Home / Financial Firm (Unknown - Insurer) / Determination 223057

Determination 223057

Foundation subsidence claim settled on 40% apportionment; applicants sought full sum insured as total loss

FirmFinancial Firm (Unknown - Insurer)
Decided2011-05-02
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$83,756
Non-financial loss—
Amount claimed$163,900
SourceAFCA PDF

Summary

The applicants claimed the full sum insured for foundation subsidence damage to their home, and the FSP offered 40% of repair costs. AFCA found the covered leaking shower base and storm drain contributed to part of the damage, the drought-related soil shrinkage was excluded, and ordered the FSP to pay $83,756.40 to settle the claim.

Under the policy, only damage caused by covered liquid escape is payable, so the independent expert's apportionment of covered and excluded causes sets the indemnity.

Issues

Subjects and remedies

home or building damagepay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Page 1 of 12 223057 Determination Case number: 223057 General Insurance - Domestic Insurance - Home Building - FSP Decision – Settlement Basis 20 April 2011 Background 1. The Applicants held a Building and Contents insurance policy with the Financial Services Provider (FSP) which was taken out on 8 September 2002. The sum insured for the insured building at the time of loss was listed at $164,000, contents for $49,000 and specified items for $12,201. 2. The Applicants proceeded to lodge a claim against their policy through their broker on 23 February 2010 for extensive damage to the insured property as a result of the sinking of the property‟s foundations. 3. The FSP partially accepted the claim and proceeded to make a contributory offer of settlement to the Applicants in the amount of $55,103.40, this being 40 percent of the total cost of repairs plus some additional benefits. 4. The Applicants remain dissatisfied with the settlement offer put to them by the FSP and believe that the insured building is a total loss and as such the FSP is obliged to settle them for the full sum insured of $164,000 minus the applicable excess of $100. Summary of Applicants ’ Position 5. The Applicants held an insurance policy with the FSP covering their home and contents upon which they lodged a claim for indemnity for extensive damage to the building. The damage was as a result of the home‟s foundation sinking due to moisture leaking into the foundation from a blocked drain pipe. 6. The Applicants do not accept the FSP‟s decision to only offer a 40 perc ent partial settlement towards the total costs of repairs, on the basis that 60 percent of the claimed damage was due to drought ground shrinkage. 7. The Applicants maintain that there was only minor cracking to the home prior to the blocking up of the drainage pipe after which rapid and major subsidence occurred. Determination Page 2 of 12 223057 Determination 8. The Applicants, relying upon the advice of their expert engineer “CO” are of the opinion that the FSP is obliged to cover them for 95 percent of the total costs of repairs allowing a 5 percent deduction for the minor drought ground shrinkage. 9. Further that all of the costs incurred by the Applicants were necessary to undertake repairs their engineer had identified as necessary in order to prevent any further damage to the home. 10. The total cost of repairs exceed the sum insured amount of $164,000 and as such, the FSP should settle the Applicants on the building being a total loss, that is settle them for its maximum liability ($164,000) minus the applicable policy excess ($100). 11. The Applicants had to sell their boat and borrow funds from the bank in order to undertake the repairs recommended by “ CO ” . Further they have had to pay interest on the borrowed funds due to the FSP‟s decision to delay and reduce the settlement the Applicants are clearly entitled to. 12. The Applicants remain dissatisfied with the service provided by the FSP during the course of the claim and allege that it has intentionally attempted to delay the settlement of the claim whilst failing to respond to communication sent in by the Applicants. Summary of FSP’s Position 13. The FSP relies on the following policy provisions: “Page 14 -16 Section 1 – Buildings and Contents Listed Events cover … We will cover your buildings and your contents for loss or damage from the events listed below.  Fire or explosion.  …  Liquid that escapes from:  A fixed pipe or something attached to a pipe, fixed gutter, fixed tank or a drain.  A bath, basin, sauna, shower base or shower wall, sink, toilet or tiled floor that has drainage holes.  Landslide or subsidence. This includes loss or damage to any gates, fences or retaining walls that are entirely or partly at the situation. However, the cover only applies if the loss or damage occurs within 72 hours of, and as a direct result of, one of the following listed events:  Storm, tsunami, rainwater, hail, snow or wind.  Earthquake. Page 3 of 12 223057 Determination  Explosion.  