Determination 225020

Storm damage claim amount and alternative accommodation disputed

FirmFinancial Firm (Unknown - Insurer)
Decided2011-06-21
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$29,489
Non-financial loss—
Amount claimed$208,800
SourceAFCA PDF

Summary

The applicants claimed storm damage to their home and sought one of three quotes between $180,000 and $198,000 plus $10,800 in alternative accommodation. AFCA ordered a cash settlement of $29,489.13, being the FSP's $25,642.72 offer plus a 15% builder's margin, and found the applicants' failure to mitigate meant the FSP was not liable for later damage or further accommodation.

The FSP's scope of works on the storm-related damage was accepted over the applicants' quotes, with a builder's margin allowed for practical repair costs, while further damage was excluded for failure to mitigate.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case number: 225020 General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim amount 11 May 2011 Background 1. The Applicants held a home insurance policy with the Financial Services Provider (FSP) for their place of residence. The relevant period of insurance operated between 1 April 2009 and 1 April 2010. During this period, the home was insured for a sum of $227,841 and the contents for $34,226. The contents sum insured comprised of $28,826 for general contents a nd $5,400 for specified contents. A $100 excess applied to each claim lodged. 2. The Applicants lodged a claim on 6 March 2010 for storm damage that occurred the same day. The FSP has accepted the claim but a dispute has arisen regarding the extent of damage. 3. The FSP has attempted to cash settle the Applicants ’ claim for the amount of $25,642.72. The FSP also arranged payment for $4,800 in alternative accommodation costs whilst this dispute is being reviewed by the Service. 4. The Applicants have rejected the FSP ’s offer and are seeking settlement for one of three quotes they have provided which range between $180,000 and $198,000. They are also seeking $10,800 for alternative accommodation expenses. 5. It is noted that the contents claim has been settled and will not be subject to this Determination. Summary of Applicants ’ Position 6. The FSP had engaged contractors to undertake emergency works on the property, which included covering the roof with temporary sheets. However, they have been informed by the SES, other professional builders and a building surveyor that the material used was inappropriate and not affixed properly. 7. Due to the extraordinary rain season, the inappropriate temporary cover and the broken roof tiles, water entered the property and caused more damage to the plaster and insulation. Determination 8. The reports from the FSP’s loss assessor and builders have been inconsistent in their comments and reasoning. For instance:  They question the FSP’s building consultant’s comment that painting is an acceptable repair method to chipped and dented window frames;  A loss adjuster engaged by the FSP to handle the contents claim identified damaged areas to include the roof plumbing, electrical installation, structural timbers and air conditioner. These areas were not included in the scope of works by SBC or SB; and  In regard to the gas cooker and oven that started to malfunction after the water leaked through the damaged roof, the FSP’s contention that it simply required a maintenance service is incorrect. The unit is fairly new and did not have any problems prior to the storm event. 9. Although the FSP acknowledges these errors exist, it does not concede that they are significant. However, they maintain these errors are significant because it shows a conflict of opinion, which means that the reports are unreliable. 10. They requested the FSP allow their own builders to repair the damage as there was a strong indication the FSP’s builders would not carry out the repairs in a workmanlike manner. This was supported by the glazier who the FSP engaged to fix the glass but did not complete the job. Further, their neighbours had negative experiences with the FSP’s contractors. 11. SBC’s report, which was initiated by the FSP, identified that the damage to the kitchen cabinets was not caused by the storm. However, the house was well maintained, had been recently renovated and they never noticed any damage to this area. Further, taking into account the severity of damage in all other parts of the home, and particularly in the kitchen area, it is not logical to accept this was the only part unaffected by the storm. In the alternative, the FSP should consider the “matching principal” in the policy which states: “ Matching Where necessary, we will pay up to $750 in any one claim for materials to match or bring about a matching finish to the new materials used in the repair or reinstatement of any building damage.” 