Home / Financial Firm (Unknown - Insurer) / Determination 218005
Determination 218005
Storm claim settlement amount and consequential compensation
Summary
The applicant's home was damaged in a March 2010 storm and the insurer cash settled the accepted storm damage. AFCA found most other damage was pre-existing wear and maintenance and the consequential compensation claim excluded, but ordered a further $1,509.86 payment for an underpayment.
Damage from long-term wear, maintenance issues and consequential loss is excluded under the policy, but the insurer must pay the underpaid amount for accepted storm damage.
Issues
- Claim amount dispute primary · upheld
“the FSP appears to have underpaid an amount of $1,509.86 and is required to make payment to the Applicant for the difference”
- Claim denial secondary · not upheld
“the FSP was entitled to limit its liability for the claim to the extent assessed by it”
Subjects and remedies
home or building damagepay claim
Text of the determination
Case No: 218005 Determination Page 1 of 10
Case number: 218005
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
28 February 2011
Background
1. On 6 March 2010 the Applicant‟s home and contents were damaged during a
severe thunderstorm in the area.
2. The Financial Services Provider (FSP) accepted partial liability for a claim
made under the Applicant‟s home insurance policy .The FSP settled the claim
by cash payment in the sum of $12,599 less a $100 policy excess. A payment
of $3,748.90 was made direct to a contractor for works carried out.
Summary of Applicant’s Position
3. His claim is for reinstatement and compensation for all losses.
4. The Applicant maintains the following issues have not been resolved:
Roof and water, flyscreen, window frame, external light and external
furniture damage
5. In addition, the Applicant is claiming:
Compensation of loss of use and enjoyment of parts of the premises due
to non-performance of the FSP contract obligations to effect reinstatement
in a reasonable timely period.
Compensation for income replacement at $200 per hour due to being
subjected to loss of time by FSP, its agents, servants and representatives
caused by non-performance of contract obligations by the FSP.
Summary of FSP’s Position
6. The Applicant reported damage to the roof, plaster, TV aerial, windscreens and
an external light.
7. A number of builders, roofers and building consultants were engaged to
determine an appropriate settlement amount to indemnify the Applicant.
Determination
Case No: 218005 Determination Page 2 of 10
8. All the reports repeatedly comment on the poor condition of the roof and poor
condition of the properly generally, in particular:
The property was generally considered to be in poor condition for its age
The gutters were completely blocked by leaves.
The internal damage to the ceiling in bedroom 3 appeared to be old. The
Applicant had confirmed that there had been a leak in the roof over a year
ago. The roof was fixed, but the ceiling was not.
The guttering in particular, and the house overall lacked adequate
maintenance and this has directly lead to collapse of sections of the eaves
lining and ingress of water.
The roofing contractor found no recent shingle damage. The contractor
removed and replaced 5 shingles which had either snapped or
deteriorated due to erosion. Close inspection revealed the breaks were
old.
9. As there were considerable maintenance issues, wear and tear and general
lack of up keep, the Applicant was cash settled for the damage to the extent
that it was consistent with the storm.
10. A scope of works was prepared for the accepted damage which included;
Bedroom 3 – painting ceiling timber straps and cornice
Bedroom 5 – painting ceiling, timber straps and cornice
Rear elevation (roof) – replace damaged terracotta shingles to lower
storey roof
Rear elevation (eaves) – replace eaves
Rear elevation (roof) – replace damaged terracotta shingles to lower
storey roof from erection and dismantling scaffolding (as alleged by the
Applicant)
Rear entry – repair window sill
11. The following payments were made:
$190 – 2 outdoor chairs and a path light
$12,409 – building repairs based on a quote provided by building
consultant
Garden lights, TV antenna and flyscreens - payment made to contractor
12. The FSP contends the Applicant‟s claim for compensation does not succeed for
the following reasons:
The policy does not cover consequential loss of profit
The Applicant has not provided evidence to substantiate his claim for
compensation.
Case No: 218005 Determination Page 3 of 10
The claim is unfounded as the FSP has carried out its obligations under
the terms of the policy.
The Applicant neglected his responsibilities as a policyholder to maintain
the building in good repair.
13. The FSP relies on the following policy provisions:
“Your responsibilities
…
Take good care of your building and your contents
Wear and tear, poor workmanship and lack of maintenance are not covered under this
policy, so it is important to always maintain your building and contents in good repair
and protect them by always using any security devices installed on the building.
