Home / Financial Firm (Unknown - Insurer) / Determination 222628

Determination 222628

Claim amount - building reinstatement after fire

FirmFinancial Firm (Unknown - Insurer)
Decided2011-09-14
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$473,371
Non-financial loss—
Amount claimed$550,000
SourceAFCA PDF

Summary

Following a August 2008 fire at commercial premises, the FSP offered $465,909 cash settlement and the applicant claimed $550,000. AFCA found reinstatement must include a new concrete slab, limited the building payment to the $471,500 remaining sum insured, and ordered reimbursement of $1,871 in quantity surveyor fees.

Repair of the slab would not restore the building to the same condition as new under the reinstatement cover, so the costings include a new slab and the sum insured caps the payment, with cash settlement required.

Issues

Subjects and remedies

business interruptionhome or building damagesmall businesspay claimpay compensation

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 222628 Determination Page 1 of 8 Case number: 222628 General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim amount 26 August 2011 Background 1. The Applicant held a business insurance policy covering commercial premises under the property section of the contract for $510,000 and gross profit of $14,450 under the business interruption section of the contract. 2. On 27 August 2008 the building suffered severe damage as a result of fire. The Financial Services Provider (FSP) accepted liability for a claim under the policy and following assessment of the damage and protracted negotiations with the Applicant, it offered to settle the claim by cash payment in the sum of $465,909. Payments totalling $$18,062.43 have been made under the business interruption claim. 3. The Applicant declined the cash payment offer of $465,909 and is claiming the sum of $550,000. Summary of Applicant’s Position 4. The Applicant obtained quotations for rebuilding the premise from three contractors in the sum of $529,840, $518,700 plus $51,870 GST and $532,815. 5. The Applicant obtained and relies on estimates provided by a quantity surveyor commissioned by him. The estimates are in the sum of $599,038 which includes replacement of the concrete slab and $522,045 which includes the cost of repairing the concrete slab. 6. The Applicant argues that the estimates show that the premises cannot be rebuilt with the sum offered by the FSP. 7. The Applic ant states that the FSP‟s offer is based on reusing the concrete slab. The Applicant further states that expert advice provided by a structural engineer confirms that it is not feasible to reuse the existing slab and therefore the higher estimate by the quantity surveyor which included a new slab is the relevant basis for settlement of his claim. 8. The Applicant asserts that given the substantial increase in the FSP‟s offer, it is apparent that the first offer of $329,780 of 19 June 2009 was unreasonable and Determination Case No: 222628 Determination Page 2 of 8 has significantly delayed reconstruction and in turn his ability to trade. Although the FSP ceased „loss of earnings‟ payment, he has continued to suffer loss of earnings and his unrecovered losses would have been mitigated had the FSP settled the claim reasonably. Summary of FSP’s Position 9. On receipt of an engineer‟s scale plans and specifications tenders which were to close on 31 January 2009 were called for reinstatement of the building. 10. Three quotations were obtained with the lowest being $298,760. Following submissions by the Applicant, the quote was revised to $329,780. 11. The Applicant‟s solicitor rejected the offer and advised the Applicant would accept $450,000. 12. Further enquires were made with the engineer who advised that the concrete slab could be repaired. A further offer in the sum of $337,500 was made to the Applicant. The offer was rejected and the Applicant advised he would accept $400,000. 13. The offer was revised and increased to $385,000. The offer was again rejected and a counter offer of $450,000 was made by the Applicant. 14. On 2 July 2010 its preferred contractor revised its quotation up to $353,045 which nevertheless was less than its offer. 15. A further engineer‟s report stated 19 August 2010 confirmed there was no further damage to the concrete slab and damage to the slab was superficial. The engineer also considered the quote by its preferred contractor was accurate with the exception of preliminary costs and the concrete slab. 16. It maintained its offer of $385,000. 17. Costings were obtained from a quantity surveyor in the sum of $465,909 using the existing slab and $522,046 constructing a new slab. 18. Based on these figures, a final offer in the sum of $465,909 was made to the Applicant. 19. The FSP relies on the following policy provisions: “Section A – Business Property Cover … Reinstatement or Replacement Cost We will pay the cost of rebuilding, replacing or repairing any damaged part of your Business Property to the same condition as when new. … Case No: 222628 Determination Page 3 of 8 If the Business property is lost or damaged you must start to rebuild, replace or repair within 6 months of the loss or damage. If you do not, we will pay your claim in accordance with the Indemnity value method of settlement unless we have agreed in writing to extend the period. We will not pay more than the Sum Insured shown on the Schedule for each item covered.” Issues 20. Whether the FSP‟s offer of $465,909 is fair in all the circumstances. Reasons for Decision 21. This matter involves a dispute in relation to the sum of money to be paid for reinstatement of a building which was destroyed by fire. The building was insured for $510,000 and in turn the property element of the claim is for this amount. 