Text of the determination
Case number: 225020
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
11 May 2011
Background
1. The Applicants held a home insurance policy with the Financial Services
Provider (FSP) for their place of residence. The relevant period of insurance
operated between 1 April 2009 and 1 April 2010. During this period, the home
was insured for a sum of $227,841 and the contents for $34,226. The contents
sum insured comprised of $28,826 for general contents a nd $5,400 for
specified contents. A $100 excess applied to each claim lodged.
2. The Applicants lodged a claim on 6 March 2010 for storm damage that
occurred the same day. The FSP has accepted the claim but a dispute has
arisen regarding the extent of damage.
3. The FSP has attempted to cash settle the Applicants ’ claim for the amount of
$25,642.72. The FSP also arranged payment for $4,800 in alternative
accommodation costs whilst this dispute is being reviewed by the Service.
4. The Applicants have rejected the FSP ’s offer and are seeking settlement for
one of three quotes they have provided which range between $180,000 and
$198,000. They are also seeking $10,800 for alternative accommodation
expenses.
5. It is noted that the contents claim has been settled and will not be subject to
this Determination.
Summary of Applicants ’ Position
6. The FSP had engaged contractors to undertake emergency works on the
property, which included covering the roof with temporary sheets. However,
they have been informed by the SES, other professional builders and a building
surveyor that the material used was inappropriate and not affixed properly.
7. Due to the extraordinary rain season, the inappropriate temporary cover and
the broken roof tiles, water entered the property and caused more damage to
the plaster and insulation.
Determination
8. The reports from the FSP’s loss assessor and builders have been inconsistent
in their comments and reasoning. For instance:
They question the FSP’s building consultant’s comment that painting is an
acceptable repair method to chipped and dented window frames;
A loss adjuster engaged by the FSP to handle the contents claim
identified damaged areas to include the roof plumbing, electrical
installation, structural timbers and air conditioner. These areas were not
included in the scope of works by SBC or SB; and
In regard to the gas cooker and oven that started to malfunction after the
water leaked through the damaged roof, the FSP’s contention that it
simply required a maintenance service is incorrect. The unit is fairly new
and did not have any problems prior to the storm event.
9. Although the FSP acknowledges these errors exist, it does not concede that
they are significant. However, they maintain these errors are significant
because it shows a conflict of opinion, which means that the reports are
unreliable.
10. They requested the FSP allow their own builders to repair the damage as there
was a strong indication the FSP’s builders would not carry out the repairs in a
workmanlike manner. This was supported by the glazier who the FSP engaged
to fix the glass but did not complete the job. Further, their neighbours had
negative experiences with the FSP’s contractors.
11. SBC’s report, which was initiated by the FSP, identified that the damage to the
kitchen cabinets was not caused by the storm. However, the house was well
maintained, had been recently renovated and they never noticed any damage
to this area. Further, taking into account the severity of damage in all other
parts of the home, and particularly in the kitchen area, it is not logical to accept
this was the only part unaffected by the storm. In the alternative, the FSP
should consider the “matching principal” in the policy which states:
“ Matching
Where necessary, we will pay up to $750 in any one claim for materials to match or
bring about a matching finish to the new materials used in the repair or reinstatement
of any building damage.”
12. In order to get an independent opinion on the damage caused by the storm,
they engaged AL to attend the property on 19 July 2010 and report on the
damage. AL provided a report which stated (in part):
“The initial hailstorm has resulted in extensive damage to the roof requiring tarp
covers to be installed. Leakage however noted around the covers which are
inadequate and have also not been correctly installed.
… The storm damage was noted as considerable with every internal room
having been affected in some way. Some ceilings are in danger of imminent
collapse especially as the roof is still leaking. … There is water/moisture to
nearly every area of linings.
The atmosphere inside the house was noted as very damp and musty. Mould is
now spreading across and behind the linings and is also evident inside
cupboards etc especially kitchen directly under original and current leaks.
… A number of windows were broken and some have been repaired however
the timber window frames appear to have had damage exacerbated by the hail.
… The roof tiles require complete replacement. Partial replacement is not an
option as further cracking and leaks will reveal themselves in the near future.
Repainting of tiles should not be an option as the paint will flake off, fade and
wear and require re-painting again in the future especially as the tiles appear
weakened.
