Home / Financial Firm (Unknown - Insurer) / Determination 219805

Determination 219805

Construction policy claims denied as fraudulent and under cessation of work exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2011-11-10
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$24,897
Non-financial loss—
Amount claimed$32,397
SourceAFCA PDF

Summary

The applicants claimed for stolen timber, broken glass and a missing pallet of roofing on a construction project after their builder went into liquidation. The FSP denied the claims and alleged the applicants were not truthful and frank. AFCA ordered payment of $24,896.88 and directed the FSP to expunge fraud references from its records.

A fraud or non-disclosure allegation requires clear and cogent proof, and the FSP's evidence relied on an unreliable police report and inferences, while its own open admission on the roofing claim barred reliance on the cessation of work exclusion under section 14 of the Insurance Contracts Act.

Issues

Subjects and remedies

home or building damagetheft or burglarycorrect recordspay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 219805 Determination Page 1 of 17 Case number: 219805 General Insurance - Domestic Insurance - Home Building – FSP Decision – Denial of claim-Fraudulent claim 3 November 2011 Background 1. On 11 March 2008, the Applicants entered into a domestic building contract with FC to construct a home on their property. Shortly after this, FC took possession of the property. 2. Construction ceased on or around November 2008 and FC was subsequently placed into liquidation on 29 May 2009. During this time, the Applicants arranged a construction insurance policy with the Financial Services Provider (FSP) through a broker. The date of inception of the policy was 6 January 2009. 3. On or around 5 March 2010, the Applicants lodged claims under the policy for:  Broken windows (the “Glass Claim”);  Missing timber (the “Timber Claim”); and  Missing pallet of roofing materials (the “Ritek Claim”). 4. The first two items were lodged as the one claim and the Ritek Claim was lodged as a second claim. In relation to the Glass Claim and Timber Claim, the Applicants identified the loss to have occurred between 15 and 20 January 2009. In relation to the Ritek Claim, the Applicants identified the loss to have occurred between 14 September and 17 October 2009. 5. The FSP, in its correspondence to the Applicants dated 24 March 2011, attempted to resolve the claims by paying $10,983.58 which was based on the following:  On a without admission basis, it was prepared to pay the Timber Claim on a value of $6,060. With the $2,500 deductible, this results in a net payout of $3,560;  The FSP assessed the Glass Claim as less than the $2,500 deductible and accordingly, it is not liable to pay any sum; and  It was prepared to accept the Ritek Claim in the sum of $9,923.58 less the applicable excess of $2,500, resulting in a payment of $7,423.58. Determination Case No: 219805 Determination Page 2 of 17 6. The Applicants responded in a letter dated 21 April 2011 acknowledging the Ritek Claim and noting they would only be seeking interest on the amount payable. They did not accept the FSP‟s positi on regarding the other claims. 7. The FSP then provided a Notice of Response and other subsequent materials denying the claims on a number of different bases, including an allegation that the Applicants have not been truthful and frank. 8. The Applicants refute these allegations and have requested a review of the FSP‟s decisions in this regard. 9. The Terms of Reference and Operational Guidelines provide that where an allegation of fraud is made in a general insurance dispute, the dispute will be referred to an Ombudsman for a Determination. 10. For the sake of brevity and conciseness, I do not propose to go through all the submissions and arguments by the parties except where deemed relevant to the substantive issue, namely the denial of the claims and the allegation that the Applicants are not being truthful and frank. Summary of Applicants ’ Position 11. They rely on the following to substantiate their position:  The Glass and Timber claims occurred during the period of insurance;  They have provided sufficient documentation setting out the extent of the Timber Claim;  The FSP‟s reliance on the Applicants‟ failure to start the project within 30 days of inception is inconsistent with the fact the FSP continued to insure them after the Applicants signed numerous declarations informing the FSP that the work had not restarted;  They have provided reasonable co-operation wherever possible;  They have been truthful and frank; and  The FSP‟s handling of the claim and its recent fraud allegation is indicative of a breach of its duty to act in the utmost good faith. 