Determination 208678

Refusal of earthquake claim for cracking to building, reduced to 50 percent contribution

FirmFinancial Firm (Unknown - Insurer)
Decided2011-01-28
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed$37,400
SourceAFCA PDF

Summary

The applicant's block of flats had cracking that he attributed to March 2009 earthquakes, and the FSP refused the claim as pre-existing ground movement. AFCA found earthquake damage was established at least in part and ordered the FSP to contribute 50 percent of the repair cost, excluding the new articulation joints.

Earthquake damage occurring within 72 hours is covered, and exacerbation of pre-existing cracks by an earthquake can still be earthquake damage, though pre-existing damage justified a 50 percent contribution.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

208678 Determination 1 of 5 DETERMINATION CASE NO: 208678 Home – earthquake – proximate cause The applicant is represented. For convenience in the Determination, the applicant and his representative will hereafter be referred to as “the applicant”. SUMMARY OF FACTS 1. The applicant held a home policy for a block of flats with the FSP (Financial Services Provider). 2. In April 2009, the applicant contacted the FSP to lodge a claim for cracking to the property following earthquake activity in March 2009. 3. The FSP appointed a loss adjustor, who inspected the building and in turn appointed an engineer to determine the cause of the damage. The consultant reported the cracking was not the result of the recent earthquakes, but rather the result of differential earth movement caused by climatic conditions, tree roots and contraction issues. The FSP subsequently refused indemnity on the basis the earthquakes were not the cause of the loss. 4. The FSP‟s internal disputes resolution department reviewed the claim at the request of the applicant. It maintained the decision to refuse the claim. The applicant continues to dispute the FSP‟s position and provides expert evidence to support his assertion the loss was the result of the earthquakes. ISSUE IN DISPUTE 5. Whether the FSP is entitled to refuse indemnity under the terms and conditions of the policy. RELEVANT POLICY PROVISONS “ Section 1 Buildings and contents Listed Events cover … We will cover your buildings and your contents for loss or damage from the events listed below. …  Earthquake or tsunami. We will only cover loss or damage as a result of an earthquake if the loss or damage occurs within 72 hours of the earthquake. ” REASONS FOR DECISION 6. The Panel is satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. 208678 Determination 2 of 5 The Applicant’s Submission 7. The cracking at the property is the result of the earthquakes. While there was some cracking at the property that had been repaired prior to the earthquakes, many cracks from the earthquake are fresh with no evidence of spider webs usually associated with pre-existing cracks of some age. 8. The cracks that exhibit no evidence of having been patched were not patched because they did not exist prior to the earthquakes. 9. The applicant provides two expert reports in support of his position and a letter from the real estate agent confirming a tenant made contact after the earthquakes to report the loss. 10. The building was built to the relevant standards and codes at the time of construction. 11. The applicant provides a quote of $37,400 to rectify the damage. The F SP’s Submission 12. The expert evidence indicates the cracking at the property is not the result of the earthquakes in March 2009, but rather earth movement as the result of climatic conditions on reactive clays, trees in the vicinity of the building and a lack of articulation joints. Accordingly, there has been no prima facie claim and the policy does not respond to the loss. 13. Cracks at the insured property have been patched in the past, indicating the movement at the property has been an ongoing issue. 14. The property is located approximately 75km from the epicentre of the earthquake. Geoscience Australia has reported the earthquake had a damage radius of only 9km from the epicentre. Consideration of each party’s submission 15. The Panel has reviewed the submissions of the parties in relation to the terms and conditions of the policy. 16. Having reviewed the policy thoroughly, the Panel is satisfied it covers damage caused by an earthquake if the damage occurs within 72 hours of the earthquake. 17. In this case, the FSP argues the applicant has not established the damage at the insured property was caused by an insured peril. The FSP is not relying on a policy exclusion, which is often the case in earthquake disputes. Therefore, the central issue in dispute is whether the applicant has established a prima facie claim under the policy. 18. The FSP‟s expert provided a report dated 7 May 2009, which includes the following information:  Geoscience Australia reports the earthquake measured 4.6 on the Richter Scale with a damage radius of 9km from the epicentre.  The property is approximately 90km from the epicentre.  The property is cracked with evidence of repairs to pre -existing cracks.  The building does not have articulation joints, which prevents the building from absorbing natural movement. 208678 Determination 3 of 5  The damage is the result of natural ground movement over an extended period of time.  There is no earthquake damage. 19. The applicant has provided the opinion of two experts in support of his submission the loss was the result of the earthquake. The first report is from a building consultancy company „BACS‟. The report dated 13 July 2009, includes the following information:  There is evidence of new cracks at the property that have not been patched and have no spider webs. New cracks are usually evident due to a lack of spider webs in the gaps.  There are no trees of any consequence close enough to possibly cause damage to the insured building. Two trees are on an adjoining property and one tree closer to a damaged wall is not an issue.  Articulation joints may well have prevented damage to the building; however, they were not required at the time of construction in the late 60s/70s.  