The timberwork eg roof frame and battens should be fully inspected prior to re-
roofing as some rot may have occurred due to the extended time of weather
exposure of non weather-durable timbers.
Full replacement of insulation also required. …
It is strongly recommended that the linings be replaced in every room even
though the face of the plaster may appear undamaged.
Kitchen cupboards require complete replacement.”
13. This report reflects the real damage at the time of inspection, but the property
has worsened since then. This was reflected by the fact that part of the roof and
ceiling collapsed around 7 September 2010. The SES were called in and it took
them nearly three hours to place and fix a temporary cover for that part of the
roof.
14. They did not agree for the FSP to undertake any more inspections as the FSP
had numerous opportunities already to determine the extent of damage.
Further, this would have led to more delays.
15. In relation to the FSP’s contention that they did not mitigate their loss:
It was the FSP’s fault for incorrectly installing the temporary roof cover ing.
Further, the FSP was aware of this issue;
The FSP was at fault for the lengthy delays. For instance, the FSP was
not ready to begin repairs until five weeks after the storm took place;
They have continually followed this matter up with the FSP and informed
them that the roof needed to be repaired; and
They sent two quotations to the FSP to repair the issues with the roof and
the kitchen. These quotations were deemed reasonable by one of the
FSP’s loss adjusters. As such, the FSP could have approved the se
quotations to stop further damage but instead chose to argue the extent of
damage to the kitchen.
16. With respect to the FSP’s submissions regarding the discrepancy between their
quotes and the FSP’s, they note the following:
The FSP’s quotes do not show t he real picture of the damage as there is
a lot more damage in the roof, plasterwork, paint and insulation;
The FSP did not make any allowance for the repair in some areas, such
as electrical wiring, timber frame and garden sheds as well as some
appliances such as air conditioner, stove, oven and alarm system;
The FSP’s builders seem to submit very competitive quotes just to win the
tender, even though it is not practical or possible for the repairs to be
done at the cost offered. However, once repairs begin, the true cost is
usually much more because extra charges are incurred. This has been
the experience of other parties with the FSP;
SB charged $4,355.45 merely for emergency repairs that were ultimately
inadequate (given the poor tarpaulin used on the roof). It is therefore
difficult to accept that the extensive repairs to the home could have been
completed for $19,567.28; and
The quotes they have provided are in line with the AL report they
obtained.
17. They are on a low income and unable to afford alternative accommodation
given they are still paying the mortgage. However, the house’s condition is
deteriorating and due to the unsafe environment, they have been forced to
move out.
18. Given all of the above, they are therefore entitled to the following:
Payment of a sum of money equivalent to six months rent for a similar
three bedroom home (this is the period estimated by the builders to
complete the repair). This is calculated at $1,800 per month for six
months, totalling $10,800; and
The approval of one of the three quotations and for the money to be
deposited into their account.
Summary of FSP’s Position
19. It submits that the issues currently in dispute between the parties are:
The extent of damage attributable to the insured event;
The cost of repairs associated with the storm damage; and
Further damage resulting due to repairs not being carried out or a cash
settlement not being issued.
20. It engaged a loss assessor to attend the property and handle the claim. This
loss assessor in turn engaged SB, a building consultant, to inspect the damage
and provide a causation report.
21. SB’s report dated 26 March 2010 indicated the scope of works for the storm
damaged areas to be $12,796.81. The photos that accompanied this report
depicted brown water stains suggesting there had been previous water entry in
the past and the general poor condition of the property. There was also
evidence of mould that was unlikely to occur to that extent within 3 days.
22. On 8 April 2010, it sent an email to the Applicants requesting that they re view
the scope of works and authorise repairs. However, as the Applicants would not
agree to this, it instructed SB to re-inspect the premises. A re-inspection report
dated 20 April 2010 stated (in part) the following:
“The customer claims the kitchen cupb oards were damaged as a result of the
water inundation. It is our opinion that the cabinets were in this condition prior to
the storm as the kitchen looked to be in disrepair with doors falling off, drawers
not opening, food stains on the melamine and mouldy sealant on the sink.
