Determination 230932

Storm roof damage claim denied as pre-existing installation defects and wear and tear

FirmFinancial Firm (Unknown - Insurer)
Decided2011-06-21
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed$24,107
SourceAFCA PDF

Summary

The applicant's roof leaked after a March 2010 hailstorm and the FSP denied the roof damage as pre-existing defects and wear and tear, after an eight-month delay in appointing an assessor. AFCA found the FSP had accepted liability by appointing its own repairer, and determined the FSP was not entitled to deny the roof damage claim, without stating a figure.

Having admitted liability by authorising repairs and delaying its assessment, the FSP could not rely on a later contrary roofing opinion, and no problems had manifested before the storm.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 230932 Determination Page 1 of 6 Case number: 230932 General Insurance - Home Building - FSP Decision - Denial of claim – Policy Exclusion 26 May 2011 Background 1. The Applicant holds a home and contents insurance policy issued by the Financial Services Provider (FSP). On 15 March 2010, the Applicant lodged a claim on the policy for storm damage to the property, caused by a major storm in Melbourne on 6 March 2010. 2. At claim lodgement the Applicant was instructed to obtain two quotes for repairs. Due to the high cost of repairs quoted by the Applicant’s repairers , the FSP appointed an assessor to assess the claim, who in turn, appointed a building expert (PM) to report on the cause and extent of the damage. 3. Upon receipt of its experts ’ reports, the FSP accepted liability and authorised for PM to carry out the repairs. After repairs were completed, further water damage occurred and PM was appointed to reinspect the property. On this occasion, PM reported that there was no evidence of any storm damage. Instead the damage was due to different profiles of tiles that were laid on the roof, which has caused oversize gaps between the tiles that has allowed rainwater to overflow and penetrate into the property. 4. The Applicant disagreed with PM’s findings. He appointed his own builder (SD) to report on the cause of damage, who stated that due to heavy rains and high wind the bedding to the valley tiles has been lifted and damaged, causing water penetration into the property. 5. Due to the conflicting findings, the FSP appointed a roof plumber (RC) to provide another report. RC stated that there was no evidence to support any storm or impact damage to the roof. The deteriorated condition of the roof was directly attributed to a number of pre-existing installation defects and some n ormal wear and tear. On the basis of RC’s report, the FSP denied liability for the roof damage. 6. The Applicant through his broker disputed the FSP’s decision and he is seeking indemnity for the roof damage from the FSP. Determination Case No: 230932 Determination Page 2 of 6 Summary of Applicant’s Position 7. The incident occurred on 6 March 2010, but a loss adjuster was not appointed until August and by this time the repair costs had escalated. 8. The F SP’s repairer quoted for repair to different areas of the roof. Therefore, the repair cost is substantially less than those provided by his repairers. 9. The FSP authorised PM to carry out repair to the lead sheeting. This confirms the damage was due to storm. 10. The works completed by the FSP’s repairer did not rectify the roof leak ( the roof never leaked until the storm on 6 March 2010). Water penetration occurred again and caused further damage to the property. Thus the cost of repairs increased from $17,916 to $24,106.60. The FSP would have accepted the quote of $17,916 but baulked at the revised quote. 11. SD’s report confirmed that heavy rains and high wind had lifted the bedding of the valley tiles, causing water penetration into the property. 12. He has cooperated and allowed at least three of the FSP’s experts to inspect the damage and all three have provided inconsistent reasons for the water ingress. 13. The FSP’s roofing contractor is no more qualified than his builder. Thus, his opinion should not carry more weight. 14. The FSP has not proven without doubt that the roof damage was caused by an event that is excluded from cover by the policy. Summary of FSP’s Position 15. Due to a large influx of claims at the time of the loss, quotations were requested where damage did not appear to be extensive. It was only at the end of July 2010 when the quotations were received from the Applicant that the extent of the damage became apparent. This prompted the FSP to engage a loss adjuster. 