Summary

After a kitchen pipe leak, the applicant sought retiling of the whole open-plan living area. AFCA limited the FSP's obligation to rectifying the kitchen and ordered a professional clean of the whole dwelling.

The policy requires repair of only the damaged portion of the floor in the room where damage occurred, so the undamaged living area was not covered.

Issues

Subjects and remedies

home or building damagepay claimrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

205163 Determination 1 of 3 DETERMINATION Case Number: 205163 Home Buildings – water damage – extent of rectification repairs SUMMARY OF FACTS 1. The applicant held a home building policy with the Financial Services Provider (FSP) from 16 June 2003. 2. The applicant lodged a claim with the FSP following the leakage of water from a pipe in his kitchen on 25 July 2007. 3. The FSP accepts that an insured event has occurred and arranged for repairs to be undertaken. Despite more than one attempt to repair the kitchen floor it remains in a damaged condition. The FSP accepts that it is responsible for repairing the floor area to a satisfactory condition. 4. The applicant asserts that as the kitchen forms part of an open plan living area, that the entire floor of the room should be replaced as matching tiles can no longer be obtained. 5. The FSP submits that it is only responsible for repairing the damaged part of the flooring and not replacing the tiles throughout the entire living area. The final cost of the dispute is yet to be quantified. ISSUE IN DISPUTE 6. Whether the FSP is required to replace all the tiles throughout the living area and not just the kitchen. RELEVANT POLICY PROVISIONS “How we settle a buildings claim We will decide how we settle your claim If your buildings suffer loss or damage, we will decide whether to repair, rebuild, or pay you the cost to repair or rebuild that part of your buildings that suffered loss or damage. If we do, we will ... only repair, rebuild or pay you for the part or parts of the building that actually sustained loss or damage, including damaged portions of fixed coverings to...floors...only in the room, hall or passage where the damage occurred. try to match any material used to repair your buildings with the original materials or nearest equivalent available to the original materials ... If we decide to repair or rebuild your buildings ... We will repair your buildings to the condition they were in just before the loss or damage occurred 205163 Determination 2 of 3 pay you the cost of repairing your buildings to the condition they were in just before the loss or damage occurred” REASONS FOR DECISION 7. The Panel is satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. 8. Following the leakage of water from a kitchen pipe on 25 July 2007, the applicant contacted the FSP to lodge a claim for damage sustained to the kitchen floor and the ceiling below. 9. Upon assessment of the claim, the FSP accepted that the claim lodged was one to which the policy would respond. 10. The FSP acknowledges that repairs to the kitchen floor have not been successful and agrees that the tiles are still required to be replaced. The dispute arises from the applicant’s request that the entire living area which encompasses the kitchen should be retiled as matching tiles are no longer available. 11. The applicant submits that the policy wording is such that his property should be replaced in a condition that it was in prior to an insured event occurring, that is with a full area of matched tiles. The applicant argues that as the kitchen section forms only part of a room then the tiling to the room should be replaced with matching tiles as it was prior to the water leak. 12. The Panel has carefully considered the policy wording and finds it clear that the FSP is required to repair the damaged portion of the floor only and not the entire area. As the living area floor outside the kitchen section remains undamaged then it follows that the FSP is not required to pay for the cost of replacing it. 13. The applicant has requested the cost to replace the kitchen. The Panel notes the FSP’s claims record dated 25 February 2010 indicates that approval was given for the removal and reinstallation of the old kitchen. 14. The applicant has not provided any evidence to substantiate the FSP has an obligation to provide a new kitchen and therefore, the Panel finds the FSP is not liable to comply with this request. The applicant also seeks the FSP arrange for the contents of the kitchen to be packed and stored whilst work is undertaken. 15. Whilst the policy does provide cover for contents to be removed and placed in storage, if the applicant is unable to remain living in the residence, the Panel is of the opinion that the general purpose of this benefit is to prevent further loss or damage to property. On this occasion, there would be no requirement to place the kitchen goods into storage as the Panel considers it reasonable that these items could be safely relocated within the residence. 16. The applicant has requested that the FSP pay the cost of alternative accommodation whilst repairs to the kitchen are completed as there would be no cooking facilities and the property would be hazardous to him and his family. 205163 Determination 3 of 3 17. The FSP has agreed, in an attempt to bring this dispute to an amicable resolution, to pay the applicant the cost of two weeks of alternative accommodation in accordance with the timescale provided by the repairer. The Panel considers this to be fair and reasonable resolution. 18. Finally, the applicant considers that the FSP be responsible for the professional cleaning of his entire home following repairs. The FSP has agreed to ensure that the damaged area is cleaned upon completion of works. 19. The Panel accepts that works of this nature can result in the production of dust and that cleaning is necessary upon completion of the repair work. The Panel notes the FSP’s efforts to effect a satisfactory technical resolution of the original problems have not been successful, thereby inconveniencing the lives of the occupants. In the circumstances the Panel believes it is fair, upon completion of the remedial work, that the dwelling should receive the benefit of a professional clean throughout. CONCLUSION 20. After a thorough reviewing all the evidence and considering the relevant issues, the Panel determines that the FSP is required to rectify the damage to the kitchen section only. This should include the cost of the removal and reinstallation of the original kitchen, and the replacement of the tiles within the kitchen area only and not the entire living area floor. 21. Furthermore, the Panel thereby determines that the FSP is required to arrange and pay for cleaning of the entire dwelling.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.