Hailstorm cash settlement disputed: roof repairs, cooker, outbuildings, contents, accommodation and expenses
Text of the determination
Case No: 214892 Determination Page 1 of 26
Case number: 214892
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Denial of claim
25 October 2011
Background
The Applicants held a home insurance policy with the Financial Services Provider
(FSP) for their residential property. The relevant period of insurance operated
between 5 September 2009 and 5 September 2010. During this relevant period,
the home was insured up to a sum of $458,778 and household contents were
insured up to $66,851. Claims were subject to a $100 excess.
The Applicants’ home was extensively damaged by a hailstorm event on 6 March
2010 and this was reported to the FSP on 7 March 2010.
The FSP accepted the claim and authorised repairs to the property. The Applicants
appointed an agent, CB, who is the father of the female Applicant and a
registered builder, to liaise with the FSP regarding these works.
As the property was not habitable, the Applicants relocated to a property that is
owned by a company associated with CB.
A dispute began to arise when the FSP engaged a contractor to conduct the roof
repairs (FD). It is agreed between these parties that FD did not conduct these
repairs to appropriate standards. Further, CB did not agree with the scope of
works subsequently provided by the engineer engaged by the FSP (JM).
Numerous correspondences passed between JM, the FSP and its agents regarding
the roof, scope of works and other ancillary issues. As a result, the FSP
decided to utilise its discretion under the policy to cash settle th e Applicants’
claim rather than proceed with repairs. Based on its calculations, it sent a
cheque to the Applicants in the sum of $144,848.
The Applicants have banked this cheque as part payment of what they maintain is
due and owing. They are seeking an additional payment of approximately
$178,196.29.
This dispute revolves around a number of outstanding issues which, for the sake of
convenience, are listed under the following broad categories that have been
utilised by both parties:
Roof repairs and rectification;
Determination
Case No: 214892 Determination Page 2 of 26
Blanco Cooker;
Light Fitting;
Outbuildings;
Garage Door;
Carpet;
Relocation costs;
Window furnishings;
MR beyond salvage items;
Other beyond salvage items;
Furniture repairs;
Tropical fish tank;
Accommodation costs;
Replacement of keys;
Additional living expenses;
Other Expenses;
Additional items and damage.
Although the FSP has allowed some additions sought by the Applicants, it has
disputed the majority of the costs as it considers its offer was fair and
reasonable overall.
As advised to the parties, FOS has considered it appropriate to expedite the dispute
in accordance with clause 8.6 of the FOS Terms of Reference. This is due to
the circumstances, quantum and complexity of the dispute. This dispute has not
been the subject of a FOS Recommendation and has proceeded directly to
Determination.
This decision has been made by a Panel consisting of an Ombudsman, a
representative with extensive experience in the insurance industry and a
representative with extensive experience in consumer claims.
The parties have provided substantial submissions regarding the claims handling
and other ancillary issues surrounding this dispute. For the sake of brevity and
conciseness, the Panel will mainly focus on the substantive issue, namely the
Applicants’ entitlemen ts under the policy and any relevant facts surrounding
this.
Summary of Applicants ’ Position
The Applicants contend the FSP’s cash settlement offer is insufficient and their
reasons are set out below under the appropriate categories.
Roof
Case No: 214892 Determination Page 3 of 26
The Applicants do not accept the proposed roof repairs and rectification allowed for
in JM’s last scope of works dated 16 July 2010 is sufficient. As a result they
engaged CoB, an independent roofing expert, to inspect the roof and provide a
report regarding the extent of damage as well as required repairs and
rectification.
The Applicants have provided a copy of CoB’s CV showing he has approximately 30
years experience in the roofing industry and is appropriately qualified to
comment on this issue.
CoB’s three reports ha ve set out an extensive amount of repairs required beyond the
scope of works allowed for and/or properly accounted for by JM and the FSP.
As a result, his recommendations should be adopted in full. Further, the costs
incurred in obtaining these three reports ($830) should also be allowed.
Pursuant to CoB’s first report, three independent quotations were obtained based on
JM’s scope of works where applicable and CoB’s recommendations. They have
relied on the most competitive one provided by CLCR for $55,863. Further,
CoB corroborated that CLCR’s quote will rectify the roof to the appropriate
minimum standards required as opposed to the quotation relied upon by the
FSP.
In addition to this, they have also obtained plumbing quotes associated with the roof
repa irs given CLCR’s quote does not encompass this. These plumbing costs
were obtained from KC and total $18,638.40.
Additional costs for obtaining three front roof gables and protecting the parquetry
floor are also required. These quotes were sourced from HH which total $4,419.
As they lacked the time and the domestic building experience, they engaged BHR, a
company owned and run by CB, to co-ordinate the quotes and manage the
entire roof restoration. His costs for doing so are also part of the claim and they
total $2,926.
In summary, there is a shortfall of $70,701.40 given the following:
CoB’s reports $830.00
CLCR quote $55,863.00
KC plumbing costs $18,638.40
HH quote $4,419.00
BHR costs $2,926.00
Less FSP settlement ($11,975.00)
Total $70,701.40
Blanco Cooker
The Applicants maintain this is unsalvageable and should be replaced. They have
provided photographs of the cooker showing the damaged parts.
Case No: 214892 Determination Page 4 of 26
The FSP is relying on JM’s scope of works despite JM failing to undertake
appropriate enquiries with the manufacturer and/or service agent regarding the
availability of spare parts. The FSP has also relied on its loss adjuster’s
enquiries with the manufacturer and service agent but on both occasions, he
failed to provide a specific list of parts that would be required. This loss adjuster
also failed to show the extent of damage to the cooker when making enquiries
with the manufacturer.
In contrast, they provided a list of specific parts to these entities and were informed
by the service agent that these were not all available nor could the cooker be
properly repaired without them.
As a result, the Applicants maintain the cooker is unsalvageable and should be
replaced.
They have agreed to accept a quote the FSP obtained for replacing the cooker,
which was for $2,541. However, they refute the FSP’s assessed costs of
installation at $150 for an electrician. To properly install the cooker, they would
require the services of both an electrician and a gas plumber. They obtained
quotes for this and they totalled $590.
