Determination 217450

Storm claim settlement amount: cash settlement versus applicant's preferred builder quote

FirmFinancial Firm (Unknown - Insurer)
Decided2011-02-23
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed$132,516
SourceAFCA PDF

Summary

After a storm damaged his newly built home, the applicant rejected the FSP's cash settlement of $96,408.80 and sought $132,516 to have his preferred builder carry out the repairs. AFCA limited the FSP's liability to $96,408.80, which had already been paid, and ordered interest of $3,390.37 for the delay.

The policy allows the insurer to choose repair or cash compensation and to pay only for the damaged portion without uniform-appearance matching, and the insurer may select the lower qualified contractor's quote.

Issues

Subjects and remedies

home or building damagenatural disasterpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 217450 Determination Page 1 of 7 Case number: 217450 General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim amount 24 January 2011 Background 1. On 22 March 2010 the Applicant‟s home suffered damage during a severe storm in the area. The home had only recently been constructed and occupied by the Applicant. 2. The Financial Services Provider (FSP) accepted liability for a claim made by the Applicant under his home insurance policy for damage arising from the storm. The Applicant obtai ned a quotation in the sum of $132,516 from the original builder to repair the damage. The FSP obtained a quotation in the sum of $87,840.80 from an alternate contractor. Following a review of the two contractor‟s estimates, the FSP revised the quotation by its pref erred contractor to $96,408.80. 3. The Applicant contends that the FSP‟s nominated contractor‟s estimate does not include all the damage. He submits that as the home was a quality constructed home which had only recently been completed, he requires the repairs to be carried out by his preferred builder. 4. As the Applicant required his preferred contractor to carry out the works , the FSP offered settlement of the claim by cash payment of the $96,408.80 to the Applicant. 5. The Applicant maintains that he is entitled to payment of the full sum of his contractor‟s quotation. Summary of Applicant’s Position 6. The house was only six months old at the time of the loss. 7. The estimate provided by the original builder amounted to $132,500 compared to a contractor chosen by the FSP who quoted $87,000 since revised to $96,408.80. 8. It is common sense that the builder who built the home, bearing in mind that it was a new home when the damage occurred, should be the person who restores the property to its original condition. Determination Case No: 217450 Determination Page 2 of 7 9. The quotation by the FSP‟s preferred builder does not cover all aspects of the remedial work necessary to restore the property which is reflected in its estimate. 10. The Applicant provided a list of the respective costings to demonstrate a number of items contained in the original builder‟s estimate are not included in the FSP‟s preferred builder‟s estimate with a difference in cost of $61,000. 11. The Applicant states the FSP erroneously claims he is seeking indemnity for the cost of replacement of the bamboo flooring in unaffected areas of the home to achieve a match. He states that the only bamboo floorings is as described in the original builder‟s estimate , and is limited to the family room, kitchen, dining, pantry, and linen cupboard. There is no bamboo flooring in the lounge room or anywhere else. 12. The original builder carried out an extensive examination of the whole of the roof area. No one else has done so. 13. The FSP‟s preferred contractor re -inspected the premises in his presence to verify the allowance in his estimate for roof repairs. The inspection was cursory and lasted only a few minutes. It is unrealistic to accept the extent of damage could be assessed in such a short time particularly as no measurements or notes were taken. 14. The Applicant submits that if all the items referred to in the breakdown of the costi ngs by the original builder were included in the list prepared by the FSP‟s preferred builder, the two would be closer and result in a figure mid-way between the amount offered by the FSP and the amount claimed by him. 15. This together with an indemnity from him in relation to future remedial work would result in a fair and equitable settlement. Summary of FSP’s Position 16. The FSP has identified the claim in relation to flooring and to the roof as the main items of contention. 17. The FSP states the Applicant is seeking to be indemnified for costs associated with replacing bamboo flooring to unaffected areas of the home to achieve a match. 18. The policy clearly limits replacement of damaged fixed flooring to where the loss or damage occurred. The policy further provides that payment will not be made to create a uniform effect throughout the home. 19. The FSP submits that it is only required to replace flooring in the rooms which sustained damage. 20. The FSP submits there is no dispute that all the roof sheets were not damaged as a result of the storm. The dispute has arisen as to whether or not it is required to indemnify the Applicant for costs associated with replacing all the roof sheets in order to achieve a match. Case No: 217450 Determination Page 3 of 7 21. The FSP submits that its obligation according to the terms of the policy is to indemnify the Applicant for the cost of repairing the damaged roof sheets arising from the storm. 