Text of the determination
217736 Determination 1 of 6
DETERMINATION
CASE NO: 217736
Home Building – service of FSP – repair rectification
– Terms of Reference 8.7a) and 9.3b)(i) (ii)
SUMMARY OF FACTS
1. The applicant insured her home building for $416,900 against loss or damage
caused by insured events. The policy commenced on 31 December 2001 and
had been renewed annually to 31 December 2010.
2. On or about 17 November 2008, the balcony of the insured property was
damaged during a storm. The Financial Services Provider (FSP) accepted
liability and repairs were commenced in about May 2009. However, the
applicant states that since that time repairs have been protracted and have not
been carried out in a professional manner and further rectification work is
required.
3. The FSP agrees that the repairs to the balcony are unsatisfactory, and it has
put the contractor on notice to complete the necessary rectification work.
4. The applicant is seeking to have the repair rectification supervised by a
neighbour, a tiler and that the FSP compensate that person for all expenses
incurred. She is also seeking compensation to the amount of $150,000 for
invasion of her privacy rights and water and power costs incurred by
contractors when working on her property.
ISSUES IN DISPUTE
5. Whether the applicant in entitled to appoint her nominee as the supervisor of
the repair rectification of the balcony of her house; and
6. Whether the applicant is entitled to compensation for invasion of her privacy
rights.
RELEVANT POLICY PROVISIONS
“Product Disclosure Statement
...
Significant features and benefits
...
Home insurance provides cover for the following.
Loss or damage to your home caused by an event listed under „Home insurance
cover‟...up to the sum insured shown on your certificate.
...
General exclusions applicable to your policy
You are not covered under any section of this policy for damage, loss or liability caused by,
arising from or involving any of the following.
General exclusions applicable to your policy
...
x Consequential loss of any kind.
...
217736 Determination 2 of 6
Paying your claim
How we pay a claim for your home
Where we pay a claim for your home, we will choose to do one of the following:
repair your home,
replace the damaged portion of your home,
compensate you the amount it would have cost us for repair or replacement.
....”
TERMS OF REFERENCE
“8.7 Recommendations and Determinations
a) Each Recommendation and Determination:
...
(ii) may either reach:
(A) a conclusion about the merits of the Dispute; or
(B) the view that, given the procedures adopted by FOS, it would not be
appropriate for FOS to reach any conclusion as to the merits of the
Dispute.;
...
9.3 Other compensation
...
b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for non-financial loss but
only where:
(i) an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant‟s expectation of
enjoyment or peace of mind has occurred; or
(ii) in the case of a Dispute pertaining to an individual‟s privacy rights – injury
has occurred to the Applicant‟s feelings or humiliation has been suffered by
the Applicant.
The maximum amount of compensation for non-financial loss will be $3,000 per
claim made in the Dispute.
c) Notwithstanding paragraphs 9.3 a) and b), FOS will not provide compensation
for:
(i) consequential financial loss; or
(ii) non-financial loss,
in a Dispute arising as a result of a claim on a General Insurance Policy that
expressly ex cludes such liability.”
REASONS FOR DECISION
7. There has been an exchange of material which the parties rely on. Each party
has had access to the material on which the other party bases its case. As a
consequence, I propose to only make reference to the material relevant to the
decision.
The Applicant’s Submission
8. The balcony of her home was damaged during a storm on 17 November 2008.
The FSP appointed a contractor to carry out repairs. However, the completed
repairs were not of a satisfactory standard leaving the balcony dangerous and
allowing rainwater to enter the adjoining bedroom.
217736 Determination 3 of 6
9. The repairs were not commenced until 25 May 2009 and from that date, she
has experienced problems with the standard of the repairs. The tiles are
uneven and there are large gaps between the tiles; sand washes from the tiles
when it rains, and there are holes and cracks everywhere and it is unfit to walk
on.
10. She engaged a tiling expert to inspect the tiling on her balcony, and she
requests that this person be appointed to supervise the rectification works. The
FSP has offered to rectify the faulty repairs, but she has lost confidence, trust,
and faith in the contractor to complete the rectification repairs to a satisfactory
standard.
11. The FSP has failed to handle her claim effectively and efficiently which has
resulted in the rectifications of the repairs that had been carried out. During the
period of repairs, various tradespeople engaged by the contractor have been
arrogant, rude, racist, reckless, and insulting to her over a period of nearly nine
months.
12. The actions, or inaction, of the FSP and its contractor have caused her distress,
grievous bodily harm, sickness, stress, nerve problems and trauma and she
contends that she is entitled to compensation. She is claiming the amount of
$150,000, or nearest offer, for mental and physical injury and including the cost
of water and electricity used by the contractor in the repair of the balcony.
The FSP’s Submission
13. A claim was lodged on 17 November 2008 for damage sustained to the balcony
of the insured property. Following an inspection by a building consultant, a
contractor was appointed to carry out repairs to the balcony.
14. Repair work was commenced in May 2009 during which it was discovered that
the stairway to the balcony had also sustained damage.
15. On 30 August 2009, the applicant contacted it to advise that there were
problems with the tiling work including dumping cement sludge in her garden. It
arranged for the contractor to attend to the applicant‟s concerns.
16. Following the rectification work to the tiles, the applicant advised that there
were still problems with the tiling including uneven edges, and the tiling was not
straight. It again contacted the contractor to attend the applicant‟s property and
address the applicant‟s concerns.
17. On 22 February 2010, the applicant contacted it requesting an inspection of the
slate tiles. The concern was that following rainfall, the tiles had allowed water to
enter the applicant‟s residence causing damage to a bedroom and lounge
room.