Accordingly, they require an additional $3,131 as no allowance was provided for this
item in the FSP’s settlement.
Light Fittings
JM’s scope of works simply allowed for the removal and storage of light fittings and
the refit of light fittings. At no point does it allow for the replacement or repair of
the light fittings.
The Applicants removed the lounge/dining rooms’ light fitting s and delivered them to
SL for their independent assessment. SL’s assessment of the lighting has been
provided and in summary, two 5 light chandeliers cannot be repaired and the
cost of replacement is $440 each. Two 3 light brass lanterns are able to be
repaired at $40 each. Delivery cost is $15 each, totalling $60.
Given this, the Applicants seek an additional $1,020.
Outbuildings
The FSP has relied on a quote from ANT to settle the outstanding building repairs
except for the roof. This quote was done pur suant to JM’s scope of works.
However, the Applicants have noted this quote was for internal damage only
and as such, it is unclear if the FSP’s cash settlement has provided a specific
allowance for the outbuildings.
The Applicants have taken the view that these costs have not been properly
accounted for but in the event they are, they have provided an alternative
adjustment for same.
Case No: 214892 Determination Page 5 of 26
Gatehouse, Gazebo & Small outhouse
The gatehouse is omitted from JM’s scope of works completely. The Applicants
obtained a quote from KC that incorporated these works and it totalled
$1,183.60.
Whilst JM’s scope of works provides some allowance for the gazebo, it did not
include all the necessary works. KC’s quote included the full cost and allowed
$3,328.60. As the FSP did no t provide a breakdown of ANT’s quotation to
determine what contribution was allowed for this, the Applicants have taken
JM’s estimates instead, which amounted to $2,500. By crediting this amount,
this results in a shortfall of $828.60 owing for the gazebo.
Whilst JM’s scope of works recognises the small outhouse, various items are
missing. KC’s quote is for the missing items and this amounts to $1,980.
Rear Store, Rear Roller Doors & Fountain Doves
Whilst JM’s scope of works recognises the rear store, there are a number of items
missing. KC’s quote includes the missing items but also includes replacement
of the roof, totalling $3,010.70. JM’s scope of works and estimate provided an
allowance for the replacement of the roof. In the absence of itemised quotes a
deduction of $1,560, based on JM’s estimate, can be deducted from KC’s
quote.
The rear store roller doors appear to be adequately accounted for if JM’s estimate
was included in the FSP’s settlement. This was quoted at $1,350.
No allowance was provided f or fountain doves in ANT’s quotation. The Applicants
have provided quotes for the supply, removal and installation of fountain doves
totalling $300.
In summary, the Applicants maintain that either an allowance of $11,152.90 or
$5,742.90 should be provided based on the following:
Gatehouse (KC quote) 1,183.60
Gazebo (KC quote) 3,328.60
Cubby House (KC quote) 1,980.00
Rear store (KC quote) 3,010.70
Rear Store roller doors (DGD) 1,350.00
Fountain doves 300.00
Total $11,152.90
Gazebo (JM estimate) (2,500.00)
Rear store (JM estimate) (1,560.00)
Rear Store roller doors (1,350.00)
Total $5,742.90
Case No: 214892 Determination Page 6 of 26
Garage Door – Remote controller operator
The Applicants obtained an independent assessment of the remote control via DGD
who stated it was damaged “ beyond economical repair by storm & hail .”
JM’s scope of works did not account for this nor is there any evidence suggesting
this item was properly reviewed. Accordingly, an additional $450 for its
replacement (as quoted by DGD) should be allowed.
Carpet
The App licants dispute the FSP’s reliance on MR’s assessment that the carpets can
be treated and restored given MR:
Omitted to mention the carpets in the study;
Their assessment is outdated given five months have passed since their initial
inspection. During this time the carpets have been subjected to further
moisture absorption, soiled due to storage of building materials, have
absorbed ceiling insulation debris as a result of traffic and accumulated
general dust and dirt; and
The FSP’s loss adjuster commented that the carpets would be replaced.
The Applicants engaged RCS to inspect and report on the carpet. RCS inspected the
carpet on 10 August 2010 and provided a report containing their
recommendations, which the Applicants contend should be adopted.
Pursuant to these recommendations, they obtained relevant quotes that totalled
$2,690. The FSP’s settlement was insufficient as it only allowed $126.50.
Relocation Costs
The FSP allowed for $1,120 for relocation costs but the Applicants have sourced two
independent quotations where the cheapest was $2,750.
The Applicants therefore seek an additional $1,630 regarding this.
Window furnishings
The Applicants dispute the FSP’s assertions that all curtains and blinds were
checked and cleaned and that only an allowance of $93.50 is required to repair
a “small piece of braid” on one of the pelmets.
The Applicants engaged CC, the original installer and manufacturer of the window
furnishings, to inspect and prepare a condition report. This report drew attention
to the bubbling, marks and stains to the fabrics, shrinkage of the drapes and
the limitations of the report.
The Applicants also engaged SDC to inspect the window furnishings and they were
not confident the furnishings could be restored.
Case No: 214892 Determination Page 7 of 26
Given this, the window furnishings should all be replaced and the sheers and sun
blind should be cleaned, as recommended by SDC. This totals $15,135, which
includes the cost of CC’s report.
Upon deducting the FSP’s settlement proportion, this allows for an outstanding
amount of $15,041.50.
MR & Other beyond salvage items
The parties appear to agree with most of the beyond salvage items sought by the
Applicants except for the shoes.
The Applicants are claiming for the replacement of 20 shoes at $40 each. The FSP
notes it has not been able to verify this figure and has allowed for half. The
Applicants dispute this as they note MR, who was engaged by the FSP to
assess the contents claim, did not have an opportunity to consider this properly.
As a result, the Applicants state they are entitled to an additional $7,677.51, of which
the FSP is disputing $600 (being half the cost of the shoes).
Furniture repairs
The FSP’s settlement was pursuant to a quote provided by MFP that totalled $3,135.
However, MFP were not prepared to carry out the repairs given the Applicants
were in dispute with the FSP.