…
This policy does not cover everything
General exclusions – apply to the overall policy
Unless included in additional covers, we will not cover loss, damage or legal liability
caused by:
…
wear and tear and lack of maintenance , including rust, corrosion, deterioration…
…
gradual loss of any kind;
structural defects and faulty workmanship in the construction of the building or
lack of maintenance to the building and/or contents;
…
Consequential losses or loss of profit;
…
Settling building claims
…
Total Building Replacement Cover will not apply if:
we determine the building to be in poor condition at the time of a claim. In this
case, we will determine a reasonable allowance to be deducted from the claim
settlement, based on the condition of the building or that part of the building that
is in poor condition, or
…
Once we accept your claim, we will decide whether to:
repair or rebuild the damaged portion of your building; or
pay you the amount we determine to be the reasonable cost of repairing the
damaged part of your building.
If we decide to pay you, the payment will be based on the amount we would have
expected to pay if the work was authorised and completed by us, and after deducting
any excess which applies to the claim.”
Case No: 218005 Determination Page 4 of 10
Issues
14. Whether the FSP settlement of the claim includes all insured damage arising
from the storm event on 6 March 2010.
15. Whether the Applicant is entitled to compensation for loss of use or part of the
premises and income replacement.
Reasons for Decision
16. The FSP seeks to rely on clauses in the policy to partially settle the claim and
therefore has the burden of establishing on the balance of probabilities that the
terms of the relevant clauses apply to the circumstances of the claim.
17. It is not in dispute that a severe storm occurred in the area of the Applicant‟s
home on 6 March 2010 which caused widespread damage. The FSP engaged
a number of contractors to inspect the Applicant‟s home and report on the
nature and extent of the damage claimed by the Applicant.
18. There has been a full exchange of material between the parties. It therefore is
not necessary to repeat the contents of those reports in full in this determination
except where relevant. The reports are summarised as follows.
19. Building consultant “SBC” – report dated 13 April 2010
Roof over main residence
Main residence:
– Several shingle tiles had slipped out of position
– The roof gutter was partially blocked with leaves
Single story area
– Several broken roof tiles were observed where a section of the
plaster soffit lining had fallen and impacted with the roof
– The perimeter stormwater gutter was completely blocked with leaves
– There were several loosely fixed hip tiles on the south east corner
where cement mortar was loose and missing.
– He found no evidence of physical damage to the tiles caused by hail
impact
– The storm may have caused several loosely fixed hip capping tiles to
slip. However the cement motor bedding had previously failed due to
long term and gradual weathering and deterioration. This was a
maintenance issue.
– The section of plaster soffit lining fell due to the perimeter guttering
overflowing. This occurred as a result of partial leaf blockage
compounded by a build up of hail and ice.
Case No: 218005 Determination Page 5 of 10
– The sarking material had perished as a result of gradual weathering
and normal deterioration.
– He was of the opinion the roof was in need of substantial renovation
which was a maintenance issue.
Internal ceilings – bedrooms 3 and 5 and bathroom
– Water damage to the ceiling in bedroom 3 appeared to be old. The
Applicant advised there had been previous leak about a year earlier.
– The damage to bedroom 5 appeared to be recent.
– The bathroom damage appeared to be recent.
– He was of the opinion water gained entry through gaps in slipped
tiles and due to overflow from the perimeter gutter blocked with
leaves and hail.
Eaves
– The degree of discolouration to the soffit linings and rotten condition
of some sections of the timber trim suggest water had been entering
the eaves over a long period of time.
– He was of the opinion the soffit linings became damaged due to
rainwater overflowing the concealed gutters which were blocked with
leaves.
Garage roof and ceiling
– The box gutter was blocked with leaves. Most of the hip tiles had
slipped down and were piled up against the parapet wall
– There was no evidence of hail damage or breakage of the slipped
tiles.
– The internal damage was due to a consequence of leaf blocked
gutters and slipped hip capping tiles.
Pool pump trellis
– The loss of structural support was due to gradual weathering and
wet and dry rot decay of the timber posts. The fixing of the fence
support to the tree constituted defective works since the tree will
grow and sway in the wind resulting in stresses to the fence posts
which are set in concrete.
Sunroom window sill
– A section of the painted surface of the sill had been impacted with
hail. When pressure was applied he found the timber was severely
rotted.
– The flyscreen door had been damaged by hail.
The consultant concluded that the areas of damage claimed by the
Applicant were pre-existing defects or maintenance issues which had
been highlighted and exacerbated by the hailstorm on 6 March 2010.