The building is in above average condition for its age and there is no evidence it has been poorly maintained.  The estate agent reported four tenants left the property in fear at the time of the earthquakes as the property was shaking badly. The tenant in Unit 1 was able to point out internal cracking as the result of the earthquakes.  The applicant reported the patching, identified by the experts was present when he purchased the property in the 1970s and he has no knowledge of its underlying cause.  The FSP insured the building knowing its age and should have been aware of the relevant building codes at that time. Therefore, any issues with the lack of articulation joints should not be a consideration.  The building has pre-existing foundation and construction problems due to a lack of articulation joints and this has no doubt contributed to the damage by the earthquakes, which released the built up stresses in the structure. 20. The applicant also provides a report from an engineer, referred to as „RB‟. The report, dated 27 August 2009, provides the following information:  The building is well kept with minor cracking as the result of ground movement, brick growth and concrete shrinkage.  There is evidence of very recent cracking.  The soil around the property is of low to moderate reactivity.  Trees have contributed to cracking at the property.  The drought has hardened the ground, sharpening the transfer of movement from the earthquake.  The earthquake pushed the building sideways across the block and forced it back again.  All the damage to the front, upper and internal areas of the building is the result of the earthquakes. 21. The FSP‟s engineer reviewed the applicant‟s expert reports and replied to the findings. The second report, dated 06 January 2010, includes the following information: 208678 Determination 4 of 5  The soil testing by „RB‟ would indicate the soil is of moderate to high reactivity.  The applicant‟s experts are in agreement that the outdated construction has contributed to cracking at the property.  Extreme drought in the area has resulted in differential movement and cracking at the property over a long period of time. It is purely coincidence that the earthquakes of March 2009 occurred after the driest months since the 1930s.  „RB‟ confirms the existence of trees in the area. A Google map image shows trees around the property. It is no coincidence that cracking in the property is located in areas where trees are present. It is more likely the trees rather than the earthquakes have caused the horizontal movement of the building.  Owners, tenants and estate agents are inclined to check for cracks after earthquake events and find damage that might otherwise have gone unnoticed.  While the engineer did not see the property prior to the earthquake and cannot definitively state the earthquake did not cause some damage, the underlying facts indicate the earthquake would not have caused the damage to the insured property, noting the issues identified and the fact the property is well outside the stated damage radius of 9km. 22. The applicant also provides a letter from the real estate agent, dated 26 June 2009, which states: “I received an urgent phone call dated – 08 th March 2009 from our tenants in unit 1/15 [insured address] that there were cracks that appeared through out the building after the earthquake. We contacted the landlord and advised him and went to look at the damage our self’s. The crack has never been there at any of our routine inspections and/or at condition reports. Knowing the building as well as I do I feel as though the crack where caused by the earthquake.” (sic) 23. In considering the evidence, the Panel is satisfied the building is of an older construction and the absence of articulation joints has contributed to cracking at the property, whether that be the result of differential movement and/or the earthquakes. However the building was fully compliant with relevant building codes extant at the time of construction. 24. The Panel has considered the fact the property lies some distance from the stated damage radius; notwithstanding this consideration, it forms the opinion that as the earthquakes‟ effects were felt over 100km from the epicentre and reportedly shook buildings, there is a possibility cracks could have been caused to susceptible buildings. 25. The Panel accepts the presence of trees in the vicinity of the building have contributed to cracking at the property over a long period of time. 26. However, the evidence to hand indicates there are new cracks in the building and the tenant in Unit 1 made contact with the estate agent only two days after the first earthquake to report the damage. 208678 Determination 5 of 5 27. In this dispute, the FSP is not relying on a policy exclusion. Rather, it argues the applicant has not established a prima facie claim under the policy. Given the evidence of new cracking and the fact a tenant reported cracking immediately after the first event; the Panel is inclined to accept the applicant has established the earthquakes have at the very least caused some damage to the building. It is also quite possible the earthquakes have exacerbated pre- existing cracks. In the Panel‟s view, the exacerbation of cracks due to an earthquake can still be reasonably regarded as earthquake damage. 28. However, the Panel acknowledges there is evidence of at least some pre- existing damage at the property and in consideration of all the evidence, is satisfied a reasonable outcome would be for the FSP to contribute 50% towards the cost of repairs. 29. The applicant has provided a quote for $37,400. This includes an allowance for four articulation joints. As these did not exist prior to the loss, the Panel is of the opinion the FSP is not liable for this portion of the rectification. CONCLUSION 30. Accordingly, the Panel determines the FSP is to contribute 50% towards the rectification of the damage. It further notes the FSP is not required to contribute towards the installation of articulation joints, as these did not exist prior to the loss. 31. The FSP is entitled to a breakdown of the applicant‟s quotation to clarify the extent of its liability.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.