22. The Applicant is seeking to have his preferred builder repair the damage. Settlement of the claim by a cash payment will provide the Applicant with the opportunity to appoint his preferred builder to undertake the repairs. 23. The FSP submits that both quotations are descriptively comparable and only the final cost is in dispute. No evidence has been provided to support the allegation that repairs cannot be properly carried out by its nominated builder. 24. As such, the FSP refutes the Applic ant‟s allegation that only his preferred builder is able to properly repair his home and the FSP maintains that its nominated builder has the necessary qualifications and expertise to do so. 25. The settlement offer in the sum of $96,408.80 accurately reflects the extent of its liability and is fair and reasonable. The Applicant has not presented any compelling evidence to justify his assertion that $132,516 is required to complete the damage related repairs. 26. The FSP relies on the following policy provisions: “ Paying your claim How we pay a claim for your home Where we pay a claim for your home, we will choose to do one of the following:  repair your home,  replace the damaged portion of your home,  compensate you the amount it would have cost us for repair or replacement. … Matching building materials Where we repair your home we will try to return your home to the same condition as when new, or when last renovated by matching building materials as far as we can. Where we cannot achieve an exact match, we will use materials that match the damaged or lost materials as near as possible in our opinion. We will only do this to the room where the loss or damage occurred. We will not pay for matching building materials in order to create a uniform effect throughout your home .” Issues 27. Whether the estimate provided by the FSP‟s nominated builder includes all insured damage, and Case No: 217450 Determination Page 4 of 7 28. Whether the FSP is entitled to settle the claim by cash payment to the Applicant. Reasons for Decision 29. When making a claim under an insurance policy, the responsibility rests with the policyholder to establish on the balance of probabilities that the damage claimed falls within the terms of cover provided by the policy. 30. The history of this matter is known to both parties. I therefore do not intend recounting the chronology in this determination except where relevant. 31. The central issue in dispute is the difference between the estimate prepared by the Applicant‟s preferred builder , and that prepared by the FSP‟s nominated builder. 32. The Scope of Works (SOW) provided by the FSP‟s nominated builder dated 7 July 2010 carrying an estimate of $87,484.80 sets out the remedial works for each area of the house. The SOW includes the following:  External 3) Strip damaged Colorbond roof sheeting and flashings 5) Supply and install Colorbond roof sheeting and flashings to match if available  Kitchen/Dining/family room 3) Strip damaged bamboo floor 4) Supply and install bamboo floor to match existing if available 33. A document issued by the Applicant‟s preferred build er dated 8 September 2010 contains a breakdown of costing relating to storm damage to the Applicant‟s home with a total of $132,516 inclusive of GST. 34. The Applicant by letter dated 8 September 2010 prepared a comparative list of costings between the two contractors as follows. “ [Applicant’s builder] [FSP’s builder] Remove roof and replace $56,815 $47,357.85 Remove and replace timber floor 16,638 19,921.50 Replace and restrap ceilings 5,720 4,742.80 Remove and replace alfresco cabinets 5,220 3,119.40 Remove kitchen cupboard and replace 1,341 no provision Remove and replace wall oven 4,661 3,430 Airconditioning 2,956 2,020.55 Case No: 217450 Determination Page 5 of 7 Remove and replace carpets 5,434 3,826.30 Remove and replace damaged skirtings 1,155 no provision Scaffolding 10,197 no provision Bins 3,267 no provision Plumber 1,031 no provision Electrician 3,176 no provision Cleaning 3,575 no provision Painter 8,580 3,091.40 Insurance 2,750 no provision Totals 132,516 87,484.80 (inclusive of GST) (GST not known) 35. The FSP sought clarification from its nominated builder in relation to the items referred to as „no provision‟. The builder confirmed: “The only items we have not included in our quote is the cleaning of the house after repairs have been carried out and the removal of the kitchen cupboard as there was no damage shown to me during inspection. We have not allowed for indemnity insurance as we are waiting on confirmation on th e job.” 36. The FSP then adjusted its nominated builder ‟s estimate to $96,408.80 by including items as follows: “Quoted amount [FSP’s builder] $87,484.80 Kitchen cupboard (Applicant’s builder] $ 1,341.00 Cleaning (Applican t’s builder] $ 3,575.00 Insurance (Applicant’s builder] $ 2,750.00 Oven $ 1,258.00 ’ 37. Based on the material presented to me, the remaining items referred to by the Applicant have been allowed for by the FSP‟s builder. 38. In relation to the flooring, I no te the FSP‟s builder‟s SOW include d provision for replacing the bamboo flooring in the kitchen, dining and family rooms. The Applicant‟s builder‟s breakdown of costings included removal and replacing existing timber floor. The breakdown provided to me does not specify the rooms in which the flooring will be replaced. 39. The Applicant by letter dated 8 November 2010, stated that the only bamboo flooring in the property is contained in the family room, kitchen, dining, pantry and linen cupboard and that it was this flooring that his builder quoted to replace. I note the sum quoted by both builders for replacement of the flooring is $16,638 (Applicant‟s builder) and $19,921.50 (FSP‟s builder). 