12. In order to get an independent opinion on the damage caused by the storm, they engaged AL to attend the property on 19 July 2010 and report on the damage. AL provided a report which stated (in part): “The initial hailstorm has resulted in extensive damage to the roof requiring tarp covers to be installed. Leakage however noted around the covers which are inadequate and have also not been correctly installed. … The storm damage was noted as considerable with every internal room having been affected in some way. Some ceilings are in danger of imminent collapse especially as the roof is still leaking. … There is water/moisture to nearly every area of linings. The atmosphere inside the house was noted as very damp and musty. Mould is now spreading across and behind the linings and is also evident inside cupboards etc especially kitchen directly under original and current leaks. … A number of windows were broken and some have been repaired however the timber window frames appear to have had damage exacerbated by the hail. … The roof tiles require complete replacement. Partial replacement is not an option as further cracking and leaks will reveal themselves in the near future. Repainting of tiles should not be an option as the paint will flake off, fade and wear and require re-painting again in the future especially as the tiles appear weakened. The timberwork eg roof frame and battens should be fully inspected prior to re- roofing as some rot may have occurred due to the extended time of weather exposure of non weather-durable timbers. Full replacement of insulation also required. … It is strongly recommended that the linings be replaced in every room even though the face of the plaster may appear undamaged. Kitchen cupboards require complete replacement.” 13. This report reflects the real damage at the time of inspection, but the property has worsened since then. This was reflected by the fact that part of the roof and ceiling collapsed around 7 September 2010. The SES were called in and it took them nearly three hours to place and fix a temporary cover for that part of the roof. 14. They did not agree for the FSP to undertake any more inspections as the FSP had numerous opportunities already to determine the extent of damage. Further, this would have led to more delays. 15. In relation to the FSP’s contention that they did not mitigate their loss:  It was the FSP’s fault for incorrectly installing the temporary roof cover ing. Further, the FSP was aware of this issue;  The FSP was at fault for the lengthy delays. For instance, the FSP was not ready to begin repairs until five weeks after the storm took place;  They have continually followed this matter up with the FSP and informed them that the roof needed to be repaired; and  They sent two quotations to the FSP to repair the issues with the roof and the kitchen. These quotations were deemed reasonable by one of the FSP’s loss adjusters. As such, the FSP could have approved the se quotations to stop further damage but instead chose to argue the extent of damage to the kitchen. 16. With respect to the FSP’s submissions regarding the discrepancy between their quotes and the FSP’s, they note the following:  The FSP’s quotes do not show t he real picture of the damage as there is a lot more damage in the roof, plasterwork, paint and insulation;  The FSP did not make any allowance for the repair in some areas, such as electrical wiring, timber frame and garden sheds as well as some appliances such as air conditioner, stove, oven and alarm system;  The FSP’s builders seem to submit very competitive quotes just to win the tender, even though it is not practical or possible for the repairs to be done at the cost offered. However, once repairs begin, the true cost is usually much more because extra charges are incurred. This has been the experience of other parties with the FSP;  SB charged $4,355.45 merely for emergency repairs that were ultimately inadequate (given the poor tarpaulin used on the roof). It is therefore difficult to accept that the extensive repairs to the home could have been completed for $19,567.28; and  The quotes they have provided are in line with the AL report they obtained. 17. They are on a low income and unable to afford alternative accommodation given they are still paying the mortgage. However, the house’s condition is deteriorating and due to the unsafe environment, they have been forced to move out. 18. Given all of the above, they are therefore entitled to the following:  Payment of a sum of money equivalent to six months rent for a similar three bedroom home (this is the period estimated by the builders to complete the repair). This is calculated at $1,800 per month for six months, totalling $10,800; and  The approval of one of the three quotations and for the money to be deposited into their account. Summary of FSP’s Position 19. It submits that the issues currently in dispute between the parties are:  The extent of damage attributable to the insured event;  The cost of repairs associated with the storm damage; and  Further damage resulting due to repairs not being carried out or a cash settlement not being issued. 20. It engaged a loss assessor to attend the property and handle the claim. This loss assessor in turn engaged SB, a building consultant, to inspect the damage and provide a causation report. 