Text of the determination
Case No: 220398 Determination Page 1 of 7
Case number: 220398
General Insurance - Domestic Insurance - Home Building - Service – Alleged
delay in authorising and completing repairs - Service quality – Limits of
liability facility policy
20 May 2011
Background
1. The Applicant held a home insurance policy with the Financial Services
Provider (FSP) for his investment property. That investment property was
tenanted at the time of the events set out below.
2. On 21 April 2009 the Applicant lodged a claim for water damage to the shower
screen and walls of the main bathroom in the property. It was accepted by the
FSP. However, repairs associated with the claim were not completed until
approximately 25 February 2010.
3. The Applicant made claims under the policy in respect to loss of rent, garden
maintenance, a re-letting fee, and electricity. The table below sets out the sums
claimed by the Applicant:
Loss of rent $10,489.42
Garden maintenance $3,080.00
Re - letting fee $544.50
Electricity $188.66
Total $14,302.58 plus interest
4. The FSP acknowledged its liability in part. It agreed to pay the sum of
$6,176.11 for the loss of rent. It disputed its liability to pay for any of the other
items.
5. After review by its internal dispute resolution process (IDR), it did agree to
make an ex-gratia offer in the sum of $1,800.
6. The Applicant rejected these offers. Subsequently, the FSP withdrew the ex-
gratia offer.
7. The matter was then referred to this Service. A Case Manager, having carefully
considered the voluminous material submitted by the parties, the arguments
advanced by the Applicant and the FSP and the policy provisions,
recommended that the FSP was justified in its decision not to offer any further
sum to the Applicant.
Determination
Case No: 220398 Determination Page 2 of 7
8. Whilst the FSP accepted the Recommendation, the Applicant has not. The
Applicant has submitted a further argument as to why the sum offered by the
FSP is unreasonable and has sought a Determination from this Service.
Summary of Applicant ’s Position
9. The Applicant’s principal complaint relates to the time which elapsed from the
date of lodgement of the claim (21 July 2009) until completion of repairs (24
February 2010). He argues that during this time, the continued visits from the
FSP’s representatives led to his tenant being upset and that this was
responsible for her terminating the lease.
10. The Applicant claims for the loss of rental from the time that the tenant vacated
the property (13 November 2009) until he found a new tenant for the property
(24 April 2010). It appears to be agreed that until 25 February 2010, the
property was not tenantable.
11. In addition to the claim for loss of rent, the Applicant claims that he is entitled to
the cost of maintenance of the gardens, a task which the tenant would
otherwise have carried out, and a re-letting fee in order that he could find
another tenant. He also claims for an electricity bill together with interest on all
of the sums which he claims that he has lost. After the Recommendation, he
made a further submission which did not include any new material.
Summary of FSP’s Position
12. The FSP admits that there was minor delay caused by its first builder (JLG) but
that this was an insignificant aspect of the overall delay.
13. It submits that the majority of the delay was caused by the Applicant due to the
following facts:
He disputed the scope of works and the costing with JLG;
He refused to pay the excess for several months;
He refused to authorise the repair works for a considerable period;
After the second builder (BBS) was agreed by both the Applicant and the
FSP, the Applicant still continued to interrupt BBS.
14. The FSP also considers that it has made every attempt to satisfy this claim. It
points out that once the Applicant advised that he had lost faith with JLG, a new
hope was obtained through BBS.
15. It also points out that after a new issue arose as to damaged carpets, it cash
settled the quote with the Applicant.
16. It also claims that although the quote from BBS included some minor items of
work for which it is not liable, it agreed to pay these.
Case No: 220398 Determination Page 3 of 7
17. It did not concede that it has any responsibility for the tenant terminating the
lease having regard to the matters referred to above.
18. It denies that the costs currently being sought by the Applicant fall within the
main insuring clause. It submits that the policy clearly provides that any liability
for lost rent, terminates when the period of untenantability ceases.
19. It therefore denies any liability for rent between 25 February 2010 and 24 April
2010. It also submits that there is no cover under the policy for the cost of
garden maintenance, electricity or re-letting the premises.
20. The sum which it has already offered the Applicant ($6,176.11) was to
compensate the Applicant for the loss of rent during the balance of the lease
(from 13 November 2009 until 12 February 2010 at $400 per week $5,256.88)
and loss of rent after the lease would have expired but until the property
became tenantable on 25 February 2010 at $495 per week - $919.23. It has
offered this sum notwithstanding that there is no proof that the property, when
re-let, was let for $495 per week as opposed to the original rental of $400.
21. Finally, as a show of good faith and in an attempt to resolve the matter
expeditiously, it offered the Applicant an additional 4 weeks rent at the higher
rental value. The Applicant refused this offer and it is now withdrawn.
