Home / Financial Firm (Unknown - Insurer) / Determination 216334

Determination 216334

Quantum of fire repair claim - adequacy of cash settlement offer

FirmFinancial Firm (Unknown - Insurer)
Decided2011-04-13
ProductGeneral Insurance · Landlord
OutcomeFor the complainant in part
Amount awarded$200,617
Non-financial loss—
Amount claimed$258,937
SourceAFCA PDF

Summary

The applicants' fire-damaged rental home claim was disputed over the scope and cost of repairs; the FSP offered a cash settlement of $111,400. AFCA averaged three builder quotes and ordered a cash settlement of $201,117 less the $500 excesses, plus statutory interest.

Where the insurer's scope of works and lowest quote are unreliable, a fair quantum is reached by averaging the competing quotes under the policy's new-for-old repair terms.

Issues

Subjects and remedies

home or building damagepay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

216334 Determination 1 of 8 DETERMINATION CASE NO: 216334 Landlord Insurance – home building – quantum SUMMARY OF FACTS 1. The applicants insured their rental home building, which had been constructed in the 1920‟s/1930‟s, against loss or damage caused by insured events with a $200 standard excess and a $300 flexi excess. The policy commenced on 9 May 2008 and had been renewed to 9 May 2010. 2. On 9 March 2010 the applicants contacted the Financial Services Provider (FSP) to report that the insured property had been damaged by fire. The FSP recorded the following description of the incident: “ My property had just recently been vacated. I have been contacted by the Police advising there was a fire in the roof in the lounge room. There was smoke damage throughout the home as well as water damage in roof and lounge room from fire hose.” 3. The FSP accepted the claim and appointed a consulting engineer to inspect the property and prepare a Scope of Works (SOW) required to repair the property. 4. The FSP provided the applicants a copy of the SOW who raised some concerns with it. The FSP contends that it amended the SOW to include all required repairs and appointed a builder with the most competitive quotation to complete repairs for the amount of $111,400. 5. The applicants contend that the quotation does not cover all the necessary repairs to their property. Under the terms and conditions of the policy the FSP made a cash settlement offer of $111,400. 6. The applicants rejected the cash offer and obtained their own SOW which has been costed by their appointed builder where the cost of repairs will be $258,937.10. 7. The FSP has maintained its position in offering the applicants a cash settlement of $111,400. ISSUE IN DISPUTE 8. Whether the FSP‟s off er of cash settlement is fair and reasonable. RELEVANT POLICY PROVISIONS “What we cover – insured events This section describes under the headings: Yes – the insured events you are covered for, No – the conditions and exclusions that specifically apply to particular insured events. Yes You are covered for damage or loss occurring during the period of cover and caused by the following events to: 216334 Determination 2 of 8 when your landlord building is insured, to that landlord building, ... ... Fire (burning with flames) ... What we will pay – new for old Repairing or rebuilding your landlord building If your landlord building is damaged during the period of cover by an insured event, we will decide if the damage: can be properly repaired, or it is so severe that we reasonably believe your building will need to be rebuilt. Repairing your landlord building When we establish that your landlord building can be properly repaired, we will decide to: repair it, or pay the cost of repairing it. When we decide to repair your building, we will use new materials. We will make reasonable endeavours to match materials. Where this does not achieve an exact match, materials that in our opinion match the damaged or lost materials as near as reasonably practicable will be used. We will not pay to replace undamaged materials or any undamaged part of them to achieve a match. ... Compliance costs In repairing or rebuilding your building, we will pay the extra costs necessary to satisfy the current requirements of any local council or government authority. ” RELEVANT LAW Insurance Contracts Act 1984 SECTION 57 INTEREST ON CLAIMS (1) Where an insurer is liable to pay to a person an amount under a contract of insurance or under this Act in relation to a contract of insurance, the insurer is also liable to pay interest on the amount to that person in accordance with this section. (2) The period in respect of which interest is payable is the period commencing on the day as from which it was unreasonable for the insurer to have withheld payment of the amount and ending on whichever is the earlier of the following days: (a) the day on which the payment is made; (b) the day on which the payment is sent by post to the person to whom it is payable.” REASONS FOR DECISION 9. The Panel is satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. 