40. In these circumstances, it is apparent that both builders, apart from the pantry and linen cupboard, quoted for essentially the same works in relation to the bamboo flooring. The evidence therefore does not support the FSP‟s assertion the Applicant is seeking to replace undamaged bamboo flooring to match the new materials. Case No: 217450 Determination Page 6 of 7 41. In relation to the roof, the FSP‟s contractor quoted to strip damaged Colorbond roof sheeting and supply and install roof Colorbond sheeting to match existing if available. The Applicant‟s builder quoted to “remove Colorbond roof and replace”. I note a sign ificant gap exists between the two costings being $47,357.85 for the FSP‟s builder and $56,815 for the Applicant‟s builder. 42. I am mindful of the Applicant‟s argument that the FSP‟s contractor‟s inspection of the roof was cursory, and that his own builder carried out an extensive examination. However, I have not been provided with a detailed report from any party on the extent of damage caused by the storm to the roof of the Applicant‟s property, and therefore must rely on the material available to me. 43. As t he FSP‟s contractor referred to replacing only damaged roofing and with a variation of about $9,457.15 in the two estimates for this component of the works, it is reasonable to conclude that the storm damage did not extend across the entire roof of the App licant‟s home. 44. The policy provides that the FSP will pay to replace the damaged portion of the home. The policy further provides that when an exact match cannot be achieved, the FSP will not pay for matching building materials to create a uniform effect throughout the home. In these circumstances and in the event the new roofing material does not match the undamaged roofing material; the FSP is not liable for replacement of the entire roof to create a uniform appearance. 45. For these reasons, I am persuaded that the FSP‟s contractor‟s SOW includes all damage to the Applicant‟s building caused by the storm. Although a significant difference exists between the estimates submitted by the contractors, the FSP is entitled to select the lower of the quotations provided that the contractor is appropriately qualified to carry out the works in a professional and workmanlike manner, and is prepared to carry out those works. I have not been provided with any evidence to show the FSP‟s nominated contractor does not satisfy that criteria. 46. The policy provides the FSP with the option to repair the home, or compensate the policyholder the amount it would have cost the FSP to repair the home. The FSP states that the offer to settle the claim by payment in cash to the Applicant provided the Applicant with the opportunity to appoint his preferred builder. 47. In the alternative, should the Applicant agree to accept the FSP‟s contractor, the Applicant is protected by the FSP‟s customer charter. The customer charter provides that where the FSP authorises repairs to the property, the FSP will guarantee for life the quality of workmanship and materials used in the repair of the property. 48. The policy further provides cover for temporary accommodation expenses if the home becomes unliveable following loss or damage. In the event the home is unliveable during the rectification works, the Applicant is entitled to reimbursement of any temporary accommodation costs incurred for similar accommodation. 49. The claim was lodged with the FSP on 22 March 2010. The FSP‟s adjuster did not attend the property until about six weeks later. The adjuster informed the FSP that the Applicant wished to have the original builder carry out the remedial works. The Applicant submitted an estimate from his preferred builder Case No: 217450 Determination Page 7 of 7 in May 2010. The FSP required a second quote which was not obtained until July 2010 being approximately four months after the loss was reported to it. There followed a number of communications resulting in the FSP adjusting its nominat ed builder‟s estimate to take into account a number of items included in the original builder‟s estimate . The Applicant has therefore been inconvenienced for an excessive period of time as a result of the delay by the FSP in obtaining a second quote. 50. Section 57 of the Insurance Contracts Act 1984 (the Act) provides that where an insurer is liable to pay to a person an amount under a contract of insurance, the insurer is also liable to pay interest on the amount to that person. 51. In the circumstances, pursuant to section 57 of the Act, I am awarding interest on the sum payable of $96,408.80 from 22 April 2010 to 23 September 2010 being the date the FSP remitted the payment to the Applicant at the rate of 8.44% being $3,390.37 Determination 52. Based on this analysis of the material I conclude that the Applicant has not discharged the onus that rests with him to show that he is entitled to have the FSP appoint his preferred contractor to carry out the remedial works on his house 53. Accordingly I determine that the FSP‟s liability for the claim is limited to the sum of $96,408.80. I further determine that the FSP was entitled to settle the claim by payment of this sum to the Applicant should he choose to have his preferred builder carry out the works. 54. I further determine the FSP pay interest on the sum payable at the rate of 8.44% from 22 April 2010 to 23 September 2010 being $3,390.37.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.