Liquid escaping from a fixed pipe or something attached to a pipe, fixed gutter, fixed tank apparatus or a drain. … Page 17-19 Additional things we will pay for when you have insured your buildings If you have cover for your buildings, the following will be paid in addition to the sum insured as listed on your schedule. We will only pay these costs when they relate to loss or damage from a listed event: …  We will pay the reasonable costs of architects, surveyors and engineers and also pay any legal fees that arise from reinstating your buildings when loss or damage occurs.  We will pay costs necessary to meet the requirements of any statutory authority in connection with the rebuildin g or repairing the buildings at the situation. …  If any trees, plants, shrubs or lawns are damaged by an insured event other than storm we will pay to replace the trees, plants, shrubs or lawns, up to $5,000 in any one period of insurance. We will pay up to $1,000 for any one tree, plant or shrub. We will not pay for damage caused by a weather-related event. … Page 27 What are not your buildings  …  Plants, shrubs, trees or grass except as provided for under „Additional things we will pay for when you have in sured your buildings.‟ … Page 32 The most we will pay for your buildings or your contents The most we will pay for any claim for your buildings or your contents is the sum insured shown on your schedule. This does not apply to amounts payable under „Additional things we will pay for when you have insured your buildings‟… … Page 46-47 What Section 1 and Section 2 of the Policy do not cover General exclusions applying to this Policy … We will not pay claims for loss, damage or liability arising from:  …  Landslide or subsidence except as detailed on page 16.” 14. Based on the description of the loss submitted by the Applicants, the fact that they advised the damage had been ongoing for three years, and taking into Page 4 of 12 223057 Determination account the reports submitted by “T” and “F”, the FSP initially concluded that the claimed loss did not fall within the terms of the policy. 15. However on receipt of the further information from the Applicants and an expert report from “ CO ” , it became apparent that possibly a portion of the claimed damage may be covered under the terms of the policy. 16. The initial expert reports from both “ T ” and “ CO ” attributed the damage to the prolonged (15 years) dry weather conditions prevalent in Victoria, with the majority of damage occurring in 2009. “CO‟s” report however also indicated that a broken/blocked storm water drain pipe (the pipe) on the west side of the building was a contributing factor for the extensive damage subject to the claim. 17. The FSP appointed expert “C” to the claim and instructed him to submit a report on the cause, extent and scope of works required to repair the damage to the building assessed to be as a result of the leaking pipe only. 18. On receipt of “C‟s” report, the FSP noted that it was the expert‟s opinion that although the leaking pipe did contribute to the loss, the movement damage would have occurred regardless of the broken pipe. 19. In line with its expert‟s recommendation, the FSP proceeded to offer the Applicants settlement of the claim in the form of a 30 percent contribution to the total cost of repairs, 30 percent of the cost of the Geotechnical report and 100 percent of “CO‟s” supplementary special report, amounting to $42,225.80. The offer of settlement was rejected by the Applicants. 20. As a consequence of the conflicting expert reports relied upon by each party, it was mutually agreed that an independent expert selected by both parties be appointed to review the claim. After considering a number of experts , both parties accepted and as such appointed “G” to the claim. 21. An expert report was submitted by “G” which concluded that the damage in question was in all probability as a result of three contributing events. He listed the three events on the basis of the more likely to least likely and the FSP maintains that the leaking pipe was listed as the least likely of events to have contributed to the resultant damage. 22. “G” in his report identified a leaking shower tray as a contributory event and which had not been identified previously. Taking this into account and in an effort to resolve the dispute, the FSP increased the settlement offer to 40 percent of the total costs of repairs, 40 percent of the Geotechnical Report and 100 percent of “CO‟s” supplementary special report, in all, an amount of $55,103.40, however this was again rejected by the Applicants. 23. The FSP maintains that all the experts appointed make reference to the nature of the clay/soil upon which the foundations are built, the impact of the extended drought conditions and the impact of the surrounding trees and shrubs on settlement of the foundations. Page 5 of 12 223057 Determination 24. In line with the available experts evidence, the major contributing factor identified is excluded by the terms and conditions of the Applicants‟ policy of insurance. Further the FSP maintains that the terms of the policy also exclude from cover costs associated with repairing/replacing the item from which the liquid escaped i.e. damaged pipe and shower base. 25. The Applicants ‟ reliance upon the “Special benefits” clause to seek a waiver of the applicable excess amount on the basis that the building is a total loss does not apply as there is neither evidence of a Catastrophic event or of the FSP‟s calculator providing an incorrect sum insured. 