21. SB’s report dated 26 March 2010 indicated the scope of works for the storm damaged areas to be $12,796.81. The photos that accompanied this report depicted brown water stains suggesting there had been previous water entry in the past and the general poor condition of the property. There was also evidence of mould that was unlikely to occur to that extent within 3 days. 22. On 8 April 2010, it sent an email to the Applicants requesting that they re view the scope of works and authorise repairs. However, as the Applicants would not agree to this, it instructed SB to re-inspect the premises. A re-inspection report dated 20 April 2010 stated (in part) the following: “The customer claims the kitchen cupb oards were damaged as a result of the water inundation. It is our opinion that the cabinets were in this condition prior to the storm as the kitchen looked to be in disrepair with doors falling off, drawers not opening, food stains on the melamine and mouldy sealant on the sink. The customer claimed that the plaster in the kitchen and lounge room cracked as a result of the storm. It is our opinion that these were structural cracks caused from shrinkage and movement as we found no water stains in the area. The customer claims that the oven is no longer working as a result of water inundation however we note that it does work and that the piezoelectric igniter was failing to light the gas in the oven and one of the hot plates, the unit simply requires a maintenance service. The customer claimed that the windows were damaged by hail, we note there was damage to the paint work however the timber frames are severely deteriorated and have come apart when the glass was replaced by the repairers. It is our opinion that the windows would require replacement and were in this condition prior to the storm. … We are of the opinion, as mentioned throughout the report, that most of this additional damage is the result of wear and tear and is not the result of the storm eve nt being claimed for.” 23. This report was forwarded to its claims department’s internal assessors to review and they supported these findings. The Applicants did not accept the findings of the report. As a result, it then instructed another building consultant (SBC) to provide a causation report and a scope of works separating all damage resulting from the hail storm and maintenance related problems. SBC provided a report dated 7 June 2010 that stated the following in its “Summary”: “I am of the opinion that h ail has impacted the building and caused damage. The hail has caused broken tiles and roof sheets, allowing water to enter and damage the residence. Hail and water damage was observed to roof tiles, laserlite roof sheets, painted surfaces of external windows (northern elevation), kitchen ceiling and cornice, kitchen cabinets on the northern and eastern elevations, sunroom ceiling and bedroom ceiling. I am also of the opinion that the damage resulted from the storm on 6 th March 2010. It is my opinion that woodrot in the front northern windows is not storm related and is a maintenance issue. In my opinion damage to the kitchen cabinets on the southern elevation is due to water penetrating through the junction of the cabinets and wall tiles over an extended period of time. I consider this to be a maintenance related issue and not due to storm activity.” 24. Pursuant to this report, it denied liability for the kitchen cabinets under the sink and the three window sills and sent a denial letter regarding these items. It also advised the Applicants that the remainder of the claim would now be accepted. 25. Three quotes were obtained by the loss adjuster pursuant to the scope of works provided by SBC. The most competitive quote was for $19,567.28 but it is prepared to settle the Applicants’ claim based on the most expensive quote, being $25,642.72. 26. The Applicants have not accepted this. They have instead furnished a number of quotes during the history of the claim, all varying in amounts, namely:  $12,800 from AK (although this was limited to replacing the entire kitchen);  $33,550 from SJG;  $66,347 from MM;  $190,000 from MM;  $180,000 from TABB; and  $198,000 from RG. 27. The significant difference in prices between the parties exposes a relevant flaw in the Applicants’ submissions. T hey have not obtained a comprehensive causation report on the condition of the property, particularly as it relates to storm damage. Their quotes are inclusive of all such damage to the property and completion of these works would restore the deteriorated damaged areas to their new condition. 28. Its assessors in contrast have applied a forensic approach and sought to distinguish between storm event related damage and damages from non event related causes. As such, it was entitled to limit its settlement to these storm related events as the other issues are excluded under the policy pursuant to the following policy provisions: “ General exclusions – apply to the overall policy Unless included in additional cover, we will not cover loss, damage or legal liability caused by:  …  wear and tear and lack of maintenance, including rust, corrosion, deterioration …  gradual loss or damage of any kind; … Unless it is stated specifically in the policy, this policy does not provide cover for:  …  replacing any undamaged part of your home to achieve a finish or appearance which matches the part which has been repaired or replaced after the damage except as described in the matching benefit on pages 26 and 36;” 29. To accept the Applicants’ quotes would essentially restore the property to a new condition and result in an unjust enrichment. Further Damage and Alternative Accommodation 30. In relation to the further resultant damage due to repairs not being carried out, it notes the policy imposes an obligation on the Applicants to maintain the property in good order. As such, they should have minimised their loss by undertaking preventable measures, such as temporary works to prevent further water damage. Alternatively, they could have:  Allowed its contractors to repair the roof to cease water entry and continue to dispute the remainder of the scope of works; or  Accepted a cash settlement for the approved works and disputed the balance. 