Home / Financial Firm (Unknown - Insurer) / Determination 227593
Determination 227593
Storm water damage claim refused under design and construction exclusion
Summary
A strata policy claim for storm water damage to internal areas was refused under exclusions for faulty design and construction. AFCA found the FSP had not established the exclusion applied, ordered it to indemnify the fair and reasonable internal repair costs with statutory interest on agreed sums, and found the assessment excessively slow.
An insurer relying on an exclusion bears the onus of establishing that it applies to the circumstances of the claim, and the FSP's expert reports did not establish that the blockage was caused by the design issues.
Subjects and remedies
home or building damagenatural disasterpay claimpay interest
Text of the determination
Case No: 227593 Determination Page 1 of 7
Case number: 227593
General Insurance - Domestic Insurance - Home Building – Overflow of roof
gutters - FSP Decision - Denial of claim
23 March 2011
Background
1. The Applicant is represented. For clarity and convenience in the determination,
I will hereafter refer to the Applicant and rep resentative as “the Applicant”.
2. The Applicant has held a Strata insurance policy with the Financial Services
Provider (FSP) since March 2010.
3. In May 2010, a unit at the insured property suffered water damage (4) following
storm activity. A claim form was completed on 30 June 2010. The claim was
subsequently assessed, with the FSP eventually refusing the claim on 27
October 2010 on the basis that the loss occurred as the result of a failure in the
design and construction of the roof. The Applicant maintained the loss was the
result of tennis balls being lodged in the guttering system.
4. The FSP’s internal disputes resolution department reviewed the claim at the
request of the Applicant. It maintained the claim was not covered as the result
of the exclusion in the policy.
Summary of Applicant’s Position
5. The loss occurred as the result of tennis balls getting lodged in the guttering
system and there would have been no issue had the guttering not been
blocked. This is proven by the fact there were no overflows in other sections of
the complex.
6. The FSP has referred to the tennis balls as the “catalyst” for the loss, which
means it was the proximate cause. There is no exclusion with relation to a
blockage in the gutters.
7. The FSP has argued there was a failure to install debris protection to the
guttering system, yet it is not a requirement of the building standards and is
actually recommended against. The Applicant provides an email from the
engineer involved in the construction, which states the building is to standards
and the FSP’s hydraulics engineer has not assessed the design and drawings.
Determination
Case No: 227593 Determination Page 2 of 7
8. The building construction was approved by the Council with the relevant
certification issued.
9. If it was deemed there was a fault with the roof, section 46 of the Insurance
Contracts Act 1984 (the Act) would apply to the circumstances of the claim to
prevent the FSP from relying on the exclusion.
10. The FSP has not acted with utmost good faith and has failed to comply with the
General Insurance Code of Practice with relation to timely assessment of the
claim.
Summary of FSP’s Position
11. Its experts report the loss was the result of faulty roof design and construction,
which was not sufficient to handle the flow of water. There was no debris
protection installed to the guttering system, which allowed the blockage to
occur and it argues the balls were merely a catalyst and not the proximate
cause of the loss.
12. Regulation 30 of the Insurance Contracts Regulations 1985 , stipulates section
46 of the Act does not apply to broad form policies and the policy in question is
a broad form policy.
13. It concedes the assessment of the claim was delayed as the result of the
available assessor living some distance from the property and accordingly it
requested quotations. When it became apparent the claim was sizable, it
engaged a building consultant.
14. The fact the Council approved the building does not dictate the construction
was adequate.
15. Reliance on a policy exclusion cannot reasonably be considered a failure to act
in utmost good faith.
16. The FSP relies on the following policy provisions:
“ Section 1 – Property Insured
…
6. Exclusions
We will not be liable for any physical loss or damage caused directly or indirectly to:
…
6.8 he (sic) Building(s) by Rainwater or Storm water seeping or percolating through
walls, roofs or floors or entering as a result of structural defects, faulty design or
faulty workmanship in the Buildings(s).
We will not be liable in respect of any physical loss, destruction or damage directly or
indirectly caused by or arising out of or in consequence of or contributed to by:
…
6.17 error or omission in design, plan or specification or failure of design;
Case No: 227593 Determination Page 3 of 7
6.18 faulty materials or faulty workman ship;”
Issue
17. Whether the FSP is entitled to refuse indemnity under the terms and conditions
of the policy.
Reasons for Decision
18. There has been an exchange of information between the parties and I am
satisfied each party has had an opportunity to address the issues raised.