The customer claimed that the plaster in the kitchen and lounge room cracked as
a result of the storm. It is our opinion that these were structural cracks caused
from shrinkage and movement as we found no water stains in the area.
The customer claims that the oven is no longer working as a result of water
inundation however we note that it does work and that the piezoelectric igniter
was failing to light the gas in the oven and one of the hot plates, the unit simply
requires a maintenance service.
The customer claimed that the windows were damaged by hail, we note there
was damage to the paint work however the timber frames are severely
deteriorated and have come apart when the glass was replaced by the repairers.
It is our opinion that the windows would require replacement and were in this
condition prior to the storm. …
We are of the opinion, as mentioned throughout the report, that most of this
additional damage is the result of wear and tear and is not the result of the storm
eve nt being claimed for.”
23. This report was forwarded to its claims department’s internal assessors to
review and they supported these findings. The Applicants did not accept the
findings of the report. As a result, it then instructed another building consultant
(SBC) to provide a causation report and a scope of works separating all
damage resulting from the hail storm and maintenance related problems. SBC
provided a report dated 7 June 2010 that stated the following in its “Summary”:
“I am of the opinion that h ail has impacted the building and caused damage. The
hail has caused broken tiles and roof sheets, allowing water to enter and
damage the residence.
Hail and water damage was observed to roof tiles, laserlite roof sheets, painted
surfaces of external windows (northern elevation), kitchen ceiling and cornice,
kitchen cabinets on the northern and eastern elevations, sunroom ceiling and
bedroom ceiling. I am also of the opinion that the damage resulted from the
storm on 6 th March 2010.
It is my opinion that woodrot in the front northern windows is not storm related
and is a maintenance issue.
In my opinion damage to the kitchen cabinets on the southern elevation is due to
water penetrating through the junction of the cabinets and wall tiles over an
extended period of time. I consider this to be a maintenance related issue and
not due to storm activity.”
24. Pursuant to this report, it denied liability for the kitchen cabinets under the sink
and the three window sills and sent a denial letter regarding these items. It also
advised the Applicants that the remainder of the claim would now be accepted.
25. Three quotes were obtained by the loss adjuster pursuant to the scope of works
provided by SBC. The most competitive quote was for $19,567.28 but it is
prepared to settle the Applicants’ claim based on the most expensive quote,
being $25,642.72.
26. The Applicants have not accepted this. They have instead furnished a number
of quotes during the history of the claim, all varying in amounts, namely:
$12,800 from AK (although this was limited to replacing the entire
kitchen);
$33,550 from SJG;
$66,347 from MM;
$190,000 from MM;
$180,000 from TABB; and
$198,000 from RG.
27. The significant difference in prices between the parties exposes a relevant flaw
in the Applicants’ submissions. T hey have not obtained a comprehensive
causation report on the condition of the property, particularly as it relates to
storm damage. Their quotes are inclusive of all such damage to the property
and completion of these works would restore the deteriorated damaged areas
to their new condition.
28. Its assessors in contrast have applied a forensic approach and sought to
distinguish between storm event related damage and damages from non event
related causes. As such, it was entitled to limit its settlement to these storm
related events as the other issues are excluded under the policy pursuant to the
following policy provisions:
“ General exclusions – apply to the overall policy
Unless included in additional cover, we will not cover loss, damage or legal liability
caused by:
…
wear and tear and lack of maintenance, including rust, corrosion, deterioration …
gradual loss or damage of any kind; …
Unless it is stated specifically in the policy, this policy does not provide cover for:
…
replacing any undamaged part of your home to achieve a finish or appearance
which matches the part which has been repaired or replaced after the damage
except as described in the matching benefit on pages 26 and 36;”
29. To accept the Applicants’ quotes would essentially restore the property to a
new condition and result in an unjust enrichment.
Further Damage and Alternative Accommodation
30. In relation to the further resultant damage due to repairs not being carried out, it
notes the policy imposes an obligation on the Applicants to maintain the
property in good order. As such, they should have minimised their loss by
undertaking preventable measures, such as temporary works to prevent further
water damage. Alternatively, they could have:
Allowed its contractors to repair the roof to cease water entry and
continue to dispute the remainder of the scope of works; or
Accepted a cash settlement for the approved works and disputed the
balance.