31. With respect to the alternative accommodation costs, such claims are payable in the event the property is unable to be lived in as a result of the damage attributable to the insured event. There is no evidence the Applicants took any steps to mitigate post event damage and deterioration. Instead, they have chosen to dispute the scope of works. Although they are entitled to dispute the scope of works, they should have still undertaken steps to mitigate their loss. 32. Further, it notes it was ready to start repairs on 8 April 2010 and communicated this to the Applicants. As at this date, the property was not in an unliveable condition and it is only now, after months in dispute, that the mould and damage has reached the point where the property may be unsafe or unsanitary. Further, it was not reasonable for the Applicants to suffer loss, such as cracked roof tiles and water seepage, and then sit back and watch it develop into an unliveable situation without any effort to mitigate their loss. 33. As such, it was the post event deterioration and damage that was permitted to develop that led to the Applicants moving out of the home. Despite this, it has arranged a payment of $5,000 to the Applicants to assist in their alternative accommodation costs. 34. Otherwise, it maintains its position regarding this dispute. Issues 35. Whether the Applicants are entitled to be settled pursuant to one of the three quotes provided; and 36. Whether the Applicants are entitled to six months alternative accommodation costs. Reasons for Decision 37. The Panel is satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. 38. It is a general principle of insurance law that the onus is on the Applicants to establish, on the balance of probabilities, that they are entitled to the amounts sought under the terms and conditions of the policy. 39. The courts have determined that in order to decide whether the loss is covered by the policy, the proximate cause of the damage must be established. This is generally done by determining the dominant or effective causes of the loss. 40. The P anel accepts the FSP’s submission that the disputed issues appear to be the following:  The extent of damage attributable to the insured event;  The cost of repairs associated with the storm damage; and  Further damage resulting due to repairs not being carried out or a cash settlement not being issued. Extent of Damage and Cost of Repairs 41. These first two points are intrinsically linked and the Panel finds it is suitable to deal with them together. 42. In determining issues such as causation and extent of damage, the Panel relies heavily on the expert materials as well as other corroborating evidence, such as photographs and witnesses. 43. The Applicants have not accepted the reports provided by the FSP’s experts regarding the extent of damage attributed to the storm. However, the Panel finds it difficult to place much weight on AL’s report. It appears this report was compiled by an architect, who is not an ideal expert to comment on the causation of home damage and the scope of works required to repair the damage. 44. In contrast, SBC is a building consultant and the report dated 7 June 2010 was authored by a licensed builder. In the Panel’s opinion, a licensed builder is more appropriately qualified than an architect to examine and report on the probable cause for building damage. Although the Panel notes the Applicants have identified that some of the FSP’s experts are in conflict, this does not mean that they should all be ignored. 45. In instances when there is some conflict between experts, the Panel is entitled to accept the expert whose report is credible and reasonable and authored by an appropriate expert. In this case, the Panel finds SBC’s report to be more comprehensive than the others presented and clearer in its reasoning and observations. 46. In particular, SBC conceded that the majority of the damage brought to their attention by the Applicants was covered by the policy. The two issues that SBC did not accept were storm related was the kitchen cabinets and wood rot at the window sill bases. 47. These two issues were not considered by AL’s report, which further supports the fact that it does not provide probative weight to the Applicants’ position. In contrast, SBC’s report stated the following regarding the kitchen cabinets and the window sill: “A closer inspection of the sink area above the cabinets revealed water was seeping through the wall tile and sink junction. Over an extended period of time water has been damaging the back and side walls of the cabinets. There was no silicon sealant applied along the junction which would have prevented the seeping of water from the sink. I am of the opinion that the cabinets on the southern elevation of the kitchen are damaged from water entering through the junction of the sink and tiled wall. There were no preventative measures taken to stop water gaining entry at this point and causing the observed damage. It is my opinion that this area of the kitchen cabinets was not damaged by the storm event…. I also observed that large sections of all three windows were displaying signs of wood rot at the sill bases of the windows. Large sections of the windows measuring 100mm in diameter had rotted out. I am of the opinion that the windows had been damaged by wood rot prior to the storm event. This will need to be repaired by the Insured pr ior to any storm related works being undertaken.” 