Determination 218380

Legal costs declined for lack of insurer approval

FirmFinancial Firm (Unknown - Insurer)
Decided2011-03-11
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed$7,014
SourceAFCA PDF

Summary

The applicants' neighbour's building works destabilised their wall and they engaged a solicitor, whose $7,014.36 invoice the FSP refused for lack of approval. AFCA found implied approval by the FSP's conduct, but limited payment to costs billed after 14 April 2010.

Approval under the policy may be implied by the insurer's course of conduct, and the FSP had constructive notice of the solicitor's engagement from 14 April 2010 without objecting.

Issues

Subjects and remedies

home or building damagepay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 218380 Determination Page 1 of 6 Case number: 218380 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim-Exclusion/ condition 21 February 2010 Background 1. The Applicants hold an Accidental Damage Home Insurance policy with the Financial Services Provider (FSP). The policy was incepted on 7 April 2003 and had an annual expiry date of 7 April 2011. The policy covered the home building up to $1,102,528. 2. On 10 April 2010, the Applicants lodged a claim through their broker advising that their neighbour ’s renovations had destabilised the insured property causing a wall to commence collapsing. 3. The FSP assessed and accepted the claim. The FSP further made payment of two of the three invoices for legal costs. The FSP considers that the first legal invoice was incurred without its approval as required by the policy. Accordingly, under the policy terms and conditions it is not liable to pay same. 4. The Applicants dispute the FSP’s declinature of the outstanding legal invoice on the basis that the works were necessary to limit the damage caused to the property. Summary of Applicants ’ Position 5. The Applicants sought legal advice immediately after damage occurred as a result of their neighbour’s building works and due to the uncooperative attitude of the builder. As a result of the advice the overall size of the claim was reduced by the immediate stabilisation and rebuilding of the property. 6. The FSP failed to provide any initial legal advice and the FSP’s assessor encouraged the Applicants to obtain the advice. Further, the Applicants allege the FSP could not have provided legal advice as quickly as required to protect the property. Determination Case No: 218380 Determination Page 2 of 6 7. The Applicants have enclosed copies of correspondence from which I note the following:  Email dated 28 April 2010 from the assessor to the Applicants confirming that the claim has been accepted. The email further directs the Applicants to arrange for their building consultant and structural engineer to provide a scope of repair works.  Cheque in the sum of $2,200 dated 29 April 2010 in payment of the building consultant’s fees. The cheque was addressed to this expert care of the Applicants’ insurance broker.  Email dated 14 M ay 2010 from a claims consultant to the Applicants’ insurance broker stating the FSP “...are continuing to liaise with the Building Consultant, Structural Engineer and lawyer regarding the reinstatement process”  Email dated 4 June 2010 from the Applicants to the FSP’s assessor. The email notes that the FSP informed the Applicants that the use of the FSP legal team could have been approved by the assessor. The Applicants note this is odd given the claim was not accepted until 21 April 2010 and no mention of the FSP solicitors was ever given. This is despite the conversation with the assessor informing him that the Council, engineer, architect and building consultant had all recommended engaging a solicitor urgently.  Email dated 15 June 2010 from a FSP claims consultant to the Applicants’ insurance broker stating the FSP considered the legal costs “...the Insured’s responsibility and Insurer’s are not liable for these costs, as they were to protect the Insured’s interest in the event that no cover was available through his Insurers.” However, the FSP agreed to the further invoice in principle as it included works to prepare a document to clarify the repairs to be undertaken and protected both the Applicants and FSP interests.  Email dated 8 July 2010 from a FSP claims consultant to the Applicants stating the FSP “...was prejudiced by the expectation of covering fees that had been incurred for a service that [FSP name] had given no authority to.” 8. The Applicant has enclosed the disputed legal invoice in the sum of $7,014.36 for works incurred between 12 April 2010 and 21 April 2010. I note the works performed by the solicitor are all related to discussions with the builder , the neighbour and their legal representatives regarding the property. The works indicates the discussions and correspondence involved obtaining undertakings from the owner and builder, inspection opportunities and methods to stabilise the property. 