Transmission repair costs and hail-damaged total loss claim settled

FirmFinancial Firm (Unknown - Insurer)
Decided2011-02-17
ProductGeneral Insurance · Motor
OutcomeFor the complainant in part
Amount awarded$2,821
Non-financial loss—
Amount claimed$46,218
SourceAFCA PDF

Summary

After a parked-car collision, the applicant's transmission problems and a later hail-damaged total loss were disputed, with the applicant seeking about $46,000. AFCA ordered the FSP to pay $2,821.39 with interest for the transmission diagnosis and repair costs and rejected the remaining claims as ambit or unsupported.

The transmission costs were apportioned equally under the fairness discretion because causation was unclear, while the hail damage and other associated costs fell outside the FSP's liability.

Issues

Subjects and remedies

motor vehicle collisionnatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

219196 Determination 1 of 6 DETERMINATION Case number: 219196 Motor Vehicle – accident related repairs – total loss- Term of Reference 8.2 SUMMARY OF FACTS 1. The applicant held a comprehensive motor policy with the Financial Services Provider (FSP) from 30 November 2005 to provide accidental loss and damage cover to a 2002 Landrover Freelander SE. 2. On 7 October 2009, the applicant lodged a claim with the FSP for damage sustained to his vehicle after it had been struck whilst parked earlier that day. 3. The FSP accepted the claim and authorised repairs to the vehicle. The damage to the vehicle was light panel damage to the nearside. 4. The applicant submits that following repairs the vehicle was not operating correctly. The FSP believed that this was due to transmission issues which were unrelated to the accident. 5. The applicant then arranged for a full overhaul of the transmission. 6. While the vehicle was at the repairers having the alleged transmission issues checked, it was damaged in a heavy hail storm which now renders the vehicle a total loss. 7. The applicant asserts that had it not been at the repairers, it would have been garaged and therefore it would not have sustained any damage from the hail storm. As such, the applicant requests that the $350 policy excess be waived. 8. The applicant sought in total $30,217.62 as of 7 October 2010. This is comprised of: “Depreciation $ 1858.56 Cost of hire car and taxi fares $ 2,464 Cost of a replacement car $ 3,971.12 Cost of insurance $ 379.83 Cost of licence and CTP $ 274.56 Replacement cost of stolen private plates $ 350 Cost of roadside assistance $ 177.87 Interest accrued on credit card $ 1,597.89 Transmission overhaul $ 5,642.78 Total loss value of vehicle $13,500 ” 9. In a further letter dated 14 December 2010, the applicant submitted a very late further statement of quantum of loss increasing the balance outstanding to $46, 217.64. I do not accept this assessment and I refer to my comments in paragraph 39 below. 10. The FSP argues that the applicant arranged for the overhaul of the transmission system on his own volition and it is not required to reimburse him for the cost of this. 11. Furthermore, the applicant has received payment from the other party‟s insurers in respect of the hire and taxi fare costs. 219196 Determination 2 of 6 12. The FSP states that there is no evidence to show that any ongoing issues with the vehicle which occurred as result of the initial impact and it has met the extent of its liability under the policy. 13. The FSP also confirms that it has paid the applicant the sum of $14,000 less the $350 policy excess in respect of the total loss claim and any additional costs incurred are non-accident related and not covered under the terms of the policy. ISSUE IN DISPUTE 14. Whether the FSP has correctly settled both claims in accordance with the terms of the policy. RELEVANT POLICY PROVISIONS “We will cover you for accidental loss...or damage to your vehicle. At our option we will: a. repair your vehicle; or b. pay you the reasonable cost of repairing your vehicle; or c. pay you the market value of your vehicle when the current schedule show that your vehicle is insured for market value ... Nor will we pay for: ... depreciation, wear and tear to your vehicle. ... mechanical or electrical breakdowns, failure or breakages to your vehicle. ... Failure of computer or similar equipment loss or damage to any machinery, equipment, part, accessory or other property ... An excess is the amount shown in the current schedule which you must pay when you make a claim under your policy unless we state an excess does not apply. ... Salvage of your vehicle when it is a total loss If your vehicle is a total loss and we have agreed to pay the market value or agreed value for your vehicle: the wreckage of your vehicle will become our property, and we will keep the proceeds of any salvage sale.” TERMS OF REFERENCE “8.2 Dispute resolution criteria Subject to paragraph 8.1, when deciding a Dispute and whether a remedy should be provided in accordance with paragraph 9, FOS will do what in its opinion is fair in all the circumstances, having regard to each of the following: a) legal principles; b) applicable industry codes or guidance as to practice; c) good industry practice; and d) previous relevant decisions of FOS or a Predecessor Scheme (although FOS will not be bound by these).” REASONS FOR DECISION 15. I am satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. 219196 Determination 3 of 6 16. The applicant contacted the FSP on 7 October 2009 to lodge a claim for nearside panel damage to his vehicle after it had been struck by another vehicle whilst parked. 