Landlord claim for balcony collapse denied as structural defect rather than storm damage
Text of the determination
209270 Determination 1 of 7
DETERMINATION
Case Number: 209270
Landlord Policy – storm damage – alleged pre-existing structural defect
SUMMARY OF FACTS
1. The applicant held a landlord policy with the Financial Services Provider (FSP)
from 28 April 2008 for a property in Mt Martha.
2. On 13 March 2010, the applicant lodged a claim with the FSP as the balcony
on the property had collapsed. He informed the FSP that the loss may have
been due to a recent storm from a week earlier.
3. The FSP engaged experts to inspect the property and report on the loss. The
FSP ultimately determined that the balcony collapsed due to inherent structural
defects and that this was not covered by the policy.
4. The applicant disputes the decision and the opinion of the FSP’s experts. The
applicant seeks indemnity for his loss, which is yet to be quantified.
ISSUES IN DISPUTE
5. Whether the applicant’s loss arose as a result of an insured event.
6. If so, whether the loss was due to a structural defect, and whether the policy
should respond.
RELEVANT POLICY PROVISIONS
Page 16-17 of the Product Disclosure Statement (PDS)
“ Storm means violent wind (including a cyclone or tornado), thunderstorm or a heavy fall of
rain, snow or hail.”
Page 18 of the PDS
“ What we do not cover - general exclusions
You are not covered under any section of the policy for damage, loss, cost or liability
caused by or arising from ...
an unreasonable failure to properly maintain or repair your insured property, ...
... structural... or other failure...”
TERMS OF REFERENCE
Page 13 of the Terms of Reference (TOR)
“8.2 ...FOS will do what in its opinion is fair in all the circumstances”.
REASONS FOR DECISION
7. I am satisfied that a full exchange of information has taken place between each
party and that each party has had the opportunity to address any issues raised.
209270 Determination 2 of 7
T he Applicant’s Submission
8. The applicant states that the deck had been part of the house (which was 40-50
years old), since he had purchased the property in 2008. He understands that it
has been present for at least 22 years and possibly as long as 35 years.
9. New tenants moved into the property on 3 March 2010. One of the tenants
reported that there was no issue with the balcony at that time, but that it
became “wobbly” in the days after a storm on or about 6 March 2010.
10. The balcony subsequently weakened and was noticeably falling by 11 March
2010. It collapsed on 13 March 2010 and the applicant made a claim.
11. The applicant submits that the storm conditions in the area on 6 March 2010
were severe and that the loss was as a direct result of the high winds and the
storm.
12. Whilst the appli cant rejects the FSP’s submission that the balcony fell due to a
“structural defect”, he concedes that the balcony could have been better built,
but as the defect was not one he could have reasonably known about, he
should not be denied indemnity.
The FSP ’s Submission
13. The FSP submits that the balcony appeared to be only five or so years old and
that the construction was structurally deficient.
14. Discussions with one of the tenants revealed that the balcony was supposedly
unstable from the time that she first stepped on it, after leasing the house on 3
March 2010, three days prior to the storm.
15. Whilst adverse weather conditions may have caused the structure to ultimately
fall, the FSP contends it was not the cause or even a significant contributing
factor. The FSP contends that the severity of the conditions on the day of the
alleged storm were not sufficient to make the deck fall.
16. The deck ultimately succumbed because it was not built to acceptable
standards.
17. The storm played no role in the onset of structural instability, nor did it
meaningfully contribute to the loss. There was no precipitating event that gave
rise to the onset of a claim.
18. The FSP contends that the applicant cannot establish that his loss was caused
by an insured event and therefore the FSP has no obligation to provide cover
for the claim.
Consideration of each party’s submission
19. There is an onus on an applicant to establish on the balance of probabilities
that a claim fits the definition of an insured event. Should this onus be
discharged, it is then the responsibility of the FSP to establish the application of
any exclusion on which it relies to deny the claim.
20. In this instance, the alleged insured event was the storm. The applicant
contends that the balcony was damaged in the storm that occurred on or about
6 March 2010, when the tenant was not present.
209270 Determination 3 of 7
21. Part of the difficulty for the applicant’s claim is that no one was present at the
premises at the time of the storm, and therefo re no direct observations of the
severity of the storm are available.
22. The applicant has tendered weather reports pertaining to the 6 March 2010 as
has the FSP. None of these reports shed any light as to the nature of the
specific weather conditions recorded at Mt Martha on the date of the alleged
incident, although it is acknowledged that Greater Melbourne was subjected to
an extraordinary series of storms and adverse weather conditions over this date
and the next day.
23. The applicant has provided a statement from the tenant to confirm she was not
present on the day of the storm, but that she noticed that there was an issue
with the deck when she returned in the following days.
24. The tenant’s partner, who did not reside at the premises confirms in writing that
he was asked to attend on the 6 March 2010, and that he observed that it was
“extremely windy” and that there were trees on the road. The exact time he
inspected the property and location of the damaged trees is not revealed.
25. Contradictory evidence has been supplied by both parties in relation to the
tenant. The FSP suggests that the tenant found the balcony to be unstable
when she moved into the property on 3 March 2010.