26. The FSP submits that the Applicants‟ demand for indemnity in the amount of $27,000 for the alleged cost of repairs to the fencing, landscaping, brick repair, rendering and concreting remains unsubstantiated. Further that the said repairs have been included with the quoted scope of works submitted by “B” and “K” based upon which the offer of settlement has been calculated and as such, would constitute a double payment to the Applicants. 27. Although the Applicants have submitted an invoice for the cost to repair/replace the fencing, this is in excess of the quoted amount of $1,000 submitted by “B” and no justification has been provided by the Applicants for the higher amount being claimed. 28. The FSP maintains that the quotes submitted by “ B ” and “ K ” are competitive and reasonable which include all the additional work claimed by the Applicants and for which they have not provided any justification. Further the FSP is within its rights to choose “B‟s” quote and scope of works as the basis for its settlement offer. 29. The FSP accepts that the original H R re -blocking quote of $49,500 submitted by the Applicants is within reasonable range of the industry standard. However, the FSP is not prepared to accept the additional $9,000 which has merely been hand written onto the original invoice by the Applicants without any explanation or justification. 30. In addition, the A pplicants‟ decision to go ahead with and authorise the foundation work at a higher quoted amount was taken independently and without consulting the FSP. Therefore this does not result in the FSP being responsible to cover the additional costs. 31. On the basis of the quoted scope of works and associated costs by both “B” and “K”, it is clear that the building is repairable as the repair costs come below the sum insured of the property, and as such, it is not a total loss. 32. The FSP acknowledges that the Applicants are entitled to additional benefits in respect to the costs ($763) associated with obtaining the required permits from the Shire Council, however limited to the percentage of liability (40%) accepted by the FSP and amounting to $305.20. 33. The bank expense s claimed by the Applicants in the FSP‟s opinion were incurred as a result of the Applicants commencing the foundation work before Page 6 of 12 223057 Determination allowing the FSP to obtain quotes. The Applicants persisted in obtaining and acting upon their own expert‟s advice , and as such, these costs are not the responsibility of the FSP. 34. The FSP maintains that the scope of work and subsequent quotes provided by both “B” and “K” are reasonable and competitive. Therefore it is both fair and reasonable for the FSP to use these quotes to base its 40 percent contribution offer to the Applicants, which it maintains is its maximum liability under the policy. Issues 35. Whether the FSP is correct in its decision to apportion its liability for the claimed loss to 40 percent of the total cost of rectification. 36. Whether the scope of works and associated repair quotes relied upon by the FSP is both fair and reasonable for the purpose of establishing the FSP‟s monetary settlement offered to the Applicants. Reasons for Decision 37. This decision has been made by a Panel consisting of an Ombudsman, a representative with extensive experience in the insurance industry and a representative with extensive experience in consumer claims. 38. The Panel has had regard to the submissions of both parties subject to this dispute in relation to the damage claimed, terms and conditions of the policy and their respective positions pertaining to the dispute. 39. The dispute has arisen as a result of the FSP‟s decision to only offer partial settlement of the Applicants claim. The Applicants allege that all the damage claimed is as result of a leaking/ blocked storm drain pipe running along the west side of the property. 40. The Panel is satisfied the provisions of the policy cover damage/subsidence caused by liquid escaping a blocked/broken drain and or liquid escaping a shower base. However the policy excludes from cover subsidence which is not a result of specific events listed in the policy. 41. The policy also requires the Applicants to obtain the FSP‟s authority to undertake repairs following an insured loss unless emergency repairs are necessary or to minimise further damage. 42. The Panel notes that the extent of loss claimed and the source of the moisture introduced into the soil under the home is not disputed by either of the parties to this dispute. The dispute essentially revolves around what is the major contributing factor for the loss and to what extent the FSP is obliged to cover the Applicants for the costs associated with repairing the insured building. Page 7 of 12 223057 Determination 43. The Applicants in coming to their position in respect to the proximate cause for the damage rely upon the expert report obtained by them. This report has been submitted by CO and is dated 26 May 2010. The expert report states in part: “OVERVIEW: DETERMINATIO N OF CAUSE OF FOUNDATION SETTLEMENT We consider that the foundation settlement and brickwork wall damage has occurred due to a sequence of