16. The FSP’s experts confirmed there was no evidence of storm damage to the roof, but instead the damage was due to a number of pre-existing defects and normal wear and tear. 17. The Applicant’s builder’s revised quotation includes the cost of removal of affected roof tiles, removal and replacement of valley gutters, supply of heavy tarpaulins and upgrade of water damaged roof membranes. The FSP’s assessor’s quote was substantially less because it does not allow for this work. 18. The FSP relies on the following policy provisions: Case No: 230932 Determination Page 3 of 6 “ General Exclusions Exclusions applicable to home, home contents and personal property Loss, damage, destruction, consequential loss or liability directly or indirectly caused by, contributed to by, resulting from, or arising out of in connection with:  Gradual deterioration, wear and tear, fading, marking, scratching, denting, chipping or lack of upkeep or maintenance  Inherent defects, faulty workmanship, structure defects or faulty design …” Issue 19. Whether the FSP is entitled to deny indemnity for the roof damage. Reasons for Decision 20. I am satisfied there has been a full exchange of material between the parties and that each party has had the opportunity to response to the issues raised. 21. I note the parties have raised numerous issues in their submissions. Whilst I have examined all the evidence, I will only discuss the issues that I consider pertinent to my determination. 22. The onus is on the Applicant to establish, on the balance of probabilities, that he suffered a loss caused by a risk insured against. Once it has been established that the loss was prima facie caused by a risk insured against, the onus shifts to the FSP to show that the loss did not occur as claimed, or that the loss is not covered by the policy if that is the FSP's belief. 23. The initial report provided by PM provides the following findings: “ In the opinion of our roof specialist the leaking to the top storey front and left side rooms of the property appears to be coming from two large splits to lead work on gable of the second storey, that have been caused by heavy hailstones. The splits in lead work have been temporarily made safe with silicon to stem after flow. He recommends removing and replacing lead work to the second storey gable. It will be necessary to engage a roof tiler to patch and repair hip and gable which will be disturbed when replacing lead work. ” 24. It is critical to note that the FSP then engaged PM which carried out repairs for a much cheaper price than was suggested by the Applicant’s expert. 25. By its actions in appointing PM, the FSP has admitted liability, notwithstanding any subsequent advice which may cast doubt upon the cause of the damage. 26. Further, any work resulting from the inadequate workmanship or inadequate scoping of the work of PM is also the liability of the FSP. Case No: 230932 Determination Page 4 of 6 27. After repairs had been completed by PM, leaking occurred again and a reinspection was conducted by PM, who provided the following comments: “Upon secondary inspection there does not appear to be any lasting storm related damage on this roof however the owner is adamant that it has only leaked since the recent hail storm. The only problem that we could see in the problem area is there are a number of different profiles of tiles which when laid together causes an oversized gap between water courses where in heavy rain would be easy for water to get through. This is the only problem that we can see that would explain further leaking. For this problem to be fixed either all tiles need to be of the same profile and/or sarking paper needs to be installed to redirect any water in the problem area” 28. The Applicant refut ed the FSP’s builder’s findings and provided a report from his own builder (STR), which reads in part the following: “ Upon a second inspection upon the request of [The Applicant] I detected the area in question where the leak is occurring. Having 30 years experience in building and construction it is my opinion that the leak and subsequent damage to the plaster, paint, carpet and roof membrane is a direct result of high winds and heavy rains, the force of the wind has lifted and damaged the bedding to the valley tiles, thus allowing water to enter and damage other areas, which previously were affected. As a consequence it no longer requires strong winds or heavy rains to result in a leak. On closer inspection I have also noted that due to the amount of water entering at this point, the valley gutter is starting to show signs of corrosion, thus requiring the valley gutters being replaced as well as re-pointing tiles, and our revised quote reflects this. Also attached is photographic evidence of the water stains to the rafters, tile battens, valley boards, propping beams and plaster ceiling. A further inspection should also be carried out to ensure