Text of the determination
Case No: 220360 Determination Page 1 of 11
Case Number: 220360
General Insurance – Business Insurance Policy – Holiday Park Buildings –
Storm and rainwater damage – Extent of damage - Quantum dispute
26 June 2011
Background
1. The Applicant insured his Holiday Park buildings under a Business Insurance
Policy against loss or damage caused by defined events for a sum insured of
$891,500 with a $250 policy excess. The policy also provided Accidental
Damage cover in the amount of $100,000.
2. On or about 25 November 2009, the locality of the insured premises suffered
a severe wind and thunderstorm storm. The insured property suffered damage
to:
Residence, reception area and office;
Radio room;
Cabins;
House roof;
Roof mounted evaporative air conditioner;
Games room;
Main toilet block; and
Disused toilet block.
3. The Financial Services Provider (FSP) accepted that the Applicant ‟s property
had been damaged by the defined event „storm‟. In a report dated 11
December 2009, a loss assessor stated that some of the damage to the
Applicant ‟s property appeared to not have been caused by the storm.
4. Following this report, the FSP appointed a consulting engineer, „S‟, to report
upon the cause of damage to brickwork associated with the office,
observatory/radio room and caravan park toilet blocks. The engineer reported
that some of the damage to the buildings was associated with seasonal
ground movement although some of the cracks had worsened since the
storm.
5. Based upon the engineer‟s report, the FSP‟s loss assessor prepared a Scope
of Works (SOW) limiting the repairs to the non-structural aspects except for
the roof of the two storey radio room.
6. On 16 March 2010, builder „B‟ submitted a quote for the cost of repairs based
upon the SOW for the amount of $51,277.82. This was later increased to
Determination
Case No: 220360 Determination Page 2 of 11
$63,215.70. The Applicant has disputed the engineer‟s opinion that some of
the damage had not resulted from the storm.
7. The Applicant engaged the services of builder „D‟ to provide a quote for
repairs. On the 28 July 2010, the builder submitted an estimate for the amount
of $106,260. However, this estimate applied to only the Applicant ‟s residence,
office and reception area.
8. In response to this quote, the FSP requested engineer S to review the two
builders‟ quotes. The engineer considered builder D‟s quote was excessive
and that builder B‟s quote was more realistic.
9. In an email dated 27 August 2010 to the FSP, the Applicant submitted a cash
settlement claim for the amount of $175,000 „...in full settlement of your
obligatio ns in regard to rectification works.‟
10. On 15 September 2010, the FSP offered to cash settle the claim for
$63,215.70 less GST, that is, $57,468.83 which was rejected by the Applicant.
11. The terms of settlement of the claim reached a stalemate.
Summary of Applicant ’s Position
12. The scope of works (SOW) prepared by the FSP‟s loss assessor does not
properly address rectification of damage caused by the storm. The SOW does
not include the following matters:
Electrical works – replacing two switchboards;
Residence roof – roof and wall has parted;
The FSP‟s engineer‟s SOW recommendations would not be viable to
rectify the damage. It would be structurally unsound and unsafe if
rectification was limited to the nature of works envisaged by the SOW;
Accommodation and temporary offices – time allowance too short;
Damage to some of the cabins has been ignored.
13. In view of the FSP‟s refusal to contemplate any changes to the SOW, he
engaged the services of consulting engineer, „H‟ , to prepare a report on the
damage to the insured property and a SOW for the required repairs.
14. When reporting on the damage to the amenities buildings, engineer H stated:
“ Amenities. The amenities buildings show obvious signs of wind damage
superimposed on pre-existing foundation movement. Some of the wall
cracking is obvious foundation movement (and these would be typically
horizontal and vertical cracking in the wing walls and step cracking in the side
walls adjacent to the endwalls and arches at the endwalls), but the majority of
the cracking on the side walls is typical of high uplift forces causing rotations
in the brick piers and tension failure of a plug of brickwork.‟
Residence/Office. The dwelling/office has similarly experienced high uplift
forces which have resulted in the complete loss of the roof of the radio roo,
Case No: 220360 Determination Page 3 of 11
fracturing of the bedding to the roof tiles, springing of flashings and general
loss of weather tightness.”
15. The engineer prepared a SOW for:
East amenities building;
West amenities building;
Residence/office;
Cabin 3;
Cabin 16;
Cabin 21; and
Cabin 22.
16. The disparity between the two builders‟ quotes is because builder B has
quoted in accordance with the loss assessor‟s SOW whereas builder D has
quoted to only reinstate the damage.
17. He has not been able to find a local builder who will quote on the loss
assessor‟s SOW for the toilets rectification. In view of the builders who have
inspected the damage it was considered that repairs affected in accordance
with the loss assessor‟s SOW would lack structural integrity.