9. I note the second invoice was for works incurred between 23 April 2010 and 14 May 2010 and the third invoice was for works incurred between 21 May 2010 and 25 May 2010. Case No: 218380 Determination Page 3 of 6 10. The Applicants have enclosed copy of the PDS with a preparation date of 20 November 2008, however the Applicants have since confirmed that the updated PDS dated 9 December 2009 was provided to them. Accordingly this determination will be based on the terms and conditions included within the PDS dated 9 December 2009. 11. The Applicants seek payment of the legal invoice in the sum of $7,014.36. Summary of FSP’s Position 12. The FSP relies on the following policy wording from its PDS with the preparation date of 9 December 2009: “Additional things we will pay for when you have insured your contents ... d. legal fees and courts costs, incurred with our approval.” 13. The FSP relies upon its first assessor report dated 14 April 2010 which states as follows: “...Within 24hrs, major cracking was now apparent in the party wall and daylight could now be seen through the cracks which had been caused as a result of the contractors undermining the insured’s foun dations underneath the party wall causing it to fall away. The insured has appointed an engineer, [name of engineer] and also a Lawyer,[name of lawyer] to act on their behalf.” The FSP considers this as proof the costs were incurred prior to lodging the claim with the FSP and that it did not approve of the engagement of a solicitor. 14. The FSP contends that there is no evidence to support the Applicants’ contention that the engagement of the solicitor assisted in mitigating the loss. 15. The FSP considers that the engagement of solicitors without its consent was to protect the Applicants’ interest in the property. 16. The FSP has paid invoice two in the amount of $6,415.90 and invoice three in the amount of $ 440.35 as a gesture of good will. 17. The FSP has enclosed copies of reports from which I note the following:  First Assessor Report dated 14 April 2010 confirms that the Council has sent an emergency order to the owner of the property to cease works and allow the insured to undertake emergency repairs. The assessor is also aware that a solicitor has been engaged in relation to the matter.  Copies of correspondence from the Applicant’s solicitors to the neighbour’s solicitors arranging for inspections and emergency works to be undertaken.  Email from the assessor to the Applicants dated 7 May 2010 stating “I spoke with [name of lawyer] who is the la wyer dealing on behalf of our Case No: 218380 Determination Page 4 of 6 insured and he has sent the attached letter to the above effect which I feel is warranted. He has also contacted the council on our behalf.”  Sixth Assessor Report dated 19 May 2010 stating “ ...We have requested that [lawyer name] provides a legal document to confirm the work that will be undertaken on the new party wall.”  Seventh Assessor Report dated 9 June 2010 recommends payment of the second legal costs invoice on the basis that the lawyer prepared documentation which protected the Applicant and FSP interests.  Tenth Assessor Report dated 5 July 2010 confirming the reasons for additional costs. The assessor states that “...Delays in establishing l egal rights to the party wall and access by each party which was finally resolved by [lawyer name], the insured’s appointed lawyer. This allowed free access to the neighbouring property by our appointed engineers/consultants and trades to prevent further d amage.”  I note that in subsequent Assessor reports a reference is made to the FSP’s solicitors. However, these solicitors were apparently engaged for recovery purposes and not to resolve the matter giving rise to the claim. Issue 18. Whether the FSP is liable to make payment of the Applicants’ outstanding legal invoice. Reasons for Decision 19. There has been an exchange of material between each party, and I am satisfied each party has had an opportunity to reply to the issues raised. 20. I have read each party’s submissions and materials and will only refer to the relevant submissions and materials raised. 21. I consider the following terms and conditions of the policy as relevant: “What you must do when you make a claim ... - Take all reasonable steps to stop any furth er loss from occurring;” 22. The policy wording clearly states that the FSP will only make payment of legal costs incurred with the FSP’s approval. 23. Accordingly, the question before me is whether the legal costs were incurred with the FSP’s approval. 