As a result, the Applicants sourced a quotation from two other contractors and the
more competitive of the two was $3,597. Accordingly, the Applicants are
seeking the balance, namely $462, for the actual cost.
Tropical fish tank
The Applicants have obtained advice from industry experts who cautioned them of
the possibility of the silicone cracking and causing water leaks due to the tank
being emptied and left idle for some time.
As it appears that the tank has been compromised, they are seeking the cost of
replacement totalling $840. They do not want to take the risk of this damaging
the property by attempting to use it against the experts’ recommendation.
Alternative Accommodation costs
Although the policy allows for a maximum of 12 months alternative accommodation
costs, this should not apply because of the defective works performed on the
roof and the FSP’s mismanagement of the claim.
Case No: 214892 Determination Page 8 of 26
The FSP has only allowed for rental accommodation up to 6 December 2010. This is
insufficient and the Applicants are seeking for these costs at least up to 6 April
2011, if not beyond that. This date was based on the likely timeframe of repairs
estimated by their proposed project manager but if the dispute continues, an
allowance should be given for this as well.
Replacement of Keys & Additional living expenses
The FSP’s allowance of the replacement of the keys ($150) is insufficient. The
Applicants have obtained a quotation from OL for $359 so they are entitled to
the balance, being $209.
The Applicants are also seeking a claim for additional living expenses of $940.64
including but not limited to redirection of home telephone and mail and supply
charges (excluding usage) for gas and electricity at the rental accommodation
(they also pay for these at the risk address). This is allowed for under the
following policy provision:
“ Additional things we will pay for when you have insured your buildings
If you have cover for your buildings, the following will be paid in addition to the sum
insured as listed on your schedule.
We will pay these costs when they relate to loss or damage caused by or arising from
accidental loss or accidental damage that is covered by this policy:
… If you normally live in the buildings, we will also pay the costs of alternative
accommodation for your pets, and their additional living expenses up to $1,000
…
Additional things we will pay for when you have insured your contents
If you have cover for your contents, the following will be paid in addition to the sum
insured as listed on your schedule. We will pay these costs when they relate to loss or
damage caused by or arising from accidental loss or accidental damage that is
covered by this policy.
…
We will pay the reasonable costs of alternative accommodation and additional
living expenses up to $1,000. We will pay these costs for up to 12 months. The
most we will pay for these costs is 20 per cent of your contents sum insured, as
listed on your schedule. We will only pay for these costs when, and only for the
period for which, you are unable to live at your situation after loss or damage has
occurred.”
The term “additional living expenses” is not defined and the Applicants maintain they
have applied a reasonable interpretation when seeking these costs.
Other Expenses
The Applicants are also seeking additional expenses they have incurred in
preventing further damage to the property. They called the SES several times
Case No: 214892 Determination Page 9 of 26
immediately after the storm and were informed it would be some days before
their property was attended to.
Accordingly, they engaged BHR who at short notice were able to make alternative
arrangements to perform “make safe” works. CB’s selfless actions were readily
acknowledged by the FSP as having mitigated the loss to an extensive degree.
BHR were required to procure the services of an alternative contractor (PCJ) to
complete their other works. PCJ charged them $3,495.64, which the Applicants
paid for. CB did not charge the Applicants for his actual work on the property.
The Applicants also sought legal advice after the FSP decided to cash settle the
claim. This cost $1,023. In addition, they incurred travel costs carrying out
security checks on the property, which they state were necessary to mitigate
their losses. They seek an additional amount of $5,563.20 in this regard based
on estimated kilometres travelled (7,417.60) at 75 cents per kilometre.
The Applicants have also incurred other additional expenses, such as stationary,
electricity, car park and so forth totalling $247.98.
This results in a total additional amount of $10,329.82.
Additional Items
The timber flooring expert engaged by the FSP, JD, to comment on the parquetry
floor indicated that a re-test was required after the repairs to the building were
completed and the floor was ready to be coated. His costs for the testing are
estimated at $385 and were not allowed for in the FSP’s settlement.
The Applicants also note that the parquetry floor should remain a live issue because
their enquiries regarding the FSP’s method of repair with other experts were
uncertain to say the least.
As the Applicants do not have the required domestic building expertise, they
maintain the appointment of an appropriate project manager for the whole
repairs and/or rectification is appropriate. Although they were initially willing to
nominate CB, his availability is limited and they have obtained an alternative
quote instead for $35,128.02.
The property has also sustained recent damage due to heavy rains on Friday, 4
February 2011 as a result of the failed retiled roof. The damage was to the
study ceiling and the fireplace hearth tiles. They have allowed $1,100 for the
former, based on ANT’s quote, and engaged HH for the fireplace repairs, which
cost $1,530.
There was some water stains to the parquetry floor in the living room but the extent
of damage is unclear.
Accordingly, an additional amount of $38,143.02 should be allowed.
Case No: 214892 Determination Page 10 of 26
Summary of FSP’s Position
FSP’s Cash Settlement
The FSP has based their cash settlement on a revised scope of works prepared by
their engineer, JM, dated 16 July 2010. Although it was initially prepared to
repair the damage, the issues with the roof and CB’s voluminous emails and
demands made this pract ically difficult, especially given CB’s refusal to allow
FD to rectify the roof issues.
As a result, the FSP appointed ANT to carry out a detailed inspection of the home
with the scope of works prepared by CB and JM. This resulted in a quotation of
$110,580 excluding the roofing rectification and repairs. Although JM provided
a more competitive quote ($97,000), the FSP has decided to cash settle the
claim based on ANT’s quotation.
ANT also advised of seven additional items not included in JM’s last scope o f works
which amounted to $7,270. This has been allowed for by the FSP.
The FSP engaged FD to provide a quote to allow another contractor to rectify its
repairs to the roof and the additional repairs required pursuant to the scope of
works developed by JM. FD did so and this amounted to $11,975. This also
formed part of the cash settlement.
The FSP has allowed for additional accommodation costs based on the estimated
time it would take to carry out all repairs to the property, including the roof
restoration. JM estimated the date of completion to be 28 October 2010 but the
FSP extended this benefit to 6 December 2010. As the FSP had already paid
for alternative accommodation up to 6 August 2010, it allowed for an additional
$10,428.
