Text of the determination
Case No: 221318 Determination Page 1 of 11
Case number: 221318
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
1 July 2011
Background
1. The Applicant held a home insurance policy with the Financial Services
Provider (FSP) covering her home and contents. The relevant period of
insurance operated between 12 March 2009 and 12 March 2010. During this
period, her building was insured for a sum of $382,000, the contents for
$103,000 and unspecified valuables for $5,000. A standard excess of $100 was
applicable.
2. On 30 November 2009, the Applicant lodged a claim for cracks to her in-ground
pool. At that time, she was unsure what caused this damage, but believed it
could have been an earthquake which occurred approximately one month prior.
3. The FSP declined the claim as the damage was not caused by an insured
event. Instead, the cause was more likely based on an event excluded by the
policy.
4. The Applicant disagreed with the FSP’s decision. She has also complained
about the delay in assessing the claim and the inappropriate advice given to
her regarding emptying the pool.
Summary of Applicant ’s Position
5. She is extremely dissatisfied with the FSP’s handling of the claim as it took 33
weeks before it made a decision, which was to deny the claim. Her claim was a
simple matter regarding a leak in the pool, which should have been capable of
a quick inspection, report and decision.
6. Delays, lack of interest or lack of expertise resulted in loss and stress on her
part, which are the direct result of the FSP’ s poor claims handling. She has set
out the chronology of the claim to substantiate this.
7. The FSP also instructed her to “stop keeping the pool topped up” and said
“don’t go near the pool in case you injure yourself in attempting to fix it”. These
instructions resulted in turning a simple leak into a disaster. This is
corroborated by the FSP’s engineer who inspected the pool and stated the
following in his report:
Determination
Case No: 221318 Determination Page 2 of 11
“We are advised the Pool is currently empty because the Owner received an
instruction to empty it during last Wet Season.
This is a potentially dangerous situation because ground water could build up
behind the back of the Pool walls during heavy rainfall and exert a lateral force of
the walls. This action could account for part of the Pool wall deformation.
The Pool base appears to have experienced ongoing deterioration necessitating
crack repair sealing. We noted the presence of ground water under the base
when walked on and the possibility exists that this trapped water could expand in
the heat of the day causing an upward pressure on the Base which has the
potential to damage it.”
8. She also questions some of his conclusions because he refers to a fibreglass
pool base when it is actually plastic.
9. As the FSP was clearly not interested in assisting her, she decided to repair the
pool herself. This was done in nine days. It is still functioning almost three
months later and has regained its normal shape despite various experts stating
this was not possible.
10. She notes the manufacturer of the pool (now out of business) had no issue with
it being installed in-ground. Neither did JH from company TT who conducted
the repairs (although she acknowledges JH would not guarantee the repairs).
The only issue that M from TT had in his conversation with her regarding this
pool was if it was not filled because of Northern Territory’s water tables.
11. The excavation, levelling and installation of the pool was conducted by DH, not
TT as alleged by the FSP. Further, there is nothing to indicate this was done
incorrectly or inappropriately, especially given there are many such pools
installed in Darwin.
12. She spoke to a Dr JB of the Geospacial and Earth Monitoring Division.
Although he stated there were no tremors for the period between 1 November
2009 and 26 November 2009, he did amend this to advise that only tremors
above 4.5 were recorded. There were many below this level but keeping
records for all of them is impractical.
Failure to exercise duty of care
13. She maintains that the FSP cannot absolve itself of responsibility for loss or
damage she sustained due to its handling of her claim.
14. She believes a reasonable period of time for the FSP to finalise her claim would
have been 30 days. This is based on three weeks to assess the claim plus nine
days to repair the pool.
