Text of the determination
Case No: 222628 Determination Page 1 of 8
Case number: 222628
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
26 August 2011
Background
1. The Applicant held a business insurance policy covering commercial premises
under the property section of the contract for $510,000 and gross profit of
$14,450 under the business interruption section of the contract.
2. On 27 August 2008 the building suffered severe damage as a result of fire. The
Financial Services Provider (FSP) accepted liability for a claim under the policy
and following assessment of the damage and protracted negotiations with the
Applicant, it offered to settle the claim by cash payment in the sum of $465,909.
Payments totalling $$18,062.43 have been made under the business
interruption claim.
3. The Applicant declined the cash payment offer of $465,909 and is claiming the
sum of $550,000.
Summary of Applicant’s Position
4. The Applicant obtained quotations for rebuilding the premise from three
contractors in the sum of $529,840, $518,700 plus $51,870 GST and $532,815.
5. The Applicant obtained and relies on estimates provided by a quantity surveyor
commissioned by him. The estimates are in the sum of $599,038 which
includes replacement of the concrete slab and $522,045 which includes the
cost of repairing the concrete slab.
6. The Applicant argues that the estimates show that the premises cannot be
rebuilt with the sum offered by the FSP.
7. The Applic ant states that the FSP‟s offer is based on reusing the concrete slab.
The Applicant further states that expert advice provided by a structural engineer
confirms that it is not feasible to reuse the existing slab and therefore the higher
estimate by the quantity surveyor which included a new slab is the relevant
basis for settlement of his claim.
8. The Applicant asserts that given the substantial increase in the FSP‟s offer, it is
apparent that the first offer of $329,780 of 19 June 2009 was unreasonable and
Determination
Case No: 222628 Determination Page 2 of 8
has significantly delayed reconstruction and in turn his ability to trade. Although
the FSP ceased „loss of earnings‟ payment, he has continued to suffer loss of
earnings and his unrecovered losses would have been mitigated had the FSP
settled the claim reasonably.
Summary of FSP’s Position
9. On receipt of an engineer‟s scale plans and specifications tenders which were
to close on 31 January 2009 were called for reinstatement of the building.
10. Three quotations were obtained with the lowest being $298,760. Following
submissions by the Applicant, the quote was revised to $329,780.
11. The Applicant‟s solicitor rejected the offer and advised the Applicant would
accept $450,000.
12. Further enquires were made with the engineer who advised that the concrete
slab could be repaired. A further offer in the sum of $337,500 was made to the
Applicant. The offer was rejected and the Applicant advised he would accept
$400,000.
13. The offer was revised and increased to $385,000. The offer was again rejected
and a counter offer of $450,000 was made by the Applicant.
14. On 2 July 2010 its preferred contractor revised its quotation up to $353,045
which nevertheless was less than its offer.
15. A further engineer‟s report stated 19 August 2010 confirmed there was no
further damage to the concrete slab and damage to the slab was superficial.
The engineer also considered the quote by its preferred contractor was
accurate with the exception of preliminary costs and the concrete slab.
16. It maintained its offer of $385,000.
17. Costings were obtained from a quantity surveyor in the sum of $465,909 using
the existing slab and $522,046 constructing a new slab.
18. Based on these figures, a final offer in the sum of $465,909 was made to the
Applicant.
19. The FSP relies on the following policy provisions:
“Section A – Business Property Cover
…
Reinstatement or Replacement Cost
We will pay the cost of rebuilding, replacing or repairing any damaged part of your
Business Property to the same condition as when new.
…
Case No: 222628 Determination Page 3 of 8
If the Business property is lost or damaged you must start to rebuild, replace or repair
within 6 months of the loss or damage. If you do not, we will pay your claim in
accordance with the Indemnity value method of settlement unless we have agreed in
writing to extend the period.
We will not pay more than the Sum Insured shown on the Schedule for each item
covered.”
Issues
20. Whether the FSP‟s offer of $465,909 is fair in all the circumstances.
Reasons for Decision
21. This matter involves a dispute in relation to the sum of money to be paid for
reinstatement of a building which was destroyed by fire. The building was
insured for $510,000 and in turn the property element of the claim is for this
amount.
22. The FSP had made a number of offers to settle the claim culminating with a
final offer at Internal Dispute Resolution (IDR) level of $385,000. Further offers
and counter offers have been made since the dispute was brought before FOS.
In each case, the offers and counter offers bring the amount in dispute to below
$280,000. As such, the Panel accepts that the dispute falls within the FOS
jurisdiction.