In relation to the conten ts, the FSP allowed $4,595 based on MR’s estimation. With
respect to the carpets, MR maintained these were restorable and only required
a steam clean.
Accordingly, this comes to a total of $144,848 given the breakdown:
Roof Repairs (FD) 11,975.00
ANT quote pursuant to JM scope of works 110,580.00
Contents claim 4,595.00
Accommodation 10,428.00
ANT quote for additional works 7,270.00
Total $144,848.00
Roof
The quotes from CLCR, KC and CB’s company allows for work that is unnecessary
or re-doing what has already been done. Further, CB’s quotation for time spent
in obtaining quotes is not claimable.
Case No: 214892 Determination Page 11 of 26
The FSP engaged JM to comment on this issue as well. JM has provided a number
of reports, the following which summarises the main points:
A thorough joint inspection with CB took place on 17 June 2010;
There were certain aspects of the tile replacement which were not in
accordance with relevant standards;
He does not agree with CoB’s conclusion that the roofing repairs conducted
by FD “failed completely” ; and
A thorough scope of works was provided to have the roof repaired and
rectified to appropriate standards.
JM is a qualified engineer as well as a registered building practitioner. Accordingly,
he is appropriately qualified to comment on this issue and pursuant to his
detailed scope of works, the FSP obtained two quotations from FD, one for the
cost it could do the work, and one for an outside contractor to do it instead. The
latter was more expensive and it has settled the Applicants’ claim pursuant to
this.
Accordingly, it maintains the allowance for this is fair and reasonable.
Blanco Cooker
The Applicants have provided insufficient evidence to establish the cooker is not
repairable.
In the event the cooker is not repairable, a suitable replacement cost is $2,526.
The cost of installation should be limited to $150 as the Applicants only require the
services of an electrician for approximately three hours and their standard rate
is approximately $50 per hour.
Light Fittings, Outbuildings & Garage Door Remote Controller
The light fittings and outbuildings have already been appropriately allowed for in the
scope of works and ANT’s quotation. Nothing further is required.
The FSP does not consider it is necessary to replace the remote controller for the
replacement garage door.
Carpet, Relocation Cost & Window Furnishings
The FSP notes MR inspected the carpets and identified that they only required a
steam clean, which costs $126.50. The FSP submits no further allowance
should be provided.
The FSP allowed f or $1,120, pursuant to MR’s quotation, regarding relocation costs.
This is similar to the costs of the first trip of $1,188 and is therefore fair and
reasonable.
Case No: 214892 Determination Page 12 of 26
MR confirmed that all curtains and blinds were checked and cleaned. Only a small
piece of braid has come away from one pelmet and this would cost $93.50 to
repair. No further allowance is required.
Beyond Salvage contents, Furniture Repairs & Tropical fish tank
The FSP acknowledges that it did not include any of the items in MR’s list for the
beyond salvage items. Although it is unable to test the amount of $3,040 sought
by the Applicants, it will agree to this.
With respect to the additional amount of $4,637.51, the FSP notes it is unable to test
the accuracy of the amount claimed. However, it is prepared to accept the
majority of this except for the 20 pairs of shoes. In relation to this aspect, it is
prepared to accept half and this allows for an additional $4,037.51.
MR provided a quote of $3,135 for furniture repairs that it obtained from a cont ractor
(MFP), which has been included in its cash settlement.
There is no evidence that the fish tank is damaged so no payment is required.
Accommodation costs & Replacement of Keys
The settlement allowed for accommodation costs up to 6 December 2011 is fair and
reasonable for the reasons already discussed.
Further, this benefit is capped at 12 months pursuant to the following policy
provision:
“… if your buildings are unable to be lived in after loss or damage has occurred, we will
pay your rental costs, or loss of rent if applicable. In both cases, the amount we will
pay will not exceed the amount that your buildings could have been rented out for each
week if the loss or damage had not occurred.
We will pay these amounts for up to 12 months. The most we will pay under this
benefit is 20 per cent of your buildings sum insured, as listed on your schedule.”
In relation to the replacement of the keys, the FSP has allowed $150 which is fair
and reasonable.
Additional Living Expenses, Other Expenses & Additional Items
There is no provision under the policy that allows for this given the Applicants are
already receiving benefits for rental costs. This is evident in the following policy
provision:
“Additional things we will pay for when you have insured your cont ents
…
We will reduce the amount we pay you, or stop paying you, if:
- We pay you for rent following damage to your buildings;”
The other expenses being claimed, namely the work performed in CB’s other project,
the Applicants’ travelling costs and legal cost s, are not allowed for under the
Case No: 214892 Determination Page 13 of 26
policy. There is a sum of $865.70 that seems to have been incurred for tarp
hire. This amount may be allowable.
The FSP does not appear to comment on the additional items sought by the
Applicants, namely the damage to the study ceiling and the fireplace hearth
tiles.
Issues
Whether the FSP’s cash settlement offer is fair and reasonable, and if not
Providing an appropriate cash settlement amount to discharge the FSP’s obligations
under the policy.
Reasons for Decision
The Panel is satisfied that a full exchange of information has taken place between
each party and that each party has had the opportunity to address any issues
raised.
Roof
Extent of Repairs
This is a substantive issue in dispute between the parties, with the additional amount
being sought by the Applicants being $74,532.40. This forms over 40% of the
additional cash settlement being sought.
There is no dispute between the parties that the initial repairs completed by FD were
inadequate. The extent of this inadequacy is in dispute. The Panel notes this
issue has been exacerbated by the Applicants’ refusal to allow FD access to
the property to rectify the issues.
The Applicants maintain that their conduct and actions during this process was
reasonable and proportionate. However, the Panel does not completely agree.
Although the Panel acknowledges there were issues with the FSP’s conduct in
this process, such as beginning roof repairs without informing the Applicants,
failing to ensure there was an agreed scope of roof works and FD doing repairs
that were below the appropriate standards, in the Panel’s view the Applicants’
response to this was disproportionate.