18. It has agreed to have further rectification repairs carried out to the balcony.
19. It concedes that rectification work carried out by its contractor has not gone
smoothly and significant further work has had to be carried out to bring the
repairs to an acceptable standard. The length of time taken to affect these
repairs has been exacerbated due to the discovery of additional damage to the
balcony and adjacent stairs which required further investigation and approval.
217736 Determination 4 of 6
20. It submits that since 7 July 2010, its contractor has stood ready, willing and
able to finalise repairs to the applicant‟s balcony, however the applicant has, to
date, failed to provide consent for these repairs to take place.
21. The applicant has made numerous allegations of racial vilification, bullying and
other colourful descriptions of it and the contractor‟s behaviour which are not
supported by any independent evidence. It denies that its staff intimidated,
bullied or racially vilified the applicant. It understands that the contractor also
denies the allegations made by the applicant about the conduct of its
employees.
22. In the absence of independent evidence supporting these numerous and
general allegations, it submits that such allegations should not be upheld.
Consideration of each party’s submission
Repairs to the Balcony
23. The balcony of the applicant‟s house was damaged in a storm on or about 17
November 2008, however, repairs did not commence until late May 2009 and
are yet to be completed to a satisfactory standard.
24. The FSP accepts that the original repairs carried out were unsatisfactory and
had the contractor complete rectification work. However, the rectification repairs
have also not been satisfactory and significant additional work has to be carried
out to bring the repairs up to an acceptable standard.
25. The FSP contends that since 7 July 2010 its contractor has been ready to
finalise repairs to the applicant‟s balcony , but the applicant has failed to provide
consent for the repairs to be carried out.
26. Although the appointed contractor‟s repair work has been unsatisfactory
requiring rectification work, which was also of an unsatisfactory standard, the
FSP has continued to engage this contractor. The applicant has stated that she
does not have confidence in the contractor completing the repairs to a
satisfactory standard.
27. On the evidence submitted to me, I am satisfied that the applicant has grounds
for this lack of confidence.
28. The applicant has requested that her neighbour, a tiler, be appointed to
supervise the rectification work to the balcony. However, no evidence has been
submitted that this person is licensed or qualified to carry out this responsibility.
29. I consider that the rectification work should be supervised by a suitably
independent, licensed and qualified building consultant who would have the
responsibility of approving the completed rectification work.
Conclusion
30. Accordingly, I find that the FSP is to consult with the applicant on the
appointment of a qualified building consultant to supervise the rectification work
to the balcony. I find that, without evidence to the contrary, the applicant‟s
neighbour, the tiler, would not be an acceptable appointment.
31. If the parties cannot come to an agreement on the appointment of a supervisor,
each party may submit to me the name of their nominee together with details of
217736 Determination 5 of 6
the qualifications and experience of that nominee, and I will make a
determination in that regard.
The claim for water and power costs
32. The applicant makes a claim that while performing work at her home, the
contractors have used her water and her electricity to perform rectification
works. If this is in fact the case, I am satisfied that these are expenses that
should be included as part of the cost of rectification and should be met by the
FSP.
33. The applicant has submitted a number of accounts from the water and power
authorities. The accounts do not provide a breakdown of the amounts
associated with th e applicant‟s home use and the amounts associated with the
rectification work.
34. It is a matter of settled law that the applicant bears the onus of proof in
establishing her loss leading to coverage under the policy.
Conclusion
35. In the absence of conclusive proof as to the water and power costs that arise
from the rectification work, I am not prepared to make a determination in this
regard.
The Claim for Compensation
36. The applicant has submitted a claim for compensation for the amount of
$150,000, or near offer, for the delay in the completion of the repairs to her
balcony because of the sub-standard repair work and subsequent rectification
work. She also contends that she was orally vilified by some of the FSP‟s
employees and contractor‟s workers.
37. The Clause 9.3 b)(i) of the Terms of Reference of the Financial Ombudsman
Service Provides:
b) “ Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for non-financial
loss but only where:
(i) an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant‟s expectation
of enjoyment or peace of mind has occurred; ...
The maximum amount of compensation for non-financial loss will be
$3,000 per claim made in the Dispute.”
38. The applicant has not submitted any evidence in support of her contention that
she was racially vilified, was bullied and incurred other oral insults from the
FSP‟s employees and the contractor‟s workers. Without any evidence in
support of her contention, I am satisfied that I cannot make a determination for
this part of her claim for compensation.
39. However, the applicant has also submitted a claim for compensation for the
delays in completing the repairs to her balcony resulting in anxiety, stress,
frustration, inconvenience, loss of amenity and enjoyment of using the balcony.
217736 Determination 6 of 6
40. There has been a period of twenty months from the date of the damage to the
balcony, that is, 17 November 2008 to July 2010, the date when the FSP and
its contractor were available to complete the rectification works. Although the
discovery of additional damage to the balcony delayed the repairs works, I
consider the period of time in handling this claim to be excessive. Further, the
required rectification works will be the third attempt to complete the repairs to a
satisfactory standard. In addition, repairs to the floor of the balcony were so
badly constructed that rainwater was able to escape into the bedroom and
lounge room of the house causing damage to the carpets.
Conclusion
41. The applicant submitted a total claim for compensation for the amount of
$150,000. However, the Terms of Reference limit any payment of
compensation to the amount of $3,000.
42. The FSP contends that FOS should not make a determination for non-financial
loss where there has been an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with the
ap plicant‟s expectation of enjoyment or peace of mind. However, the FSP has
not submitted any arguments in support of this position.
43. On the evidence submitted, I find that the applicant has suffered:
“an unusual degree or extent of physical inconvenience, ti me taken to resolve
the situation or interference with the Applicant‟s expectation of enj oyment or
peace of mind....”
DETERMINATION
44. Accordingly I determine that the FSP is to pay the applicant the amount of
$1,500 under clause 9.3 (b)(i) of the Terms of Reference.