Home / Financial Firm (Unknown - Insurer) / Determination 209682

Determination 209682

Storm damage to pergola refused as wear and tear

FirmFinancial Firm (Unknown - Insurer)
Decided2010-10-22
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$4,107
Non-financial loss—
Amount claimed$8,214
SourceAFCA PDF

Summary

The applicants' pergola was damaged in a storm, and the FSP refused the claim as wear, tear and construction defects. AFCA found the storm and the deteriorated structure were consecutive causes, so it ordered the FSP to contribute 50% of the estimated replacement cost.

Where a covered storm and an excluded deteriorated condition both contributed to the loss, the panel apportioned the loss under fairness principles, and sections 46 and 54 of the Insurance Contracts Act did not apply.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

209682 Determination 1 of 5 DETERMINATION CASE NO: 209682 Home Building – proximate cause – exclusion – Section 46 Insurance Contracts Act (1984) SUMMARY OF FACTS 1. The applicants have held a home building and contents policy with the Financial Services Provider (FSP) since November 2009. 2. In February 2010, the applicants lodged a claim for damage to a pergola following a storm. They subsequently requested a „make safe‟ and the FSP appointed a builder who attended and took the pergola down. 3. The FSP subsequently refused indemnity for the claim on the basis the damage was the result of wear and tear and construction defects rather than the insured event of storm. The applicants disputed the decision, noting there was nothing wrong with the pergola prior to the storm, and they would not have allowed the builder to take the pergola down had they known the claim would be denied. 4. The FSP‟s internal disputes resolution team reviewed the matter at the request of the applicants. It maintained the decision to refuse the claim. The applicants continue to dispute the FSP‟s position, arguing they had only purchased the property two years prior to the loss, and they were unaware of any issues with the construction. They argue that Section 46 of the Insurance Contract Act 1984 (the Act) should preclude the FSP from denying the claim on the basis that they were unaware of the deterioration and maintenance issues. ISSUE IN DISPUTE 5. Whether the FSP is entitled to refuse indemnity under the terms and conditions of the policy. RELEVANT POLICY PROVISIONS “ What we cover – insured events This section describes under the headings: Yes - the insured events you are covered for, No - the conditions and exclusions that specifically apply to particular insured events. Yes You are covered for damage or loss to your home building occurring during the period of cover and caused by the following events … Storm and rainwater including stormwater runoff from areas surrounding the site, or water escaping from any water main, drain, pipe, street gutter, guttering or surface. Storm means violent wind (including a cyclone or tornado), thunderstorm or a heavy fall of rain, snow or hail. … What we do not cover – general exclusions 209682 Determination 2 of 5 You are not covered under any section of the policy for damage, loss, cost or liability caused by or arising from or involving: … wear and tear, rust, deterioration or corrosion, mechanical, structural, electrical, electronic or other failure or breakdown, other than as provided for under „Damage to electric motors‟ on page 22. ” LAW INVOLVED Section 46 of the Insurance Contracts Act 1984 provides that if a claim is made in respect of a loss that occurred in whole or in part as a result of a defect or imperfection in a thing and the insured was not aware of the defect or a reasonable person in the circumstances could not be expected to have been aware of the defect or imperfection the insurer may not rely on an exclusion clause that refers to the condition of the thing before the contract was entered into. Section 54 of the Act provides that where but for this section an insurer may refuse to pay a claim, either in whole or in part by reason of some act of the insured or another person, being an act that occurred after the contract was entered into, the insurer may not refuse to pay that claim by reason only of that act, but its liability in respect of the claim is reduced by the amount that fairly represents the extent to which the insurer‟s interests were prejudiced by that act, and where the act could reasonably be regarded as being capable of causing or contributing to a loss in respect of which cover is provided by the contract, the insurer may refuse to pay the claim. FOS TERMS OF REFERENCE 8.2 Dispute Resolution Criteria Subject to paragraph 8.1, when deciding a Dispute and whether a remedy should be provided in accordance with paragraph 9, FOS will do what in its opinion is fair in all of the circumstances, having regard to each of the following: a) legal principles; b) applicable industry codes or guidance as to practice; c) good industry practice; and d) previous relevant decisions of FOS or a Predecessor Scheme (although FOS will not be bound by these). REASONS FOR DECISION 6. There has been an exchange of the material upon which the disputing parties rely. Accordingly, the Panel is satisfied each party has had full access to the material on which the other party bases its case, and also an opportunity to reply to any matters raised. In view of the aforesaid, it is unnecessary to analyse the material in any detail unless required. The Applican ts’ Submission 7. The FSP‟s contractor took it upon himself to take the pergola down instead of putting screws in to keep it in place. The assessor said the claim would proceed and therefore there would be no problem. The contractor left a quarter of a pergola and a mess in their yard, and the remaining pergola had to be removed by a builder they arranged as it was unsafe. 209682 Determination 3 of 5 8. They were not aware of any issues with the pergola, having only purchased the home approximately 18 months before the loss. The FSP‟s buil der also confirms they could not have been aware of the issue. 9. Other posts in the pergola were in good condition and it could have been repaired. The rotten timber referred to is a veneer and not the structural timber. 10. Sections 46 and 54 of the Act should prevent the FSP from refusing the claim, noting they were not aware of any issue with the pergola. The FSP’s Submission 11. The loss is not the result of an insured event but rather, wear, tear, maintenance and structural issues which are excluded under the policy. 12. The applicants submit it has an obligation to reinstate the pergola because it arranged a make safe which resulted in part of it being removed; however, its builder notes that upon attending the property, he discovered most of the pergola had already been removed due to its unsafe nature and the make safe was required to prevent further damage. Consideration of each party’s submission 13. The Panel has reviewed the submissions of the parties in relation to the terms and conditions of the policy and the Insurance Contracts Act 1984 . 