Determination 215942

Delay in hail damage claim handling and repairs, and claim for consequential financial loss

FirmFinancial Firm (Unknown - Insurer)
Decided2011-08-15
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed$1,550
SourceAFCA PDF

Summary

The complainant claimed $1,550 in financial loss for a nine-month hail repair delay caused by a scope-of-works dispute. AFCA rejected the financial loss claim and awarded $500 for non-financial loss, referring the systemic issues to the Manager for Code of Compliance and Systemic Issues.

Consequential financial loss is excluded under the policy, but non-financial loss compensation is payable for the serious delay in the assessor's scope of works, under clause 9.3(b) of the Terms of Reference.

Issues

Subjects and remedies

home or building damagenatural disasterpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 215942 Determination Page 1 of 5 Case number: 215942 General Insurance - Domestic Insurance - Home Building - Service - Delay in claim handling 1 July 2011 Background 1. This is a review of Recommendation by the Service dated 19 January 2011. 2. The Applicant has rejected the Recommendation and pursuant to the Terms of Reference (TOR), the matter has been referred to me for Determination. 3. The relevant facts, policy provisions and issues in dispute are set out in the Recommendation annexed herewith. For the sake of brevity and conciseness, I will not repeat same. 4. On 7 March 2011, the Applicant advised the Financial Services Provider (FSP) of damage caused by a hail storm. A dispute arose regarding the scope of works for repairs to the residential building. 5. The matter was referred to the Financial Ombudsman Service (FOS) as there was a dispute involving the scope of works and there was a request for financial compensation by the Applicant. As a result of facilitated discussions between the parties, a scope of works was agreed upon by the parties. 6. The Applicant maintains he is entitled to compensation from the FSP for delays in the handling of the claim and in completing the repairs. 7. The FSP declined the Applicant’s claim for compensation because the disagreement regarding the scope of works led to major delays and there is no cover under the policy for consequential loss. Summary of Applicant’s Position 8. The Applicant submits that it took three months to reimburse him for his out of pocket expenses. 9. The Applicant notes it took five months from the incident to provide an adequate scope of works for a relatively simple program of work. The Applicant states that the original instructions to assessors were to focus on the western side of the home which was not appropriate given that the damage was all Determination Case No: 215942 Determination Page 2 of 5 over. Additionally, the scope of works omitted relevant items such as the damaged cowl on the chimney. The Applicant further notes that the FSP agreed to the changes required to the scope of works. 10. The Applicant states it took six months from the incident to appoint a builder due to the scope of works being inadequate. 11. The builder undertook to complete the repair works in 66 days. The Applicant’s attempt to vary the contract to include the ability to cancel the contract was rejected by the builder who advised the work could be undertaken in 42 days. The work by the builder actually took 94 days to complete. 12. It took a total of nine months from the date of incident to complete the repair works. 13. The Applicant notes that the FSP had 45 days during the Internal Dispute Resolution process to rectify the issues. However, it still took six months for the works to be completed. 14. The Applicant considers the FSP failed to process the claim efficiently, remediate funds paid by him efficiently and expedite a resolution of the matter. 15. The Applicant has sought the sum of $1,550 for the entire nine month delay. 16. The Applicant notes the policy terms and conditions exclude consequential loss but notes that the amount sought is compensatory for the systemic failures of the FSP to process the claim in a timely manner. Summary of FSP’s Position 17. The FSP relies on its policy provisions which exclude consequential loss as follows: “Unless we state differently in your policy, we will not p ay for: ... j. consequential loss.” 18. The FSP acknowledges that the timeframes involved during repairs to the property were far outside its normal expectations. However, during this particular time, the FSP experienced an unprecedented number of claims for the Western Australian hail storm. This created issues with assessor and builder availability and meeting of expectations. 