Determination 215730
Retaining wall storm damage claim reduced because of delayed reporting and prejudice
Summary
The applicants claimed for a storm-damaged pool retaining wall that they had not reported in 2007. AFCA rejected the FSP's defect exclusion but found the FSP prejudiced by the delay, and ordered reimbursement of $1,000 less the $100 excess.
The defect exclusion cannot apply where the insured could not reasonably have been aware of the defect, but the insured's failure to report earlier reduced the payout to the cost of repair at the time.
Issues
- Claim denial primary · upheld
“the FSP is unable to rely on the clause excluding damage arising from a defect or fault.”
- Product terms interpretation secondary · not upheld
“I accept that the FSP was prejudiced by the applicants' failure to follow up the comment with the FSP in 2007.”
Subjects and remedies
home or building damagenatural disasterpay claim
Text of the determination
215730 Determination 1 of 5
DETERMINATION
Case number: 215730
Home Building – storm – structural defect
– delay in reporting damage – FSP’s prejudice
SUMMARY OF FACTS
1. On 12 March 2010 the applicants lodged a claim under their home building
insurance policy for damage to a stone retaining wall around their pool. The
applicants believed the damage was first caused during intense storms in the
area in 2007 which caused other damage to their home for which the FSP
authorised repairs.
2. The Financial Services Provider (FSP) denied liability for the claim on the
grounds the deterioration of the wall resulted from water runoff from ongoing
storm events getting behind the wall. It was unable to escape due to the lack of
drainage holes i n place.
ISSUES IN DISPUTE
3. Whether the collapse of the wall was due to incorrect construction techniques.
RELEVANT POLICY PROVISIONS
“What we cover – insured events
Yes
Storm and rainwater including stormwater runoff from areas surrounding the site, or water
escaping from any water main, drain, pipe, street gutter, guttering or surface.
No
Damage or loss caused by water seeping into or otherwise entering your building due to:
a defect or fault in the design, structure or construction of your building where you
could not reasonably be expected to be aware of the defect or fault,
…
When you claim on your policy your responsibilities include
Preventing further damage or loss
Following an event that is likely to result in a claim, you must take all reasonable precautions
to prevent any further damage, loss, cost or liability.‟
TERMS OF REFERENCE
8.2 Dispute Resolution Criteria
Subject to paragraph 8.1, when deciding a Dispute and whether a remedy should be
provided in accordance with paragraph 9, FOS will do what in its opinion is fair in all
the circumstances, having regard to each of the following:
a) legal principles:
b) industry codes, practice guides, and good industry practice; and
c) previous FOS decisions.
215730 Determination 2 of 5
REASONS FOR DECISION
4. I am satisfied that a full exchange of information has taken place between each
party and that each party has had the opportunity to address any issues raised.
The Applicants Submission
5. In June 2007 extensive repairs were carried out to the house caused by intense
storms in the area. The repairs were authorised by the FSP.
6. Damage to the pool was on the same side as the damage which occurred to
the house.
7. At the time of the 2007 incident one of the FSP‟s builder sent to quote for the
damage to the house mentioned that the wall around the pool would „need
some work‟. Neither the builder who won the contract or the engineer
mentioned anything about the pool.
8. The wall looked all right at the time and as their concern was for the house
damage which was significant they did not give any consideration to the
builder‟s comment until this year when they observed a bulge in the wall.
9. They did not tell the FSP of the builder‟s remarks at the time as they were
involved with the house repairs and the builder who undertook the work and the
engineer involved did not mention it.
10. They arranged for a building inspection and an engineer inspection prior to
purchasing the house and their reports did not mention anything about
problems with the wall drainage.
11. They consider the storm which caused the house damage in 2007 also affected
the pool wall but it took longer for them to become aware of it.
The FSP’s Submission
12. The damage was not the result of a single event but occurred due to
deterioration over time and structural failure. These events are excluded under
the policy.
13. Even in circumstances where the initial damage was caused by an insured
event, the claim would not be accepted as the policy contains exclusions which
defeat the claim.
14. The applicants ignored the retaining wall until it was on the brink of collapse.
Had it been informed of the damage in 2007, the wall would have been
repairable for approximately $1,000 if the claim was accepted.
15. It therefore has been prejudiced by the applicants‟ inaction to report or repair
the damage at that time and the extent of that prejudice was the cost to repair
the whole wall
16. The engineer reported the damage was the result of hydrostatic force due to
build up of water as there were no competent arrangements for the removal of
the water
215730 Determination 3 of 5
Consideration of each party’s submission
17. When making a claim under an insurance policy, the responsibility rests with
the policyholder to establish on the balance of probabilities that the damage
claimed falls within the terms of the policy. A FSP seeking to rely on clauses in
the policy to deny the claim has the burden of establishing on the balance of
probabilities that the terms of the relevant clauses apply to defeat the claim.
18. The FSP relies substantially on the report provided by an engineer
commissioned by it to report on the cause of the failure of the retaining wall.
The report dated 11 June 2010 provided the following information:
- The available information indicates that there are no competent
arrangements for removing water which might enter behind the stone
fencing.
- It was evident that the stone fencing has separated from the excavated
embankment against which it was constructed.