216334 Determination 3 of 8 The FSP’s Submission 10. On 25 March 2010, it received a report from a consulting engineer in which the engineer stated that roof rafters were inadequately constructed with the roof batten span too great and not fixed to the rafters. In the engineer‟s opinion, the ceiling joists and rafters to the hip roof require upgrading to present day standards. 11. The engineer also noted that the skillion roof profile needed changing to suit a roof slope of 2 degrees. Further, the overlap of the hip roof to the rear skillion roof was poorly constructed and needed upgrading. 12. On 31 March 2010, it requested quotations based on the SOW from two builders. Following concerns from the applicants it arranged for an assessor to attend the premises for a review. 13. Following this assessment, a second SOW was prepared and sent to the quoting builders. Quotations were received from builders “M” and “W” with it accepting the lower quotation from “ W ” . 14. On 21 May 2010, the male applicant requested copies of the quotations and SOWs prior to agreement for “ W ” to undertake repairs. 15. On 24 May 2010, it reviewed the engineer‟s report and builder “W‟s” quotation and it was determined that it should cash settle the claim based on builder “W‟s” quote, which it considers to be fair and reasonable, due to the applicants‟ house being “totally out of the Code”. 16. On 26 May 2010, the male applicant was informed that his property was not a total loss and its liability was only to the fire damaged areas of the house and for these areas to be brought up to Code. 17. The cash settlement was based on the most complete and competitive quote and that his concerns as to whether builder “W‟s” quote include both the original and amended SOWs had been satisfied. 18. However, the SOW does not include upgrades to the applicants‟ property which are required by law, but were not affected by the fire. Its building engineer noted that the upgrades are required and in those circumstances it offered to make a cash settlement which the applicants can use to repair the building while undertaking relevant upgrades as required to unaffected parts of the building. 19. The applicants engaged a building consulting company (BCC) to pro vide an independent SOW and quotation to undertake those works. It submits that the quotation provided by BCC for $258,417.50 is unable to be properly compared with the quotes already provided given that the quote from BCC is based on the applicants‟ own S OW and not the SOW provided by its building engineer. 20. The applicants have not provided any evidence to support their contention that the original and amended SOWs provided by its building engineer are inappropriate or lacking. 21. It submits that there is no detail within the BCC quote about differentiation between repair and replacement of fire damaged building parts and those required to bring the building up to current building standards. Further, the 216334 Determination 4 of 8 applicants have not put forward any opinions as to why the BCC SOW should be preferred over the SOW provided by its building engineer. 22. Given the uncertainties surrounding the report and quote from BCC, it submits that it is entitled to rely on the SOW provided by the building engineer and the competitive quote provided by builder “ W ” . 23. In the absence of any expert or other compelling evidence to the contrary, it submits that there can be no challenge to the reasonableness of it relying on the experience of its own building assessors together with that of the bui lding engineer and the expertise of builder “ W ” . The Applicants’ Submission 24. On 6 April 2010, they were provided with a SOW from the FSP that they considered was inadequate with no provision for any cleaning and blood sealing of hardwood framing, roof structure, cladding, linings, replacement windows, kitchen cabinets, bathroom fixtures and fittings, carpet etc. 25. They discussed their concerns with the FSP following which an additional SOW was issued. The FSP obtained quotations for the cost of repairs from two builders, “W” and “M”. On 25 May 2010, they were informed by the FSP that it had determined to cash settle their claim for $108,900 in accordance with the lowest quotation from builder “W”. 26. They requested copies of the quotations but the quote from builder “M” was supplied with the cost of repairs amount blacked out. However, they considered that the SOW, with a few minor omissions, was detailed and thorough. On 26 May 2010, they were provided with copies of the quotations submitted by both builders. 