Determination 218587

Cash settlement for fire-damaged business premises disputed as inadequate

FirmFinancial Firm (Unknown - Insurer)
Decided2011-03-10
ProductGeneral Insurance · Business / commercial
OutcomeFor the complainant in part
Amount awarded$154,334
Non-financial loss—
Amount claimed$175,336
SourceAFCA PDF

Summary

A fire-damaged commercial building was settled in cash by the FSP at $143,609.06, and the business disputed this against its own higher quote of $175,336.36. AFCA decided the FSP must pay a cash settlement of $154,334 with interest on the additional $10,725.

The FSP was entitled to rely on the lowest comparable quote, but it should have reconciled its position with the applicant's quote, so an additional allowance was fair in all the circumstances.

Issues

Subjects and remedies

home or building damagesmall businesspay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

218587 Determination 1 of 4 Case number: 218587 General Insurance – Small Business – Fire – Quantum 28 February 2011 Background 1. The Applicant insured his business premises under a commercial business plan policy held by the Financial Services Provider (FSP). 2. On 23 March 2009 the Applicant lodged a claim for damage to the property which had been caused by fire that day. 3. The FSP accepted the claim and arranged for a scope of works for reinstatement to occur. 4. Three quotations based on the scope of works were provided and the Applicant requested that only one of the builders complete the work. 5. Following commencement of the reinstatement and demolition, further damage was identified and two further scopes of works were completed. Based on the three scopes of works, the total cost to reinstate the building was quoted at $152,970 inclusive of GST. 6. Based on the additional costs, the FSP offered the Applicant a cash settlement of $143,609.06 based on the least of the three quotes it initially received and the total quotation cost of the additional repairs. GST has been deducted. 7. The Applicant is dissatisfied with the settlement offer having received its own quotation for reinstatement which amount to $175,336.36. GST is also deducted. Summary of Applicant ’s Position 8. The Applicant says that the settlement amount offered by the FSP is inadequate to reinstate the property to its pre-damaged condition. 9. The Applicant says that damage to the property was overlooked by the FSP’s expert and that is the reason why it sought an additional quote from its builder. Determination 218587 Determination 2 of 4 10. The Applicant is concerned that the cheaper quote will leave work undone or badly done. 11. The Applicant suggested an independent quantity surveyor to resolve the dispute. 12. The Applicant says it is more appropriate that its quotation be relied on in providing a cash settlement to ensure the property is fully reinstated, so that no problems occur in the future. Summary of FSP’s Position 13. The FSP says that it has provided a fair and reasonable cash settlement offer under the terms and conditions of the policy. 14. The FSP says it is entitled to rely on the lowest quotation to settle a claim. The Applicant has not identified any specific additional damage which has been over looked by the FSP save to air conditioning. 15. The FSP says therefore in relying on the lowest original quotation plus the quotes for the additional damage, it has discharged its obligation to the Applicant under the terms and conditions of the policy. 16. Finally the FSP submits that it has included $5,000 in contingency expenses and therefore the total settlement offer is fair and reasonable. This has been verified by an independent expert. The Applicant has not provided any independent expert and its allegation that the cheaper quote will leave work undone is unsubstantiated. 17. The FSP says it is unnecessary to appoint a further quantity surveyor as the quantity surveyor it appointed has produced or assessed the quotes for the works and confirmed the quotes relied on, and the offer made by the FSP will get the repairs/reinstatement done. 18. The FSP relies on the following policy provisions: ” Replacement If a building or item of other property is damaged and replacement is shown on the certificate of insurance, we replace, reinstate or repair the part of the building or item of other property that is damaged as far as possible to its original condition, using materials that are readily available in Australia. Or, at our option, we pay the reasonable cost of doing so. ... If we choose to pay you to replace, reinstate, or repair we deduct an amount for wear, tear and depreciation if you do not replace, reinstate or repair within a reasonable time. ...” TERMS OF REFERENCE 218587 Determination 3 of 4 Dispute resolution criteria Subject to paragraph 8.1, when deciding a Dispute and whether a