18. The FSP has made issue that he was contemplating replacing the existing
storm damaged structure with something more elaborate. He is contemplating
replacing some storm damaged buildings but this should not be allowed as an
excuse for the FSP to understate the nature of rectification work required.
19. There are no costs included in his builder D‟s quote which relate to any
proposed redevelopment beyond reinstatement of storm damage. In fact, in
August 2010, he suggested that a builder be engaged by the FSP to complete
rectification works. (This was done prior to him being aware that the FSP
could avoid this option).
20. The FSP has stated that a true replacement cost for the radio room is not
measureable until repairs are commenced or completed. However, it is not
clear why this compels acceptance of builder B‟s quote over that of builder D.
Further, safety fencing etc and temporary accommodation is in builder D‟s
opinion required as the nature of the work is more extensive that that
envisaged by the loss assessor‟s SOW.
21. He has also incurred clean-up costs for the amount of $9,761 which the FSP
contends comprises a separate claim.
Summary of FSP’s Position
22. It relies on the engineer S‟s report which is quite detailed in its explanation of
the resultant damage by storm and that of seasonal earth movement.
23. When the Applicant disputed the settlement offer of $57,468.82 made on 21
September 2010, it was suggested that to obtain agreement between the
Case No: 220360 Determination Page 4 of 11
parties on the SOW, a meeting take place between the loss assessor,
Applicant, builder and engineer commissioned by the FSP.
24. A meeting is yet to take place. The FSP relies on the following policy/contract
provisions:
„ 1 – BUSINESS INSURANCE
Section A – Business Property Cover
What you are covered for
We will cover you for loss or damage caused, during the Period of Cover, to your
Business Property by the events listed under Defined Events Cover and Accidental
Damage Cover.
...
Defined Events Cover
We cover you for loss or damage at the Business premises caused by the following
Defined Events:
...
7. storm and rainwater, ...
...
Accidental Damage Cover
We will cover you for Accidental Damage to Your Business Property at the Business
premises other than the events or items listed under What you are not covered for
under Accidental Damage Cover.
The maximum amount we will pay for Accidental Damage Cover for any occurrence
is the accidental damage Sum Insured shown on the Schedule.
What you are not covered for under Accidental Damage Cover
We will not pay for claims under Accidental Damage Cover for loss or damage:
1. caused by any Defined Events covered in Defined Events Cover;
2. ...
3. caused by events or to the items listed under General Policy Exclusions on
page 48;
4. ...
5. ...
6. caused by storm and rainwater, other than damage to fences made entirely
from brick , stone, concrete and/or iron;‟
Issues
25. Whether the FSP has indemnified the Applicant under the terms and
conditions of the policy of insurance.
Case No: 220360 Determination Page 5 of 11
Reasons for Decision
26. There has been an exchange of material which the parties rely on. Each party
has had access to the material on which the other party bases its case. As a
consequence, it is not necessary to go into all of this material in any great
detail.
27. The storm damage to the Applicant ‟s property occurred on or about the 25
November 2009. However, the property remains in a state of disrepair which
has, and will continue to, have a detrimental effect on the Applicant ‟s
business.
28. Main chronology of events is as follows:
25 November 2009 – storm event;
26 November 2009 – claim lodged;
26 November 2009 – lo ss assessor‟s first attendance;
11 December 2009 – loss assessor‟s second attendance – confirmed it
was arranging for an engineer‟s report;
21 December 2009 – Engineer S inspected property and completed his
report on or about the 3 January 2010;
11 January 2010 – loss assessor‟s third report – confirmed engineer S
due to submit his report;
25 January 2010 – loss assessor‟s fourth report – confirmed engineer‟s
report had been received; loss assessor submitted a SOW;
19 February 2010 – loss assessor‟s fifth report - reported it was awaiting
builders‟ quotations;
4 March 2010 – loss assessor‟s sixth report - Upon receipt of tenders for
repair will seek further instructions.