19. Due to the nature of the dispute, it has been referred for a determination in
accordance with the Operational Guideli nes to the Terms of Reference.
20. The parties discuss the application of section 46 of the Act to the dispute in
their submissions:
Section 46 of the Insurance Contracts Act 1984 provides that if a claim is made in
respect of a loss that occurred in whole or in part as a result of a defect or imperfection
in a thing and the insured was not aware of the defect or a reasonable person in the
circumstances could not be expected to have been aware of the defect or imperfection
the insurer may not rely on an exclusion clause that refers to the condition of the thing
before the contract was entered into.
21. I have reviewed the submissions of the parties in accordance with the terms
and conditions of the policy and section 46 of the Act. The Applicant submits
the loss was caused by tennis balls blocking the guttering system while the
FSP argues the loss was the resulting of design and construction faults with the
roof.
22. Having reviewed the policy, I am satisfied it excludes loss resulting from faulty
design or construction.
23. There is an invoice on file, from a roof plumber indicating the estate agent paid
$66 to “ Remove balls f rom blocked gutter” .
24. The FSP argues the tennis balls were merely a “catalyst” and the underlying
design and construction issues were the proximate cause of the loss. It
provides a report prepared by a hydraulic engineer, dated 11 October 2010,
which states:
“…Using the roof are a in sq m calculated and applying the rainfall intensity, a
box gutter drain of 238831.29 sq mm is required to drain safely a roof area of
105.91 sq m.
…
The box gutter appears to be undersized for a 1:100 year storm intensity event.
Eave gutters required to accommodate a 1:20 year storm event under the code –
but box gutters due to its construction within a building, require calculation
applicable to a 1:100 years storm event.
Case No: 227593 Determination Page 4 of 7
An allowance must also be made above the maximum calculated water flow level
of twice the maximum flow depth plus at least 25mm at the longest drainage
distance along the box gutter.
Debris protection should be installed as raised domed wire grates to at least
enable drainage around an obstruction. This apparently was not installed.
An overflow arrangement should be installed to allow unusually heavy rainfall
events so that debris and blockages that may occur can be passed and
discharge can occur freely at a volume equivalent to the maximum box gutter
discharge. The overflow should have a maximum allowance terminating below
the box gutter pan.
Conclusion
Calculations from the records provided conclude the box gutter on this premises
is undersized by approximately 75%. The box gutter will be required to be
upgraded and replaced allowing for the maximum volume /flow as calculated
above plus an allowance at the longest or highest point from the outlet with a
safety margin of a minimum of 25mm over the gutter length.
Raised domed debris protective grating will be required at the rain water head
and downpipe entrance.
Adequate overflow provisions are required in the system but in this scenario
possibly at the rainwater head.” (sic)
25. The FSP also provides a building consultant’s report dated 20 October 2010,
which states:
“Care must be taken when constructing a “butterfly roof” because the water
collected by the box gutter system is capable of draining in all weather conditions
and its construction must meet the AS 3500 standard. The average recurrence
for internal gutters to accommodate is one in 100 years rainfall event. The rainfall
in intensity for Bermagui at the time in questions is given as 270mm in one hour.
…
Conclusion
I am of the opinion that the drainage system installed in this building contains a
major design flaw and does not meet the AS3500 standards (see additional
supporting report by [company] Hydraulic Engineer and I conclude that major
rectification works are needed to ensure that flooding via the inadequate box
gutter and roof drainage does not reoccur. ”
26. A further report from the same building consultant, dated 08 November 2010,
states:
“…Of major con cern was the mechanical blockage of a downpipe, box gutter and
rainwater head. If the construction of these faculties do not have emergency
overflows along the length, especially where the maximum depth occurs at a far
end, the system will suffer from severe overflow along the gutter length.
The further allegation made of this project was that a ball had blocked the outlet
of the gutter. This predicament must always be catered for in a simplistic
common sense manner, by installing domed mesh outlets, to prevent such a
blockage causing failure of the system and allowing a calculated cross-section
area to cater for maximum flow possible away from the building to satisfy this
event
Case No: 227593 Determination Page 5 of 7
Another area of concern was an upturned walls and flashing that acts as an extra
area for rainfall capture of driving rain, and increases the area to be calculated
for sizing and gutter run-off.
The area of rainfall was measured on site. The rainfall volumes were drawn from
statistics and local maps. Measurements of box gutter Length x Depth x Width
were supplied. Outlet parameters to outside walls, photographs of box gutter and
existing overflow arrangement in case of blockages or surcharge were supplied.