23. As advised to the parties, FOS has considered it appropriate to expedite the
dispute in accordance with the Operational Guidelines to the FOS Terms of
Reference. This is because of the complex nature of the issues. This dispute
has not been the subject of a FOS recommendation and has proceeded directly
to Determination.
24. There has been an exchange of material between the parties on which each
party relies. Each party therefore has had the opportunity to comment on the
issues.
25. Prior to making a finding in this determination, the Panel has read and
considered all the material presented to FOS.
26. The Applicant is seeking a benefit under the policy and therefore has the
burden of establishing on the balance of probabilities that the benefit claimed
falls within the terms of cover provided by the contract.
27. As there has been an exchange of material between the parties, the Panel
does not intend to repeat the chronology or recite the various reports on which
each party relies in this determination except where considered relevant.
Sum Insured
Case No: 222628 Determination Page 4 of 8
28. According to a copy of the renewal schedule for the period of insurance from 21
April 2008 to 21 April 2009, the Applicant‟s building was insured for $510,000.
29. Following the loss, the FSP arranged for removal of the debris at a cost of
$38,500. The relevant policy terms provide:
“Additional Benefits
Removal of debris
If Business Property has been damaged or destroyed and is covered, we will pay the
reasonable costs incurred in the demolition and/or removal of debris from the Business
Premises.
We will pay up to the amount shown on the Schedule for removal of debris, or if this is
insufficient and you have not exhausted your Sum Insured on the damaged items
requiring demolition and/or removal of debris, we will pay up to the remaining balance
of the Sum Insured.”
30. As the Schedule does not contain a specific sum insured for removal of debris,
the $510,000 sum insured from buildings applies and is reduced by the $38,500
payment. As such, the balance remaining for payment of the claim is limited to
$471,500.
Concrete slab
31. The Applicant notes that the slab was severely damaged by the fire over a
number of areas and not limited to just one section. The localised repairs would
be required over the whole slab leaving a patchwork appearance.
32. The Applicant asserts that the slab had the entire electrical conduit and cabling
laid under the concrete slab. There are numerous “T” insertions in the conduit.
33. The Applicant states that the electrician who installed the wiring/conduit
advised that it would be impossible to lead cables through the existing conduit
with so many right angle bends.
34. Engineer MP commissioned by the FSP, in his report dated 12 May 2009
advised that a meeting was held with the Applicant during which a number of
issues of concern to him were discussed. The engineer‟s report details the
action taken following that meeting. Apart from issues relating to the concrete
slab, the Applicant has not specified any items which continue to be of concern
to him.
35. In relation to the concrete slab, the engineer‟s report refers to an earlier report
of 14 April in which it was noted that replacement of the slab was not required
but may require localised repair. The contractors' quotations obtained by the
FSP did not allow for replacement of the slab.
36. By email dated 18 March 2010 engineer MP discussed the issues in relation to
repairing compared with replacing the slab and noted the following relevant
points:
Case No: 222628 Determination Page 5 of 8
The slab was not damaged to the extent that it required replacement for
structural reasons.
It was practically feasible to repair the localised damage to the surface by
scabbing back the damaged areas to sound concrete, then repairing the
concrete with high strength mortars.
Cuts made in the slab to replace electrical conduits could be reinstated by
dowel-pinning new areas to the existing slab before pouring replacement
concrete over the trenched areas.
This process would result in a patched appearance unless the entire slab
was coated with a hard-wearing topping compound. Slabs with coated
surfaces would require re-coating over time.
For this reason, the repaired slab is not practically the same as the
original slab.
37. In a further report dated 19 August 2010 engineer MP advised:
The electrical conduits would not have been damaged in the fire. New
electrical wiring can be drawn through the existing conduits. If this is not
possible then local removal of slab for installation of new conduits can be
undertaken.
The slab can be reinstated locally with repair mortars and methods
outlined in the repair scrapes and slight spalling of the slab. The estimated
cost for this work was $2,200
38. A quantity surveyor CPR commissioned by the Applicant ,reviewed MP‟s report
and provided the following comments in his report of 4 July 2011
The impact of sawing the concrete slab for laying electrical conduit and
cable would significantly reduce the strength of the slab and create weak
zones in the stiffened raft system.
The stiffness of such a footing system relies o n the slab resisting heave
and pressure induced by reactive clays in the site.
Saw cutting through and trenching below the slab would cut through the
top reinforcing bars of the footings, reducing the negative movement
resistance to less than one half of its original capacity.
39. The quantity surveyor CPR concluded:
“Due to the age of construction and the proposed saw cutting and reinstatement
for in ground services below the existing slab, it is considered that the existing
footing system is not suitable to support the load of the proposed Building works
on the referenced drawings.”