remedy should be provided in accordance with paragraph 9, FOS will do what in its opinion is fair in all the circumstances, having regard to each of the following: a) legal principles; b) applicable industry codes or guidance as to practice; c) good industry practice; and d) previous relevant decisions of FOS or a Predecessor Scheme (although FOS will not be bound by these). Issues 19. Whether the FSP has been fair and reasonable in providing the cash settlement of $143,609.06 based on quotations it received under the terms and conditions of the policy. Reasons for Decision 20. I am satisfied that a full exchange of information has taken place between the parties and that each party has had the opportunity to address any issues raised. 21. I have considered all the material in the submissions of both parties and all the accompanying material. 22. I have reviewed the policy which makes it clear that it is at the FSP’s option to replace, reinstate or repair the damaged building, or, at its option, to pay the reasonable cost of doing so. 23. Further, providing there is a comparison of “apples with apples” , the FSP is entitled to rely on the lowest quotation to settle a claim. 24. Although the Applicant says the settlement amount offered by the FSP is not reasonable and he is concerned that the cheaper option will leave work undone or badly done, he has not provided sufficient evidence to substantiate these contentions. I have perused the quotation provided by the Applicant. Whilst it may not be as comprehensive as the documentation provided by the FSP from its expert, I accept that it breaks down the costs for the Applicant. But there is no explanation as to why the quote is more ($36,272.72 more) than that allowed by the FSP’s expert. Or, in other words, there is no explanation as to why the quotes relied upon by the FSP will mean the building will be repaired or reinstated in a sub standard manner. 25. The biggest differential in the quotes was the amount quoted to render and plaster, and to paint. The FSP allowed a total of $10,500 whereas the Applicant ’s quote for this part of the works totals $48,000. That is a substantial differential and I cannot accept such a differential without further evidence as to why that substantially larger amount is acceptable. 218587 Determination 4 of 4 26. I note the Applicant ’s concern that the work once begun indicated that other work was required. Perhaps the Applicant lost confidence in the FSP for this reason, but it is not uncommon when reinstating a fire damaged building that further works are discovered once the demolition has begun. In my view, the FSP has reacted reasonably to two requests from the Applicant to pay for the further work to be done once discovered. On the first occasion, the FSP even accepted the quote from the Applicant ’s then preferred builder. 27. The Applicant is concerned that the FSP did not accept its suggestion of an independent quantity surveyor ’s attempt to resolve the dispute. The FSP said it was unnecessary, as it already had engaged one. Perhaps this would have resolved the dispute. In any event, it is not apparent to me that the FSP has attempted to reconcile the quote provided by the Applicant with its other quotes, and I am of the view that to do so would have been fair in all the circumstances and that would have been good insurance practice too. 28. The three quotes provided by the FSP are not itemised as to price. There is just a lump sum at the end. So, I am unable to discern anything from them as to the fair and reasonable cost of repairs/reinstatement to help an assessment of the reason for the differential between the offer of the FSP compared with the offer of the Applicant. 29. I consider the FSP should have made more of an attempt to reconcile its position with the Applicant once the Applicant provided his quote. In all the circumstances, I am of the view that it is fair in all the circumstance to allow a further amount of $10,725 to the Applicant. I have calculated this amount by considering the quote provided by him and allowing a further 15% on the amounts costed by the FSP’s expert for demolition, roof and ceiling framing, structural steel, roofing, render and plasterboard, painting, electrical and fire service. This amount is in addition to the $5,000 the FSP has allowed for contingencies. Determination 30. Therefore, for the reasons set out above, and because I consider it fair in all the circumstances as set out above, I determine that the FSP is required to pay the Applicant a cash settlement under the terms and conditions of the policy of an amount of $154,334. 31. I further determine the FSP is to pay to the Applicant interest on the amount of $10,725 at the statutory rate from 4 August 2010 being the date of its IDR decision.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.