12. The Applicants have provided numerous submissions and evidence to substantiate their position, which will be considered where relevant in the “Reasons for Decision”. Summary of FSP’s Position 13. The FSP has provided a number of arguments substantiating its position to deny the Applicant s‟ claims. Jurisdiction Case No: 219805 Determination Page 3 of 17 14. The FSP submits the Service should exercises its discretion not to determine this dispute pursuant to clause 5.2(a) of the Terms of Reference given the following:  The Service has limited procedures to undertake a thorough process of investigation, discovery and gathering of evidence as opposed to a Court;  Outside of this setting, the FSP is significantly prejudiced and would be denied natural justice in the Determination of a dispute, particularly as it is only binding on the FSP;  Without the benefit of subpoenas, it cannot obtain - Copies of all correspondence between any of the Applicants, builders, liquidators/administrators of the former builder, suppliers and sub- contractors; - All evidence of the movements of and contacts made, by the Applicants; - All financial circumstances of the Applicants; - An investigation of further evidence that may be recovered with respect to the movements of the Applicants;  As credibility is a substantive issue, the Service is unable to determine this without the ability of cross examination; and  Any reluctance by the Applicants to pursue the matter in Court raises doubts about the veracity of their claim. Inability to prove that an event occurred 15. The Applicants are unable to establish the claims satisfy the definition of “Damage” or “Occurrence” due to the fact:  The Applicants expected these claims given the many similar incidents of theft and malicious damage at the property (as set out in the police report number E*****947) and their failure to construct a fence around the property;  It is uncertain if the Glass Claim and Timber Claim occurred during the period of risk; and/or  The Glass Claim does not exceed the deductible amount of $2,500. 16. In particular, the evidence shows that the Applicants expected the events given the police reports reveal that the male Applicant himself had requested police patrols in January 2009 “ as this is becoming a regular occurrence ”. Conditions and Exclusions 17. The FSP submits the evidence supports the following independent bases to deny the claims:  As the Applicants did not engage another builder until December 2009, the exclusion clause regarding “Cessation of Work” applies; Case No: 219805 Determination Page 4 of 17  The Applicants are unable to establish the alleged incidents for the Glass Claim and Timber Claim occurred during the period of insurance despite being specifically required to do so under the policy;  Failing to inform the FSP that it would not be proceeding with the “Project” within 30 days and/or taking any steps to protect the site;  Despite the alleged damage occurring in January 2009 and September/October 2009, the Applicant s failed to “ inform [FSP] of the event as soon as practicably possible ” , resulting in significant prejudice;  Failing to provide all assistance the FSP reasonably required pursuant to the policy; and  Failing to “ take all reasonable steps to prevent incurring any loss, damage or liability ” as required by the policy. Truthful and Frank & Utmost Good Faith 18. The FSP submits the numerous inconsistencies it has highlighted regarding the claims satisfy the test provided for by the Court of Appeal in the case of NRMA Insurance Ltd v McCarney (1992) 7 ANZ Ins Cas 61-146 which sets out the impact of an insured failing to comply with the contractual provision of being truthful and frank. 19. Further, the Applicants have clearly made false statements in an attempt to induce the FSP to pay the claim. 20. Regardless whether it was intentional or simply careless, the Applicants put in inflated claims for the Timber Claim and Glass Claim. They later had to concede (when it suited them) that they did not have the knowledge to actually assess what timber had been delivered, stolen and replaced. Similarly, in order for the Glass Claim to exceed the deductible, the Applicants reconstructed that further windows and panes were damaged. 21. The FSP also submits the Applicants breached their duty of utmost good faith, pursuant to section 13 of the Insurance Contracts Act 1984 (the Act) given the following:  Failed to take reasonable steps to prevent further occurrences continuing (such as immediately commissioning another builder, arranging a security service or fencing the property);  Abandoning the site, other than for sporadic inspections of no more than once a week, for 11 to 12 months without informing the FSP; and  Failing to inform the FSP of the Glass Claim and Timber Claim immediately, or at any time prior to the further alleged theft incident (Ritek Claim) some 8 months later. 