Case No: 218005 Determination Page 6 of 10
20. Roofing contractor responsible for carrying out make safe repairs – email dated
11 March 2010.
“… the roof was unaffected by storm damage and has maintenance issues.
Water ingress to the roof was caused by a ridge tile that had slipped from its
position and faulty chimney flashings allowing backwashed water to enter the
roof void. We replaced the ridge back to its original position and inspected the
roof and adjusted some tiles.”
21. Loss assessor report dated 7 June 2010.
The building and garage down pipes have been blocked by large amounts
of leaf debris for a very long time which may involve a number of years.
The guttering in particular and the house overall lacked adequate
maintenance and this lead to the collapse to various sections of the eaves
linings and ingress of rainwater from the storm event.
22. Building services consultant “UBS” – report dated 21 June 2010
A roofing contractor had inspected the lower roof on 15 June and the main
roof on 16 June.
The Applicant claimed that the roofing contractor had damaged the roof
during his inspection on 16 June which was leaking since then to bedroom
1 and 4.
The damage to bedrooms 1 and 4 did not appear to have commenced
recently and was not consistent with t he Applicant‟s claim that the
damage occurred the previous day.
The roofer found no recent shingle damage. The contractor removed and
replaced approximately 5 shingles all of which had either snapped or
deteriorated due to erosion. Close inspection of the cracked edges of
each shingle revealed the breaks were old as they were covered in dirt
and lichen growth.
The consultant concluded that the problems with the roof over bedrooms
1 and 4 were not caused by the roofing contractor as the damage to the
defective tiles was confirmed to be old. The roof at that location had not
suffered any storm damage. Damage to bedrooms 1 and 4 directly related
to rainwater entry through broken and delaminated shingles as a res ult of
general wear over time.
The internal damage did not appear to be fresh.
The consultant estimated the cost to repair the damage in bedrooms 1
and 4 to be $2,640.
23. Roof contractor MRT – report dated 17 June 2010.
“Roof is in poor state of repair. As roof maintenance has seemed to be lacking
over all parts of the roof I feel this is not attributed to storm. Hailstones may have
shifted existing broken terracotta shingles near bedroom rows along Southside of
two story roof causing a piece of eve sheeting to fall down onto roof below and
also break more terracotta shingles on this single storey roof. Approximately forty
(40) shingles need replacing on upper and lower roof.”
Case No: 218005 Determination Page 7 of 10
24. The Panel has been provided with a number of photographs of the Applicant‟s
home including the roof, internal and external damage.
Roof
25. The Applicant‟s premises were inspected by the roofing contractor who carried
out the make safe repairs, building consultant SBC, building consultant UBS
and a second roofing contractor.
26. The Panel considers these contractors were appropriately qualified to report on
the condition of the roof of the Applicant‟s premises and the l ikely cause for that
condition.
27. Significantly, the contractors reported no evidence of storm damage to the roof.
Snapped shingles had been found. However inspection of the cracked edges of
each shingle revealed the breaks were covered in dirt and lichen growth
leading to the conclusion that the breaks were old. Several terracotta tiles had
slipped out of position. The mortar on which the hip capping tiles were fixed had
failed due to long term weathering and deterioration. A significant number of
shingles were cracked due to fatigue or foot traffic.
28. The Applicant‟s assertion that shingles had been damaged when the roof was
inspected by a roofing contractor was investigated. Inves tigation of the incident
found that the problems with the ingress of water was not caused by the roofing
contractor as the tiles were old and the internal damage did not appear to have
occurred recently.
29. The Panel is of the opinion the evidence leads to the conclusion that the
condition of the roof was not caused by the March 2010 storm, but was due to
gradual wear and deterioration over time
30. However an allowance was made in the payment to the Applicant for the cost of
replacing the terracotta roof tiles to the lower story roof damaged by the falling
eaves.
Eaves
31. The evidence established that roof tiles above the rear eaves had become
dislodged prior to the March 2010 storm exposing the eaves to hail and rain.
The degree of discoloration of the soffit linings and rotten condition of some
sections of the timber trim led to the conclusion the water had been entering the
eaves over a period of time and not from a single storm event.
32. It was reported that other areas of plaster lined soffit was also damaged by
water penetration.
33. The gutters were reported to be blocked with leaf debris which blocked the
gutter allowing water to overflow into the eaves.
34. Based on this evidence, the Panel is of the opinion the damage to the eaves
was not caused directly by the storm, but by ongoing problems with the roof
and guttering.