22. The FSP had made a number of offers to settle the claim culminating with a final offer at Internal Dispute Resolution (IDR) level of $385,000. Further offers and counter offers have been made since the dispute was brought before FOS. In each case, the offers and counter offers bring the amount in dispute to below $280,000. As such, the Panel accepts that the dispute falls within the FOS jurisdiction. 23. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This is because of the complex nature of the issues. This dispute has not been the subject of a FOS recommendation and has proceeded directly to Determination. 24. There has been an exchange of material between the parties on which each party relies. Each party therefore has had the opportunity to comment on the issues. 25. Prior to making a finding in this determination, the Panel has read and considered all the material presented to FOS. 26. The Applicant is seeking a benefit under the policy and therefore has the burden of establishing on the balance of probabilities that the benefit claimed falls within the terms of cover provided by the contract. 27. As there has been an exchange of material between the parties, the Panel does not intend to repeat the chronology or recite the various reports on which each party relies in this determination except where considered relevant. Sum Insured Case No: 222628 Determination Page 4 of 8 28. According to a copy of the renewal schedule for the period of insurance from 21 April 2008 to 21 April 2009, the Applicant‟s building was insured for $510,000. 29. Following the loss, the FSP arranged for removal of the debris at a cost of $38,500. The relevant policy terms provide: “Additional Benefits Removal of debris If Business Property has been damaged or destroyed and is covered, we will pay the reasonable costs incurred in the demolition and/or removal of debris from the Business Premises. We will pay up to the amount shown on the Schedule for removal of debris, or if this is insufficient and you have not exhausted your Sum Insured on the damaged items requiring demolition and/or removal of debris, we will pay up to the remaining balance of the Sum Insured.” 30. As the Schedule does not contain a specific sum insured for removal of debris, the $510,000 sum insured from buildings applies and is reduced by the $38,500 payment. As such, the balance remaining for payment of the claim is limited to $471,500. Concrete slab 31. The Applicant notes that the slab was severely damaged by the fire over a number of areas and not limited to just one section. The localised repairs would be required over the whole slab leaving a patchwork appearance. 32. The Applicant asserts that the slab had the entire electrical conduit and cabling laid under the concrete slab. There are numerous “T” insertions in the conduit. 33. The Applicant states that the electrician who installed the wiring/conduit advised that it would be impossible to lead cables through the existing conduit with so many right angle bends. 34. Engineer MP commissioned by the FSP, in his report dated 12 May 2009 advised that a meeting was held with the Applicant during which a number of issues of concern to him were discussed. The engineer‟s report details the action taken following that meeting. Apart from issues relating to the concrete slab, the Applicant has not specified any items which continue to be of concern to him. 35. In relation to the concrete slab, the engineer‟s report refers to an earlier report of 14 April in which it was noted that replacement of the slab was not required but may require localised repair. The contractors' quotations obtained by the FSP did not allow for replacement of the slab. 36. By email dated 18 March 2010 engineer MP discussed the issues in relation to repairing compared with replacing the slab and noted the following relevant points: Case No: 222628 Determination Page 5 of 8  The slab was not damaged to the extent that it required replacement for structural reasons.  It was practically feasible to repair the localised damage to the surface by scabbing back the damaged areas to sound concrete, then repairing the concrete with high strength mortars.  Cuts made in the slab to replace electrical conduits could be reinstated by dowel-pinning new areas to the existing slab before pouring replacement concrete over the trenched areas.  This process would result in a patched appearance unless the entire slab was coated with a hard-wearing topping compound. Slabs with coated surfaces would require re-coating over time.  For this reason, the repaired slab is not practically the same as the original slab. 37. In a further report dated 19 August 2010 engineer MP advised:  The electrical conduits would not have been damaged in the fire. New electrical wiring can be drawn through the existing conduits. If this is not possible then local removal of slab for installation of new conduits can be undertaken.  The slab can be reinstated locally with repair mortars and methods outlined in the repair scrapes and slight spalling of the slab. The estimated cost for this work was $2,200 38. A quantity surveyor CPR commissioned by the Applicant ,reviewed MP‟s report and provided the following comments in his report of 4 July 2011  The impact of sawing the concrete slab for laying electrical conduit and cable would significantly reduce the strength of the slab and create weak zones in the stiffened raft system.  The stiffness of such a footing system relies o n the slab resisting heave and pressure induced by reactive clays in the site.  