The applicants claimed $1,440.15 in veterinary costs for their dog's vomiting and diarrhoea, which occurred on the last day of the 30 day waiting period. The FSP denied the claim and AFCA agreed, reversing the case manager's recommendation.

Under the policy's midnight commencement definition the policy started at 24:00 on 8 February 2010, so the waiting period ran to 10 March 2010 and the contra proferentem argument did not succeed because the wording was not ambiguous.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 219856 Determination Page 1 of 4 Case number: 219856 General Insurance - Domestic Insurance - FSP Decision - Denial of Claim – Exclusion – Pre-existing Condition – Waiting Period – Policy Interpretation – Midnight – Contra Proferentem 27 June 2011 Background 1. This dispute arises under a pet insurance policy taken out by the Applicants with the Financial Services Provider (FSP). The policy in question covered the Applicants’ dog. The point at issue is the actual commencement date of the policy. 2. The Certificate of Insurance states in its relevant part: “This policy’s Start Date 8 February 2010 This policy’s End Date 8 February 2011”. 3. The Applicants lodged a claim with the FSP for a sum of $1,440.15 veterinarian expenses in respect of the treatment of the dog. The treatment was administered on 10 March 2010 for vomiting and diarrhoea. 4. The FSP denied the claim on the ground that the dog’s illness occurred during the 30 day “waiting period” and that the claim fell within the policy exclusion. 5. In denying the claim, the FSP stated in a letter written following Internal Dispute Resolution: “According to you r Certificate of Insurance, your policy started at midnight (24h00) on the 8 February 2010, thus the first day of the Waiting Period was the 9 February 2010. Your 30 day waiting period ended on 10 March 2010 (inclusive) and therefore the first eligible day for claiming for an illness was 11 March 2010.” 6. The Applicants referred the dispute to the Service and on 4 March 2011, the Case Manager made a Recommendation that the FSP indemnify the Applicants in the sum of $1,440 less any applicable excess. 7. The FSP rejected the Recommendation and in accordance with the Terms of Reference of the Service, the matter has been referred to me for determination. Determination Case No: 219856 Determination Page 2 of 4 Summary of Applicants ’ Position 8. The Applicants state that the policy commenced on 8 February 2010 and the 30 day waiting period ended on 9 March 2010 that is one day prior to the illness of the dog and the subsequent expenses incurred thereby. 9. The Applicants asserted that the use of the 24 hour clock notation i.e. 24:00 is ambiguous and incorrect because 24:00 is not denoted on any clock. The Applicants argue that if the FSP intended the commencement to be the end of 8 February 2010 then it should have stated 9 February 2010 as the commencement date. 10. The Applicants are also concerned that they were advised by the FSP’s employees that the claim had been approved for payment. Summary of FSP’s Position 11. The policy was incepted on the internet and the application was finalised at 12:23:51 of 8 February 2010 i.e. 12:23:51pm. 12. The FSP relies upon a notice on the internet to the Applicants that she would have received stating “Your policy will commence at midnight on the policy commencement date.” 13. Thus, the FSP contends the policy commenced at 24:00 on 8 February 2010 and the 30 day waiting period for illness ended at 24:00 on 10 March 2010. The FSP relies upon the policy provisions in the Product Disclosure Statement (PDS): “ Section 1 – Definitions … Commencement Date means midnight (24h00) on the date when Cover first starts as shown on your Certificate of Insurance. … Pre-existing Condition means: … … any illness or symptoms or signs of that illness occurring or existing in any form during the Waiting Period. … Waiting Period means a period starting from the Commencement Date of the first Policy Period during which an Illness Condition that occurs or shows clinical signs will be excluded from Cover unless otherwise stated on your Certificate of Insurance. The Waiting Period is 30 days except…” 14. The FSP denies that the Applicant-wife was advised that the claim had been approved. Its Client Services Officer only indicated that the claim will be processed. Case No: 219856 Determination Page 3 of 4 Issue 15. Whether the FSP is entitled to deny the claim. Reasons for Decision 16. As noted by the Case Manager, the nub of the dispute concerns the interpretation of the policy provision found on page 9 of the PDS: “ Commencement Date means midnight (24h00) on the date when Cover first starts as shown on your Certificate of Insurance ” . 17. Page 9 of the PDS when read in conjunction with the Certificate of Insurance would read: “Commencement Date means midnight (24h00) of 8 February 2010” . 18. The Case Manger after considering and analysing the matter formed the view that the subject policy was ambiguous and in accordance with the principle of “contra proferentem”, it was to be construed favourably to the Applicants. The Case Manager correctly referred to publications on the internet in the website Wikipedia. These publications tend to emphasise the exquisite nature of the dispute concerning the issue of determining the commencement point of any day. 19. After carefully considering the matter, I have formed a different view. As noted above, the policy clearly states that the first commencement date means midnight (24:00) on the date when cover first starts as shown on the certificate of insurance. In this case, the first commencement date is clearly shown as 8 February 2010. Thus, the policy clearly states that it commences at 24:00 on 8 February 2010. It logically follows that the policy which is a period for one year then expires at the last moment in time namely 23:59 on 8 February 2011. 20. I note the Applicants have cited the website Greenwich Mean Time that states: “Every day starts precisely at midnig ht and A.M. starts immediately after that point in time e.g. 00:00:01 A.M…. To avoid confusion timetables, when scheduling around midnight, prefer to use either 23:59 or 00:01 to avoid confusion as to which day is being referred to.” 21. In my view that publication is correct and it confirms that every day commences at midnight and starts at the first moment in time after midnight. 22. I note that if the Applicants ’ interpretation of the policy is correct, then notwithstanding that the policy was incepted at 12:23:51 of 8 February 2010, the Applicants would have been insured for that period between 00:00:01 of 8 February 2010 notwithstanding that the policy was only incepted at12:23:51 after that day. That is to say, the Applicants would argue that they would be entitled to the benefit of half a day (approximately) insurance for which they had not been charged a premium. All insurance is effected prospectively not retrospectively. It also follows logically that between 12:23:51 of 8 February at Case No: 219856 Determination Page 4 of 4 midnight, the policy would not be operational that is to say it came into operation at midnight on 8 February 2010. 23. There is some merit in the Applicants’ argument contain ed in their most recent submission dated 22 April 2011 that the use of the 24:00 time period can be confusing. It seems to me that where a policy is being commenced on the internet and the exact time is noted for the inception of the policy, that that should be the date rather than the notional date chosen by the FSP. However, I do not think that criticism wo uld justify a finding that the FSP’s documentation in respect of the inception of the policy is ambiguous or misleading. 24. It is most unfortunate that the animal that was the subject of the insurance became ill on the last day of the 30 day period but that is the fact and in respect of the important issue of timeliness, the clear and expressed provisions of the policy must apply. Determination 25. I determine that the FSP is entitled to deny indemnity to the Applicants ’ claim for the expenses incurred.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.