22. Consistent with section 54 of the Act, the FSP notes the provision of misleading information, failing to co-operate and/or not providing relevant information has prejudiced it to the full extent of the claim. Case No: 219805 Determination Page 5 of 17 23. The FSP relies on the following policy provisions: “ Glossary of Terms Used … „ Damage ‟ means sudden physical loss or damage that you could not have expected and did not intend to happen. … „ Occurrence ‟ means an event, including the continued or repeated exposure of persons or property to conditions that are generally the same, which you could not have expected and did not intend to happen. … Section One – Material Damage [FSP] will provide Indemnity for Damage to the Project, or other property specified in the Schedule …” Issues 24. Whether the Service has jurisdiction to consider this dispute; 25. Whether the FSP was entitled to deny the claim; and 26. Whether the Applicants were not being truthful and frank. Law Involved 27. The Applicants bear the onus of establishing, on the balance of probabilities, a prima facie claim under the terms of the policy. Once established, the onus then shifts to the FSP. In establishing fraud, it is necessary to show a dishonest act or omission with an intention to deceive so as to obtain a material advantage. Where an insurer alleges fraud, the onus shifts to the insurer to prove the Applicants were involved in or knew of the fraudulent event or activity. 28. Although the FSP need only establish this on the balance of probabilities, an allegation of fraud requires clear or cogent proof. The classic formulation is in Briginshaw v Briginshaw [ 1938] 60 CLR 336. Dixon J said (at 361-362): “Except upon criminal issues to be proved by the prosecution, it is enough that the affirmative of an allegation is made out to the reasonable satisfaction of the tribunal. But reasonable satisfaction is not a state of mind that is attained or established independently of the nature and consequence of the fact or facts to be proved. The seriousness of an allegation made, the inherent unlikelihood of an occurrence of a given description, or the gravity of the consequences flowing from a particular finding are considerations which must affect the answer to the question whether the issue has been proved to the reasonable satisfaction of the tribunal. In such matt ers “reasonable satisfaction” should not be produced by inexact proofs, indefinite testimony, or indirect inferences.” 29. Under the Terms of Reference, when arriving at a determination, an Ombudsman shall have regard to what is fair in all the circumstances, good insurance practice, the terms of the policy and established legal principle. Case No: 219805 Determination Page 6 of 17 Whilst the process before the Ombudsman is not the same as before a court, nevertheless the words of the High Court should always be taken into account when determining in accordance with the Terms of Reference whether the FSP has established, on the balance of probabilities, that the claim is fraudulent. Insurance Contracts Act 1984 30. Section 13 of the Act provides that a contract of insurance is a contract based on the utmost good faith, and there is implied in each contract, a provision requiring each party to act towards the other party, in respect of any matter arising under or in relation to it, with the utmost good faith. Section 56 of the Act provides: “(1) Where a claim under a contract of insurance, or a claim made under this Act against an insurer by a person who is not the insured under a contract of insurance, is made fraudulently, the insurer may not avoid the contract but may refuse payment on the claim. (2) In any proceedings in relation to such a claim, the court may, if only a minimal or insignificant part of the claim is made fraudulently and non-payment of the rest of the claim would be harsh and unfair, order the insurer to pay, in relation to the claim, such an amount (if any) as is just and equitable in the circumstances. (3) In exercising the power conferred by subsection (2), the court shall have regard to the need to deter fraudulent conduct in relation to insurance but may also have regard to any other relevant matter.” Reasons for Decision 31. I have read the material provided by the parties prior to making this determination. 32. I am satisfied there has been a full exchange of material between the parties and that each party has had the opportunity of clarifying the issues that arise from the material. The Evidence Police Reports 33. The FSP is relying on the narrative contained in two of the police reports, one dated 25 March 2010 that is associated with the Glass and Timber Claims and the second dated 22 July 2010 associated with the Ritek Claim. 