26 March 2010 – loss assessor‟s seventh report – still waiting for its
builder, „B‟, an d Applicant ‟s builder to submit quotes;
22 April 2010 – loss assessor‟s eighth report – had received builder B‟s
quote dated 16 March 2010 – Applicant unable to obtain quote –
reported Applicant considering substantial renovation of the site;
24 May 2010 – loss assessor‟s ninth report – we now await a second
builder‟s estimate before proceeding any further with claim;
13 August 2010 – loss assessor receives additional quote from builder B
for amendment to its first quote;
Case No: 220360 Determination Page 6 of 11
26 August 2010 – loss assessor‟s te nth report – had obtained
Applicant ‟s builder „D‟s‟ report dated 28 July 2010 – assessor considered
D‟s quote contained additional works that do not form part of the claim;
27 August 2010 – Applicant sends email to FSP expressing frustration at
delays in processing his claim – submits settlement claim for the amount
of $175,000; [P139]
30 August 2010 – FSP responds to Applicant ‟s email – informs him that
it will instruct its engineer S to review the q uotes from builder B and
builder D for repairs to the Radio Room;
13 September 2010 – engineer S informs FSP that after reviewing
photographs and previous reports it considers builder D‟s quote to be
excessive;
21 September 2010 – loss assessor‟s eleventh report – no comment as
to claim;
23 September 2010 – FSP confirms that its current cash settlement offer
is $57,468.82 – FSP also states that if Applicant does not agree with the
offer, a meeting between Applicant, loss assessor, builder B, and its
engineer S be convened in an attempt to expedite the claim;
1 November 2010 – loss assessor‟s twelfth report – loss assessor
advised FSP that subsequent to arranging a meeting between the
parties, the Applicant ‟s engineer „H‟ had contacted them; loss assessor
advised FSP it would be beneficial for the engineer to report on behalf of
the Applicant;
22 December 2010 – report and scope of works submitted by engineer
H.
29. It appears that the FSP has done very little, if anything, to progress the
Applicant ‟s claim to a satisfactory conclusion.
30. The Applicant has informed the Financial Ombudsman Service that the
damage to his property has worsened considerably over the last 20 months
due to the rainwater escaping under building foundations and the action of
strong wind on the damaged structures.
31. In view of the ongoing difficulties in attaining settlement of this claim, the
Panel determined that an independent structural engineer (G) be appointed to
examine and report on the damage to the Applicant ‟s property.
Independent Engineer’s Report
32. In its report dated 14 February 2012 G records it carried out an on-site
inspection of the damage and reviewed the respective engineering reports
submitted by the Applicant and the FSP prior to making its report.
Case No: 220360 Determination Page 7 of 11
33. The report addresses three main areas of dispute resultant from the identified
damage, namely the damage to the main office/residential building and the
damage to the eastern ablution block and the western ablutions block.
The Main Office/residential Building
34. G reported that, at the time of inspection, the remaining damage was mainly
superficial but there “was evidence of damage caused by significant wind
loads being generated into the structure and ceiling by the wind loads on the
now demolished radio room elevated above the main ceiling and roof line.”
35. G also reports on damage from “ water ingress and also lateral movement of
the ceiling structure along with dislodgment of brickwork locally on the
southern wall.”
36. In addition G reported on damage to the eastern veranda where paving had
“pulled away as have the arches that are attached to the front of the building,
but it found that this damage (unlike the foregoing damage described in 34
and 35 above) was not storm related but rather the result of foundation
movement.
37. The Panel accep ts G‟s report as to the causes of the identified damage
sustained to the office/residential building.
38. Accordingly it concludes that the FSP is liable for the cost of the repair of
damage caused as identified in 34 and 35 above (which does not include any
foundation work) but not any of the damage described in 36.
The Ablution Blocks
39. The report goes on to describe the damage identified to the Eastern and
Western ablution blocks and concludes “30% of the damage to the two
ablution blocks has been caused by wind damage (storm event) and the other
70% has been caused by foundation movement…”
40. Accordingly, the Panel determines the FSP is liable for 30% of the cost of the
damage identified to the two ablution blocks.
Cost of Repairs
41. The Panel accepts the Scope of Works prepared by the assessor and upon
which the quotes were based quoted on fairly reflects the work required under
the policy to rectify the storm damage as described by engineer G.
The Panel has before it two quotes. It also has a table showing a
combined estimate. The combined estimate is the work of the
assessor. It contains items from each of the quotes where the higher
quote has been chosen. It also includes items identified after the
preparation of the original quote and therefore not included as part of
the original quote.
Case No: 220360 Determination Page 8 of 11
42. Having carefully considered all of the available evidence the Panel concludes
the composite estimate is sufficiently adequate for it to use as a basis for its
decision (rather than again calling for quotes having regard to the extended
time frame of the claim) but in doing so it will admit a margin of 22.5% to the
composite estimate to allow for the engineer‟s opinion "true replacement cost
is not measurable until repairs are commenced or completed." and the
arbitrary nature of the decision.
Settlement
43. The combined estimate totals $57,468.82 which after applying the allowed
22.5% margin becomes $70,399.30
44. Included in the estimate are the quotes for the ablutions blocks quoted at
$8,050.90 and $6,864 respectively making a total of $14,914.90 which after
including the 22.5% margin becomes $18,270.75.
45. As the FSP is answerable for only 30% of the ablution block damage its
portion is confined to $5,481.22 thus $12,789.53 being the 70% portion for
which it is not liable must be removed from the $70,399,30 bringing the
composite estimate total to $57,609.75
46. The Panel determines the FSP is liable in the amount of $57,609.75 in full
settlement of the cost of repairs for damage covered under the policy to the
residence/office and the two ablutions blocks.