15. The FSP’s failure to comply with this reasonable timeframe is a breach of its
duty of care towards her. As such, she is seeking payment for $13,920 that is
based on the following:
Case No: 221318 Determination Page 3 of 11
Cost and labour of maintai ning the level of the pool until receipt of the
FSP’s instructions to cease filling it. This time period was between 26
November 2009 and 28 April 2010 – 104 hours at $22 per hour totalling
$2,288. She has based the hourly rate on her income;
Chlorine for this period - $100;
TT’s cost to repair the bubbles in the pool - $200;
Both her and her neighbour’s labour in removing a sludge of live and dead
cane toads and frogs from the pool to enable the repairs to be carried out
– 6 hours @ $22 per hour totalling $132;
Loss of use of the pool for the period commencing from 20 April 2010 to
date. The nearest pool is approximately 20km away and daily use of this
would entail one hour return travel, two hours supervision plus entry fees
(at approximately $100 per trip). Based on two visits per week - $6,000;
Stress caused by the FSP’s failure to resolve the claim over this extensive
period - $5,000;
Removal of rocks behind collapsed section of the pool - $200.
Summary of FSP’s Position
16. The insured residence is located in a rural subdivision approximately 70km
southwest from the city of Darwin. Although the actual residence did not sustain
any damage, the in-ground pool developed two large bubbles in the centre of
the floor area.
17. According to the Australian Government Geoscience Australia records, an
earthquake of 7.0 magnitude occurred on 24 October 2009 in the Banda Sea.
The epicentre was several hundred kilometres from Darwin and at a depth of
155km, with a felt radius of 1,247km and a damage radius of approximately
99km.
18. It appointed a loss adjuster to assess the damage and attempt to determine the
cause. Although the loss adjuster expressed some reservations about whether
this earthquake caused the damage, it engaged a number of contractors to
provide a quotation. One contractor (PPSF) provided a report (after inspection
6 February 2010) into the damage which stated in part:
“… this is a plastic pool and it can not be repaired.
Why the centre of the floor has distorted and cracked I do not know. The sides of
the pool have not moved in and the strengthening ribs in the floors have not
distorted in any way.
I do not see how this can be earthquake damage when the sides of the pool
have not moved in any way.”
Case No: 221318 Determination Page 4 of 11
19. Although the loss adjuster attempted to obtain another report from two different
pool companies, its efforts were unsuccessful. One repairer refused to do so as
it only deals with fibreglass pools whilst the other continually ignored requests
for a written report.
20. The loss adjuster made contact with a company (TT) who he believed originally
installed the pool. The loss adjuster set out a report dated 14 July 2010 that
contained the following details of his conversation with one of TT’s
representatives:
“… who has advised us that the in ground pool subject to this claim is as
suspected in fact a half tank, originally designed to be used within the
aquaculture industry with the recommendation that the tank be put into service
above ground.
[M] further advised that he concurred with the initial advices which we received
fr om the only other contractor … that once a poly product is installed in ground
there is always an issue in the way it is installed as the tank is not originally
designed for in ground installation and his own company [TT] does not honour
any warranty for t he failure of the tank if installed „in ground‟.
… we discussed informally with [RC] who again reinforced [M] from [TT] advices
that a poly (plastic water tank) is not designed for in ground installation due
mainly to the lateral pressure from corrosive/hostile soils which the plastic poly
material is subjected to and unable to withstand the lateral pressure.”
21. The FSP engaged an engineer to inspect the pool on 2 July 2010. The
engineer did so and provided a report dated 12 July 2010 with the following
relevant comments:
“… These Earthtremors are not of such an intensity that will damage stable
structures and we do not support the assertion that this Pool was damaged by
such an event.
It is difficult to determine what caused the initial cracks in the base of the Pool
but possibilities are:-
Manufacturing defects.
Pool base founded on inappropriate hard sharp aggregate rather than
bedding sand.
Inadequate subsoil drainage to the side with backfilled aggregate. This is the
more likely cause because the wall deformation exists only on the retained
aggregate side. The additional lateral loading from ground water may have
caused the walls to deflect inwards.”
22. Given all of the above, the Applicant has not been able to establish, on the
balance of probabilities that her claim for accidental damage was caused by an
earthquake.