34. The first report‟s narrative contains the following: “Since this house has begun construction there have been a number of malicious damages and stealings occurring there. Since the last event on 3/1/09 another 6 windows have been smashed. Neighbours have seen a number of vehicles and persons leaving the scene. It cannot be stated when this occurred or by whom. Case No: 219805 Determination Page 7 of 17 Victim is requesting extra patrols in the area as this is becoming a regular occurrence. Record at this stage. Since the initial report Police have canvassed the area. The only neighbours are about 60m down hill from the location. There Police spoke with witness [R] who stated that since constructin [sic] began she had seen a number of vehicles attend and leave from the location. The witness mentioned specifically a „Shimano‟ pantech truck, a silver commodore, a blue car NFD and a maroon Toyota Hilux with QLD plates *****W. On no occasion has the witness seen any person load any materials onto any vehicle. Police spoke with the witnesses husband who is a carpenter by trade and he stated that the building site has been left unsecured for a long time and the only offences he had witnessed related to the windows being smashed and on that occasion he stated the offenders were on foot as no vehicles were in the area. Mr. [R] has also stated haveing [sic] conversations with subcontractors from the building site who have informed him of the builder being unable to pay their costs for some time, in particular the plumbing. Police have asked that the victims supply quotes for the missing timber as well as delivery dates etc. Police have made enquiries in relation to the maroon vehicle seen at the location. … The POI admitted to be at the location on the date in question. He recalled that he built other properties in the estate and that he was on a break from work and went to the unused building site and consumed some alcoholic beverages, specifically XXXX Gold stubbies. There is no direct evidence to place the POI in possession of the timber packs in question. Police have attempted to contact the victim and the builder on a number of occasions in an attempt to find out who delivered the timber in question and on what dates. At 11:25am Police spoke with [MF] and requested invoices from timber deliverers and discovered [JHW] were delivering the timber. Awaiting faxed invoices so [JHW] can be spoken to. Shortly after receiving an abrupt phone call from female claiming to be [MF‟s] mother. Insisted on speaking with teh [sic] Commissioner. Awaiting invoices. [JHW] Murwillumbah contacted and are searching records for purchase and delivery invoices but at this stage can not confirm that the timber was purchased there. Police spoke with [PR] with [JHW] who stated that no decking timber was delivered to that address. Also stated that [F] had called earlier in the day requesting same records. [F] has not been contactable since originally requesting these records. At this time it cannot be shown that the timber was delivered to the address at … and that it existed. On 23/3/09 Ms. [F] attended [TH] Police Station and clarified that the total timber stolen was $6060.00 and not $30,000.00. Police spoke with [WF] and informed him of the situation. Case No: 219805 Determination Page 8 of 17 There are no further avenues of investigation that can be investigated at this time as there are no witnesses. Parties updates. 35. The second police report provided the following narrative: “The PR report s that about October 2008, there was a large amount of Rytek Roofing delivered to the dwelling being constructed by the PR, for numerous reasons the construction at the location has ceased, believed to be either the builder of [sic] owner does not have sufficient funds at this time to continue the construction. At the time the PR believes that there was approximately $9000 worth of material delivered. Sometime between October 2008 and October 2009, person/s unknown have removed the roofing from the site. There are nil suspects or CCTV available, PR wishes to put in an insurance claim to recover their l oss.” Witness‟ Evidence 36. To corroborate the timeframe of the Ritek Claim occurring between 14 September and 17 October 2009, the Applicants have provided an affidavit from IDS. IDS provided the following relevant information in his affidavit:  He was liaising with the Applicants because he was interested in purchasing the property;  He corresponded with the Applicants during 20 August 2009 and 3 November 2009. In this time, he attended the property and was aware there was a large packaged pallet of Ritek roofi ng sitting at the front of the property on the eastern elevation;  He was able to confirm it was Ritek roofing as he had a discussion with the male Applicant regarding the use of it at the property. He needed to be fully appraised of the materials intended to be used given his interest in purchasing the property and the fact he is in the building trade; and  Although he could not recall the exact date, it was during a weekend in the middle of October 2009 when he attended the property and observed the roofing missing. He then notified the Applicants of this. 37. The Applicants also provided a statement from DC which contained the following relevant remarks: “I now know a lady by the name of [VM] to be the owner of the property at [insured address] which is in the same estate as mine…. [V‟s] property is visible to the