24. I note the policy wording does not require written approval specifically, further there is no further definition in the policy wording of what constitutes approval. Case No: 218380 Determination Page 5 of 6 Accordingly, I have referred to the plain ordinary English meaning of approval as provided by the Macquarie Dictionary: “ approval ... noun 1. the act of approving; approbation. 2. sanction; official permission. – phrase 3. on approval , for examination, without obligation to buy ... approve1 ... – verb (t) 1. to pronounce or consider good; speak or think favourably of: to approve the policies of the government. 2. to confirm or sanction officially; ratify. 3. Obsolete to demonstrate in practice; show. 4. Obsolete to make good; attest. 5. Obsolete to prove by trial. 6. Obsolete to convict. – verb (i) 7. (sometimes followed by of) to speak or think favourably: his parents didn't approve of her; we'll start at once if you approve. [Middle English aprove(n), from Old French aprover, from Latin approbāre ] – approvable, adjective – approver, noun – approvingly, adverb ” 25. Given the above, I consider that approval may be explicitly provided or implicitly provided by verbal representations or actions. 26. I am satisfied that at no time did the FSP provide explicit approval for the incurring o f legal costs. However, the actions of the FSP’s assessor in requesting works be performed on the FSP’s behalf such as the drafting of legal documents certainly suggests an implicit approval of the works performed. For these reasons I consider that invoices two and three should have been paid not as a good will gesture but as a result of the FSP’s implicit approval. 27. It is necessary to assess whether the works comprising the first invoice were performed as a result of the FSP’s explicit or implicit approval. 28. I note that the evidence indicates the solicitors were engaged prior to the approval of the claim and/or the attendance o f the assessor. This is because the date of loss is recorded as 9 April 2010 and by the time of the assessor’s attendance on 13 April 2010 (with report dated 14 April 2010) the solicitors had been engaged. However, it is clear an emergency order to prevent further damage being caused was required given the imminent collapse of the Applicants’ property. Further, the policy does place an onus on the Applicants to prevent further damage and the Applicants’ actions were consistent with this duty. 29. The solicitor’ s invoice indicates that he commenced billable work on 12 April 2010. Case No: 218380 Determination Page 6 of 6 30. I consider that the FSP received constructive notice of the solicitor’s appointment as of the date of the report being 14 April 2010. Further, there is no evidence of the FSP taking steps to engage its own solicitors despite the obvious need to mediate the legal rights and interests of the parties involved. In this regard, I note the Applicant’s evidence concerning the lack of co operation from the neighbour’s builder. 31. I also note the FSP commenced instructing the Applicant’s solicitors. This suggests a course of action which provided tacit approval of the engagement of solicitors after the FSP received notice of same. 32. I note the assessor’s comments regarding the solicitor resolving the issue of legal rights to the party wall and access to the neighbouring property to prevent further damage. This strongly suggests the solicitor did in fact prevent further damage occurring by resolving the legal issues to enable the necessary works which prevented further deterioration. Further, the documents indicate that the solicitors eventually drafted legal documents requiring rectification works by the other party. Accordingly, it would appear that the engagement of solicitors by the Applicants was in fact beneficial to the FSP. 33. I further note that the engagement of the solicitors was consistent with the Applicants’ duty to mitigate any additional damage or loss to the property. 34. I consider that once the FSP had constructive notice of the engagement of solicitors then failed to engage its own solicitors, failed to provide notice to the Applicants that it did not approve of the legal costs incurred and then instructed the solicitors, the FSP had engaged in a course of conduct which provided tacit approval of the costs incurred. Determination 35. Accordingly, I determine that the FSP should be liable for the first legal invoice as it has provided an approval by its course of conduct. However, the costs should be limited to only those costs incurred after 14 April 2010 being the date the FSP had constructive notice. 36. I determine the FSP should make payment to the Applicants for the portion of legal works billed after 14 April 2010 within 21 days of receiving notice of the Applicants’ acceptance of this Determin ation.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.