19. The FSP has provided a detailed timeline from which I note the following: There is a 1.5 month delay between the first and second assessor reports. The FSP apologised to the Applicant, noting that issues arose due to the Western Australian hail storm. Between 7 May 2010 and 9 September 2010, the Applicant and FSP engaged in discussions regarding the scope of works, alternative Case No: 215942 Determination Page 3 of 5 settlement options and issues with proposed building contract amendments. The Applicant would not sign the scope of works until 9 September 2010 as he wanted an amendment to the building contract. The building works were undertaken from 9 September 2010 to 16 December 2010. The final scope of works agreed upon by the parties was dated 30 August 2010 (the incorrect scope being sent out on 17 August 2010). 20. The FSP contends that a substantial portion of the delays were due to the failure of the parties to come to an agreement on the scope of works. 21. The FSP notes it was prepared to commence works earlier with an assurance that if further damages were found, then the additional damages could be added to the scope of works and repairs authorised. 22. The FSP contends that it also offered to provide cash settlement (based on the scope of works) on several occasions so that the Applicant could engage his own builders. I note the first such offer appears to have been made on 3 September 2010. Issue 23. Whether the Applicant is entitled to compensation pursuant to clause 9.3(b) of the Terms of Reference (TOR). Reasons for Decision Summary of Recommendation 24. In essence, the FSP took from 7 May 2010 until 30 August 2010 to provide a suitable scope of works due to the assessor’s fail ure to inspect all damaged areas of the property. 25. From 1 September 2010 to 9 September 2010, the delays which occurred were not the fault of the FSP. 26. The builders also took 28 days more than the stipulated completion time in the contract, but the Case Manager did not consider this as an unusual delay to rectify the building. 27. On the material before her, the Case Manager was satisfied that the building repairs were delayed by at most, three months, by reason of the FSP’s conduct. Further, she found the delay led to an unusual degree of physical inconvenience and time taken to resolve the situation. Pursuant to clause 9.3(b), the Case Manager recommended that the Applicant is entitled to compensation for non-financial loss. Case No: 215942 Determination Page 4 of 5 Basis of Rejection by the Applicant 28. The Applicant rejected the Recommendation on the following basis: The Applicant made a claim for $1,550. The claim relates to incidents prior to the contact with FOS and due to the systemic failure by the FSP to deal with the insurance matter. The Applicant notes paragraph 30 of the Recommendation which states the source of the delay could not be determined. The Applicant has provided correspondence supporting his view as to the cause of the delay. The Applicant asserts that there has been systemic failure on the part of the FSP to discharge their duties. FSP Response 29. The FSP accepted the Recommendation. Issues Raised by the Material 30. The Applicant’s claim for $1,550 is based on financial loss of wages, which the FSP does not cover. The compensation pursuant to TOR 9.3(b) is provided for nonfinancial reasons and not based on consequential financial loss. 31. Paragraph 30 of the Recommendation states: “I note that the discussions regarding the scope of works took from approximately 7 May 2010 until 30 August 2010. The discussions were apparently generated from the failure by the assessor to inspect all the damaged areas of the property and include all hail damage. As these items were later accepted by the FSP, I accept these items were the result of hail damage and should have been included within the scope of works originally. It is unknown why it took approximately 3 months after the original assessments to obtain a proper scope of works and I consider this constitutes an unusual amount of time taken to resolve the dispute over the scope of works.” 32. I believe it was unknown why the assessor failed to inspect all areas and the scope of works took so long to produce. Ordinarily this should not occur and the FSP has not adequately explained the reasons for this. 33. The Applicant has alleged systemic failures and I believe it is appropriate for me to refer the matter to the Manager for Code of Compliance & Systemic issues. 34. It is my task to assess what is a reasonable and fair sum to award the Applicant by way of compensation. I accept there is a degree of subjectivity in making such awards. The maximum that can be awarded for non financial loss is $3,000. Compensatory awards for non financial loss are not awarded unless there has been a serious failure by the FSP in the conduct of the claim. The Case manager recommended the sum of $500 and having regard to the matters outlined above, I agree that it is an appropriate sum to award in this case. Case No: 215942 Determination Page 5 of 5 Determination 35. I determine it is fair in all the circumstances to award the Applicant the sum of $500 by way of compensation for non financial loss.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.