events. Initially, foundation soil shrinkage most likely occurred during the drought period which was extreme in 2009. The settlement of foundations may have had some effect on the probable differential settlement of the SWD pipe particularly on the west side. As a consequence, it is most likely that damage and blockage has occurred to the SWD pipe, which, during recent rain periods has allowed water to escape along the drain (i.e. evidence of greater seepage where the magnitude of settlement is greatest) causing the underpinning foundation soils to saturate (locally) and further exacerbate settlement of the foundations and thus increase the crack widths on the walls especially during late 2009 and early 2010. It has been observed that the cracking is still progressing and slowly getting worse. CONCLUSION There is no doubt that the prolonged dry weather conditions together with consequential damage of the SWD system have contributed to the settled state of the foundations and superimposed walls. …” 44. The Applicants maintain that the FSP is obliged to cover 95 percent of the rectification costs and that only 5 percent of the damage is as result of the extended drought conditions prevalent in Victoria over the previous 15 years. In coming to this position the Applicants rely upon a further report submitted by their expert “ CO ” and dated 16 February 2011. The expert report states in part: “CONCLUSION 1. It is scientifically, logically and geotechnically impossible for seeping water to stop on the West side of the house and not affect the North and South walls. 2. It is scientifically, logically and geotecnically possible and highly probable that the seeping water caused at least 95% of the damage to the house.” 45. The FSP strongly disputes the Applicants‟ expert‟s contention in respect to the apportionment of the extent of loss attributed to the leaking storm water drain pipe and as such the extent of indemnity the FSP is obliged to provide the Applicants in this regard. 46. The FSP in an effort to establish the extent of its liability in respect to the claimed loss proceeded to appoint its own expert to the claim. The FSP‟s expert “ C ” after having completed its assessment of the loss submitted its initial report dated 12 July 2010. This report states in part” “ OBSERVATIONS … Many of the cracks and gaps observed internally showed signs of having been previously repaired. These repairs were most noticeable in the passage adjacent to the front door, within the sunroom, within the laundry and toilet, and along the main passage. The evidence of previous repairs indicates a long term foundation movement issues. …. Page 8 of 12 223057 Determination At the time of our inspection, the western most ridge tile had cracked completely and had dislodged from the ridge, leaving……the adjacent ridge tiles indicates that these had been fixed with a different coloured mortar. This again indicates signs of previous repairs, and highlights long term movement issues at the residence. ….There was also evidence of previous repairs to the sewer pipe work along the west side of the residence. This again indicates long term settlement issues. … CONCLUSIONS: In order to fulfil our instructions to “identify and Scope the damage as a result of the leaking pipe”, we are therefore required to form conclusions as to the amount to which the leaking stormwater drainage pipe has contributed to the overall damage to the residence. Our conclusions are therefore as follows:  There has been long term settlement of the foundations, which would have occurred regardless of the condition of the stormwater drainage pipes. This long term settlement has been caused by the inadequacy of the foundations to resist seasonal movements within the reactive clay soils. The movement has been exacerbated by the long term drought conditions which have occurred within Victoria over the last fifteen years, and particularly during the very dry period ate the start of 2009.  Soil movements have caused blockage and/or leaks within the stormwater drainage pipe on the west side of the residence. This has allowed excess moisture to seep into the soils, as noted in the two previously mentioned Reports.  The excess moisture in the soil has caused further differential movement and settlement of the foundations in the vicinity of the stormwater drainage pipework. … We therefore propose that the Insurer make a contribution to the total cost of repairs, commensurate with out recommendations regarding the extent of damage caused by the stormwater drainage pipe work We would suggest that a contribution of 30% would be reasonable, given that the damaged and/or blocked drainage pipework is located only along the northern and western elevations of the residence; and also given that the residence would have been damaged in any event, regardless of whether or not the stormwater drainage pipework had leaked. ” 47. Also submitted to the FSP was a further report from “C” dated 4 March 2011. This report states in part: “…We have considerable experience of investigating this type of Claim, in situations where comparative moisture tests were completed. We state our original opinion that we consider it highly unlikely that moisture from pipe leaks on the west elevation has caused