The Panel considers CB’s emails, demands and involvement excessive in the
circumstances. Although the Panel appreciates CB is a registered builder and
was making genuine attempts to protect the Applicants’ interests, his actions
did not facilitate or assist in achieving the primary aim, namely to repair the
property back to its pre-accident condition as quickly as possible. For instance,
many emails were sent regarding the FSP’s loss adjuster’s alleged failure to
respond to the Applicants’ request for sarking and seeking acknowledgement of
Case No: 214892 Determination Page 14 of 26
this omission. Although there may be some merit to this issue, the attention this
issue generated was excessive and resulted in the parties deviating from the
primary purpose of repairing the property as quickly as possible.
In particular, the voluminous emails provided by CB served little constructive
purpose given their length, frequency and demand for a response. This resulted
in the FSP’s engineer, loss adjusters and staff spending time and effort
reviewing the contents, making enquiries and providing an appropriate
response at which point, another quick and lengthy response was forthcoming
from CB. Often, the emails were arguing the same points back and forth (such
as the sarking) and this held up the progress of the repairs.
Despite this though, there is no dispute that the roof requires rectification and
repairs. It is unfortunate that the Applicants refused FD an opportunity to do this
given this is the normal process allowed for when a contractor provides
defective building work. In this instance, the Panel accepts the FSP’s position
that it would have been reasonable to allow FD at least one opportunity to
rectify and repair the works upon being presented with an agreed scope of
works.
Further, it was noted in JM’s scope of works that any works completed by FD can be
verified by an independent inspection of a suitably qualified roofing expert if
required. This would have afforded further protection to the Applicants and
supports the FSP’s position that FD should have been allowed an opportunity
to rectify the defects.
However, as this is no longer an option, the Panel is required to assess an
appropriate amount allowable in the circumstances. The Applicants have
provided three reports from CoB and they consistently state that the scope of
works allowed for by FD would not reinstate the roof to an appropriate
condition.
JM ’s evidence to refute this has been limited. He has provided a scope of works of
additional repairs required but in some instances, his description is not specific
because it required FD to assess the extent of repairs necessary, such as:
Any chipped or substandard tiles to be removed or replaced; and
The contractor to correct at his own expense any aspects of the existing
installation which do not comply with the appropriate standards.
Accordingly, JM’s comments that his scope of works comprehensively addr esses all
the required work is not strictly correct because he does not specifically identify
the aspects of the existing installation that do not comply with appropriate
standards. This aspect of the work, which is the substantive issue in dispute,
has been left to FD to identify and cater for.
Although FD attempted to do so, the Panel is not persuaded it has done so
appropriately. As identified by CoB, FD did not accept that they were certain
issues that required rectification, such as:
Roof tiling – FD c onsidered ” roof tiling perfect ”;
Case No: 214892 Determination Page 15 of 26
“ Bent nail in tile, common practice where existing battens are used. Enough
nails in the batten to secure tile ”
CoB has provided numerous comments about FD’s assessment which, in
comparison, the Panel finds more persuasive. CoB has based his comments by
referring to appropriate standards as well as an explanation as to why the work
done was defective. FD’s comments above were not supported by any
explanation to substantiate their conclusion or how their position is consistent
with appropriate standards.
Accordingly, the Panel is persuaded that the quotation provided by FD does not
appropriately reflect the required repairs and/or rectification required. Further,
JM’s scope of works is not detailed enough because he has not be en able to
identify the specific defects that require correction.
In relation to the reports provided by CoB, JM’s comments in rebuttal are limited.
Although he has disagreed with some of the global comments made by CoB,
he has not provided substantive reasons regarding the specific issues identified
by CoB. JM’s comments are general in nature whilst CoB’s are specific and
corroborated by the appropriate standards.
In these circumstances, the Panel accepts CoB is appropriately qualified to examine
and report on the relevant defects and required rectification. In addition, the
Panel considered his comments were consistent with the photographs supplied
and is more persuasive than JM’s evidence and FD’s quotation. Accordingly,
the Panel prefers his evidence.
Quantum
The next issue is whether the quotations provided by the Applicants are consistent
with CoB’s recommendations and reasonable in the circumstances. The FSP,
in its Notice of Response, has highlighted a number of works quoted by CLCR
is unnecessary or re-doing what was already done. It has also provided a
general comment that this applies to the Applicants ’ other quotes.
In this regard, CoB has provided further reports reviewing the quotations and stating
that they will be sufficient to bring the r oof’s repairs and rectification to the
required standards. The FSP has not provided expert evidence to rebut this
beyond JM’s report which, for the reasons outlined above, the Panel is not
inclined to prefer.
Given this, the Panel is persuaded on the evidence that the quotations provided from
CLRC and BR should be accepted.
The Panel is concerned by the discrepancy between the quotation provided for the
house gable, fascia and eaves. The initial quotation was for $1,452 and then an
alternative quotation was found for $3,376, which is more than double.
Although the Applicants identified an extra front gable required replacement,
this final amount appears excessive compared to the first quote for the two front
gables. The Panel considers an allowance of $2,178 is appropriate and this is
Case No: 214892 Determination Page 16 of 26
based on a 50% loading on the first quotation to reflect the additional extra
gable.
Also, the Panel notes the initial quote to protect the parquetry floor during the roof
installation was $668 which then increased to $1,043 with no explanation. This
also appears excessive and as a result, the Panel will allow the original sum of
$668.
The Applicants have also sought reimbursement of CB’s time in obtaining quotes
and reports. The policy provides no allowance for the costs of what the FSP
has described as claims preparation, which the Panel accepts is essentially
what this cost relates to. As a result, the Panel will not provide any allowance
for same.
Further, the costs for a project manager are unnecessary. Most building repairs to a
domestic home do not require the use of a project manager. A registered
builder with appropriate experience is more than qualified to undertake this task
without a project manager overseeing the whole operation.
Accordingly, the Panel will provide no allowance for a project manager.
The costs of CoB’s three reports will be allowed given they have provided probative
value to this substantive issue. The Panel will provide this allowance pursuant
to its discretion under clause 9.4 of the Terms of Reference.