Issues
22. Whether the Applicant is entitled to a further payment as set out above.
Reasons for Determination
23. I am satisfied that a full exchange of information has taken place between each
party and that each party has had the opportunity to address any issues raised.
24. The onus is on the Applicant to establish, on the balance of probabilities, that
he suffered a loss that the FSP is responsible for.
The FSP’s handling of the matter
25. As can be seen from the arguments above, in this matter, much turns upon the
question as to the adequacy of the FSP’s handling of this matter. On the face of
it, a delay of some 10 months in effecting repairs which were not exceedingly
complex or expensive does seem excessive.
26. When considering this issue, I note t he FSP’s proposition that much of the
delay was caused by the Applicant. It points, in particular, to his refusal to
authorise the first builder (JLG) to go ahead with the work, or to pay the three
excesses of $100 to that builder.
Case No: 220398 Determination Page 4 of 7
27. A problem which confronts the FSP as to this argument however is that,
ultimately, when it did decide to appoint an alternative builder (BBS), the
amount quoted by BBS was some $6,000 higher than the quote from JLG.
Further, the Applicant has pointed out that in fact the quote from BBS was
remarkably similar to the quote which the Applicant had obtained from his own
preferred builder, but which the FSP rejected because it considered that it was
excessive.
28. Therefore, although I am satisfied that the Applicant did delay the
commencement of work, I am satisfied that in doing so, he has been vindicated
by the higher sums charged by BBS which tends to indicate that the original
quote from JLG was inadequate. Alternatively, there may have been a
disagreement between JLG and BBS as to the scope of the works to be carried
out. By accepting the BBS quote, it appears to me that the FSP has, effectively,
admitted that the more detailed scope of works and the higher quotation were
reasonable.
29. In these circumstances, it appears to me that a central tenet of the FSP’s
response in this matter, notably that the delay was caused by the Applicant, is
very hard to justify.
30. There is also evidence which suggests that ultimately the tenant was also
causing delays by refusing to allow various agents of the FSP to attend the
property. I note that the tenant was pregnant and that all of the attendances by
various representatives of the FSP must have been irksome. In the
circumstances, I am not surprised that the tenant decided to vacate the
property after obtaining an order at the relevant tenancy tribunal, that she was
entitled to do so.
31. The Applicant has described the action taken by the tenant at the tenancy
tribunal as leading to a finding that “the te nant could break the lease as the
house was water damaged and unliveable, also should not have to put up with
continual visits by the insurance company and its representatives. ”
Delay on the part of the FSP
32. The FSP has submitted that its overall contribution to the delay was not
excessive. The claim form was submitted to the FSP on 21 April 2009.
Although, on 11 May 2009, a representative of an assessing firm (C&C) was in
contact with the Applicant’s broker indicating that C&C were handling the
matter, it w as necessary for the Applicant’s broker to email the FSP on several
occasions to point out that nothing further had been heard from C&C.
33. Subsequently, the FSP advised the Applicant’s broker that C&C had been
awaiting the results of leak detection tests. On 7 July 2009 C&C finally
arranged for an FSP preferred builder, JLG to quote for the works.
34. Thereafter, there were various discussions, negotiations and correspondence
between the insured broker, the insured, C&C and JLG. By 19 August 2009,
the Applicant’ s broker was advising that the Applicant was refusing to pay the
excess until the works had begun. This led to an effective standoff until 15
Case No: 220398 Determination Page 5 of 7
September 2009. Thereafter, additional water damaged areas were discovered
which led to a further meeting between the Applicant, his broker, and a JLG
representative to submit variations to the previous quotation. By this time, it
appears that the Applicant had lost confidence in JLG and an appointment was
made with another builder (LB).
35. Thereafter for reasons which are not entirely clear, yet another builder (BB)
came onto the scene, offered a quotation and was authorised to carry out the
works.
36. After considering all of these events, I am of the view that there was delay on
the part of the FSP and this should be taken into consideration, together with
the fact that the quote from JLG was (as previously stated) for a sum which was
a great deal less than the sum which the FSP ultimately agreed to pay to BB.
37. The relevant policy provision regarding additional benefits states:
“We will only pay these costs when they relate to loss or damage from a listed event …
… If your building is so damaged that it cannot be lived in by tenants, we will pay
up to 20% of the sum insured for your building, for: loss of rent or rentable value
if the home is tenanted or is between tenants at the time the loss or damage
occurred.
… Under this additional benefit, we will not pay for:
(a) …
(b) Any rent lost outside the period of untenantability …”
38. As is evident, on the face of it, the policy excludes any rent lost whilst the home
is untenanted. However as the property was untenantable until 25 February
2010, the FSP has agreed to pay the Applicant’s rent until that date.
