Storm claim settlement amount: cash settlement versus applicant's preferred builder quote
Text of the determination
Case No: 217450 Determination Page 1 of 7
Case number: 217450
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
24 January 2011
Background
1. On 22 March 2010 the Applicant‟s home suffered damage during a severe
storm in the area. The home had only recently been constructed and occupied
by the Applicant.
2. The Financial Services Provider (FSP) accepted liability for a claim made by
the Applicant under his home insurance policy for damage arising from the
storm. The Applicant obtai ned a quotation in the sum of $132,516 from the
original builder to repair the damage. The FSP obtained a quotation in the sum
of $87,840.80 from an alternate contractor. Following a review of the two
contractor‟s estimates, the FSP revised the quotation by its pref erred contractor
to $96,408.80.
3. The Applicant contends that the FSP‟s nominated contractor‟s estimate does
not include all the damage. He submits that as the home was a quality
constructed home which had only recently been completed, he requires the
repairs to be carried out by his preferred builder.
4. As the Applicant required his preferred contractor to carry out the works , the
FSP offered settlement of the claim by cash payment of the $96,408.80 to the
Applicant.
5. The Applicant maintains that he is entitled to payment of the full sum of his
contractor‟s quotation.
Summary of Applicant’s Position
6. The house was only six months old at the time of the loss.
7. The estimate provided by the original builder amounted to $132,500 compared
to a contractor chosen by the FSP who quoted $87,000 since revised to
$96,408.80.
8. It is common sense that the builder who built the home, bearing in mind that it
was a new home when the damage occurred, should be the person who
restores the property to its original condition.
Determination
Case No: 217450 Determination Page 2 of 7
9. The quotation by the FSP‟s preferred builder does not cover all aspects of the
remedial work necessary to restore the property which is reflected in its
estimate.
10. The Applicant provided a list of the respective costings to demonstrate a
number of items contained in the original builder‟s estimate are not included in
the FSP‟s preferred builder‟s estimate with a difference in cost of $61,000.
11. The Applicant states the FSP erroneously claims he is seeking indemnity for
the cost of replacement of the bamboo flooring in unaffected areas of the home
to achieve a match. He states that the only bamboo floorings is as described in
the original builder‟s estimate , and is limited to the family room, kitchen, dining,
pantry, and linen cupboard. There is no bamboo flooring in the lounge room or
anywhere else.
12. The original builder carried out an extensive examination of the whole of the
roof area. No one else has done so.
13. The FSP‟s preferred contractor re -inspected the premises in his presence to
verify the allowance in his estimate for roof repairs. The inspection was cursory
and lasted only a few minutes. It is unrealistic to accept the extent of damage
could be assessed in such a short time particularly as no measurements or
notes were taken.
14. The Applicant submits that if all the items referred to in the breakdown of the
costi ngs by the original builder were included in the list prepared by the FSP‟s
preferred builder, the two would be closer and result in a figure mid-way
between the amount offered by the FSP and the amount claimed by him.
15. This together with an indemnity from him in relation to future remedial work
would result in a fair and equitable settlement.
Summary of FSP’s Position
16. The FSP has identified the claim in relation to flooring and to the roof as the
main items of contention.
17. The FSP states the Applicant is seeking to be indemnified for costs associated
with replacing bamboo flooring to unaffected areas of the home to achieve a
match.
18. The policy clearly limits replacement of damaged fixed flooring to where the
loss or damage occurred. The policy further provides that payment will not be
made to create a uniform effect throughout the home.
19. The FSP submits that it is only required to replace flooring in the rooms which
sustained damage.
20. The FSP submits there is no dispute that all the roof sheets were not damaged
as a result of the storm. The dispute has arisen as to whether or not it is
required to indemnify the Applicant for costs associated with replacing all the
roof sheets in order to achieve a match.
Case No: 217450 Determination Page 3 of 7
21. The FSP submits that its obligation according to the terms of the policy is to
indemnify the Applicant for the cost of repairing the damaged roof sheets
arising from the storm.
22. The Applicant is seeking to have his preferred builder repair the damage.
Settlement of the claim by a cash payment will provide the Applicant with the
opportunity to appoint his preferred builder to undertake the repairs.
23. The FSP submits that both quotations are descriptively comparable and only
the final cost is in dispute. No evidence has been provided to support the
allegation that repairs cannot be properly carried out by its nominated builder.
24. As such, the FSP refutes the Applic ant‟s allegation that only his preferred
builder is able to properly repair his home and the FSP maintains that its
nominated builder has the necessary qualifications and expertise to do so.