Other Items
47. The Applicant has drawn attention to a number of additional items which he
states remain outstanding. The item are:
Contents. Curtains, carpets, and bedding for which the Applicant
claims replacement.
48. In its report of 26/11/2009 the assessor reports the carpet cleaner as “being in
attendance”. It also reported, on 25/1/2010, “the insured is still arranging for
the assessment of contents items including dry cleaning and laundering of
materials.
49. In the event these matters are still outstanding the Applicant is to make a
formal claim with substantiation for the FSP‟s consideration.
50. In the event the matter is not resolved either party may approach the Service
for a further determination.
Electrical appliances
51. The Panel notes the assessors reported on 25/1/2010 “Electrical items have
been checked and no damage was found; we await the invoice and report
from our technicians (name of contractors).” Contractors invoice authorised
4/3/2010.
Case No: 220360 Determination Page 9 of 11
52. On the available evidence the Panel determines the FSP is not liable for
electrical appliances.
Cabin cladding
53. The Applicant refers to damage to park cabin cladding and roofing. The
assessor reported there was damage to the flashing of one cabin. It was
reported “the flashings had not been repla ced, however, temporarily repaired
by their son who is a caravan mechanic. [Cabin 3]
54. In its report of 25 January 2010, it reported “water damage was found to a
ceiling of a second cabin.” [Cabin 16.]
55. The cost of damage to cabin 16 was included in the combined estimate
costed at $800 (repaint ceilings).
56. The Panel determines the FSP remains liable for the cost of replacing the
temporarily repaired flashing on Cabin 3. Further, it determines the FSP is to
assess and determine its liability for the dented wall sheets, capping and air
conditioners on cabins 21 and 23.
57. In the event the matter is not resolved either party may approach the Service
for further determination.
Removal of debris
58. The Applicant claims “cleanup costs” in the amount of $9,761.
59. The Panel is not aware of the nature of the cleanup costs claimed but it notes
the Applicant has stated the FSP advised the matter comprises a separate
claim.
60. If the costs are the subject of a separate claim the FSP is to formally advise
the Applicant why that is the case and the Applicant will need to claim
accordingly.
61. If the claim is related to matters the subject of this claim the FSP must make a
determination of its liability and within 14 days of receipt of this Determination
advise the Applicant of its decision.
62. In the event the matter remains in dispute either party may approach the
Service for further determination.
Loss assessor and engineers cost
FOS Terms of Reference
“ 9.4 Applicant ’s costs in pursuing the matter
FOS may decide that the Financial Services Provider contribute to the legal or
other professional costs or travel costs incurred by the Applicant in the course
of the Dispute. Unless exceptional circumstances apply, FOS will not require
the Financial Services Provider to contribute more than $3,000 to these
costs.”
Case No: 220360 Determination Page 10 of 11
63. The Applicant repeatedly disputed the scope of works prepared by the
Assessor and the opinion of the FSP‟s engineer without success. In the
circumstance the Panel considers it was necessary for the Applicant to
engage an engineer to provide a detailed analysis of the damage and/or the
specific extent of works required for rectification.
64. In addition they engaged a loss assessor “to assist with the preparation and
settlement of their insurance claim”. However the FSP denied th e appointment
was necessary arguing the drawn out settlement was due to the Applicant ‟s
delay in providing a builder‟s quote and there were no technical matters
requiring attention. The Panel notes the FSP‟s arguments and also that the
appointment was made after the matter had been submitted to the Service for
review.
65. The Panel determines the FSP is required to reimburse the Applicant for his
engineer‟s fee subject to proof of payment by the Applicant and subject to a
limit of $3,000. The Panel determines the FSF is not liable for the loss
assessor‟s fee.
Temporary repairs to office/residence immediately following the storm $2,500.
66. The Panel is surprised that this matter appears not to have been put to the
FSP before the Applicant raised it in his letter to the Service dated 26 March
2012.
67. However, having regard to the nature of the damage sustained to the
residence/office, the Panel considers the sum claimed to be acceptable and
directs payment by the FSP unless payment for tempo rary repairs has been
otherwise made.
Hire of container to provide temporary storage facility.
68. The assessor reported “Shipping container has been hired to relocate office
contents whilst more permanent repairs are completed.”
69. The Panel determines the FSP is liable for the costs of hire of the shipping
container.
Costs in pursuing the claim $3,750
70. The Applicant is claiming for various faxes, phone calls, photocopies and
other administrate costs in pursuing his claim through the Service.
71. There is no policy provision under which the Applicant can claim such costs
and the Service does not have the power to award them.
72. The Panel determines the FSP is not liable to reimburse the Applicant for
such expenses.
Case No: 220360 Determination Page 11 of 11
Determination
73. The FSP is liable for interest at the statutory rate on the sum of $57,609.75
from 15 September 2010 until settlement is affected.