39. The Applicant, of course, seeks a further two months rental to cover him for the
period until the property was in fact tenanted. As to this, it must be said that the
origi nal tenant’s lease expired on 13 February 2010 in any event. Furthermore,
if, as is implicit in the Applicant’s claim, but for all of the events set out above,
the tenant may have remained in the property on a continuation of the lease,
there is no solid evidence that she would have agreed to pay the $495 per
week as opposed to $400 per week, the existing rent for which the Applicant
was able to re-let the property from 24 April 2010.
40. I have given the matter the most careful consideration. On balance, I consider
that if the FSP and its agents had attended to the matter speedily, it is likely
that the repairs would have been completed well before the expiry of the
tenancy which was due to occur on 12 February 2010.
Other expenses claimed by the Applicant
41. The other expenses for which the Applicant seeks recompense are, apparently,
not specifically covered by any of the insuring clauses within the policy. The
property has significant external grounds and the Applicant claims that he
incurred fees of some $3,080 for garden maintenance. This does seem a very
large sum.
Case No: 220398 Determination Page 6 of 7
42. I consider in any event that this is not a sum for which a specific allowance may
be made under the terms of the policy; however, it is a matter to be taken into
consideration when considering other aspects of this Determination.
43. As to the re-letting fee, and the claim for electricity, I am of the view that neither
are covered under the terms of the policy, and I do not make any allowance for
them.
Financial Ombudsman Service - Terms of Reference
I consider that clause 9 of the Terms of Reference (TOR) is relevant to this matter.
Clause 9 is in the following terms:
“9 Remedies
9.1 Types of remedies
Subject to paragraphs 9.2 to 9.8, FOS may decide that the Financial Services Provider
undertake a course of action to resolve the Dispute including:
a) the payment of a sum of money;
b) the forgiveness or variation of a debt;
c) the release of security for debt;
d) the repayment, waiver or variation of a fee or other amount paid to or owing to
the Financial Services Provider or to its representative or agent including the
variation in the applicable interest rate on a loan;
e) the reinstatement or rectification of a contract;
f) the variation of the terms of a Credit Contract in cases of financial hardship;
g) the meeting of a claim under an insurance policy by, for example, repairing,
reinstating or replacing items of property; and
h) in the case of a Dispute involving a privacy issue with an individual - that the
Financial Services Provider should not repeat conduct on the basis that it
constitutes an interference with the privacy of an individual or that the Financial
Services Provider should correct, add to or delete information pertaining to the
Applicant.
9.2 Compensation for direct financial loss or damage
Subject to paragraph 9.7, FOS may decide that the Financial Services Provider
compensate the Applicant for direct financial loss or damage.
9.3 Other compensation
a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial
Services Provider compensate the Applicant for consequential financial loss or
damage up to a maximum amount of $3,000 per claim made in the Dispute.
b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial
Services Provider compensate the Applicant for non-financial loss but only
where:
(i) an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant’s e xpectation of
enjoyment or peace of mind has occurred; or
(ii) in the case of a Dispute pertaining to an individual’s privacy rights - injury
has occurred to the Applicant’s feelings or humiliation has been suffered
by the Applicant.
The maximum amount of compensation for non-financial loss will be $3,000
Case No: 220398 Determination Page 7 of 7
per claim made in the Dispute.
c) Notwithstanding paragraphs 9.3 a) and b), FOS will not provide compensation
for:
(i) consequential financial loss; or
(ii) non-financial loss,
In a Dispute arising as a result of a claim on a General Insurance Policy that
expressly excludes such liability.
d) The cap on liability in paragraph 9.3 a) does not in any way restrict FOS’s
ability to make an interest award under paragraph 9.5.
Conclusion
44. I consider that when the FSP offered the Applicant what was effectively an
additional 4 weeks rent which covered the period from 24 February 2010 to 24
March 2010; it was acting in a very appropriate manner. The sum was,
perhaps, offered in at least partial recognition of the substance to the
Applic ant’s claim about the FSP’s handling of the matter. Having regard to the
fact that the Applicant has, apparently, had the benefit of advice from a broker
throughout the handling of this matter, I am surprised that the ex-gratia offer
was rejected.
45. I do consider that pursuant to clause 9 of the TOR, it is reasonable that the FSP
make some payment to the Applicant in respect to this matter having regard to
my conclusion as to delay on the part of the FSP. I take into consideration the
fact that the Applicant has apparently lost the value of the garden maintenance
services which were being provided by the tenant as an obligation under her
lease. Were it not for the fact that the Applicant has rejected the ex-gratia offer
for the additional rental, I would also have made some allowance under the
heading of loss of rental.
Determination
46. I determine that the FSP’s offer to finalise the Applicant’s claim for loss of
rental, in the sum of $6,176.11 is fair and reasonable.
47. Pursuant to clause 9.3(a), I determine that the FSP should pay to the Applicant
the sum of $1,500 for consequential financial losses which he has sustained,
overwhelmingly as the result of the delays in resolution of the matter by the
FSP and its agents.