25. The settlement offer in the sum of $96,408.80 accurately reflects the extent of
its liability and is fair and reasonable. The Applicant has not presented any
compelling evidence to justify his assertion that $132,516 is required to
complete the damage related repairs.
26. The FSP relies on the following policy provisions:
“ Paying your claim
How we pay a claim for your home
Where we pay a claim for your home, we will choose to do one of the following:
repair your home,
replace the damaged portion of your home,
compensate you the amount it would have cost us for repair or replacement.
…
Matching building materials
Where we repair your home we will try to return your home to the same condition as
when new, or when last renovated by matching building materials as far as we can.
Where we cannot achieve an exact match, we will use materials that match the
damaged or lost materials as near as possible in our opinion. We will only do this to
the room where the loss or damage occurred.
We will not pay for matching building materials in order to create a uniform effect
throughout your home .”
Issues
27. Whether the estimate provided by the FSP‟s nominated builder includes all
insured damage, and
Case No: 217450 Determination Page 4 of 7
28. Whether the FSP is entitled to settle the claim by cash payment to the
Applicant.
Reasons for Decision
29. When making a claim under an insurance policy, the responsibility rests with
the policyholder to establish on the balance of probabilities that the damage
claimed falls within the terms of cover provided by the policy.
30. The history of this matter is known to both parties. I therefore do not intend
recounting the chronology in this determination except where relevant.
31. The central issue in dispute is the difference between the estimate prepared by
the Applicant‟s preferred builder , and that prepared by the FSP‟s nominated
builder.
32. The Scope of Works (SOW) provided by the FSP‟s nominated builder dated 7
July 2010 carrying an estimate of $87,484.80 sets out the remedial works for
each area of the house. The SOW includes the following:
External
3) Strip damaged Colorbond roof sheeting and flashings
5) Supply and install Colorbond roof sheeting and flashings to
match if available
Kitchen/Dining/family room
3) Strip damaged bamboo floor
4) Supply and install bamboo floor to match existing if available
33. A document issued by the Applicant‟s preferred build er dated 8 September
2010 contains a breakdown of costing relating to storm damage to the
Applicant‟s home with a total of $132,516 inclusive of GST.
34. The Applicant by letter dated 8 September 2010 prepared a comparative list of
costings between the two contractors as follows.
“ [Applicant’s builder] [FSP’s builder]
Remove roof and replace $56,815 $47,357.85
Remove and replace timber floor 16,638 19,921.50
Replace and restrap ceilings 5,720 4,742.80
Remove and replace alfresco cabinets 5,220 3,119.40
Remove kitchen cupboard and replace 1,341 no provision
Remove and replace wall oven 4,661 3,430
Airconditioning 2,956 2,020.55
Case No: 217450 Determination Page 5 of 7
Remove and replace carpets 5,434 3,826.30
Remove and replace damaged skirtings 1,155 no provision
Scaffolding 10,197 no provision
Bins 3,267 no provision
Plumber 1,031 no provision
Electrician 3,176 no provision
Cleaning 3,575 no provision
Painter 8,580 3,091.40
Insurance 2,750 no provision
Totals 132,516 87,484.80
(inclusive of GST) (GST not known)
35. The FSP sought clarification from its nominated builder in relation to the items
referred to as „no provision‟. The builder confirmed:
“The only items we have not included in our quote is the cleaning of the house
after repairs have been carried out and the removal of the kitchen cupboard as
there was no damage shown to me during inspection. We have not allowed for
indemnity insurance as we are waiting on confirmation on th e job.”
36. The FSP then adjusted its nominated builder ‟s estimate to $96,408.80 by
including items as follows:
“Quoted amount [FSP’s builder] $87,484.80
Kitchen cupboard (Applicant’s builder] $ 1,341.00
Cleaning (Applican t’s builder] $ 3,575.00
Insurance (Applicant’s builder] $ 2,750.00
Oven $ 1,258.00 ’
37. Based on the material presented to me, the remaining items referred to by the
Applicant have been allowed for by the FSP‟s builder.
38. In relation to the flooring, I no te the FSP‟s builder‟s SOW include d provision for
replacing the bamboo flooring in the kitchen, dining and family rooms. The
Applicant‟s builder‟s breakdown of costings included removal and replacing
existing timber floor. The breakdown provided to me does not specify the rooms
in which the flooring will be replaced.
39. The Applicant by letter dated 8 November 2010, stated that the only bamboo
flooring in the property is contained in the family room, kitchen, dining, pantry
and linen cupboard and that it was this flooring that his builder quoted to
replace. I note the sum quoted by both builders for replacement of the flooring
is $16,638 (Applicant‟s builder) and $19,921.50 (FSP‟s builder).