Case No: 218005 Determination Page 8 of 10
35. However, an allowance has been made in the payment to the Applicant for the
cost of replacing a section of the upper story eaves lining.
Window sill
36. The evidence established that the paint on the window sill was affected by the
hail. However the underlying timber was rotted.
37. The policy does not cover deterioration or gradual damage of any kind.
38. In these circumstances, the FSP is not required to pay the cost of replacing the
timber window sill.
39. However the FSP advised that it accepted liability for rectification of the window
and obtained a quote in the sum of $1,200 for this work. The payment to the
Applicant included an allowance for this sum.
Assessed damage
40. According to the evidence, damage to bedrooms 1 and 4 arose as a result of
rainwater entry through broken and delaminated shingles over time.
41. The policy provides cover for the event “storm”. “Event” is defined by the policy
to mean „A single occurrence”. As the damage has been ongoing over time, the
Panel accepts that the damage to bedrooms1 and 4 does not fall within the
cover provided by the policy.
42. The FSP accepted damage to the interior of the home according to a scope of
works prepared by the consultant UBS. Those works included:
Bedroom 3 replacement sections of plaster ceiling
Bedroom 5 replacement section of plaster ceiling
Rear elevation replace terracotta shingles to lower story roof
Rear elevation replace sections of upper story eaves
Rear elevation replace any terracotta shingles damaged from erection
/dismantling scaffolding
Rear entry repair window sill.
43. The consultant provided an estimate for these works in the sum of $11,209.
The FSP increased this sum to include the cost of rectifying the window
damage.
44. The FSP confirmed a payment of $190 which included two outdoor chairs and a
path light had been included in the remittance issued to the Applicant.
45. A payment in the sum of $12,599 was made to the Applicant which included the
estimates for the cost of rectifying the damage according to the scope of works.
Case No: 218005 Determination Page 9 of 10
46. The FSP confirmed that a payment of $3,748.90 had been made direct to a
supplier for electrical works, replacement of garden lights, TV antenna,
scaffolding and flyscreens.
47. The Applicant has not provided any evidence or expert reports to show that any
of the additional damage for which the FSP declined indemnity was a result of
the claimed storm, but rather relies on his own statement that the FSP is
responsible for rectifying all damage claimed.
48. In the absence of any evidence to the contrary, the Panel is inclined to rely on
the expert reports provided by the various building experts.
49. Based on the forgoing analysis of the material presented to FOS, the Panel is
of the opinion that the extent of the damage accepted by the FSP less the
policy excess was fair in all the circumstances and according to the terms of the
policy.
50. The policy provides that the FSP may decide whether to repair the damage or
pay the policyholder the amount it would cost the FSP to repair the damage.
The Panel therefore accepts that the FSP was entitled to pay to the Applicant
the cost of repairing the insured damage. The FSP based the costing on
estimates obtained from contractors and may be regarded as reliable.
51. The Panel has had some difficulty in reconciling the actual amounts paid. The
cash payment already made to the Applicant was based on the scope of works
prepared by contractor UBS and this appears correct. However the FSP has
advised that it has also made a payment direct to the electrical contractor for
$3,740.90, whereas the quoted cost of works was $5,446.76. The difference
appears to be the result of the contractor‟s recommendation to cash settle
certain items claimed.
52. Although the FSP has allowed a cash payment of $190 for these items, the
difference noted between the contractor‟s quote and the amount paid to the
contractor was actually $1, 697.86. On this basis the FSP appears to have
underpaid an amount of $1,509.86 and is required to make payment to the
Applicant for the difference.
Compensation
53. The policy provides that the FSP will not cover loss or damage caused by
consequential losses or loss of profit.
54. The Applicant‟s claim for compensation for loss of enjoyment and use of parts
of the house and compensation for loss of time may reasonably be regarded as
caused as a consequence of the claim.
55. In view of the policy exclusion, the Panel is therefore unable to favourably
consider the Applicant‟s claim for compensation.
Case No: 218005 Determination Page 10 of 10
Determination
56. For these reasons, the Panel determines the FSP was entitled to limit its liability
for the claim to the extent assessed by it. However as its payments to the
Applicant in the sum of $12,409 plus the payment in the sum of $3,740.90
made to the contractor appear to have not fully discharged its obligations, it is
required to make a further cash payment of $1,509.86 in order to fully meet its
obligations.
57. The Panel further determines the FSP was entitled to pay to the Applicant the
cost of the accepted insured damaged.
58. The Panel also determines that the FSP was entitled to deny the Applicant‟s
claim for compensation for his consequential losses.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.