- In their opinion this is an indication that surface water from uphill runoff
has entered the space behind the wall creating hydrostatic forces.
- The hydrostatic forces have pushed the wall away from the embankment.
The report concluded:
“In our opinion the stone facing that forms the retaining wall at this site has
moved as a result of the accumulation of rainfall runoff behind it. The movement
appears to have first been seen in June 2007 and further movements have been
observed in March and April 2010.
The accumulation of rainfall runoff behind the wall has caused hydrostatic forces
that have led to the stone facing separating from the excavated embankment
against which it had been constructed.
It is evident that the failure of the stone facing has not been the result of a single
event, but has been progressive.
The initiating failure (whenever it occurred) would have reduced the wall‟s ability
to resist the forces that would be caused by any recurrence of water entering.
The likelihood of further movements would therefore have increased from the
time of the first failure.
There is no indication that the retaining wall‟s construction incorporates any back
drainage or weep holes that would allow accumulated water to disperse without
accumulating a head of water behind the stone facing that forms the retaining
wall.”
19. The engineer‟s report is supported by a number of photographs which show the
topography relevant to the applicants‟ home. Their site is located on a hill with a
steep slope rising up from the rear of the home. A reserve behind the rear
boundary fence has on open swale parallel to the rear boundary. It is
reasonable to conclude from the photographs that in high intensity rainfalls
such as was experienced in the Newcastle June 2007 storms that rainwater
may overflow the swale and run downhill onto the applicants‟ property.
20. According to the consultant, surface water from uphill runoff entered the space
behind the wall creating hydrostatic forces. The policy provides cover for
damage or loss to the building which includes structural improvements caused
by stormwater runoff from areas surrounding the site.
215730 Determination 4 of 5
21. The FSP states the applicants have failed to establish the damage sustained to
the retaining wall was a result of a single event of storm but has not identified
the terms of the policy which require the damage to have occurred as a result
of a single event.
22. The operative clause of the policy states:
“You are covered for damage or loss to your home building occurring during the
period of insurance and caused by the following events: ”
23. The policy further provides cover for „… storm and rainwater including
stormwater runoff from areas surrounding the site …” . Storm is defined as a
violent wind or a heavy fall of rain.
24. The policy defines “Insured Event” to mean
“The occurrences we have listed on pages 8 -13 which cause damage and loss to
your building.”
25. I am satisfied the applicants have established a prima facie claim under their
policy that is the wall was damaged in a storm in 2007.
26. The evidence has also established that the wall did not have weep holes or
back drainage to allow the water to disperse and that this was a factor in the
damage.
27. The policy excludes damage or loss due to a defect or fault in design where the
policyholder could reasonably be aware of the defect or fault.
28. The applicants advised that prior to purchasing the home, a building inspection
and engineer‟s inspection were commissioned and neither report mentioned
any problems with the wall. They contend that without appropriate qualifications
they could not be expected to be aware of the drainage problem.
29. In these circumstances I am persuaded that the applicants could not
reasonably be expected to be aware of the defect or fault which contributed to
the extent of the damage. It follows that the FSP is unable to rely on the clause
excluding damage arising from a defect or fault.
30. The FSP argues that the applicants were aware of the damage to the wall at
the time of their claim in 2007 and were prejudiced by their failure to take any
action at that time.
31. According to the evidence, following the storm damage in 2007 an engineer
was engaged and several contractors were invited to quote for repairing the
insured damage. One of those contractors made a passing comment to the
applicants that the wall surrounding the pool would „need some work‟. However
that contractor was not successful and the contract was given to another
builder.
32. The applicants advised that neither the successful contractor or the engineer
made any reference to the condition of the wall. The applicants also advised
that as the wall „l ooked alright ‟ they did not give it any further thought. It was not
until March/April 2010 being approximately three years later, that a bulge in the
wall was noticed.
33. In my opinion, the applicants‟ knowledge of the condition of the wall in 2007
must be assessed in context. A passing comment without any further
explanation for the comment from a builder who did not win the contract does
215730 Determination 5 of 5
not carry any significant weight when considered in the context that the
applicants‟ main concern was damage to the house and other experts who
assessed and repaired damage made no mention of the wall.
34. I accept the applica nts‟ argument that they had no reason to believe the wall
suffered serious damage in 2007 and were entitled to believe that any damage
should give reason for immediate concern.
35. Nevertheless I accept that the FSP was prejudiced by the applicants‟ failure t o
follow up the comment with the FSP in 2007.
36. The policy provides that following an insured event that is likely to result in a
claim, the policyholder must take all reasonable precautions to prevent any
further damage or loss.
37. The Terms of Reference provide that FOS will do what in its opinion is fair in all
the circumstances having regard to legal principles, and good insurance
practice
38. The FSP has established that it is not liable for the full cost of repairing the wall.
It is therefore my opinion having regard to what is fair, that the applicants are
entitled to the cost to repair the damaged wall in 2007 less any excess which
applies to the claim. The FSP contends that had it been informed of the
damage in 2007, the wall would have been repaired for $1,000.
CONCLUSION
39. For these reasons I determine the applicants are entitled to reimbursement of
$1,000 to the cost to repair the damaged wall less the $100 policy excess.