31. With respect to the alternative accommodation costs, such claims are payable
in the event the property is unable to be lived in as a result of the damage
attributable to the insured event. There is no evidence the Applicants took any
steps to mitigate post event damage and deterioration. Instead, they have
chosen to dispute the scope of works. Although they are entitled to dispute the
scope of works, they should have still undertaken steps to mitigate their loss.
32. Further, it notes it was ready to start repairs on 8 April 2010 and communicated
this to the Applicants. As at this date, the property was not in an unliveable
condition and it is only now, after months in dispute, that the mould and
damage has reached the point where the property may be unsafe or
unsanitary. Further, it was not reasonable for the Applicants to suffer loss, such
as cracked roof tiles and water seepage, and then sit back and watch it develop
into an unliveable situation without any effort to mitigate their loss.
33. As such, it was the post event deterioration and damage that was permitted to
develop that led to the Applicants moving out of the home. Despite this, it has
arranged a payment of $5,000 to the Applicants to assist in their alternative
accommodation costs.
34. Otherwise, it maintains its position regarding this dispute.
Issues
35. Whether the Applicants are entitled to be settled pursuant to one of the three
quotes provided; and
36. Whether the Applicants are entitled to six months alternative accommodation
costs.
Reasons for Decision
37. The Panel is satisfied that a full exchange of information has taken place
between each party and that each party has had the opportunity to address any
issues raised.
38. It is a general principle of insurance law that the onus is on the Applicants to
establish, on the balance of probabilities, that they are entitled to the amounts
sought under the terms and conditions of the policy.
39. The courts have determined that in order to decide whether the loss is covered
by the policy, the proximate cause of the damage must be established. This is
generally done by determining the dominant or effective causes of the loss.
40. The P anel accepts the FSP’s submission that the disputed issues appear to be
the following:
The extent of damage attributable to the insured event;
The cost of repairs associated with the storm damage; and
Further damage resulting due to repairs not being carried out or a cash
settlement not being issued.
Extent of Damage and Cost of Repairs
41. These first two points are intrinsically linked and the Panel finds it is suitable to
deal with them together.
42. In determining issues such as causation and extent of damage, the Panel relies
heavily on the expert materials as well as other corroborating evidence, such as
photographs and witnesses.
43. The Applicants have not accepted the reports provided by the FSP’s experts
regarding the extent of damage attributed to the storm. However, the Panel
finds it difficult to place much weight on AL’s report. It appears this report was
compiled by an architect, who is not an ideal expert to comment on the
causation of home damage and the scope of works required to repair the
damage.
44. In contrast, SBC is a building consultant and the report dated 7 June 2010 was
authored by a licensed builder. In the Panel’s opinion, a licensed builder is
more appropriately qualified than an architect to examine and report on the
probable cause for building damage. Although the Panel notes the Applicants
have identified that some of the FSP’s experts are in conflict, this does not
mean that they should all be ignored.
45. In instances when there is some conflict between experts, the Panel is entitled
to accept the expert whose report is credible and reasonable and authored by
an appropriate expert. In this case, the Panel finds SBC’s report to be more
comprehensive than the others presented and clearer in its reasoning and
observations.
46. In particular, SBC conceded that the majority of the damage brought to their
attention by the Applicants was covered by the policy. The two issues that SBC
did not accept were storm related was the kitchen cabinets and wood rot at the
window sill bases.
47. These two issues were not considered by AL’s report, which further supports
the fact that it does not provide probative weight to the Applicants’ position. In
contrast, SBC’s report stated the following regarding the kitchen cabinets and
the window sill:
“A closer inspection of the sink area above the cabinets revealed water was
seeping through the wall tile and sink junction. Over an extended period of time
water has been damaging the back and side walls of the cabinets. There was no
silicon sealant applied along the junction which would have prevented the
seeping of water from the sink.
I am of the opinion that the cabinets on the southern elevation of the kitchen are
damaged from water entering through the junction of the sink and tiled wall.
There were no preventative measures taken to stop water gaining entry at this
point and causing the observed damage. It is my opinion that this area of the
kitchen cabinets was not damaged by the storm event….