17. The FSP accepted that the claim and arranged for the vehicle to be inspected at a local repairer. The repairs to the bodywork were authorised by the FSP and subsequently completed. 18. When submitting a claim, the burden of proof lies with the applicant to demonstrate on the balance of probabilities that all of the loss claimed is as a result of an insured event. Only once an insured event has been established, does the onus transfer to the FSP to show on the balance of probabilities that all or some of the loss claimed falls within an exclusion of the policy. Vehicle Transmission Issue 19. The main issue in dispute concerns the problems associated with the vehicle‟s transmission. The applicant contacted the FSP to advise that the repairer had confirmed to him that there was an issue with the transmission. The FSP arranged for the transmission to be stripped down to ensure that the casing had not sustained a fracture during the impact. The transmission specialist reported on 2 December 2009: “Vehicle towed to workshop after repairs from crash, present slip codes, going into limp mode, oil burnt. Codes present were 2nd, 3rd and 4th gear slip codes. ... Transmission stripped to find that end clutches were destroyed and running metal on metal, further investigation found that intermediate speed sensor electrical connector was suspect and sensor did not test within range. End case was tested for any cracks that may have been a result of any impact in that region but were unable to find any cracks that may cause a cross bleed or total pressure bleed off. It is our belief that the damage is caused by the faulty speed sensor and has been an ongoing issue and not an after product of an impact. Slip codes can be present due to clutches being burnt or speed sensor not performing properly, both faults were present in this transmission. Owner and insurer informed that transmission will require complete recondition, under instruction from insurer the transmission was re-assembled, without any repairs and re- fitted to vehicle and collected by insurer.” 20. The FSP had informed the applicant of the issues regarding the transmission, however he refused to have any work carried out to the vehicle. Hence the reason it was re- assembled on the FSP‟s request. 21. The transmission specialist further reported on 12 July 2010 (“the Second Report”): “In July 2008, Landrover Freelander...was brought to us for inspection. We found problems with the pulse generator which in turn had caused damage to the 3rd gear clutch pack and surrounding clutches. Whilst the vehicle did drive at the time, it was recommended to the owner that in the long term an overhaul would be necessary. ... On January 2010, [applicant] booked the vehicle into our workshop for a transmission overhaul as we had originally diagnosed as the repair required to fix the vehicle. The vehicle was collected by [applicant] from our workshop on 24 February 2010. Three days later, [applicant] phoned to complain of a fault in the vehicle. This fault was a completely different problem to the other faults we had 219196 Determination 4 of 6 experienced in the vehicle. We proceeded to undergo extensive diagnostics on the transmission which lasted approximately 4 months. The diagnostic measures were to the extreme of 3 completely different transmissions being built and fitted to vehicle, sensors were replaced, tyre pressure/sizes investigated and computer replaced, all to no avail. Eventually, the vehicle was sent to (R) as we were satisfied the new problem was not transmission related and had not been there when the vehicle was originally brought to us prior to the accident. We therefore suggest that in retrospect, whatever is causing these recent problems in the transmission most likely have been caused by the accident in October 2009 and due to all this extra and extensive diagnostics carried out, our previous report of December 2009 as incomplete and is now superseded and fully corrected by this report.” 22. There are a number of causation issues in this matter, some of which are unrelated to this issue. I accept that if the continuing fault was collision related the applicant is entitled to look to the FSP for re -imbursement of the cost to diagnose and cure the fault. 23. It is clear from the second report of the transmission specialist that the requirement for an overhaul of the transmission in the applicant‟s vehicle was suggested to the applicant over 12 months prior to the accident. I am of the opinion that this is a cost the applicant would probably have had to bear in any case. 24. The applicant asserts that he authorise d the transmission overhaul to “ prove a point” to the FSP that the faults lay outside of the transmission and as such , he should be reimbursed the cost of these works. In other words, only by investigating and addressing the transmission problem could the applicant exclude it as the cause of the fault and proceed to correctly diagnose and hopefully cure the fault. This may be a mute point, but it seems clear to me that the correct diagnosis of the fault was and is a matter in issue between the parties. The applicant sought to prove that the continuing fault was related to the collision. 25. In their second report the experts stated “This fault was a completely different problem to the other faults we had experienced in the vehicle…” . Sadly, there is no indication as to what the alleged fault codes related to, or whether the fault related to the component (transmission), or whether it was a fault in the vehicle‟s computer system. The inference from the report is that it relates to the latter, but it is not clear. There is a lack of detail but the report goes on by a process of deduction that, notwithstanding the failure to diagnose the “fault”, with the benefit of hindsight it must have been caused by the collision. Thus, whilst there is a critical gap in the evidential chain, there is a temporal connection with the collision. That is to say, there is an assumption that the collision caused the fault which is the subject of complaint. 