40. CPR provided the following estimates:
Total Budget Estimate (excluding GST and FEE)
Using existing slab $522,046
New slab $599,036
Case No: 222628 Determination Page 6 of 8
41. The quantity surveyor “RLB” commissioned by th e FSP in a report dated 1 June
2011 provided the following estimates:
Replacement Cost assessment
Using existing slab $465,909.00
New slab $543,345.50
42. RLB appraised the report by CPR and in a report dated 2 June 2011
commented:
5% allowance for design contingency appears excessive.
No additional allowance need be made for escalation due to the
competitive state of the market. WTP estimates for render coat/painting,
chain mesh fence, paint finish to blockwork, walls, purlins, epoxy floor
coating, security bars and contractor‟s preliminaries were considered
unreasonable.
Summary
43. The expert opinion is divided as to whether the concrete slab may be repaired
to a condition which would allow it to function without compromising its integrity.
While the opinion in this regard is divided, it is appropriate to consider the issue
in the context of the policy terms.
44. The policy provides cover for reinstatement or replacement conditions. This
means that the policy will respond to a claim for damage by paying the cost of
rebuilding, replacing or repairing any damaged part to the same condition as
when new.
45. After analysis of the evidence the Panel considers the report by CPR is to be
preferred.
46. It is not in dispute the concrete slab sustained damage during the fire.
47. In the Panel‟s opinion, sawing/cutting into the slab with remedial works
involving pinning, covering with replacement concrete which then requires a
coating to overcome the patchwork appearance does not adequately satisfy the
terms of the policy.
48. Moreover, photographs of the interior of the damaged premises show the area
of concrete flooring to be open planned and extensive without interference by
partitioning. Hence any patchwork would be visible so that any coating would
be required to provide a constant appearance which if not maintained would
detract from that appearance.
49. Further the question of structural integrity as noted by CPR is a concern and
should not be easily dismissed.
50. For these reasons, the Panel concludes the costings are to include
replacement of the slab.
Case No: 222628 Determination Page 7 of 8
Quantum
51. The estimates provided by the two quantity surveyors which include a new slab
are in the sum of $522,046 and $599,035. As the building sum insured of
$510,000 has been reduced by the cost of removing the debris to $471,500 the
maximum sum payable for the building damage is limited to $471,500.
52. Estimates including a new slab provided by both quantity surveyors exceed the
remaining sum available. Therefore, it is not necessary to prefer one estimate
over the other.
53. As the cost to reinstate the building including a new slab, exceeds the sum
insured, the Applicant is deemed to be self insured for any costs in excess of
the sum insured. When circumstances such as this arise, a FSP is prevented
from enforcing reinstatement of the damaged property. In these circumstances ,
the Applicant is entitled to payment of the claim by cash settlement.
Costs
54. Clause 9.4 of the FOS Terms of Reference provide:
“ 9.4 Applicant’s costs in pursu ing the matter
FOS may decide that the Financial Services Provider contribute to the legal or
other professional costs or travel costs incurred by the Applicant in the course
of the Dispute. Unless exceptional circumstances apply, FOS will not require
the Financial Services Provider to contribute more than $3,000 to these costs.
55. The Applicant commissioned a quantity surveyor to provide estimates for the
cost of reinstating the building. This was done following complaints by the
Applicant in relation to a number of issues and in particular the concrete slab.
56. The reports provided by the quantity surveyor have contributed to the outcome
of the despite. The Panel is therefore satisfied that pursuant to clause 9.4 of the
Terms of Reference, the Applicant is entitled to be reimbursed for the quantity
surveyor‟s fees incurred by him to further present hi s claim.
Loss of earnings
57. The Terms of Reference provide that FOS may consider disputes between an
FSP and an Applicant arising from a “Small Business Product”. Howe ver the
Terms of Reference further provide that a Small Business Product” does not
include cover in relation to Loss of Profits/Business Interruption.
58. The Applicant‟s policy has been extended to include cover provided under the
Business Interruption section. Any loss of income as a result of the fire damage
falls within the cover provided by this section of the contract.
59. The Panel pursuant to the Terms of Reference is therefore unable to consider
the Applicant‟s request for consideration of lost earnings.
Case No: 222628 Determination Page 8 of 8
Determination
60. For the reasons expressed above the Panel determines the FSP;
a. settle the building damage claim by payment of $471,500 to the Applicant;
b. reimburse the Applicant to sum of $1,871 for quantity surveyor‟s fees
incurred.
s