23. In the event the policy does respond to the claim, it submits it is entitled to rely
on the following exclusion clauses:
“We will not pay for any accidental loss, damage, injury or liability for, occurring from or
arising out of:
Case No: 221318 Determination Page 5 of 11
gradual deterioration, wear and tear, lack of maintenance, faulty workmanship,
faulty design or structural defects; …
rust, corrosion, wet or dry rot, mildew, rising damp or seepage …;
cracking, chipping, scratching, fadi ng, shrinkage, settling or expansion …;
vibration, erosion, subsidence, landslip, landslide, mudslide, collapse, shrinkage
or any other earth-movement (other than earthquake)
… We will not pay claims for accidental loss or damage to your home, your content s,
unspecified valuables or specified valuables caused by or arising out of: …
storm or rainwater to retaining walls, paths, driveways, tennis court surfaces,
swimming pool or spa covers. We will also not pay for the cost of refilling or
cleaning mud or de bris from tanks, swimming pools or spas; …
We will not pay claims for accidental loss or damage to your home or your contents,
unspecified valuables or specified valuables in respect of: …
the costs incurred in replacing the apparatus, item or defective part from which
the liquid escapes causing accidental loss or damage caused by the escape of
liquid.”
24. It also submits the escape of liquid did not cause any damage. Instead, all
costs are associated with repairing a crack in the “half tank”, presumably as a
consequence of the inappropriateness of the “half tank” as an in -ground
domestic pool.
Issues
25. Whether the FSP is liable to repair the Applicant’s pool;
26. Whether the FSP breached a duty of care towards her; and if so
27. Whether the Applicant is entitled to the additional expenses sought.
Reasons for Decision
28. I am satisfied that a full exchange of information has taken place between each
party and that each party has had the opportunity to address any issues raised.
The Claim
29. The onus is on the Applicant to establish, on the balance of probabilities, that
she suffered a loss caused by a risk insured against. Once this has been
established, the onus shifts to the FSP to show, on the balance of probabilities,
the claim falls within an exclusion of the contract of insurance.
30. The relevant insuring clause within the policy is under the heading “Section 2A
– Your Home: What Is Covered” and it states the following:
Case No: 221318 Determination Page 6 of 11
“ What we will pay for
We will cover you for accidental loss or damage to your home occurring during the
pe riod of insurance.”
31. The policy has specifically defined “accidental loss or damage” to mean:
“… loss or damage which occurs and is unintended by:
1. you;
2. any person acting with your express or implied consent; or
3. persons lawfully at your home.”
32. There is no dispute that the Applicant’s pool was damaged and it was
unintended by her, anyone acting with her express or implied consent or
persons lawfully at her home. As such, on the face of the facts, her claim falls
within a risk insured against.
33. The FSP has submitted that it is able to establish that earthquake was not the
cause of the loss. As such, it submits the Applicant is unable to establish an
event covered by the policy. However, it appears the FSP is omitting the fact
that her policy covers her f or “accidental loss or damage”, which is a broad
insuring clause. The circumstances are such that it appears the claim falls
within this broad insuring clause.
34. The onus is therefore on the FSP to establish that the dominant cause of the
Applicant’s loss is excluded by the policy. In relying on its policy, it has quoted
different exclusion clauses in its Notice of Response. It has also acknowledged
that the cause of the damage is difficult to determine but it has raised various
possibilities behind the potential cause.
35. In discharging its onus, I do not consider it reasonable or fair in all of the
circumstances for an insurer to rely on numerous provisions in its policy in the
hope that one would apply. Good insurance practice would dictate that it
choose the appropriate exclusion based on the available evidence as opposed
to adopting a “scattergun” approach.
36. Further, as set out above, the FSP has the onus to establish an exclusion
applies on the balance of probabilities.
37. The experts the FSP has relied on are not conclusive as to the basis for the
Applicant’s loss. PPFS’s report provides little probative value to its case as he
says that he cannot determine the basis for the damage beyond stating it was
not earthquake.
38. The engineer has also noted that he canno t determine what caused the initial
cracks but postulated three different possibilities. He concluded that the most
likely cause was:
“Inadequate subsoil drainage to the side with backfilled aggregate.… The
additional lateral loading from ground water may have caused the walls to deflect
inwards.”
Case No: 221318 Determination Page 7 of 11
39. Even in stating this was the most likely cause, the engineer was still equivocal
in his assessment given his use of the word “may” and his description of
causes as “possibilities”.
40. The FSP has also relied on its loss adjuster’s conversation with two others who
have apparently informed him that the type and nature of the structure was
inappropriate for in-ground use. However, I do not accept this evidence
satisfies the FSP’s onus as:
It is second hand; and
It is not corroborated by the engineer or any other firsthand evidence, or
written report.