I also observed that large sections of all three windows were displaying signs of
wood rot at the sill bases of the windows. Large sections of the windows
measuring 100mm in diameter had rotted out. I am of the opinion that the
windows had been damaged by wood rot prior to the storm event. This will need
to be repaired by the Insured pr ior to any storm related works being undertaken.”
48. The Panel finds SBC’s reasoning as to why these items were not proximately
caused by the storm to be sound. Further, SB also supported SBC’s findings
regarding the kitchen cabinet.
49. AL’s report does not mak e any attempt to identify the proximate cause of the
damage to these areas. In relation to the kitchen cabinets, AL merely states it
requires complete replacement and that the timber window frames “appear to
have had damage exacerbated by the hail”. AL doe s not attempt to expand on
this comment, such as whether the hail was the proximate cause of the
damage or what issue was exacerbated by the hail.
50. Given this, the Panel accepts that SBC’s report should be considered as the
appropriate basis for determining the proximate cause of damage as at the time
of their inspection. It therefore follows that the scope of works set out and the
quotation provided in support sets out the extent of the FSP’s liability for the
damage evident at that time.
51. The Applicants have provided three quotes they maintain are consistent with
AL’s report. However, the Panel does not accept these quotes provide any
probative value given the following:
The maximum quote the FSP obtained was for $25,642.72 pursuant to
SBC’s scope of works. Although this scope of works did not include the
window sills and kitchen cabinets, it is difficult to accept that the most
expensive tender obtained by the FSP underquoted the true cost by
approximately $150,000; and
These quotes were in line with AL’s re port, which the Panel found was not
probative to the Applicants’ case; and
They were not compiled pursuant to SBC’s scope of works.
52. The Panel will therefore rely on the quotes obtained by the FSP as setting out
the likely cost involved in repairing the storm related damage as evident at
SBC’s inspection.
Further Damage
53. The issue in dispute between the parties regarding this is whether the
Applicants have undertaken reasonable steps to mitigate their loss.
54. The Applicants have highlighted the fact that the sheet affixed to the roof was
inadequate, which seems to be corroborated by SBC who stated in their report:
“During my inspection of the roof area I observed that the roof had been
temporarily secured by an Insurance builder. The Insured was concerned that
further water is entering the building. I recommend the temporarily installed
tarpaulin be removed and a more robust and appropriate tarpaulin be installed as
there is the potential for further water entry.”
55. The FSP does not appear to dispute this and indeed makes reference to this in
some of the emails produced. However, the Panel notes that the Applicants
refused access to any of the FSP’s contractors after disputing SBC’s report and
scope of works. As such, it appears the only way the FSP could have repaired
this issue was to concede to the Applicants’ position, which the FSP found was
not reasonable in the circumstances.
56. The Panel notes that a party is normally required under common law to take
reasonable steps to minimise their loss. Whether a party has done so is a
question of fact and depends on the circumstances of a particular case.
57. The Panel finds that the Applicants actions in this regard were not reasonable.
They chose to continually follow up the FSP and dispute the scope of works
and contractors to be used. They wished to utilise their own contractor because
they believed the FSP’s contractors would not have completed the works in a
workmanlike manner.
58. This presumption was based on a negative experience of other neighbours.
However, the Panel does not accept this in itself was sufficient to reject access
to the FSP’s contractors as the Applicants provided no corroborative evidence
regarding this allegation.
59. The Applicants have also relied on the fact they continually attempted to
resolve this dispute with the FSP by providing quotations which they felt were
reasonable. However, one of these quotations was for the replacement of the
whole kitchen, which the Panel accepts the FSP was not liable to repair, given
the damage to the kitchen cabinets was not proximately caused by the storm.
60. Regardless of this, it is the Panel’s opinion that a home owner whose roof is
leaking and continuing to leak should undertake reasonable steps to ensure
this stops. In these circumstances, especially as the matter became protracted,
it would have been reasonable for the Applicants to attempt to ensure this issue
was rectified as a matter of priority rather than attempting to compel the FSP to
resolve the claim on their terms.
61. This could have been done by the following:
Utilising the cash settlement received from their contents claim to either
repair the roof themselves or engage someone to affix the tarpaulin
properly. The Panel notes the contents were cash settled for $30,556 on 4
June 2010 and the Applicants had submitted quotes totalling $6,514.50
for the total roof restoration;
Insist the FSP either repair the roof or rectify the temporary works by
allowing its contractors access to their property; or
Accept a cash settlement in partial settlement for the roof repairs whilst
still preserving their right to contest the balance.