40. In these circumstances, it is apparent that both builders, apart from the pantry
and linen cupboard, quoted for essentially the same works in relation to the
bamboo flooring. The evidence therefore does not support the FSP‟s assertion
the Applicant is seeking to replace undamaged bamboo flooring to match the
new materials.
Case No: 217450 Determination Page 6 of 7
41. In relation to the roof, the FSP‟s contractor quoted to strip damaged Colorbond
roof sheeting and supply and install roof Colorbond sheeting to match existing if
available. The Applicant‟s builder quoted to “remove Colorbond roof and
replace”. I note a sign ificant gap exists between the two costings being
$47,357.85 for the FSP‟s builder and $56,815 for the Applicant‟s builder.
42. I am mindful of the Applicant‟s argument that the FSP‟s contractor‟s inspection
of the roof was cursory, and that his own builder carried out an extensive
examination. However, I have not been provided with a detailed report from any
party on the extent of damage caused by the storm to the roof of the Applicant‟s
property, and therefore must rely on the material available to me.
43. As t he FSP‟s contractor referred to replacing only damaged roofing and with a
variation of about $9,457.15 in the two estimates for this component of the
works, it is reasonable to conclude that the storm damage did not extend
across the entire roof of the App licant‟s home.
44. The policy provides that the FSP will pay to replace the damaged portion of the
home. The policy further provides that when an exact match cannot be
achieved, the FSP will not pay for matching building materials to create a
uniform effect throughout the home. In these circumstances and in the event
the new roofing material does not match the undamaged roofing material; the
FSP is not liable for replacement of the entire roof to create a uniform
appearance.
45. For these reasons, I am persuaded that the FSP‟s contractor‟s SOW includes
all damage to the Applicant‟s building caused by the storm. Although a
significant difference exists between the estimates submitted by the
contractors, the FSP is entitled to select the lower of the quotations provided
that the contractor is appropriately qualified to carry out the works in a
professional and workmanlike manner, and is prepared to carry out those
works. I have not been provided with any evidence to show the FSP‟s
nominated contractor does not satisfy that criteria.
46. The policy provides the FSP with the option to repair the home, or compensate
the policyholder the amount it would have cost the FSP to repair the home. The
FSP states that the offer to settle the claim by payment in cash to the Applicant
provided the Applicant with the opportunity to appoint his preferred builder.
47. In the alternative, should the Applicant agree to accept the FSP‟s contractor,
the Applicant is protected by the FSP‟s customer charter. The customer charter
provides that where the FSP authorises repairs to the property, the FSP will
guarantee for life the quality of workmanship and materials used in the repair of
the property.
48. The policy further provides cover for temporary accommodation expenses if the
home becomes unliveable following loss or damage. In the event the home is
unliveable during the rectification works, the Applicant is entitled to
reimbursement of any temporary accommodation costs incurred for similar
accommodation.
49. The claim was lodged with the FSP on 22 March 2010. The FSP‟s adjuster did
not attend the property until about six weeks later. The adjuster informed the
FSP that the Applicant wished to have the original builder carry out the
remedial works. The Applicant submitted an estimate from his preferred builder
Case No: 217450 Determination Page 7 of 7
in May 2010. The FSP required a second quote which was not obtained until
July 2010 being approximately four months after the loss was reported to it.
There followed a number of communications resulting in the FSP adjusting its
nominat ed builder‟s estimate to take into account a number of items included in
the original builder‟s estimate . The Applicant has therefore been
inconvenienced for an excessive period of time as a result of the delay by the
FSP in obtaining a second quote.
50. Section 57 of the Insurance Contracts Act 1984 (the Act) provides that where
an insurer is liable to pay to a person an amount under a contract of insurance,
the insurer is also liable to pay interest on the amount to that person.
51. In the circumstances, pursuant to section 57 of the Act, I am awarding interest
on the sum payable of $96,408.80 from 22 April 2010 to 23 September 2010
being the date the FSP remitted the payment to the Applicant at the rate of
8.44% being $3,390.37
Determination
52. Based on this analysis of the material I conclude that the Applicant has not
discharged the onus that rests with him to show that he is entitled to have the
FSP appoint his preferred contractor to carry out the remedial works on his
house
53. Accordingly I determine that the FSP‟s liability for the claim is limited to the sum
of $96,408.80. I further determine that the FSP was entitled to settle the claim
by payment of this sum to the Applicant should he choose to have his preferred
builder carry out the works.
54. I further determine the FSP pay interest on the sum payable at the rate of
8.44% from 22 April 2010 to 23 September 2010 being $3,390.37.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.