48. The Panel finds SBC’s reasoning as to why these items were not proximately caused by the storm to be sound. Further, SB also supported SBC’s findings regarding the kitchen cabinet. 49. AL’s report does not mak e any attempt to identify the proximate cause of the damage to these areas. In relation to the kitchen cabinets, AL merely states it requires complete replacement and that the timber window frames “appear to have had damage exacerbated by the hail”. AL doe s not attempt to expand on this comment, such as whether the hail was the proximate cause of the damage or what issue was exacerbated by the hail. 50. Given this, the Panel accepts that SBC’s report should be considered as the appropriate basis for determining the proximate cause of damage as at the time of their inspection. It therefore follows that the scope of works set out and the quotation provided in support sets out the extent of the FSP’s liability for the damage evident at that time. 51. The Applicants have provided three quotes they maintain are consistent with AL’s report. However, the Panel does not accept these quotes provide any probative value given the following:  The maximum quote the FSP obtained was for $25,642.72 pursuant to SBC’s scope of works. Although this scope of works did not include the window sills and kitchen cabinets, it is difficult to accept that the most expensive tender obtained by the FSP underquoted the true cost by approximately $150,000; and  These quotes were in line with AL’s re port, which the Panel found was not probative to the Applicants’ case; and  They were not compiled pursuant to SBC’s scope of works. 52. The Panel will therefore rely on the quotes obtained by the FSP as setting out the likely cost involved in repairing the storm related damage as evident at SBC’s inspection. Further Damage 53. The issue in dispute between the parties regarding this is whether the Applicants have undertaken reasonable steps to mitigate their loss. 54. The Applicants have highlighted the fact that the sheet affixed to the roof was inadequate, which seems to be corroborated by SBC who stated in their report: “During my inspection of the roof area I observed that the roof had been temporarily secured by an Insurance builder. The Insured was concerned that further water is entering the building. I recommend the temporarily installed tarpaulin be removed and a more robust and appropriate tarpaulin be installed as there is the potential for further water entry.” 55. The FSP does not appear to dispute this and indeed makes reference to this in some of the emails produced. However, the Panel notes that the Applicants refused access to any of the FSP’s contractors after disputing SBC’s report and scope of works. As such, it appears the only way the FSP could have repaired this issue was to concede to the Applicants’ position, which the FSP found was not reasonable in the circumstances. 56. The Panel notes that a party is normally required under common law to take reasonable steps to minimise their loss. Whether a party has done so is a question of fact and depends on the circumstances of a particular case. 57. The Panel finds that the Applicants actions in this regard were not reasonable. They chose to continually follow up the FSP and dispute the scope of works and contractors to be used. They wished to utilise their own contractor because they believed the FSP’s contractors would not have completed the works in a workmanlike manner. 58. This presumption was based on a negative experience of other neighbours. However, the Panel does not accept this in itself was sufficient to reject access to the FSP’s contractors as the Applicants provided no corroborative evidence regarding this allegation. 59. The Applicants have also relied on the fact they continually attempted to resolve this dispute with the FSP by providing quotations which they felt were reasonable. However, one of these quotations was for the replacement of the whole kitchen, which the Panel accepts the FSP was not liable to repair, given the damage to the kitchen cabinets was not proximately caused by the storm. 60. Regardless of this, it is the Panel’s opinion that a home owner whose roof is leaking and continuing to leak should undertake reasonable steps to ensure this stops. In these circumstances, especially as the matter became protracted, it would have been reasonable for the Applicants to attempt to ensure this issue was rectified as a matter of priority rather than attempting to compel the FSP to resolve the claim on their terms. 