62. There is no evidence the Applicants undertook any of these or other steps to
protect their property from further water inundation.
63. Upon SBC’s inspection on 31 May 2010, it is reasonable to accept that their
scope of works would have included any water damage that may have
accumulated to that date. This is based on the fact SBC acknowledged almost
all of the water damage brought to their attention by the Applicants was due to
the claimed event except for the kitchen cabinets and window sills. The Panel
notes this inspection occurred almost three months after the event.
64. The Panel therefore does not accept that it is reasonable that the FSP should
remain on risk for all the further damage that has occurred after SBC’s
inspection, especially as it appears the Applicants exercised little initiative to
protect the property themselves.
65. It is therefore the Panel’s opinion that the Applicants have not exercised
reasonable steps in minimising their loss. Accordingly, the FSP is not liable for
additional damage that occurred after SBC’s inspection.
Alternative Accommodation
66. The policy provides for alternative accommodation costs under the following
policy provision:
“If we agree that an insured event has caused so much damage to your building that
you cannot live in it, we will pay alternative accommodation costs. The amount we will
pay is the amount it could have been rented for, and we will pay this amount for the
period from the time the building is unable to be lived in as a result of the damage and
while it is being repaired, rebuilt or replaced up to a maximum period of twelve
months.”
67. It appears that the Applicants were able to inhabit the premises early in the
claims process and there was no evidence to suggest that repairs could not
have been done whilst they remained there. It was due to the prolonged nature
of this dispute that resulted in the premises being uninhabitable.
68. The Panel has accepted that the further damage after SBC’s inspection was
substantively due to the Applicants’ failure to take reasonable steps to minimise
their loss. Further, the policy expressly excludes loss caused by:
“…lack of maintenance to the building …”
69. However, the Panel notes the FSP has provided approximately $5,000 in
alternative accommodation costs whilst this dispute was before the Service.
This would account for almost three months accommodation based on the
Applicants’ rate. The Panel accepts this was a reasonable outcome in the
circumstances and does not consider there is any basis to award more to the
Applicants.
Conclusion
70. The Panel accepts the FSP’s liability is limited to SBC’s scope of works dated 7
June 2010 that were associated with the claim. However, given the additional
damage that has incurred, the Panel does not accept it is practical for the FSP
to now attempt to repair the damage pursuant to this scope of works.
71. As such, the Panel accepts a cash settlement is an appropriate outcome in
these circumstances. In determining an appropriate figure, the Panel notes that
it is common for the actual cost of repairs to exceed the quoted amount.
Further, the evidence appears to indicate the FSP’s contractor did not
undertake appropriate emergency works regarding the roof. Although this
additional damage was likely accounted for by SBC at their inspection, the
Panel considers it is appropriate to allow some margin for this.
72. In determining an appropriate figure, the Panel refers to clause 8.2 of the
Terms of Reference, which states:
“… when deciding a Dispute and whether a remedy should be provided in accordance
with paragraph 9, FOS will do what in its opinion is fair in all the circumstances, having
regard to each of the following:
a) legal principles;
b) applicable industry codes or guidance as to practice;
c) good industry practice; and
d) previous relevant decision of FOS or a Predecessor Scheme (although FOS will
not be bound by these).”
73. Taking into consideration all of the above, the Panel considers it is fair in all the
circumstances to allow a 15% builder’s margin to a cash settlement amount
based on the quotation the FSP was willing to settle this dispute on. This
calculation results in a payout figure of $29,489.13.
Determination
74. On the basis of the available information, the Panel determines that the FSP
pay the amount of $29,489.13 to the Applicants in full and final settlement of
this claim.
75. In the event the Applicants accept this Determination, this amount should be
paid within 14 days of the FSP being notified of its acceptance unless it
requires a binding release to be signed first. In the event the FSP requires a
binding release to be signed, it should:
Ensure a release is sent to the Applicants within 7 days of being notified
of the Applicants’ acceptance of the Determination; and
Pay the above amount within 7 days after it has received an appropriately
signed release.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.