Saw cutting through and trenching below the slab would cut through the top reinforcing bars of the footings, reducing the negative movement resistance to less than one half of its original capacity. 39. The quantity surveyor CPR concluded: “Due to the age of construction and the proposed saw cutting and reinstatement for in ground services below the existing slab, it is considered that the existing footing system is not suitable to support the load of the proposed Building works on the referenced drawings.” 40. CPR provided the following estimates:  Total Budget Estimate (excluding GST and FEE) Using existing slab $522,046 New slab $599,036 Case No: 222628 Determination Page 6 of 8 41. The quantity surveyor “RLB” commissioned by th e FSP in a report dated 1 June 2011 provided the following estimates:  Replacement Cost assessment Using existing slab $465,909.00 New slab $543,345.50 42. RLB appraised the report by CPR and in a report dated 2 June 2011 commented:  5% allowance for design contingency appears excessive.  No additional allowance need be made for escalation due to the competitive state of the market. WTP estimates for render coat/painting, chain mesh fence, paint finish to blockwork, walls, purlins, epoxy floor coating, security bars and contractor‟s preliminaries were considered unreasonable. Summary 43. The expert opinion is divided as to whether the concrete slab may be repaired to a condition which would allow it to function without compromising its integrity. While the opinion in this regard is divided, it is appropriate to consider the issue in the context of the policy terms. 44. The policy provides cover for reinstatement or replacement conditions. This means that the policy will respond to a claim for damage by paying the cost of rebuilding, replacing or repairing any damaged part to the same condition as when new. 45. After analysis of the evidence the Panel considers the report by CPR is to be preferred. 46. It is not in dispute the concrete slab sustained damage during the fire. 47. In the Panel‟s opinion, sawing/cutting into the slab with remedial works involving pinning, covering with replacement concrete which then requires a coating to overcome the patchwork appearance does not adequately satisfy the terms of the policy. 48. Moreover, photographs of the interior of the damaged premises show the area of concrete flooring to be open planned and extensive without interference by partitioning. Hence any patchwork would be visible so that any coating would be required to provide a constant appearance which if not maintained would detract from that appearance. 49. Further the question of structural integrity as noted by CPR is a concern and should not be easily dismissed. 50. For these reasons, the Panel concludes the costings are to include replacement of the slab. Case No: 222628 Determination Page 7 of 8 Quantum 51. The estimates provided by the two quantity surveyors which include a new slab are in the sum of $522,046 and $599,035. As the building sum insured of $510,000 has been reduced by the cost of removing the debris to $471,500 the maximum sum payable for the building damage is limited to $471,500. 52. Estimates including a new slab provided by both quantity surveyors exceed the remaining sum available. Therefore, it is not necessary to prefer one estimate over the other. 53. As the cost to reinstate the building including a new slab, exceeds the sum insured, the Applicant is deemed to be self insured for any costs in excess of the sum insured. When circumstances such as this arise, a FSP is prevented from enforcing reinstatement of the damaged property. In these circumstances , the Applicant is entitled to payment of the claim by cash settlement. Costs 54. Clause 9.4 of the FOS Terms of Reference provide: “ 9.4 Applicant’s costs in pursu ing the matter FOS may decide that the Financial Services Provider contribute to the legal or other professional costs or travel costs incurred by the Applicant in the course of the Dispute. Unless exceptional circumstances apply, FOS will not require the Financial Services Provider to contribute more than $3,000 to these costs. 55. The Applicant commissioned a quantity surveyor to provide estimates for the cost of reinstating the building. This was done following complaints by the Applicant in relation to a number of issues and in particular the concrete slab. 56. The reports provided by the quantity surveyor have contributed to the outcome of the despite. The Panel is therefore satisfied that pursuant to clause 9.4 of the Terms of Reference, the Applicant is entitled to be reimbursed for the quantity surveyor‟s fees incurred by him to further present hi s claim. Loss of earnings 57. The Terms of Reference provide that FOS may consider disputes between an FSP and an Applicant arising from a “Small Business Product”. Howe ver the Terms of Reference further provide that a Small Business Product” does not include cover in relation to Loss of Profits/Business Interruption. 58. The Applicant‟s policy has been extended to include cover provided under the Business Interruption section. Any loss of income as a result of the fire damage falls within the cover provided by this section of the contract. 59. The Panel pursuant to the Terms of Reference is therefore unable to consider the Applicant‟s request for consideration of lost earnings. Case No: 222628 Determination Page 8 of 8 Determination 60. For the reasons expressed above the Panel determines the FSP; a. settle the building damage claim by payment of $471,500 to the Applicant; b. reimburse the Applicant to sum of $1,871 for quantity surveyor‟s fees incurred. s

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.