the electrical safety of the cables and light fittings in the area, as well as ensuring the integrity of the insulation in the area has not been undermined by the water, which may resulted in the upgrade of both insulation and electrical supplying/fittings. ” 29. Due to the conflicting findings the FSP appointed RC, a roofing contractor to report on the cause of the damage. RC’ s report provides the following conclusions: “ CONCLUSIONS Point 1 The main point of rainwater ingress from the roof into the hallway to the second storey of the house can be directly attributed to a pre-existing installation defect, associated with the installation of tiles to a triangle shaped area, within an area of two valley installations. Point 2 This pre-existing installation fault has been in existence on the roof since original roof installation time. Notwithstanding leakage may well have only been highlighted in recent times, I stand by my comments, that leakage is due to an installation defect and NOT storm damage of any kind. Case No: 230932 Determination Page 5 of 6 Point 3 The initial installation defect was somewhat masked by the installation valley cement work, albeit, this valley cement work was never installed in an appropriate or compliant manner. Overtime, this valley cement work has deteriorated and thus, is allowing significant rainwater overflow of the valley into the hallway Point 4 A past repair attempt in the form of the application of a flexible pointing product to the valley cement work, may have provided some short- term relief to rainwater ingress however, it is NOT an appropriate or compliance repair method to address this pre-existing installation fault. Point 5 The second point for rainwater penetration from the roof into the hallway is occurring when rainwater is overflowing between undamaged roof tiles, directly downstream of a valley discharge point. Point 6 The Australian Roof Tiling Standard address this exact leakage scenario by mandating, that either flashing or supplementary waterproofing, in the form of sarking must be installed to prevent water inundation. I report that none of the acceptable methods to prevent water inundation have been provided and therefore, this second site for the water leakage into the hallway can again be attributed to a pre-existing installation fault. Point 7 The prime point for rainwater penetration from the roof into the daughter’s bedroom within the Bay window area can be attributed to a breakdown in a waterproofing membrane, covering the bay window roof. Point 8 There is a second point of water penetration into the daughter’s bedroom, emanating from the state of the roof cement work. Leakage is occurring from the roof cement work, as the cement work installation method does NOT comply with Australian Roof Tiling Standards Point 9 Rainwater leakage into the ground floor gymnasium is occurring due to the detachment of a hanging flashing. Point 10 Rainwater leakage due to the detachment of the hanging flashing can be directly attributed to a pre-existing installation fault, in that the hanging flashing was never provided with any appropriate form of mechanical fastening to properly secure it to position as was required. Point 11 No storm or impact damage to the roof At the time of my inspection I found no evidence of any existing storm damage to any area of the house, nor do I find any evidence of past storm damage to any areas of the roof of this house Case No: 230932 Determination Page 6 of 6 In summary I found NO storm damage, No impact damage and NO storm created openings or disturbance to the roof system at the time of my inspection. Point 12 Notwithstanding the fact, that some repairs have been carried out prior to my attendance to this site and therefore I am limited in precise and definitive diagnosis concerning these areas. I am still of the opinion that there was never any storm damage to the roof of this house and there has been an ongoing failure to correctly diagnose the actual points of rainwater penetration, from the roof into the house. ” 30. As RC admits very candidly in “Point 12” , the earlier work covered by PM has “muddied the waters” . I find it hard to accept RC’s opinion that there was no storm damage in the light of the earlier opinions of PM and the Applicant’s preferred tender or “ST S ”. 31. The FSP concedes that in allowing an eight month delay before appointing an assessor, it may have been in error. I think it is now too late to rely upon the RC opinion having regard to all that has already occurred. 32. I also note the uncontradicted evidence that no problems manifested themselves before the torrential storm on 6 March 2010. Determination 33. Accordingly, I determine the FSP is not entitled to deny the Applicant’s claim for the roof damage.