26. The FSP has at least in part relied upon this alleged admission from the tenant
to undermine the applicant’s claim. It formed part of its submissi on to this office
to reject the claim.
27. In contrast, the applicant has submitted an apparent partial telephone transcript
from the tenant, in which the tenant confirms that the deck was not unstable
until after the storm.
28. The applicant has also obtained a written statement from the tenant, in which
the tenant confirms that she observed no issue with the deck prior to the storm,
and more specifically that it was “not shaky or wobbly” prior to the storm.
Further to this, she noticed upon her return on 7 March 2010 that the deck was
“unstable”.
29. The deck’s condition deteriorated over the ensuing days, and it finally collapsed
on 13 March 2010.
30. The applicant suggests that the deck was damaged in the storm, as evidenced
by the recollections of the tenant, who reported no problems with the deck prior
to the 7 March 2010. Further, the applicant suggests that the effect of the storm
was to weaken the deck significantly, causing the ultimate collapse of it several
days later.
31. Upon inspection of the home, the FSP’s ass essor conceded some weather
related damage had been incurred to the applicant’s property, and this portion
of the claim was settled. The FSP’s engineer later conceded that the storm
“may have” played a role in the collapse of the deck.
32. The sum total of this evidence, together with the known conditions from the
claim date are sufficient to establish that the applicant’s home was subjected to
storm-related conditions on or about the 6 March 2010. I am satisfied that at
least a prima facie case for storm damage has been made by the applicant.
209270 Determination 4 of 7
33. The FSP’s assessor determined after inspection of the property that there was
no evidence of wear and tear or “rot or rust or termite action to cause the
event”.
34. These observations suggest that the assessor found no reason to decline the
claim when initially inspecting the damage. He does not venture any opinion as
to possible storm damage, nor does he provide comment on whether the claim
appears genuine or not.
35. The assessor recommended the appointment of a structural engineer to
evaluate the construction of the deck, which he assessed to be between five to
ten years old. He also considered it to be not acceptable by “today’s
standards”.
36. The structural engineer inspected the damage and provided a written report. He
ventured that the balcony failed due to the “pull out” of the nails affixing it to the
living room floor of the house. The engineer submits that the balcony floor joists
had no “bearing on the steel beam”.
37. The engineer suggeste d that the “collapse occurred due to poor construction”.
The report further concedes that the storm “may have” assisted in the collapse
of the balcony, but he did not consider it to be the cause.
38. He further provided opinion that the structure was not compliant with current
building codes, and that it was “not expected” to have complied with the
previous codes. The expert never investigated the relevant codes to verify if
this was the case or not, nor did he examine these codes in detail to specify
where the construction was deficient.
39. The engineer submits that he asked the applicant to obtain the original building
permits and other material from the local council for review. Subsequent
enquiries were conducted by the applicant, but he was verbally informed by the
relevant council that no such permits existed.
40. The applicant has since commissioned an agent to design plans to replace the
deck, and he submits that the proposed method of construction is substantially
similar to the original deck, and yet still compliant with the relevant building
codes. The FSP has not challenged this assertion.
41. This lends support to the applicant’s contention that whilst the engineer might
have built the deck in a different (and arguably more robust) fashion, that is not
to say that the original construction was not in accordance with acceptable
building standards and codes.
42. Noting that the home was a recent purchase, the applicant still had the Section
32 building notice from the time of sale. These documents reveal that no
building approvals had been granted on the property for the previous seven
years and no work had been attempted without a permit (to the vendor’s
knowledge).
43. This information suggests that the applicant purchased the property in good
faith and with no reason to suspect that any recent work had been done.
44. If the FSP was to require the original plans and permits for the decking (if
indeed they existed), there is no reason that it could not have made the
relevant application with a duly endorsed signed authority from the applicant.
209270 Determination 5 of 7
Noting that the council informed the applicant that the documents did not exist,
it would likely have been a futile exercise.
45. When inspecting the property, the structural engineer reported to the applicant
that he believed that there was no valid claim for the balcony and (at the time),
the applicant reluctantly agreed.
46. After some consideration, and discussion with other professionals, the applicant
contacted the FSP the next day to submit that he wanted to obtain a further
report to investigate the possible causes of the incident.
47. The FSP’s file indicates that after being informed of the applicant’s intentions,
immediate plans were made to re- contact the tenants to “further clarify the
circumstances giving rise to the structure[’]s failure” . The FSP also made plans
to further investigate the severity of the storm’s alleged impact on the property.
48. These arrangements by the FSP were made after a decision had effectively
been given to the applicant on the merits of his claim. It is clear that t he FSP
did not believe that the claim was one for acceptance. However, I query its
commitment to fully investigate the claim and properly consider the evidence
before the decision to deny indemnity was made.
49. The FSP should not have denied the claim if it was necessary to conduct
further enquiries to ratify the decision. I do not consider that this was simply a
matter of clarifying details, but rather a matter of finding evidence to support the
denial. It is apparent that the FSP attempted to do this only after its decision
was questioned by the applicant.
50. The FSP’s expert evidence indicates that the balcony might not have been
suitably constructed, although further effort should have been made to establish
an actual build date and to consider same in accorda nce with the standards of
the time.