damage to internal walls and rooms located on the east side of the residence. It is our opinion, that it is much more likely that this damage has been caused by shrinkage of the foundation soils, due to the effects of the drought, and surrounding vegetation, as stated above. We not that this opinion is also confirmed with the [G] Report, which lists the drying effect of trees as the most likely cause of damage at the residence. [G] Page 9 of 12 223057 Determination also notes that the contribution to the damage from the drying effects of the trees is considered to be higher than any other stated cause of damage. … Furthermore, the CSIRO paper states that, even if there were no stormwater drainage around the residence, the effects of the recent drought on the Insured’s foundations, when combined with the further moisture demand from the surrounding vegetation, would have caused substantial foundation settlement and resultant damage. … Given the above, we are unable to agree with the conclusion contained within the Supplementary Report from [CO], that seeping water has caused at least 95% of the damage to the house. In our opinion, this percentage is likely to be around 30% only, as stated within our First Report.” 48. The Panel notes that the parties to this dispute acknowledge the conflicting positions taken by their appointed experts and as such came to an understanding that an independent expert acceptable to both parties would be appointed. In line with this agreement and after considering multiple options, “ G ” was appointed to the claim and instructed to submit a report on the cause and extent of the damage to the insured property. 49. After completing its assessment of the damage and having reviewed both “C” and “CO‟s” original reports, “G” submitted its report dated 22 November 2010 for review and consideration. 50. The Panel has given considerable consideration to the independent expert‟s report. This report states in part: “At your request we carried out and inspection of the above property on 9 November 2010, for the purpose of determining independently the reasons for structural damage that has occurred to the dwelling…. 1 Background … Clay soils in the Yarram area are known to be reactive, and damage such as observed prior to the underpinning work is not uncommon in the township, especially during dry seasons where excessive soil drying shrinkage may result if influenced by trees. … 3.2 [CO] … The [CO] soil report classifies the site as Class M, however the extent of damage and movement recorded in the condition report (100-120mm) suggests otherwise. The guidelines given in AS2870 Residential Slab and Footings Code, table 2.3 for ym>70mm, suggest the site would be classified as Class E, and the movement profile would likely be in the range 2 to 3 depth. … 6. The conclusion that “..a contribution of 30% would have been reasonable…” is difficult to substantiate. Whilst we agree that the damage would certainly have been initiated by soil drying shrinkage, without detailed observations over several years, both prior to and after the broken stormwater drain event, there is Page 10 of 12 223057 Determination insufficient evidence upon which to draw such a conclusion. This is now further complicated by the discovery of the leaking shower base, which given the extent if staining of the base brickwork and rising damp, appears to have been continuing for some time and will have some influence on the damage that has occurred. … 4 Discussion [G] is of the opinion that the damage to the dwelling has been caused by a number of factors, and in order of the likely influence from the first having the highest likelihood of causing damage, to the third being the least: 1. Differential soil during shrinkage, initiated by the drought conditions over the past 15 years, but caused by native trees and shrubs located around the dwelling, specifically on the south, west (now removed) and north sides. 2. Softening of the soils on the west side due to inundation from the leaking shower base that appears to have been continuing for some time. 3. Softening of the soils due to inundation from the blockage of the stormwater drains on the west side. … The extent of damage, considering specifically the damage that has occurred to the Lounge and Sun Room areas, and the geometry of the internal strip footings, indicates that the inundation from the blockage of the stormwater drains on the west side could not have been the sole cause of the damage.” 51. Having reviewed all the evidence made available and relied upon by the parties to this dispute, the Panel is satisfied that the insured property has suffered extensive damage and also that this damage is not as a result of a single event. 52. Further, it appears likely that the causes identified by expert “G” have not occurred concurrently, but rather consecutively, although it is probable that there would have been some overlap of the effects of these causes. 53. Therefore the Panel needs to determine, on the balance of probabilities, the extent of damage attributable to each event which has contributed to the loss and as such determine the extent of indemnity the Applicants are entitled to. 54. It has been taken into consideration that the experts appointed by the each party varied in their opinions regarding the extent and proximate cause of the damage, howev er, taking into consideration the independent expert‟s report , the Panel is satisfied that there is sufficient evidence to provide a fair and reasonable determination in this regard. 