This therefore allows for an additional $66,202.40 to be paid to the Applicants
regarding the roof given the following:
CoB’s reports 830.00
CLCR quote 55,863.00
KC plumbing costs 18,638.40
House gable 2,178.00
Protection of parquetry floor 668.00
Less FSP settlement (11,975.00)
Total $66,202.40
Blanco Cooker
The FSP has questioned whether this item needs to be replaced given JM’s scope of
works did not allow for it. However, the policy states the following regarding its
obligation to pay a claim for damage to a building item:
“How we pay a claim for your buildings
When loss or damage occurs to your buildings, we will pay the cost of rebuilding your
buildings or repairing the damaged portions to the same condition as when they were
new.”
Case No: 214892 Determination Page 17 of 26
It does not appear to be in dispute that the cooker has sustained some damage.
Accordingly, the FSP has the obligation to ensure that its cash settlement allow
the Applicants to repair the item like it was new.
In this regard, the Applicants have provided evidence that the necessary parts
required to achieve this are not available. The FSP has not been able to
specifically rebut this beyond stating it questions whether that is the case.
The FSP’s argument in this regard is not sufficient. The FSP has a cont ractual
obligation to ensure the cooker is repaired as new and it is unclear on the
evidence that the cash settlement it has allowed would adequately provide for
this.
Accordingly, the Panel accepts the cooker should be replaced. The replacement cost
of $2,541 appears to be agreed between the parties.
The costs of installation are also in dispute. However, the Panel accepts the
Applicants’ costs of $590 reflect the real costs given the FSP’s were only an
estimate and did not factor into consideration the gas plumber.
The Applicants are seeking $3,131 in addition to the cash settlement but the Panel
does not accept this is the case. The FSP’s cash settlement was based on JM’s
scope of works which allowed for a service cost of Blanco appliances.
Accordingly, the proportion allowed for this should be credited to the
replacement costs of this item.
Unfortunately, the FSP has not provided a breakdown of ANT’s quotation to
determine what proportion was allowed for this. Accordingly, the Panel will refer
to JM’s quote, which allowed $500. For the sake of consistency, the Panel
considers the JM amounts should have a loading of approximately 14% to
reflect the fact the FSP has sett led the Applicants’ claim based on ANT’s quote,
which was 14% greater in total than JM’s. This results in an allowance of $570.
This amount will therefore be credited and as a result, an additional $2,561 will be
allowed for regarding the replacement of the Blanco cooker.
Light Fittings
The Panel accepts the Applicants’ evidence in this regard as they have provided an
independent assessment from a lighting company. In contrast, the FSP has
relied solely on JM’s report which does not provide specific commen ts
regarding this issue.
The FSP has submitted that an appropriate allowance was provided but there is no
breakdown regarding this cost in ANT’s quote. Further, JM’s scope of works
only provided for the light fittings to be cleaned. Nothing appears to have been
allowed for repair or replacement.
Given this, the Applicants’ quotation of $1,020 should be allowed in full.
Outbuildings
Case No: 214892 Determination Page 18 of 26
The Applicants have queried whether ANT’s quotation provided any allowance for
the outbuildings given the FSP’s reference that it was only for internal damage.
However, the Panel accepts it clearly does given ANT’s quotation specifically
says “ Our quotation is based on the Scope of Works provided by [JM] ”.
The FSP’s reference to internal damage was likely done in error because t he scope
of works and ANT’s quotation clearly indicate these repairs formed part of the
cash settlement.
In light of this, the Panel notes the rear store roller door is no longer in dispute.
Gatehouse
The Applicants have provided photographs showing damage to this which has not
been accounted for at all in JM’s scope of works.
Further, despite JM’s further reports, no comment has been made regarding this
specific issue. Instead, JM has provided a global comment that all areas of
repairs were identified and accounted for, which is insufficient in the Panel’s
opinion.
Accordingly, the Panel accepts an allowance should be provided for this. The only
quotation available before it is the one supplied by the Applicants, which the
Panel will accept.
Gazebo
The App licants have identified various items omitted from JM’s scope of works, such
as:
Strips 11 l/m of spouting, fixes 17 l/m, but 21.5 l/m are required;
Allow 30 sq/m roof sheets but 37 sq/m are required to allow for pitch and
waste;
Allows for 10 l/m of ridge cappings, but 20 l/m are required to allow for pitch
and overlaps;
No allowance made for OH&S scaffoldings.
The Applicants have estimated an additional $828.60 should be allowed for the items
omitted in the scope of works. They have based this difference on the cost
allowed for in JM’s quote.
As JM allowed $2,500, the Panel considers a credit of $2,850 should be considered
as being the likely amount allowed for in ANT’s quote. Accordingly, this results
in an additional $478.60 to the Applicants.
Small Outhouse
The Applicants have stated the scope of works have omitted the following:
Hail damaged spouting – south;
Case No: 214892 Determination Page 19 of 26
Hail damaged downpipe – south;
Replacement of existing sarking to verandah;
No allowance made for OH&S scaffoldings.
They have also provided photographs showing damage to these items. These works
were in addition to that allowed for in JM’s scope of works.
JM has not commented on the Applicants’ submission and given the photographs in
support, the Panel has no option but to accept the Applicant s’ position in this
regard.
Accordingly, the Panel accepts an additional amount of $1,980 should be allowed.
Rear Store
In this regard, the Applicants have identified various works that were omitted in the
scope of works and also provided photographs in support. Again, JM or the
FSP has not addressed these specific items and in absence of same, the Panel
is inclined to accept the Applicants’ position.
The Applicants have credited the amounts allowed for in JM’s estimate for this item
in the absence of the costs allowed for in ANT’s quotation. Applying the 14%
loading as stated above, the Panel considers a credit of $1,778.40 should be
allowed.
This results in an additional amount of $1,232.30 owing to the Applicants.
Fountain Doves
In relation to the fountain doves, the Applicants have sought an additional $300. The
FSP has noted it provided no allowance for this, which is also supported by
ANT’s quotation. This cost therefore appears reasonable given the Applicants
have provided quotations in support.