south west of our property and we have a clear view of the eastern side of her home. Around October 2009, my father in law and I were out in the yard when we observed a mobile crane up at [V‟s] property loading what looked like roofing material onto a truck. It was a very large pallet of material that I assume had to be craned off in its entirety due to sheer weight and size. I do not recall the time of day but can state it was daylight. The mate rial being craned off the ground was on the eastern side of [V‟s] property which was near to and visible from the road and from our property. At Case No: 219805 Determination Page 9 of 17 the time the home was still under construction and I assumed that they may have been removing excess or incorrect material as they were in plain sight of passing traffic and therefore I did not believe it to be suspicious. 38. MF provided a statement in an attempt to clarify the police‟s reference to her evidence in the report dated 25 March 2010. This statement contained the following relevant remarks:  She was the owner and operator of FC;  She attended the police station for the purpose of presenting documents that would support the claim of timber materials present at the property;  She explained to the officer that due to being locked out of the office, she was unable to obtain all the relevant proof of loss; and  She categorically denies that she alleges the timber stolen was not worth $30,000. 39. The Applicants have noted the following regarding the Timber and Glass claims:  AB and WB (the male Applicant ‟s parents) were on site on 19 January 2009 and identified the timber and Ritek roofing;  The female Applicant had visited the site approximately 4 to 5 days prior to the discovery of the theft of the timber and the glass damage and did not identify any issue; and  The theft of the timber and the glass damage was identified by the male Applicant on 20 January 2009 and reported to the police. Documents and other Evidence 40. The female Applicant noted that she and JG, a contractor engaged by the builder‟s warranty insurer to review the Applicant s‟ claim under that policy, inspected the property on 14 September 2009. During this inspection, they both observed the Ritek roofing. The female Applicant has also produced a photograph of the roofing and this was contained in JG‟s report dated 11 October 2009. 41. In relation to the Timber Claim:  The Applicants noted that a progress payment in the sum of $121,912.40 was provided to FC for the “Frame Up” . This was corroborated in JG‟s report;  The Applicants provided a spreadsheet reconciling the timber that was supplied and stolen with the timber they replaced;  Invoices of the replaced timber were supplied; and  The spreadsheet provided by the Applicants referred to invoices from FC but were not provided to the Service. However, the FSP does not appear to refute their existence. Case No: 219805 Determination Page 10 of 17 42. In relation to the Ritek Claim, no documentation was provided but the parties acknowledge that an invoice dated 10 October 2008 from Ritek to FC existed. The Applicants acknowledged that they did not replace this roofing and as a result, no replacement invoices were provided in support. 43. With respect to the Glass Claim, no documentation is available but the parties appear to acknowledge the existence and authenticity of the following documentation and events:  An invoice numbered 17629 totalling $32,703.55 for the glass supplied to the site prior to the Glass and Timber claims;  The glass supplier accessed the site at one point to recover some of the glass supplied because an invoice remained unpaid; and  A quotation number 17810 dated 24 November 2009 for the sum of $4,659.70 that was for the replacement of 22 panes of glass, forms the basis of the Applicant s‟ Glass Claim. Consideration of the Evidence Terms of Reference 44. The FSP bases its allegation of fraud substantially upon inconsistencies in the Applicants ‟ statements and the police reports obtained. 45. An allegation of a failure to be truthful and frank and a breach of the utmost good faith is a serious allegation. If established, it has a major impact on an individual‟s ability to obtain insurance and in some circumstances, finance. In view of the significance of the allegation, it is important the evidence provided by the FSP is clear and cogent. An allegation will not be satisfied by inexact proofs, indirect testimony or speculation. Whilst the onus on the FSP before the Ombudsman is not the same as the onus before a Court, nevertheless the Ombudsman is guided by the principles laid down b y the Courts. The FSP will normally need to produce evidence of motive, opportunity, character and credibility, supported by expert evidence where appropriate. 46. Notwithstanding these allegations, the FSP remains of the opinion that the Service is not the appropriate jurisdiction to consider the dispute due to its limited procedures to fully consider the issues. It states that the Court ‟s processes would allow the FSP to access documents it cannot otherwise obtain and to cross-examine the witnesses. 