27. Following a review of the lowest quote they found that:  The quote was dated 19 May 2010, eight weeks after the builder‟s estimator attended their property;  The document referred to the original SOW dated 24 March 2010 and not the later amended SOW;  The quote stated: “note: cost assumes that wall frames and structure which cannot be vis ually inspected are sound;”  The mention of the PC items appeared inadequate, that is, o Electrical $4,000, and o Curtains and rods to 5 rooms $1,000 28. On or about 25 May 20 10 they received a quotation from builder “H” for the amount of $179,740.00 based on the original and amended SOWs. 29. On 3 June 2010, the male applicant met with builder “ W ” to discuss the quotation. During the course of the meeting it was established that:  The estimator who originally inspected the property no longer worked for the company; and  The person submitting the quote had not inspected the property, but had “sighted images”. 30. On 12 June 2010, they forwarded an email to the builder “ W ” advising that as the FSP was insisting on cash settling their claim based on its quote, he sought answers to five questions including whether the builder was prepared to accept 216334 Determination 5 of 8 instructions from the male applicant directly. His enquiries have not been addressed. 31. On 14 July 2010, they received a report, SOW and estimate of $256,500 from their appointed building consultant “MC”. The SOW is far more detailed and addresses the specific issues relating to cleaning, bleed sealing of smoke damaged areas, accessing wall cavities etc. Although the estimate is higher than they anticipated, it is clear fire restoration is highly labour intensive and far more expensive than new build rates. 32. They cannot accept the lowest quote provided by builder “ W ” for reasons which include, but are not limited to: (1) The quote still only refers to the original scope of works dated 24 March 2010. (2) The attending estimator commented that repair costs would be nearly as much as the cost of a new building. A broad figure of $175,000 was discussed. (3) The attending estimator left builder “ W ” prior to submitting a quote. Neither parties involved in submitting the quote have attended the site. (4) As the builder was aware they were to be cash settled, it may have influenced pricing. (5) The FSP is clearly not prepared to back its nominated builder and authorise repairs, for reasons they still do not have a satisfactory answer to. 33. The original SOW was clearly inadequate and did not address the issues of dealing with extensive fire, heat and smoke damage throughout the building. The FSP‟s insistence to cash settle has left them in a position where they would receive an amount of money which is inadequate. It would also appear, based upon the lack of response from builder W, that they would be unable to engage the builder to complete the work at that price. 34. In reviewing the building engineer‟s SOW dated 24 March 2010, they find it astonishing that the FSP would approve a SOW that allows for the retention of charred timbers. The SOW did not even refer to any cleaning or bleed sealing of the structural roof timber. It raises a number of issues including odour retention and the high likelihood that they would be unable to sell the property should they choose to do so. 35. The FSP has stated that the SOW it relies upon includes upgrades to fire affected areas as required by changes in the building code. However, it also states that the SOW does not include upgrades to the insured property which are required by law, but have not been affected by the fire. They have made repeated requests of the FSP to provide details of the “undamaged areas of the home” to which it was referring and which required to be brought up to „Code‟. They have not been provided with this information. 36. The FSP states that they have not provided any evidence to support their contention that the original and amended SOWs provided by its building engineer are inappropriate or lacking. 216334 Determination 6 of 8 37. They appointed a building consultant, “MC” to inspect and prepare a SOW and quotation for repairs to their property. “ MC ” provided an extremely detailed report as to the extent of damage and its SOW addresses the reinstatement required. 38. The FSP refers to „differentiation‟ between repair and replacement of the damaged parts and those which are required to bring the house up to sta ndard. It does not appear to recognise that the fire breached the roof space, damage has occurred, and that it is unacceptable to leave fire and smoke damaged materials in situ, and it has failed to allow for appropriate repair to comply with the current Building Codes. 39. The second builder, “M”, appointed by the FSP to provide a quotation for repairs, ignored the original SOW and allowed for the demolition and reconstruction of the roof structure. Builder “ M ” did physically inspect the property. 