41. Further, the evidence obtained is subject to doubt as according to the FSP’s
loss adjuster’s report, one of these companies (TT), originally installed the pool.
However, the Applicant has stated this is not the case. I accept the Applicant on
this point because it would seem unreasonable that TT would say this pool
should not have been installed in-ground and then do it anyway for the
Applicant.
42. As such, it would appear the loss adjuster’s recollection of the conversation is
either incomplete or TT’s comments are questionable given this contradiction.
In any event no written report is provided by TT or RC or L&N.
43. Further, it is reasonable to expect that the FSP would have been able to
corroborate these comments by written reports or by an expert. Such
corroboration would not require this expert to attend the scene given
photographs and details of the pool were readily available. The omission to
obtain such firsthand evidence does not satisfy me that this second hand
evidence should be given requisite weight.
44. Accordingly, I find the evidence led by the FSP is equivocal and does not
satisfy me, on the balance of probabilities that the cause of the Applicant’s loss
falls within an exclusion clause.
45. The FSP is therefore required to indemnify the Applicant for this claim.
46. I note the Applicant has stated that she has repaired the bubbles in the pool
and the issues with it have now resolved. However, the FSP’s material
indicates that the pool could not be repaired and instead needed to be
replaced.
47. Although I accept the Applicant maintains there is no current issue with her
pool, I am reluctant to leave the matter there given the FSP’s material and the
fact that TT, whom she engaged to conduct the repairs, refused to guarantee
them.
48. Given this, I find that the FSP do the following:
Reimburse the Applicant the costs she incurred in repairing the pool,
subject to her producing an invoice in support;
Case No: 221318 Determination Page 8 of 11
Engage an appropriate expert to determine if the repairs were adequate;
and
In the event that expert determines the repairs are inadequate, then the
FSP should undertake appropriate repairs/replacement.
Failing to exercise duty of care
49. The Applicant has also sought additional items regarding the FSP’s alleged
breach of its duty of care towards her in the handling of the claim.
50. Having reviewed the matter, I am of the view that the FSP’s claims handling is
a concern given the delay between the claim lodgement and the claim decision.
Although I accept there was some issues experienced in having the necessary
experts review the claim and provide a report, these issues were not due to the
Applicant’s conduct in any way. Further , the FSP’s file notes of 29 June indicate
an acceptance of the “mismanagement of the claim.”
51. I accept the FSP is entitled to investigate the claim. However, I do not accept
that 33 weeks (or 231 days) from claim lodgement to claim denial for this claim
is reasonable. Despite the FSP experiencing a number of issues with obtaini ng
contractors to attend the site, I note it is a national insurance company whose
market base appears to be wide and varied. In purporting to offer this type of
policy to such a wide market, it is expected that it would be in a position to
review and assess claims within a reasonable period of time regardless of the
location.
52. As such, I accept the FSP’s delay in declining the claim was excessive and
unreasonable in the circumstances.
53. I also note the FSP has not refuted the Applicant’s submission that it i nformed
her to stop filling the pool. Based on its own engineer’s comments, the
Applicant’s compliance with these instructions has potentially led to further
damage.
54. The FSP did not appear to accept this as it noted that all the costs associated
with the c laim is consistent with the original damage and not due to “escape of
liquid”. However, its own engineer is of the view the ongoing pool wall
deformation was partly caused by the instruction to empty the pool. As such,
the FSP advised her inappropriately when informing her to empty the pool.
55. Given this, I accept the FSP has not acted efficiently and appropriately in the
handling of the claim.
56. The Applicant has sought additional costs as a result of the FSP’s handling of
the claim. A large proportion of these costs are the cost of her labour or loss of
use of the pool.
Case No: 221318 Determination Page 9 of 11
57. In relation to the loss of use of the pool, I note this is not an actual loss she has
suffered, but rather a perceived one.
58. In relation to the chlorine and removal of rocks, the Applicant has not explained
how this was a direct result of the FSP’s handling of the claim. It would appear
the chlorine is a usual expense associated with the maintenance of the pool.
With respect to the removal of rocks, again the Applicant has not explained how
this was the direct result of the FSP’s actions or inactions. Further, she has
provided no invoices or other evidence that this is an expense she actually
incurred.