47. Having considered the evidence, I do not consider the Service should exercise its discretion in this manner. It appears the FSP has raised such a serious allegation and is then seeking to obtain the necessary direct evidence to substantiate it via the Court‟s proce sses rather than having obtained the evidence and basing its allegations upon that evidence. 48. Further, I consider the Service‟s accessibility to Applicants when such an allegation is made is fundamental to its purpose given: Case No: 219805 Determination Page 11 of 17  The impact such an allegation has on the Applicants; and  The Service has had extensive experience in dealing with similar allegations and as such is more appropriately equipped to analyse and evaluate the evidence, and;  As the alternative dispute resolution service relevant to this FSP, the Service affords the Applicants the opportunity to pursue an alternate dispute resolution course, just as the Applicants have elected to do so. 49. I therefore do not consider it is appropriate that the Service should exercise its discretion under clause 5.2(a) of the Terms of Reference to not consider this dispute. Timber and Glass Claims 50. I do not accept the FSP‟s position that the Applicants expected and/or intended the loss and resultant claims to occur because there were previous incidents in the past. This would suggest that if a person has one theft on their property, then every subsequent theft that occurred was an event that was expected and/or intended and should ultimately not be covered. 51. I do not consider this is a reasonable interpretation consistent with the commercial purpose of the contract, namely the promise to indemnify the insured for damage to the property that they did not expect. I accept the Applicants‟ evidence that they did not expect these events to occur. 52. The FSP has argued the Applicants are unable to establish the event occurred during the period of insurance and that the amount stolen is also in doubt. In making these allegations, the FSP is relying substantially on the police report dated 25 March 2010. 53. However, the contents of the Police report are challenged by the Applicants and at least one witness. 54. As a consequence, I consider that there is some doubt regarding the police report as:  There is no corroborating evidence from either the author and/or an investigating officer to substantiate the comments in the police report;  The narration in such a report would be given little to no weight by a Court without such corroboration;  The FSP is relying on the unidentified author‟s conversations with a number of witnesses, such as R and MF, but failed to seek evidence directly from these parties to corroborate and substantiate the narrative ‟s reference to same; and  The Applicants have provided direct evidence from relevant parties to rebut the comments, for instance the statement from MF and their own evidence. Case No: 219805 Determination Page 12 of 17 55. In light of this, I therefore accept that the Applicant s‟ evidence establishes that the theft of the timber and the damage to the glass likely occurred during the period between 15 January and 20 January 2009. This was within the period of insurance. 56. The Applicants have noted that in relation to the Glass Claim, 22 panes of glass were damaged. Although the police report identified six windows being smashed, the Applicants have noted this does not necessarily translate to panes as the two terms are not interchangeable. I find this explanation reasonable. 57. Although the police report does make reference to a previous incident involving glass, the FSP has failed to establish the extent of this and the Applicants have refuted such an incident occurred. Given the lack of corroborative evidence provided by the FSP from the police in this regard, I therefore accept the Applicants‟ evidence. 58. Accordingly, based on the available evidence, I accept the Applicants have established that 22 panes of glass were damaged during the period of insurance and the replacement cost is approximately $4,659.70. 59. In relation to the Timber Claim, I do not consider the FSP has provided appropriate evidence to rebut the amount of the Applicant s‟ claim. The FSP has again substantially relied on the police report which, for the reasons outlined above, I am not inclined to prefer. 60. The FSP has also raised inferences regarding the fact the Applicants initially claimed a greater amount and then adjusted it to a lower amount when it suited them. The Applicants responded noting that they are inexperienced in the building trade and had trouble quantifying the amount sought. This explanation is reasonable and given the amount spent by the Applicants regarding the frame up, I do not consider that the amounts were so grossly exaggerated that an inference of a failure to be truthful and frank is appropriate. 