Home / Financial Firm (Unknown - Insurer) / Determination 214545
Determination 214545
Liability to refund make safe repair cost if landlord claim not pursued (excess)
Summary
After a storm, the FSP arranged make-safe repairs costing $992.55, which was below the policy excess. AFCA found the applicant must pay 50% of the make-safe invoice if he does not proceed with the claim, reducing the full amount the FSP sought.
The make-safe work was reasonably required and the PDS applies an excess to claims, but the excess was notified late and the PDS does not link it to make-safe work, so a fair split applies.
Issues
- Claim amount dispute primary · not upheld
“I determine that the applicant is required to pay 50% of the make safe invoice in the event he chooses not to proceed with a claim.”
- Poor communication secondary · upheld
“The FSP's notes say the applicant was informed about the excess only six days after lodgement, after the make safe work had been completed.”
Subjects and remedies
debt waiver or reduction
Text of the determination
214545 Determination 1 of 4
DETERMINATION
Case number: 214545
Make Safe – excess
SUMMARY OF FACTS
1. The applicant has held a Landlord insurance policy with the Financial Services
Provider (FSP) since January 2009. The policy is subject to a $1,000 excess.
2. In August 2009, the applicant contacted the FSP to advise his tenant had
advised tiles had come loose following a storm. The FSP appointed a company
to conduct a „make safe‟ and provide a report.
3. The company reportedly attended the property, but could not conduct make
safe repairs on the day as 2 contractors are required for double storey
properties. The company came back and conducted temporary repairs in the
following days. It was reported the roof would require further repairs to the
value of $2,500.
4. The company‟s invoice for the make safe repairs was $992.55. The applicant
noted he may not proceed with the claim. The FSP advised in that case he
would be required to pay the cost of the make safe, being less than the $1,000
excess. A dispute developed, with the applicant stating he was not informed the
excess would apply and the FSP‟s policy wording is ambiguous.
5. The FSP‟s internal disputes resolution department reviewed the dispute at the
request of the applicant. It maintained the applicant was liable for the $992.55 if
he did not proceed with the claim.
6. The dispute was considered by a Case Manager of the Service who issued a
Recommendation on 10 November 2010. In that Recommendation, the Case
Manager determined the dispute on the basis that the FSP was entitled to an
excess where a claim had been made, but that the make safe repairs were
conducted after the initial damage and that the FSP informed the applicant
about the excess six days after the lodgement of the claim and after the make
safe repairs had been completed. The Case Manager recommended that it was
fair that the applicant pay 50% of the make safe invoice in the event he did not
proceed with the claim.
7. The Recommendation was not accepted by the applicant. Pursuant to clause
8.5(c) of the Terms of Reference of the Service, the applicant requested that
the dispute proceed to Determination.
OVERVIEW OF THE APPLICANT ’S POSITION
8. The applicant maintains that the make safe repairs were performed on a day
after the storm when the damage had passed and the works were not required,
they were unreasonable and they were not authorised and the same result
could have been achieved by the use of a tarpaulin.
214545 Determination 2 of 4
9. The applicant further maintains that their Policy Disclosure Statement states the
FSP will pay the cost of make safe repairs and does not specify an excess is
payable if the claim is withdrawn.
OVERVIEW OF THE FSP’S POSITION
10. The FSP maintains that the policy is clear in that it states that an excess is
payable on each claim and does not provide that an excess will be waived
where there have been repair costs and the insured decides to withdraw the
claim.
11. Further the FSP maintains that the make safe repairs were reasonable and
were necessary and were the correct repairs in the circumstances.
ISSUE IN DISPUTE
12. Whether the applicant is required to refund the cost of make safe repairs if he
does not proceed with his claim.
RELEVANT POLICY PROVISIONS
“ What we cover – insured events
This section describes under the headings:
Yes - the insured events you are covered for,
No - the conditions and exclusions that specifically apply to particular insured events.
…
Yes
…
Storm and rainwater including stormwater runoff from areas surrounding the site, or water
escaping from any water main, drain, pipe, street gutter, guttering or surface.
Storm means violent wind (including a cyclone or tornado), thunderstorm or a heavy fall of
rain, snow or hail.
…
Other costs
We will also pay for the following where applicable.
…
Making safe
We will pay the reasonable cost of, and, at our option, arrange for any temporary work
required to make-safe your damaged or destroyed landlord building.