In total, the additional amount to be paid to the Applicants regarding the outbuildings
is $5,174.50 based on the following:
Gatehouse 1,183.60
Gazebo 478.60
Small Outhouse 1,980.00
Rear Store 1,232.30
Fountain doves 300.00
Total $5,174.50
Garage Door – Remote controller
The Applicants have provided a brief statement from the closest accredited dealer
indicating that the unit is damaged and beyond economical repair.
Case No: 214892 Determination Page 20 of 26
The FSP has relied on the fact JM did not consider the remote control needed
replacement. However, it is unclear on what JM based this assessment on and
he does not appear to have commented on this in his subsequent reports.
In light of the report and the Applicants’ evidence, the Panel accepts this cost should
be allowed.
Carpet
The Applicants have relied upon a report from RCS to substantiate their position. In
contrast, the FSP is relying upon MR which only allowed $126.50 because they
noticed the carpet was not damaged and only required a steam clean.
The Applicants have stated MR’s report should not be preferred because it is
outdated, did not include the study and the FSP’s loss adjuster mentioned the
carpets need to be replaced.
However, the Panel does not accept MR’s comments should be readily discounted.
RCS’s report corroborated MR’s position to a certain extent by stating “ there
appears to be little or no damage to the carpet throughout, and it should be
readily restorable ”. Despite this though, RCS’s report is detailed regarding the
restoration process required and provided photographs in support. The FSP
has not opted to engage MR to rebut RCS’s recommendations and comments.
MR’s evidence is instead limited to a two line comment without any detail
behind it.
In light of these irreconcilable views and with a view to finalising this aspect the
Panel believes it would be fair in all the circumstances to allow 50% of the total
amount sought. Given the only quotations available to implement these
recommendations have been provided by the Applicants, the Panel will allow
the additional $1,281.75.
Relocation Costs
The Applicants are seeking an additional $1,630 as they consider MR’s quotation is
outdated and does not properly account for the logistics of the relocation costs.
The evidence is unclear regarding this large discrepancy. However, the Applicants
have noted that the costs of moving from the damaged property to the
alternative accommodation had two different cost components. The first was
conducted by them at a cost of $1,188. The second was paid for by the FSP
and was conducted by MR. It is unclear how much this second part cost and
whether MR is basing their quotations on this alone.
In the Panel’s opinion, it would appear the Applicants’ cost in this regard is
appropriate and an additional $1,630 should be allowed.
Window furnishings
Case No: 214892 Determination Page 21 of 26
The Panel does not accept the Applicants’ evidence in this regard. The report relied
upon does not appear to advocate the complete replacement to the extent
claimed.
Further, it appears some of the cost is to replace other materials to obtain a
matching appearance. For instance, this is noted in CC’s report dated 17
August 2010 which stated “ Fabrics have been discontinued for approx. 2 yrs. It
is not possible to use a different fabric for 1 pelmet, as there are 3 others in the
lounge covered with the original fabric. All blinds & pelmets to be replaced with
another fabric ”.
The policy does not allow for undamaged property to be replaced for a matching
appearance pursuant to the following policy provision:
“We will try to match any material used to repair y our buildings with the original
materials. If we cannot, we will use the nearest equivalent available to the original
materials. We will not pay any costs for replacing undamaged property.”
Further, the report from SDC was equivocal as to whether the furnishing could not be
restored. Although they indicated they were not confident, the Panel does not
consider this should be taken to mean that the furnishings should be replaced,
especially given MR has indicated otherwise.
Accordingly, the Panel is not prepared to endorse the amount sought by the
Applicants. However, neither does the Panel accept that the scope allowed for
by MR reflects the actual repairs necessary.
Given the lack of proper quotes and scope of works before it, and again with a view
to finalising this aspect the Panel will provide an estimate, although somewhat
arbitrary which it believes is fair in all the circumstances. As the Panel does not
accept that replacement of all window furnishings is necessary and the FSP is
not required to replace undamaged areas to provide a matching appearance,
the Panel will allow an additional $2,500 in these circumstances.
Beyond Salvage Items
The only issue in dispute between the parties is the 20 pairs of shoes. There is no
basis to doubt the Applicants’ evi dence in this regard as the costs appear
reasonable and the FSP has no basis to rebut the Applicants’ evidence.
The Panel therefore accepts the Applicants are entitled to an additional amount of
$7,677.51.
Furniture Repairs & Fish Tank
Case No: 214892 Determination Page 22 of 26
The FSP has settled the Applicants’ claim based on a quotation from MFP. However,
the Applicants have noted that MFP is not prepared to honour the quotation
given they are in dispute with the FSP.
They have provided an alternative quotation for $3,597. Given MFP is no t prepared
to honour the quotation that the FSP based this proportion of the loss to, the
Panel considers the FSP is required to make up the difference to reflect the
actual cost the Applicants will incur.
In relation to the fish tank, the Panel does not accept the Applicants are entitled to
this replacement. The Applicants have noted they are not prepared to risk using
the tank because of the expert’s comments that it may be compromised.
However, the Applicants are required to establish that the fish tank is not
salvageable pursuant to the insured event and in the Panel’s opinion , the
expert evidence is too equivocal to discharge their onus in this regard.
Accordingly, the Panel is not prepared to provide any allowance for the fish tank.
Alternative Accommodation
The Applicants believe that the 12 month cap should not apply because of the
defective roof repairs and the mishandling of the claim. However, the Panel
does not accept this.
As outlined previously, the Panel accepts that the Applicants’ representa tive has
substantively contributed to the delay because of the numerous emails and the
refusal to allow FD the opportunity to rectify the roofing defects. Further, the
Applicants’ proposed project manager allowed for three and a half months to
complete all the repairs and rectification, which means that the 12 month cap
would have been more than adequate if the parties were able to exercise a
reasonable approach.
However, as the Panel has accepted the FSP’s cash settlement offer was
inadequate, in particula r regarding the roof repairs, the Applicants’ pursuit of
the dispute has been vindicated to a certain extent. Accordingly, it is fair in all
the circumstances that the Applicants obtain the balance of the 12 month cap
but the Panel is not prepared to award an amount beyond this.