61. The FSP has also referred to its assessment of the claim and noted the following:  There is no evidence or report that the theft included the removal of installed timbers;  Good construction practice indicates any timber stored on site would have been supplied immediately preceding the cessation of works; and  It was estimated by the adjuster that timber in the sum of $6,414.49 supplied from 13 to 17 October 2008 may have been stored preceding the cessation of works. This timber was likely the subject of the theft. 62. However, the FSP has not provided any loss adjuster reports to corroborate its position. Instead, it has provided an unsigned two page summary of the adjuster‟s actions. It is unclear if this was written by the adjuster because it makes reference to the adjuster as a third person. Case No: 219805 Determination Page 13 of 17 63. I do not consider this evidence is appropriate or persuasive. The summary above is based on presumptions with no substantiation. Further, there is nothing to indicate that the timber being claimed by the Applicants is inconsistent to the timber that was on site and unused. 64. The Applicants chose not to lodge a claim for these incidents until 5 March 2010, which is more than a year after the incidents occurred. The FSP has noted this is in breach of their policy condition to “ inform [FSP] of the event as soon as practicably possible ”. 65. In this case, I consider the Applicants have clearly breached this policy condition given the timeframe that lapsed and I am not satisfied they have provided a reasonable explanation for this. The incident occurred within two weeks of incepting the policy so it is unclear why they had the presence of mind to notify the police but not the FSP. 66. Despite this though, I note section 54(1) of the Act applies regarding this policy condition and this provision states the following: “ 54 Insurer may not refuse to pay claims in certain circumstances (1) Subject to this section, where the effect of a contract of insurance would, but for this section, be that the insurer may refuse to pay a claim, either in whole or in part, by reason of some act of the insured or of some other person, being an act that occurred after the contract was entered into but not being an act in respect of which subsection (2) applies, the insurer may not refuse to pay the claim by reason only of that act but the insurer‟s liability in respect of the claim is reduced by the amount that fairly rep resents the extent to which the insurer‟s interests were prejudiced as a result of that act. ” 67. In this case, I am not satisfied the FSP has established the extent of its prejudice regarding the Applicant s‟ failure to report the incident as soon as reasonably practicable. The Applicants have provided direct evidence establishing the date of the loss which, for the reasons outlined above, I am not satisfied the FSP has rebutted. Further, I am not satisfied that the FSP has established its failure to rebut this was linked to the delay in reporting the claim. 68. Although it is possible to accept the loss adjuster would have suffered some impediment in assessing the loss given the delay, I am not satisfied this in itself is sufficient to establish the extent of the FSP‟s prejudice. The FSP has not provided any of the loss adjuster‟s reports or direct evidence from the loss adjuster to explain how the delay prejudiced his task and if it did so, the extent of the prejudice. 69. Given this, I am not satisfied the FSP has established any prejudice by the Applicant s‟ failure to report the incidents as soon as reasonably practicable. 70. The FSP has also argued the Applicants have not taken reasonable steps to secure the site. However, I do not consider this is applicable given the following:  The losses occurred within two weeks of the policy being incepted; Case No: 219805 Determination Page 14 of 17  The FSP had been notified in a “Single Project Declaration” dated 1 December 2009 that the description of work to be completed was lock up and fit out. Further, in this same declaration, the Applicants responded “ Will be getting temporary fencing ” in response to the question “ Details of Security on Site ”; and  Despite being in receipt of this information, the FSP never informed the Applicants that the failure to fence the site would result in any claims occurring prior to this date and/or afterwards not being covered. 71. In light of this, I therefore consider the FSP is not entitled to rely on this provision and I accept the Appli cants‟ argument that the FSP has essentially waived its rights in this regard by its conduct. 72. In addition, I am not satisfied that the FSP has adequately explained how a fence would have prevented acts of vandalism or theft by people intent on carrying out those acts. 73. The FSP has also indicated that the Applicants failed to provide reasonable co - operation. However, I can find no evidence of same. The FSP has not referred to any specific request that the Applicants have failed to satisfy. I therefore find th e FSP‟s reference to this policy condition to be without merit. 