Determination 216183
Denial of storm damage claim (exterior damage, skylight and guttering)
Summary
The applicant claimed under his home building policy for storm-related exterior and interior damage, and the FSP declined the claim. AFCA declined to order payment for the exterior skylight and guttering damage but ordered the FSP to repair or pay for interior damage caused by water ingress through the skylight once the applicant repairs the skylight.
Exterior damage arose from skylight installation defects, blocked guttering and possible subsidence, which the policy excludes or does not cover, while resultant water ingress damage is covered.
Subjects and remedies
home or building damagenatural disasterpay claim
Text of the determination
Case No: 216183 Determination Page 1 of 4
Case number: 216183
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
18 April 2011
Background
1. This is a review of a Recommendation by the service dated 15 February 2011.
The Applicant has rejected the Recommendation and pursuant to the Terms of
Reference the matter has been referred for Determination.
2. The relevant fact, policy provisions and issues in dispute are set out in the
Recommendation annexed herewith. For the sake of brevity and co nciseness I
will not repeat same.
3. I have read the material submitted by the parties and I have carefully
considered the submission including the Applicant‟s submission dated 28
February 2011.
4. I have read the Recommendation and I have noted the reasons give n by the
Case Manager in Support of the Recommendation.
Salient Facts
5. On 10 May 2010 the Applicant contacted the Financial Services Provider (FSP)
to claim under his home building policy for exterior and internal storm damage
to the home.
6. The FSP engaged a building expert to inspect the damage. The building expert
reported that the exterior damage arose from defective workmanship to the
skylight and blockage of guttering.
7. The FSP declined the claim to the exterior damage on the basis that there was
no storm damage to the roofing and the Applicant had failed to maintain same.
8. The Applicant disputes the FSP‟s declinature on the basis that the claim is valid
and he seeks payment of all damage to the insured property.
Determination
Case No: 216183 Determination Page 2 of 4
Summary of Recommendation
The Applicant had interior damage which according to the expert evidence
had been caused by a defective seal around a skylight and blocked gutter
which allowed backflow.
The gutters were growing grass and had significant debris which is clear
evidence of failure to maintai n which the policy excludes.
The Case Manager considered the skylight issues were not excluded
because the Applicant could not possibly have been reasonably aware of
the defect given he had engaged a qualified builder to install the skylight.
9. Accordingly, the Case Manager recommended the following:
The FSP is not liable for repairs to the defective skylight or to clear the
guttering.
The Applicant shall make repairs to the skylight to ensure it does not allow
the entry of water (“skylight repairs”). The App licant shall arrange for the
repairs within 30 days of notification of both parties‟ acceptance of this
Recommendation.
The Applicant shall provide evidence of the skylight repairs to the FSP.
Within 14 days of receiving evidence of the skylight repairs, the FSP shall
arrange for repairs or make payment of repairs to the damage to the right
hand side of the kitchen/meals area and/or any other item of damage
caused by water ingress through the skylight.
Reasons for Decision
10. The Applicant rejected the Recomme ndation on the following basis:
The Applicant‟s t enants were delayed for a period of eight weeks and
caused the Applicant difficulties in having the matter dealt with earlier.
The Applicant provided an opinion of „round flashing with holes and gaps‟
which is supported by the build inspection report sent to the FSP. This
report also states the problem could have happened by thunder and
heavy rain, long spells of dry periods then heavy rain and thunder and
possible movement could have contributed to the problem.
The Applicant disputes the use of the term „poor workmanship‟ by the
tradesperson and he considered this shows bias and is derogatory
towards any tradesperson. The Applicant considers such a statement
suggests the builder did not know what he was doing and is “pretty
ordinary”.
11. I note the following in relation to the issues raised by the Applicant:
The issue of delay was irrelevant to the reasons for the Recommendation
and I am uncertain why the Applicant felt it was an issue. The fact is that
the presence of grass and complete blockage of the gutters was evidence
Case No: 216183 Determination Page 3 of 4
of a long term failure to clean the gutters. The tenants may have failed in
their duties according to the lease but there is no evidence of same.
Further, the Applicant does not describe when the last inspection was
made and whether he noted this as an issue.
The Applicant incorrectly states that the report provided by his expert
states the damage could have occurred due to thunder and heavy rain,
long spells of dry periods then heavy rain and thunder and possible
movement could have contributed to the problem. The report actually
states:
“Lead flashing was sitting up across the front of the square skylight above the
affected kitchen plasterboard with the flexible seal broken under the flashing and
an indication from the sealant line that the roof tiles had settled lower down the
roof. The section of the brickwork and the veranda post in this area are leaning
out a bit with gaps now visible between the brickwork and the kitchen window
frame trim. The prolonged dry spell in recent years may have caused some
foundation movement or settling in turn causing brickwork and roof tile
movement in this area. The change of roof pitch at the base of the skylight also
lessens the slope at this point and with the seal broken the south facing flashing
would be susceptible to leaks in extreme weather. The lead flashing could be
extended further down over the roof tiles.”
The only effect suggested by the weather, is in fact ground movement
(subsidence) may have caused the damage. Subsidence of course is
specifically excluded under the claim.
12. The comment regarding a defect in the skylight is based on the event wording
in the policy terms and conditions. Further, the FSP ‟s report indicates incorrect
installation of the skylight caused the damage which resulted in a portion of the
damage, caused by the leaking skylight to be covered. The Applicant‟s
comments do not assist his position, because if there was a finding that the
skylight was not defectively installed the n the damage would not be covered at
all. Further, if I rely solely on the expert‟s report which suggests wear and
tear/subsidence this would not be covered by the policy and nor would the
resultant damage.
13. For the sake of completeness I note that I agree with the findings of the Case
Manager.
Determination
14. The FSP is not liable for the repairs to the defective skylight nor for the clearing
of the guttering
15. Within 30 days of notice of acceptance of this Determination the Applicant shall
arrange for repairs of the skylight to prevent water entry.
16. The Applicant shall provide evidence of the repairs so effected.
17. Within 14 days of receiving evidence of the repairs to the skylight the FSP shall
arrange for repairs or make payment for the cost of repairs for the damage to
Case No: 216183 Determination Page 4 of 4
the right hand side kitchen/meals area and or any other damage caused by the
water ingress through the skylight.