…
Excesses
An excess on your policy is the amount that you must first contribute towards each claim.…
The excesses that apply to your policy will be shown on the most recent of your insurance
schedule and your renewal notice. When you make a claim we may require you to pay the
excess or we may deduct the excess from any payment we make. We will tell you when and
how the excess is to be paid or deducted.”
TERMS OF REFERENCE
8.2 Dispute resolution criteria
Subject to paragraph 8.1, when deciding a Dispute and whether a remedy should be
provided in accordance with paragraph 9, FOS will do what in its opinion is fair in all
the circumstances, having regard to each of the following:
a) legal principles;
b) applicable industry codes or guidance as to practice;
214545 Determination 3 of 4
c) good industry practice; and
d) previous relevant decisions of FOS or a Predecessor Scheme (although FOS
will not be bound by these).
“8.5 Dispute is resolved on the basis of the Recommendation.
c) If, within 30 days of receiving the Recommendation, either:
(i) The Financial Services Provider does not accept the
Recommendation in relation to the Dispute; or
(ii) Either party requests FOS to proceed from a Recommendation
to a Determination
FOS will proceed to a Determination by either an Ombudsman or by
a FOS Panel (as the Chief Ombudsman or his or her delegate
decides is appropriate). Before the Determination is made, the
parties will be given a reasonable opportunity to make submissions,
and provide any further information, in response to the
Recommendation.”
REASONS FOR DECISION
13. I have reviewed all the material provided by the parties and the reports included
in their respective submissions.
14. The Recommendation of the Case Manager has not been accepted by the
applicant and as such, this matter will proceed to Determination in accordance
with the Terms of Reference of the Service.
15. Subsequent to the Case Manager‟s Recommendation, the applicant lodged a
further submission by way of an email dated 11 February 2011. The FSP has
made additional comments dated 18 February 2011. I have considered all of
the material as part of this Determination.
16. The applicant has provided a recording of a conversation from 25 June 2010.
This is a recording of a conversation which took place after the events, the
subject of this claim. In those circumstances, I am not satisfied that the content
of the conversation can be regarded as relevant to the Determination of this
claim.
17. The discussion between the applicant and the FSP‟s representative, recorded
in that conversation, can only be a theoretical discussion dependent upon the
particular way the applicant explained the circumstances. Without reference to
all of the material, the discussion cannot be regarded as an accurate
assessment of the claim.
18. I do not propose to rely upon the recorded conversation in the making of this
Determination.
19. I have considered the fact that the make safe repairs were completed in the
days following the initial storm rather than immediately after the storm. I agree
with the Case Manager that the make safe repairs were still reasonably
required as if nothing was done, further damage could have occurred, because
it is clear that damage arose from the storm and any further storm activity
would have led to further damage.
20. There is no evidence to support the proposition that a tarpaulin would have
sufficed in the circumstances. In this regard, I confirm that I have discounted
the recorded conversation of 25 June 2010.
214545 Determination 4 of 4
21. There is also no evidence to support the applicant ‟s assertion that the make
safe work could have been performed for between $220 - $320.
22. In all of the circumstances, I am satisfied that the work performed by way of
make safe is reasonable and was required in the circumstances.
23. The Product Disclosure Statement makes it clear that an excess is payable in
the event of a claim and I regard the cost of the make safe work as being part
of the work which the FSP would be required to undertake during the normal
claims process.
24. I do not see it as being reasonable that the FSP is required to undertake make
safe work after being notified by the applicant of the damage and then not
being reimbursed in respect to that make safe work either by way of
reimbursement from the applicant, or alternatively, payment of the excess once
the formal claims process is undertaken.
25. The conclusion is that I consider it to be reasonable that the applicant is either
required to reimburse the FSP for what I say is reasonable and required make
safe work, or alternatively, the applicant is required to pay the excess in
accordance with the claims process.
26. However, and on the other hand, I note that the Product Disclosure Statement
does not specifically link the make safe work and the excess. I also note that
the FSP ‟ s notes say that the applicant was informed about the excess, but only
six days after the lodgement of the claim and after the make safe work had
been completed.
27. Considering all of these matters, I agree with the Case Manager and I regard it
as appropriate in accordance with the Terms of Reference of the Service that it
is fair and reasonable for the applicant to pay the FSP 50% of the make safe
costs if he does not proceed with the claim.
28. I also accept the Case Manager‟s commentary that the Product Disclos ure
Statement could have been better worded in relation to the make safe
provision, even though it does state an excess is applicable to claims.
DETERMINATION
29. I determine that the applicant is required to pay 50% of the make safe invoice in
the event he chooses not to proceed with a claim.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.