61. This could have been done by the following:  Utilising the cash settlement received from their contents claim to either repair the roof themselves or engage someone to affix the tarpaulin properly. The Panel notes the contents were cash settled for $30,556 on 4 June 2010 and the Applicants had submitted quotes totalling $6,514.50 for the total roof restoration;  Insist the FSP either repair the roof or rectify the temporary works by allowing its contractors access to their property; or  Accept a cash settlement in partial settlement for the roof repairs whilst still preserving their right to contest the balance. 62. There is no evidence the Applicants undertook any of these or other steps to protect their property from further water inundation. 63. Upon SBC’s inspection on 31 May 2010, it is reasonable to accept that their scope of works would have included any water damage that may have accumulated to that date. This is based on the fact SBC acknowledged almost all of the water damage brought to their attention by the Applicants was due to the claimed event except for the kitchen cabinets and window sills. The Panel notes this inspection occurred almost three months after the event. 64. The Panel therefore does not accept that it is reasonable that the FSP should remain on risk for all the further damage that has occurred after SBC’s inspection, especially as it appears the Applicants exercised little initiative to protect the property themselves. 65. It is therefore the Panel’s opinion that the Applicants have not exercised reasonable steps in minimising their loss. Accordingly, the FSP is not liable for additional damage that occurred after SBC’s inspection. Alternative Accommodation 66. The policy provides for alternative accommodation costs under the following policy provision: “If we agree that an insured event has caused so much damage to your building that you cannot live in it, we will pay alternative accommodation costs. The amount we will pay is the amount it could have been rented for, and we will pay this amount for the period from the time the building is unable to be lived in as a result of the damage and while it is being repaired, rebuilt or replaced up to a maximum period of twelve months.” 67. It appears that the Applicants were able to inhabit the premises early in the claims process and there was no evidence to suggest that repairs could not have been done whilst they remained there. It was due to the prolonged nature of this dispute that resulted in the premises being uninhabitable. 68. The Panel has accepted that the further damage after SBC’s inspection was substantively due to the Applicants’ failure to take reasonable steps to minimise their loss. Further, the policy expressly excludes loss caused by: “…lack of maintenance to the building …” 69. However, the Panel notes the FSP has provided approximately $5,000 in alternative accommodation costs whilst this dispute was before the Service. This would account for almost three months accommodation based on the Applicants’ rate. The Panel accepts this was a reasonable outcome in the circumstances and does not consider there is any basis to award more to the Applicants. Conclusion 70. The Panel accepts the FSP’s liability is limited to SBC’s scope of works dated 7 June 2010 that were associated with the claim. However, given the additional damage that has incurred, the Panel does not accept it is practical for the FSP to now attempt to repair the damage pursuant to this scope of works. 71. As such, the Panel accepts a cash settlement is an appropriate outcome in these circumstances. In determining an appropriate figure, the Panel notes that it is common for the actual cost of repairs to exceed the quoted amount. Further, the evidence appears to indicate the FSP’s contractor did not undertake appropriate emergency works regarding the roof. Although this additional damage was likely accounted for by SBC at their inspection, the Panel considers it is appropriate to allow some margin for this. 72. In determining an appropriate figure, the Panel refers to clause 8.2 of the Terms of Reference, which states: “… when deciding a Dispute and whether a remedy should be provided in accordance with paragraph 9, FOS will do what in its opinion is fair in all the circumstances, having regard to each of the following: a) legal principles; b) applicable industry codes or guidance as to practice; c) good industry practice; and d) previous relevant decision of FOS or a Predecessor Scheme (although FOS will not be bound by these).” 73. Taking into consideration all of the above, the Panel considers it is fair in all the circumstances to allow a 15% builder’s margin to a cash settlement amount based on the quotation the FSP was willing to settle this dispute on. This calculation results in a payout figure of $29,489.13. Determination 74. On the basis of the available information, the Panel determines that the FSP pay the amount of $29,489.13 to the Applicants in full and final settlement of this claim. 75. In the event the Applicants accept this Determination, this amount should be paid within 14 days of the FSP being notified of its acceptance unless it requires a binding release to be signed first. In the event the FSP requires a binding release to be signed, it should:  Ensure a release is sent to the Applicants within 7 days of being notified of the Applicants’ acceptance of the Determination; and  Pay the above amount within 7 days after it has received an appropriately signed release.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.