59. As for the labour costs, the policy provides that an insured must “2. Prevent
further dama ge” and “that (an insured) must take all reasonable steps to reduce
the accidental loss or damage, or to prevent further accidental loss and
damage.”
60. In my view, it was unreasonable to expect the Applicant to have to keep filling
the pool for so much time. The claim should have been investigated and
resolved more quickly. Accordingly, some part of that labour was properly done
to prevent further damage and some part was labour done by the Applicant
because of the delay on the part of the FSP.
61. The Applicant has sought compensation in the sum of $5,000 for the stress
associated with this claim.
62. I note under clause 9.3(b)(i) of the Service’s Terms of Reference, I am
empowered to award compensation up to $3,000 for non-financial loss but only
where:
“an unusual degree or extent of physical inconvenience, time taken to resolve
the situation or interference with the Applicant‟s expectation of enjoyment or
peace of mind has occurred;”
63. I accept that the FSP’s handling of the claim, the fact the Applicant had to keep
filling the pool for so long and its incorrect instructions regarding the emptying
of the pool constituted an unusual degree and/or extent of physical
inconvenience to the Applicant and that the time taken to resolve the situation
has interfered wi th the Applicant’s expectation of peace of mind.
64. This provision in the Terms of Reference is to be used sparingly as it is meant
to encompass extreme situations. Although I accept the Applicant has suffered
an unusual degree of inconvenience etc, I am not satisfied it is to the extent
that the maximum amount should be awarded.
65. Further, I do not consider an arbitrary figure of $5,000 without any
substantiation is an appropriate basis to award a monetary amount.
66. The FSP was asked to comment on this aspect of the claim and responded by
referring to page 12 of the Policy which under General Exclusions excludes
“ consequential loss of any kind.” The FSP says that n otwithstanding
paragraphs 9.3 a) and b), FOS will not provide compensation for:
Case No: 221318 Determination Page 10 of 11
“ (i) consequential financial loss; or
(ii) non-financial loss,
in a Dispute arising as a result of a claim on a General Insurance Policy
that exp ressly excludes such liability.”
67. I agree that the FSP’s policy excludes consequential loss. However, I am also
of the view that consequential loss is for defined items of loss which can be
quantified and accordingly, some part of what the Applicant claims may be
excluded but such an exclusion clause cannot be extended to also exclude
non-financial loss without expressly excluding suc h liability.
68. Non-financial loss is a considerably broader category than consequential
financial loss and I consider that there would be no justifiable rationale to
extend the exclusion clause to exclude the entire category of non-financial loss
as provided for in the Terms of Reference. If the policy had intended this to
occur, it would have stated consequential loss and specifically non-financial
loss were excluded.
69. On the basis of this analysis, I am of the opinion that the said exclusion clause
does not preclude an award for non financial loss under clause 9.3 of the
Terms of Reference.
70. Given all of the above and exercising my discretion under clause 9.3(b) (i) of
the Terms of Reference, I am of the opinion that compensation for non financial
loss in the amount of $1,000 is appropriate and fair in all of the circumstances.
71. I also confirm that the Applicant’s complaints about the FSP’s handling of her
claim will be referred to the Code Manager to determine whether investigation
under the General Insurance Code of Practice is required.
Determination
72. On the basis of the available information, I determine that the FSP:
Reimburse the Applicant the costs incurred in repairing the pool subject to
her producing an invoice in support;
Engage an appropriate expert to determine if the repairs she completed
were adequate. In the event the repairs are inadequate, then the FSP
should undertake appropriate repairs/replacement pursuant to its
obligations under the policy; and
Pay the Applicant the amount of $1,000 in compe nsation under clause
9.3(b)(1) of the Terms of Reference; and
73. In the event the Applicant accepts this Determination, the FSP should do the
following upon being notified of her acceptance:
Pay the Applicant the amount of $1,000 within seven days;
Case No: 221318 Determination Page 11 of 11
Pay the Applicant’s cos t in repairing the pool within seven days of
receiving an appropriate invoice less excess; and
Engage an expert to inspect the pool within 14 days. This timeframe is
contingent on the Applicant ensuring her pool is available for inspection.