14. Having reviewed the policy thoroughly, the Panel is satisfied it covers loss resulting from storm, rainwater or wind, but excludes losses resulting from deterioration, maintenance issues or structural failure or breakdown. 15. The FSP submits the applicants have failed in their onus to establish a prima facie claim under the policy, and the loss is subject to exclusions under the policy. 16. The FSP‟s contractor attended the site on 12 February 2010 and provided the following report: “At the time of inspection I spoke with [applicant] who informed me that due to strong winds his pergola has been damaged. Someone has pulled down pergola due to it being unsafe and could cause more damage. On my inspection of the property I found that the timber pergola had been pulled down so it would prevent more damage to the property. It is noted that this issue is due to the bolts in top of the centre post have been rusted through allowing the wind to get under the pergola and lift the roof then it has come down and fell apart. The client would have not been aware of this before the storm. In my opinion the timber used for pergola are undersized for the span, the roof was under pitched for the type of roof. The front beam in parts has rotted as it has been exposed to water over a long period of time. Due to the above items [contractor] could not replace the pergola to match existing. We would have required a lot larger section sizes of timber to complete the job. A make safe done to pull pergola down to prevent more damage to property. We recommend cash settle to client for repairs.” (sic) 17. The FSP had two assessors review the report and photographs and both conclude (in the FSP‟s system notations beginning lines 90 and 161) that the 209682 Determination 4 of 5 loss is the result of maintenance issues. The second assessor noted the loss was not the result of one single storm event. 18. The applicants reported that “The storm last night caused the pergola at the rear of the house to be damaged ”. It is not disputed that a storm did occur or that damage was occasioned. In its IDR letter the FSP stated “…was due to the bolts in the top of the centre post being rusted through, allowing wind to get under the pergola and lift the roof”. 19. In the Panel‟s view, there is sufficient evidence for the applicants to establish a prima facie claim. 20. However, it is also not in dispute that the pergola was deteriorated and had structural issues. The building consultant noted “…the timber used for the pergola are undersized (sic) for the span, The roof was under pitched for the type of roof. The front beams in parts has rotted (sic) as it has been exposed to water over a long period of time”. The applicants note this, but submit that although the damage to the pergola may have resulted from deterioration, they were not aware of its condition. 21. The applicants submit that as they were not aware of the issues with the pergola and, the comments from the FSP‟s builder support this submission, they argue that Section 46 of the Act applies to defeat the FSP‟s exclusion. 22. The Panel notes for Section 46 to have application, the FSP is required to rely on a provision in the contract that has the effect of limiting or excluding the insurer‟s liability under the contract by reference to the condition, at a time before the contract was entered into, of the thing. 23. In this case, the FSP is not relying on any such provision. It is simply stating the loss is not covered due to the exclusions of “ wear and tear, rust, deterioration or corrosion” and structural failure. It also argues the applicants have not established a single storm event has caused the loss. 24. In these circumstances, the Panel notes Section 46 of the Act has no application to the circumstances of this dispute as the exclusions do not refer to the condition a thing before the contract was entered into. 25. Likewise Section 54 of the Act has no application to the dispute, as it deals with the actions of an insured after the contract has been entered into. This dispute relates to the building at the property and whether the FSP is entitled to rely upon exclusions in the policy. 26. The applicants argue they have suffered prejudice as had they been aware the claim would not be covered, they would not have allowed the FSP‟s contractor to take down the pergola. The FSP argues the applicants requested a make safe at the property, and the contractor had to take the pergola down in the interests of safety and to prevent further damage to the building. 27. The Panel has carefully considered the evidence and the submissions from each party. In the Panel‟s view, on the balance of probabilities there were two proximate causes for the damage, a prima facie insured event of storm and the previously existing deteriorated state and construction of the structure. In the Panel‟s view , these are consecutive causes; the storm caused a degree of damage, but the extent of the resultant damage was exacerbated by the deteriorated state and structure of the pergola. 209682 Determination 5 of 5 28. In the Panel‟s view both played a part in the resultant damage; it is likely that the pergola would not have occasioned the damage had the storm not occurred, conversely had its condition not been deteriorated then the extent of the damage would likely to have been less severe. On this basis, part of the loss could be said to have arisen from an insured event and part of the loss could be said to have arisen from a cause for which cover is excluded. 29. In determining this dispute, the Panel is mindful of the FOS Terms of Reference Paragraph 8.2. Therefore, having regard to what is fair in all the circumstances, the Panel determines that each party should contribute to the loss. The FSP has provided an estimate as to the likely cost of replacement, being $8,214. The Panel therefore determines that the FSP should contribute 50% towards this cost. 30. The applicants have also argued that the FSP should not have dismantled the damaged pergola. However they have not provided any expert evidence to show that the removal of the pergola was unwarranted, rather it is noted that the FSP dismantled the structure at the applicants‟ request. Further , there is no evidence to show that the pergola was capable of being repaired or would be serviceable for the future. 31. The Panel is thus prepared to accept the contractor‟s action in taking the pergola down was reasonable in the circumstances, considering it was hanging down and attached to the main building. CONCLUSION 32. The evidence before the Panel indicates the damage to the pergola was the result of two consecutive proximate causes both of which contributed to the amount of the loss. Accordingly, the Panel determines the FSP is required to pay the applicants the sum of $4,107, being 50% of the estimated cost of replacement of the pergola. 33. The Panel further considers the FSP took reasonable measures in removing part of the pergola to secure the property, as requested by the applicants.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.