This will result in an additional payment of $10,428.
Replacement of Keys
The Applicants have provided a quotation regarding the rekeying and keying of all
the keys and locks, which was specific to their circumstances. In contrast, the
FSP is relying upon a general quote from ANT which did not specify the locks
and keys in general.
Given this, the Panel accepts the quotation allowed for by the Applicants and as a
result, will award an additional $209.
Case No: 214892 Determination Page 23 of 26
Additional Living Expenses
The P anel accepts the FSP’s submissions that the applicable policy wording is the
one disclosed in their materials given the following:
The Applicants’ policy relevant to this claim was renewed on 5 September
2009;
The policy relied upon by the Applicants was only effective on 23 December
2009;
The policy version number for the latter noted the date as “10/09”, which
implies it only came into existence after the Applicants’ policy was
renewed;
Most insurers do not alter the policy wording during the currency of the policy.
Instead, the new policy wording is adopted upon renewal, which means
this policy would have become effective when the Applicants renewed
their policy; and
The Applicants’ broker may have been confused by the fact that this policy
was being used by the FSP at the time of the claim occurred but did not
apply to the Applicants’ claim because the renewal occurred two months
prior to the new version being released.
Upon reviewing this policy, the Panel does not accept that there is an allowance for
the additional items sought by the Applicants. Under the policy provision for
“Additional things we will pay for when you have insured your buildings”, the
only allowance is a $1,000 limit for additional accommodation costs and living
expenses of pets. This is evident in the following policy wording:
“If you normally live in your buildings, we will also pay the costs of alternative
accommodation for your pets, and their additional living expenses, up to $1,000”
Under the heading “Additional things we will pay for when you have insured your
contents”, the policy entitles the FSP to reduce any benefit if it is paying the
Applicants’ rent following damage to the building. In this case, the FSP has
chosen to exercise its option to limit this benefit to additional accommodation
costs it has paid.
Other Expenses
The Applicants have sought a number of additional items, most of which are not
provided for at all in the policy. For instance their travelling expenses to visit the
property.
Although the Service does provide an allowance for legal costs under clause 9.4 of
the Terms of Reference, this is usually when an Applicant engages a legal
representative to advocate their dispute before the Service. Further, it is a
discretionary award. Accordingly, the Panel does not consider it is appropriate
to award any amount for these legal costs.
The policy also does not provide for stationary expenses to present a case before
the Service and electricity usage for the insured property. In conclusion, most of
Case No: 214892 Determination Page 24 of 26
the items sought are not allowed for under the policy and the Panel is not
prepared to award an amount for same.
The Applicants have sought the costs incurred by CB in providing emergency works
on their property, which the FSP has acknowledged mitigated losses
extensively. These additional costs were incurred from a contractor CB
engaged to complete a project his company had to abandon to tend to the
Applicants’ emergency works.
The FSP has only agreed to an additional amount of $865.70 in this regard, which
relates to the tarpaulin hire.
The Panel notes that in such a situation, “make safe” works would have inevitably
occurred and these costs would have been payable by the FSP. In this case,
such a cost was avoided by the assistance of CB. The quantum sought, namely
the expenses incurred by CB to abandon an urgent project to attend to the
Applicants’ property, is reasonable and the Panel is prepared to allow same.
This results in an additional payment of $3,495.64.
Additional Items
The Panel does not accept that the parquetry floor should remain a live issue. This
issue appears to have been thoroughly investigated by the FSP, both through
JM and with the appointment of JD, and they did not identify any substantive
concerns. Accordingly, there is minimal persuasive evidence to indicate that the
method of repair would realistically compromise the future performance of this
floor.
The Applicants have identified that according to JD, a further re-testing would be
required before coatings are applied. The Applicants are seeking a n additional
amount of $385 in this regard, which is based on JD’s previous cost. This is
reasonable.
The Applicants have also noted that additional damage occurred due to the failed
retiled roof on 4 February 2011. However, the Applicants have an obligati on to
reasonably mitigate their loss. The Panel notes that the FSP cash settled them
prior to this incident by payment of $144,710.27, which is more than sufficient
for the completion of the roof repairs using the quotations provided by the
Applicants.
There is no dispute between the parties that the roof repairs done by FD were
inadequate. However, there was a dispute regarding the extent of this and the
Applicants refused permission to allow FD to rectify and complete the roof
repairs.
Given this, the obligation was therefore upon the Applicants to undertake the
necessary measures to protect their property from further loss or damage. In
these circumstances, the Panel accepts the Applicants had the necessary
funds to complete these repairs given the cash settlement was sent to them a
number of months before the additional damage occurred.
Case No: 214892 Determination Page 25 of 26
Accordingly, the Panel is not prepared to allow any costs for additional damage
subsequent to the cash settlement.
Conclusion
Given all of the above, the Panel accepts that an additional amount of $103,476.80
should be paid to the Applicants in full and final settlement based on the
following:
Roof 66,202.40
Blanco Cooker 2,561.00
Light Fittings 1,020.00
Outbuildings 5,174.50
Garage Door – Remote control operator 450.00
Carpet 1,281.75
Relocation Costs 1,630.00
Window furnishings 2,500.00
Beyond Salvage items 7,677.51
Furniture repairs 462.00
Alternative Accommodation 10,428.00
Replacement of keys 209.00
Other Expenses 3,495.64
Additional Items 385.00
Total $103,476.80
Determination
On the basis of the available information the Panel determines that the FSP pay to
the Applicants:
The amount of $103,476.80; and
Interest on the above sum in accordance with the Insurance Contracts Act
(1984) from 27 July 2010 (being the date of its IDR letter) to the date
when payment is effected. The applicable interest rate is 8.25%.
In the event the Applicants accept this Determination, this amount should be paid
within 21 days of the FSP being notified of its acceptance unless it requires a
binding release to be signed first. In the event the FSP requires a binding
release to be signed, it should:
Ensure a release is sent to the Applicants within 7 days of being notified of the
Applicants’ acceptance of the Determinatio n; and
Case No: 214892 Determination Page 26 of 26
Pay the relevant amount within 7 days after it has received an appropriately
signed release.