy that expressly
excludes such liability”
36. Under 9.3(b) of the Terms of Reference (TOR), there must be an unusual
degree or extent of physical inconvenience, time taken to resolve the situation
or interference with the Applicant’s expectation of enjoyment or peace of mind
before compensation for non-financial loss may be determined.
37. Having considered all the material before me together with the relevant TOR
and in the absence of any argument to the contrary, I am satisfied that the FSP
has failed to (within a reasonable timeframe) fulfil its obligations under the
policy. As a result the Applicant has:
Faced physical inconvenience.
Endured an interference with her expectation of enjoyment and peace of
mind.
Dealt with a lack of security at the property over an extended period of
time.
Been subjected to an unreasonable period of time in respect to the
management of her claims.
38. Therefore, I am satisfied that such an unusual degree of physical
inconvenience and time taken to resolve the situation entitles the Applicant
pursuant to clause 9.3(b) of the TOR to non-financial compensation in the
amount of $2,000.
Determination
39. Accordingly, for reasons stated above, I determine that:
The FSP replace the rear wrought iron door with a new wrought iron door
of similar quality, standard and decorative work. In addition, the FSP is to
carry out the required rectification of filling, plastering and paintwork
associated with the insured event and subsequent attempts to repair this
area of the home.
The Applicant obtain and submit to the FSP a reasonable quote from a
repairer of her choosing for repairs to the front wrought iron gate,
sandstone step and base of the fence to the FSP for consideration.
The FSP is to within 14 days of receiving such quote from the Applicant
cash settle the Applicant for the cost of repairs.
The FSP in line with the relevant TOR is to compensate the Applicant in
the form of a payment of $2,000 for reasons stated above.
Case No: 231663 Determination Page 7 of 7
The Applicant’s complaints regarding the FSP’s claims handling will be referred to
the Code Manager to determine whether investigation under the General
Insurance Code of Practice is required.
.