55. Despite the opinion of “ CO ” the Panel is not persuaded that the seepage of water from the blocked/leaking stormwater drain pipe on the west side of the house has resulted in 95 per cent of the damage as claimed by the Applicants. 56. The Panel notes that the FSP has maintained its position that the blocked/leaking stormwater drain pipe has contributed to approximately 30 percent of the claimed loss. Also, after being made aware by “G” of the leaking Page 11 of 12 223057 Determination shower base, it increased its offer of contribution by a further 10 percent to cover damage from this additional event. 57. Relying upon t he independent expert‟s opinion in coming to its final position the Panel is satisfied that the FSP has accepted the outcome of the independent expert report. The Panel further notes that in providing his expert opinion “ G ” has listed the leaking shower base as more likely a greater contributing factor to the loss above that of the blocked/leaking stormwater drain pipe. 58. A reasonable interpretation of this would mean that the leaking shower base event has a higher percentage of contribution to the loss than the leaking pipe. This is at odds with the FSP‟s view that the stormwater pipe would have contributed 30% to the damage and the shower base 10% of the damage. However this does not necessarily mean that the FSP‟s overall assessment of its contribution is incorrect. 59. Based on the report of the independent expert “G”, the Panel believes a fair and reasonable assessment of the factors contributing towards the total damage claimed by the Applicants would be: 1. 40 per cent of the damage as a result of differential soil during shrinkage, initiated by the drought conditions over the past 15 years, but caused by native trees and shrubs located around the dwelling, specifically on the south, west (now removed) and north sides. 2. 35 per cent of the damage as a result of the softening of the soils on the west side due to inundation from the leaking shower base that appears to have been continuing for some time. 3. 25 per cent of the damage as a result of the softening of the soils due to inundation from the blockage of the stormwater drains on the west side. 60. The Panel notes that the independent expert has identified and formed the opinion that the leaking shower base has also resulted in the staining and damage to the bedroom wall due to the rising damp. The report states: “An inspection of the underfloor space through an opening in the Bedroom 1 floor indicates that the load bearing internal brick walls in fact carried down through the floor structure as noted above. In addition we observed that the bathroom shower base is leaking badly evidenced by staining sown the brick sub wall and rising damp on the bedroom wall (photos No. 27 and 28).” As it has been established that the leaking shower base is an event covered under the terms of the policy, the FSP is obliged to cover the cost of rectifying the moisture damaged wall. 61. The Panel has considered the quotes submitted by “B” and “K” and is satisfied that these are both reasonable and competitive. Further it considers that the additional costs claimed by the Applicants in the tota l amount of $27,000 have not been substantiated and would seem to have been covered within the quotes relied upon by the FSP. Page 12 of 12 223057 Determination 62. The FSP however in its submission has made mention of the fact that it would be open to consider any further quotes and invoices s ubmitted by the Applicants as long as they are fair and reasonable and pertaining to the events covered by the terms of the policy. The Panel is satisfied that the FSP is entitled to rely upon the quotes submitted by “B” and “K” in determining the reasonable cost of repairs pertaining to the claimed loss. 63. The Panel considers that the FSP in relying upon the expert reports submitted by the Applicants has utilised such in the investigation and subsequent determination of the claim. Therefore the Panel is of the position that the FSP is required to settle the Applicants for the costs incurred in obtaining the said expert reports from “ CO ” . 64. The Panel is not satisfied that it has been established that the FSP has intentionally delayed the settlement of the claim. As such it would not be reasonable to hold the FSP responsible for bank costs incurred by the Applicants in obtaining and paying off the loan obtained to carry out a portion of repairs. Determination 65. Accordingly the Panel determines that the FSP is obliged to settle the Applicants‟ claim in line with the figures calculated below: 60% Building reinstatement based on “B‟s” quote = $72,705.60 Costs associated with obtaining expert reports x 2 = $10,593 60% contribution to cost of obtaining Council Permits = $457.80 66. Therefore, the FSP is to settle the Applicants‟ claim in an amount of $83,756.40 within 21 days of receiving this determination.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.