51. The FSP has been reliant on the applicant to obtain this information, but it could
have easily obtained the information itself. If the FSP is to submit that the
balcony was not built to acceptable standards, then the onus rests with the FSP
to establish when the construction was done and what the standards were at
the time. The FSP appears to have based its findings on the premise that the
balcony was five or so years old, but this is openly challenged by the applicant.
52. The applicant claims that the balcony was built between 22-35 years ago. He
has tendered an e-mail allegedly from his neighbour that the balcony was
present at least as far back as 1998, when he had moved into the area.
53. A signed photograph from another neighbour was also provided, showing the
applicant’s home in the background and the deck. The neighbour indicates that
this photo was taken in 1992 when he moved into the area.
54. The Section 32 notice from the sale of the property indicates that the previous
owner had not been aware of, nor attempted any construction at the property
for at least seven years, being as far back as 2001.
55. Based on the provided material, I accept that the balcony was at least 18 years
old and I have no reason to doubt the applicant’s claims that it may have been
significantly older.
209270 Determination 6 of 7
56. If the premise for the reports compiled by the FSP’s experts we re that the
balcony was around five years old (as appears to have been the case), it may
have influenced the perception of its structural integrity as determined by the
engineer. That the applicant alleges it is significantly older might have an
impact on the opinions submitted as to the construction of the deck.
57. In the denial letter from the FSP of 6 April 2010, the FSP accepted that storm
related damage was present at the property, but its experts could not form an
opinion as to whether the storm affected the deck. The letter confirms that the
engineer conceded that the storm “may have helped” the collapse of the deck,
but he suggests that it did not cause it.
58. The letter also stated that the engineer attributed the damage to other factors
such as the unsound construction of the deck and possible differential
settlement. I consider that this implies that the FSP and/or the engineer were
not sure about the exact cause.
59. The denial of the claim was due to there being no insured event, despite the
earlier concession that the home had been damaged in the storm. That the
experts could not definitively attribute the deck’s collapse to the storm did not
confirm that there was no insured event, as the experts could not rule out the
storm’s impact either.
60. The FSP went on to suggest that the defective design of the deck was
instrumental in its collapse, and the writer noted that she was “satisfied there is
no storm related damage”. The evidence from the experts was not as certain on
this issue and I fail to see how the FSP could be. It is later conceded that the
deck “may have collapsed after heavy rain”, but that the collapse was
“inevitable” in any event.
61. In summing up, the FSP submits that there is “no evidence... to suggest that
the rain would have been a factor had there been no structural defect present”.
62. This conclusion from the FSP (and the various reports from their experts)
conversely does not address whether the deck would have collapsed in the
storm regardless of the alleged defect. At the time of the denial, the perception
held was that the deck was around five years old, but I accept that this was not
the case.
63. In the knowledge that the deck had stood for at least 18 years, and possibly
much longer, was it possible that it would not have failed but for the storm? I do
not consider that this question was ever addressed by the FSP.
64. The perception that the collapse of the deck was “inevitable” was spec ulated by
the FSP’s engineer, but given that the storm “may have” played a role, it was
necessary that he venture an opinion as to when the collapse might have
occurred, without the intervention of the storm.
65. Having reviewed all of the submitted evidence from the respective parties, I
consider that it was likely that the age of the deck was a factor in its demise and
that the structural integrity was perhaps not as strong as it could or should have
been.
66. The delay from the onset of the storm to the eventual collapse of the deck is
unusual, but not inexplicable in terms of it being the cause of the loss. I accept
that the structure may have been affected and weakened to the extent that
209270 Determination 7 of 7
subsequent foot traffic caused it to fall. This does not invalidate the likelihood
that the storm was the proximate cause of the damage.
67. Notwithstanding the delay between the storm and the subsequent collapse of
the deck, I am satisfied that the loss occurred as a result of the storm which
damaged or severely weakened the structural integrity of the deck.
68. The FSP has tendered much evidence as to the structural integrity of the deck,
but this has little to do with the impact of the storm on its demise. That the deck
has stood for at least 18 years suggests that its construction was not as poor as
suggested, and the expert evidence puts little consideration as to the effect of
the storm on the loss.
69. I am satisfied that the storm played a significant role in the collapse of the deck.
Given its age and the comments about its structural integrity, it is appropriate
that some apportionment of damage is made, rather than payment for the full
cost of the structure.
70. I accept that the deck could have been better constructed, but given the time
that it appears to have stood. I am satisfied that the construction of it was
sound enough for its purpose.
71. The evidence from the FSP’s experts as to the reasons for failure should not be
disregarded, and having consideration to what is “fair in all the circumstances”
and the delay in the deck’s collap se, I consider that the FSP should attend to
payment of 65% of the applicant’s loss.
CONCLUSION
72. I determine that the FSP should attend to payment of 65% of the applicant’s
assessed loss, noting that no quotes have been submitted at this time.
73. I further determine that the FSP is entitled to appoint an assessor to determine
a fair and reasonable cost for reinstating the deck to an acceptable standard, in
conjunction with the applicant and/or his preferred repairer.