74. Although the Applicants lodged one claim for both losses, I do not accept they occurred in the one event. It is unlikely that the thief took the time and effort to load and cart away over $17,000 worth of timber whilst also maliciously damaging 22 window panes. 75. In my opinion, it is more likely these incidents occurred independently of each other. 76. Pursuant to the insurance schedule, the Applicant s‟ contract notes a deductible of $2,500 occurs f or each and every “Event”. “Event” is defined in the policy to mean “ a single event of loss or damage ”. 77. Given the above, I am therefore satisfied that the Timber and Glass claims occurred from independent events and accordingly, a $2,500 deductible applies to each. 78. This therefore results in a net payout of $17,473.30 to the Applicants for both claims, namely $2,159.70 for the Glass Claim and $15,313.60 for the Timber Claim. Ritek Claim 79. The FSP, in its letter to the Applicants dated 24 March 2011, stated the following regarding this claim: “However, we are prepared to accept the Ritek Claim in the sum of $9,923.58 less the applicable excess of $2,500, resulting in a payment of $7,423.58 ” Case No: 219805 Determination Page 15 of 17 80. In their letter dated 5 April 2011, the Applicants acknowledged this offer and did not address it further beyond stating they would be seeking interest. It is reasonable to accept that at this point, this issue had been resolved except to the extent of interest. Case No: 219805 Determination Page 16 of 17 81. However, the FSP appears to have retreated from this position by stating it is entitled to rely on its policy exclusion regarding “Cessation of Work”. In particular, it appears to submit that the amount it was willing to pay for the Ritek Claim was part of a “without prejudice” offer. 82. Upon reviewi ng the FSP‟s letter though, I note the only reference to an offer being made on a without admission basis was regarding the Timber Claim. The wording regarding the Ritek Claim made no reference to it being made on a “without prejudice” offer or on a withou t admission basis. Instead, in my opinion, the wording clearly communicates the FSP‟s admission of liability for the claim and the extent of same. 83. Accordingly, I consider the FSP is not entitled to retreat from this open admission and rely on a policy provision to deny this aspect of the claim pursuant to section 14(1) of the Act, which states: “ 14 Parties not to rely on provisions except in the utmost good faith (1) If reliance by a party to a contract of insurance on a provision of the contract would be to fail to act with the utmost good faith, the party may not rely on the provision. ” 84. This is based on the following:  The FSP had ample opportunity to investigate the claim and consider its rights; and  The FSP made a clear statement of intent almost a year after the claim, namely the acceptance of the Ritek Claim and the extent of it. 85. Accordingly, I accept the FSP is liable to pay this claim and its liability is $7,423.58. Truthful and Frank & Utmost Good Faith 86. In light of the reasons above, I do not consider the FSP has established the Applicants have not been truthful and frank and/or breached their duty of utmost good faith . Indeed, the FSP‟s submissions are based on inferences and implications with little to no direct evidence to substantiate same. 87. Further, the Applicants were not notified of such an allegation until the FSP‟s response to the Service dated 13 April 2011. Prior to this, the correspondence between the parties related to the Applicant s‟ alleged failure to substantiate the amounts they were seeking. There was no reference that such serious allegations were being contemplated. I consider the FSP‟s actions in this regard to be contrary to good industry practice. Case No: 219805 Determination Page 17 of 17 Interest 88. I have considered the Applicants‟ request for interest. I note my commentary above regarding delay between the events and the lodgement of the claims. In view of my commentary and the need to be fair in all circumstances in accordance with the Terms of Reference of the Service, I am not satisfied that it is appropriate to award interest in this matter. Determination 89. I determine that the FSP do the following:  Pay to the Applicants the sum of $24,896.88;  The FSP cause to be expunged from its records, and the records of any organisation with whom it has communicated, any reference to fraud or to a failure to be truthful and frank and/or a breach of utmost good faith on behalf of the Applicants. 90. In the event the Applicants accept this Determination, the FSP should pay the appropriate sum and undertake the appropriate action within 14 days of being notified of the Applicants‟ acceptance

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.