26. Whilst the evidence is less than cogent, it does tend to support the applicant‟s position. It also seems clear to me that the damage to the transmission, as diagnosed before the repair work, was not caused by the collision. The continuing fault (be it within the computer system or in a mec hanical or electrical component) may have been separate and apart from the da mage shown in the early testing which was not accident related. 219196 Determination 5 of 6 27. In the event, the applicant has an expert in his favour to support the argument that the continuing warning of fault is accident related. The FSP, although in a position of some disadvantage by not obtaining an expert‟s report at an earlier stage, has not provided any evidence to contradict the opinion expressed by the applicant‟s expert. It must be said that the experts‟ reports do not sit well together and the adoption of the “temporal co nnection” referred to above may appear to be a less than satisfactory explanation as to the cause of the problem and its connection with the collision. 28. In a court of law, these evidential issues are decided on the balance of probabilities, but the Service ‟s decision makers (including myself) are not so constrained. If one were to apply a strict application of the law of evidence one could reach a conclusion that the evidence is eve nly balanced. That would derive an unsatisfactory outcome. I find I am not able to ascertain or calculate the portion of cost solely attributable to the testing and diagnosis of the continuing fault. 29. This is a vexed and difficult matter to resolve, but I have formed the view that it is appropriate to apply Terms of Reference 8.2 whereby I am empowered to make an award based on fairness in all the circumstances. Notwithstanding the evidential difficulties facing the parties as outlined above, I determine it is appropriate to apportion the cost of the transmission diagnosis and repairs equally between the parties. I refer to my conclusion below. Other matters 30. Whilst undergoing the transmission overhaul authorised by the applicant, the private number plates were stolen. As the applicant had placed his vehicle in the care of the transmission repairer and not the FSP, I do not consider that the FSP can be held liable for the cost of replacing these. 31. Furthermore, whilst at the repairer on 22 March 2010, the vehicle was extensively damaged during a hail storm. The app licant lodged another claim with the FSP who, after inspecting the vehicle, declared it to be a total loss. 32. The FSP arranged for the collection of the vehicle in order to minimise any potential storage charges. The applicant asserts that this was done without his authority and that the FSP effectively stole his vehicle. 33. The FSP has paid the applicant the pre-accident market value of the vehicle. As such, I am of the opinion that the FSP has the right to retain the vehicle salvage in accordance with the policy terms. The FSP has confirmed that should the applicant wish to purchase the salvage he is at liberty to put forward an offer for it. 34. The applicant argues that had the FSP diagnosed the ongoing issues with the vehicle at an earlier date then the vehicle would not have been at the repairers, exposed to the elements. The applicant claims the vehicle would have been in a garage protected from the hail. As such, he does not consider that he should have to pay his excess. 35. I am of the view that the applicant‟s vehicle would not have been at the repairers had he not decided to „prove a point‟ to the FSP and for work which would have been required anyway. 219196 Determination 6 of 6 36. The policy wording is clear and unambiguous in relation to the payment of an excess in the event of a claim. The applicant submits that a sequence of events has unfolded from the initial claim and therefore only one excess would apply. 37. I am satisfied that the FSP cannot be held accountable for the positioning of the vehicle at the time of hail storm and therefore, the secondary damage claim is subject to the application of a policy excess. 38. As I am unable to accept that the FSP is responsible for the cost the vehicle being written off during a hail storm, the FSP cannot be held responsible for other associated costs the applicant has incurred in obtaining a replacement vehicle, or interest accrued by the applicant for paying such associated costs by means of his credit card. 39. Finally, the applicant has submitted a number of assessments of quantum of his claim. As noted in paragraph 9 above , the assessments culminated in the late submission claiming a balance of $46,217.64. In my opinion, these assessments are ambit claims and are fanciful and not substantiated. If the applicant wishes to pursue these claims he must do so in another forum. CONCLUSION 39. Accordingly, in respect of the transmission issues, I determine the FSP pay the sum of $2821.39 together with interest thereon at the statutory rate from 24 February 2010 until the date of settlement. 40. I also determine that the FSP is not required to make any further payment to the applicant and has otherwise met the extent of its liability under the terms of the policy.