The roof drainage areas were calculated in accordance with the Code (AS 3500).
The rainfall intensity applied to obtain the “litres per second discharge” from the
roof area was calculated - again using the Code (AS 3500, CSIRO and Weather
Bureau Statistics documented and ARI).
The formula applicable to open channel flow was applied.
All of the above was then compared to the existing site sizes and provisions of
drainage to arrive at the estimated conclusions and the result documented.
In short, the construction of the roof drainage was inadequate under the Code
and it was not properly safeguarded to prevent blockages.” (sic)
27. The Applicant submits the building was inspected and certified by the Council
after construction. The Applicant submits the proximate cause of the loss was
the blockage from the tennis balls, which is proven by the fact no other area of
the complex experienced water inundation as the result of the event. The
Applicant notes there is no requirement under AS 3500 to have guards on
gutters. AS 3500 even suggests that it may be better not to install guards.
28. I have considered s ection 46 of the Act. I note the exclusion in the FSP’s PDS
does not refer to the state of a thing prior to the inception of the policy. For
section 46 to have application, the insurer is required to rely on a provision in
the contract that has the effect of limiting or excluding the insurer’s liability
under the contract by reference to the condition, at a time before the contract
was entered into, of the thing which is being considered. In this case, the FSP
is not relying on any such provision.
29. In any case, the Applicant does not accept there is a defect.
30. In considering the evidence, I note there appears to be evidence to indicate the
roof guttering system is not sufficient for requirements. However, I am also
mindful that either tennis balls or a small football (as noted in the original
assessment report) were removed from the guttering system. The roof
plumbing report notes “balls” were removed; indicating it is likely that more than
one ball was blocking the system.
31. In essence, this dispute relates to whether the loss was caused by the faulty
design and construction of the roof and plumbing or blockages by the balls in
the guttering system.
32. The FSP appears to largely ignore the blockage issue, stating the blockage
was a “catalyst” rather than the proximate cause. The argument as to the
meaning of the terms “catalyst” and “proximate cause” has been discussed by
the parties; I do not regard the distinction as significant.
Case No: 227593 Determination Page 6 of 7
33. The Applicant submits that no other area of the complex suffered water
inundation as the result of the storm event. It would therefore seem the loss
only occurred in the area where there was a blockage in the guttering. The
FSP’s expert has noted that a “ simplistic common sense” approach should
always be adopted and domed mesh outlets installed to prevent such
blockages. The Appl icant correctly notes that “common sense” is a relatively
subjective area and such a statement cannot be relied upon to defeat a claim.
In any event, the relevant Australian Standard specifically negatives the
mandating of domed mesh. I also note the absence of reports of any earlier
events leading to overflowing water. Whilst the incident of 25 May 2010 was
extreme, I believe that within the previous 18 months, there must have been
some incidents of heavy rain.
34. In the circumstances, while I accept there is evidence the roof may have some
design issues, I am not persuaded that the loss in question was the result of the
issues identified. I pay particular regard to the fact the only reported area of
damage to the complex occurred in the area of the blockage.
35. At law, when an insured lodges a prima facie claim and the insurer wishes to
deny the claim on the basis of an exclusion in its policy, it bears the onus to
establish the exclusion applies to the circumstances of the claim.
36. In this instance, I am not persuaded the FSP has established the loss in
question was the result of the reported design and construction issues.
37. The time taken to assess (and then deny) this claim was excessive. The file
indicates that this may have lead to a loss of rent. But the material on the file
does not permit me to determine the issue of quantum.
Determination
38. On the basis of the available information, I determine the FSP has an obligation
to indemnify the Applicant for the fair and reasonable costs of the internal
repairs.
39. There is a submission indicating the Applicant was in the process of attending
to the required repairs. If the repairs are progressing or have been completed, I
direct the Applicant to provide the FSP with documentation outlining the costs
incurred, and details of any claim in respect to lost rent.
40. In the event that payment has been made for the repairs (and subject to
agreement between the parties as to the reasonableness of the repair costs), I
direct the FSP to pay interest at the statutory rate upon the agreed sum, from
30 August 2010 until settlement of the claim.
41. While not specifically relevant to this dispute, I note the Applicant may also wish
to further investigate the reported issues with the guttering system on the roof
to ensure it meets all requirements so there are no further issues in the future.
Case No: 227593 Determination Page 7 of 7
42. I trust the parties will co-operate in good faith to ensure the claim is resolved in
a timely manner.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.