40. The FSP has stated that if the Financial Ombudsman Service (FOS) finds that its SOW is correct but is not satisfied with the quotation from “ W ” , it should give consideration to the quotation provided by “ M ” . They have submitted that the original quotation from “ M ” was far more appropriate and realistic, and similar to the quotation proved by “ H ” . However, they submit that this original cost should not be utilised as it does not address the far more comprehensive and technically complete SOW prepared by “ MC ” . 41. Although the FSP has stated that FOS should not base any quotation on the SOW provided by “ MC ” , it has not provided any comment, explanation or evidence as to why “MC‟s” quote is incorrect. 42. In light of their original desire to build a new dwelling, they are still prepared to negotiate a settlement figure, but believe the estimate provided by their builder “ MC ” should be utilised as a starting point. Consideration of each party’s submission 43. The Panel is faced with handing down a decision in this dispute based on the submissions of both party‟s which vary widely in the preparation of Scopes of Work and quotations for repairs. 44. The FSP has submitted the following quotations based upon the original and amended SOW prepared by a building engineer: (1) Builder W $108,900 (incl GST) Plus electrical repairs $ 4,000 asbestos removal and disposal $ 3,900 curtains and rails $ 1,000 Total $117,800 Plus the cost for replacement of carpets and vinyl floor coverings. (2) Builder M $165,195 (incl GST) Excludes cost of removal and disposal of asbestos 216334 Determination 7 of 8 45. The applicants have supplied the following quotations. (3) Builder H $179,740 (incl GST) Note: The quote is based upon the FSP‟s SOW; Price could change when wall and ceiling sheeting is removed – revealing smoke and heat damage. (4) Builder MC Approximate quote $258,417 (incl GST) 46. Although the FSP has accepted the quotation put forward by builder “ W ” , and has based its cash settlement offer to the applicants on that quote, when compared with the three other quotes, the Panel has serious concerns as to whether the builder would be able to complete the repairs at the price submitted. For example, the building en gineer‟s SOW provides for many items to be either repaired or replaced. The Panel would expect that the costs of repairing or replacing would differ. Therefore, the Panel will not include the quotation in its deliberations. 47. The FSP correctly states that th e quotation provided by the applicants‟ builder, “ MC ” , is unable to be properly compared with the quotes that it has submitted given that the quote from “ MC ” is based on “MC‟s” own SOW and not the SOW provided by the building engineer. 48. However, as mention ed above, the building engineer‟s SOW has a number of areas where repair or replacement is left to a builder‟s opinion. Further, the Panel is puzzled by the FSP not questioning the building engineer as to his belief that roof rafters “...were only lightly charred and are reusable” in view of the policy of insurance providing “new for old” conditions. 49. Although the FSP contends that the SOW provided by “ MC ” includes repairs of property that was not damaged in the fire, it has not provided any evidence of this. 50. The Panel is left with determining which quotation of those submitted by builders “ M ” , “ H ” or “ MC ” is the most fair and reasonable. The quotations are: 1. Builder “ M ” submitted on 25 April 2010 $165,195 Quote provides for replacement of the roof which is not included in the building engineer‟s SOW. 2. Builder “ H ” submitted on 24 May 2010 $179,740 and 3. Builder “ MC ” submitted on 6 October 2010 $258,417. 51. Builder “ M ” has not provided a quote for the removal and disposal of any asbestos; builder “ H ” states that his price may change when wall and ceiling sheeting is removed revealing smoke and heat damage; while builder “ MC ” has provided for both of these contingencies. Conclusion 52. The three quotations are not based upon identical SOWs and there is a difference of $93,222 between the lowest and highest quotes. Although the 216334 Determination 8 of 8 SOW provided by “ MC ” is very thorough, and “ MC ” has quoted on that SOW, the quote has not been submitted to any other builder for consideration. 53. Having considered all of the evidence submitted by the parties, the Panel finds that a fair and reasonable solution to arriving at a quantum for the cost of repairs is to average out the quotes submitted by “ M ” , “ H ” , and “ MC ” . This averaged amount is $201,117. 54. Accordingly, the FSP is to cash settle the applicants‟ claim for the amount of $201,117 less the $500 policy excesses. 55. The applicants‟ rental property has not been available for rental while their claim has been in dispute, and they have had to continue their mortgage repayments. Accordingly, the Panel also determines that the FSP is to pay statutory interest under section 57 of the Insurance Contracts Act 1984, at the rate of 8.33%, from 30 July 2010, the date of the FSP‟s IDR decision, to the date the determination is satisfied.