Home / Financial Firm (Unknown - Insurer) / Determination 202424

Determination 202424

Storm claim for collapsed bluestone wall declined

FirmFinancial Firm (Unknown - Insurer)
Decided2010-08-26
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant claimed under his home policy after a bluestone dividing wall collapsed in gale-force winds, and the FSP denied it as caused by faulty design, deterioration and structural failure. AFCA found the FSP had not discharged its onus and ordered the applicant indemnified for his proportion of the reinstatement cost, with no figure stated.

The insurer did not prove the faulty design, wear and deterioration exclusions, since the wall was built under the regulations current at the time.

Issues

Subjects and remedies

home or building damagenatural disasterpay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

202424 Determination 1 of 6 DETERMINATION Case number: 202424 Home Building – storm – faulty design – deterioration SUMMARY OF FACTS 1. On 5 September 2009 a blue stone dividing wall at the applicant‟s tenanted property collapsed during strong winds. 2. A claim under his home insurance policy was denied by the Financial Services Provider (FSP) on the grounds the collapse of the wall was due to inadequate design and faulty construction and not from an insured event. ISSUES IN DISPUTE 3. Whether the damage was caused by inadequate design and faulty construction of the blue stone wall. RELEVANT POLICY PROVISIONS “Storm … We will under buildings insurance  …  rebuild or repair that part of any gate, fence, free standing wall that was damaged by wind, unless  they were not kept in good order and repair, that is they were not structurally sound or well maintained. … What you are not covered for – general exclusions We will NOT cover  loss, damage, injury or death that occurs as a result of – … – wear, tear, rust, corrosion, deterioration or erosion . – … – faulty design or workmanship – … – mechanical, structural o r electrical failure of an item.” REASONS FOR DECISION 4. I am satisfied that a full exchange of information has taken place between each party and that each party has had the opportunity to address any issues raised. The Applicant’s Submission 5. The FSP‟s engineer‟s reports are speculative. They contain no definitive evidence to support their conclusions. 6. There are no specific requirements or building regulations for fences up to 2m high. 7. Gale force winds up to 120 kph + were experienced over a ten day period. 202424 Determination 2 of 6 8. The fence/wall was designed and built 40 years ago to appropriate requirements of the day by qualified architects and stone -masons. 9. The „incident‟ which caused the damage was storm and gale force winds over a period of 10 days which collapsed the wall. These circumstances meet the terms of the policy. 10. The wall has been in an excellent state of repair and had not moved as indicated by the plunge pool gates locking mechanism not needing adjustment in the last 4 years. 11. The value of the replacement wall is established to be in the order of $40,000 to $50,000. 12. Their neighbour ‟ s home insurance policy is similar to their policy and their neighb our‟s insurer accepted the claim. The FSP ’s Submission 13. It relies on reports obtained from a consultant builder and a consultant engineer. 14. The maximum wind gust on the day of the loss was 46kmh and according to the Beaufort Wind Scale, was unlikely to cause any sort of damage. The damage to the bluestone wall was a result of faulty design or workmanship, structural failure, wear and tear and deterioration all of which are excluded from the policy cover. 15. Maximum wind gust recorded on 1 and 4 September 2009 of 72kmh was not capable of causing any damage to a bluestone wall. 16. Additionally, free standing walls are covered for „wind‟ damage if they are kept in good order and repair. 17. There was no damage to the appli cant‟s property caused by storm. 18. The expert evidence is that the damage was not directly caused from winds that occurred during August/September 2009. 19. In any event, the principles of Wayne tank and Pump Company Ltd v Employers Liability Assurance Corporation Ltd [1974] 1QB 57 that when two or more proximate causes give rise to a claim, one of which is excluded, the insurer is entitled to apply the exclusion, and has no liability for the loss 20. The damage was not due to storm or any insurable event covered by the policy. 21. The maximum wind gusts on the date of the loss was 46kmh would not have caused the damage. 22. On balance, the damage was caused by wear, tear, deterioration as well as faulty design and workmanship. Consideration of each party’s submission 23. When making a claim under an insurance policy, the responsibility rests with the policyholder to establish on the balance of probabilities that the cause for the loss claimed falls within the terms of cover provided by the contract. An insurer relying on clauses in the contract to deny the claim has the burden of establishing on the balance of probabilities that the terms of the relevant clauses apply to defeat the claim. 202424 Determination 3 of 6 24. As there has been an exchange of the material between the parties, the reports submitted to me will be summarized only and quoted where relevant. 25. The FSP relies substantially on reports from consultants commissioned by them. 26. The report by “MM” provided the following relevant information:  Cause for the collapse is unknown  There is no evidence of brick support pillars in the wall  Suggested wall height was not in accordance with building standards. 27. Report by “HCE” dated 1 October 2009 included the following relevant information  The Bureau of Meteorology (BOM) maximum wind gust in Melbourne during August/September 2009 was 104kmh (56.2 knots) on 25 August 2009.  The fence is approximately 1900mm high with the lower 500mm retaining soil. A design check of such a fence showed that it is inadequate to resist normal loads applied to the wall.  In his opinion, the collapse has not directly resulted from winds that occurred in August/September 2009. The recorded 56.2 knots that occurred on 25 August 2009 was within current code requirements and design criteria for a wall, and would not have been of sufficient strength to directly result in the collapse, but highlighted pre-existing problems with the fence.  In his opinion, the collapse was due to inadequate design and construction to resist normal loads. 28. In a further report dated 4 January 2010 consultant HCE provided the following information:  The BOM maximum wind gusts recorded in Melbourne and Frankston around 5 September 2009 was 46kmh.  Normal wind loads in accordance with current code requirements include gusts up to approximately 160kmh.  In their opinion, building regulations at the time the wall was constructed would have required structures to resist much higher wind gusts than 46kmh.  Rotation of the lower section of the wall suggests that movement of the wall has been occurring over some period of time.  Rotation of the wall may have resulted from differential settlement due to seasonable changes in moisture content accentuated by tree root drying originating from trees adjacent to the fence.  In their opinion collapse of the wall was accentuated by the rotation evident at the lower section of the wall resulting in the centre of gravity not being central to the wall which would contribute to further movement and the collapse.  In their opinion, the collapse has not directly resulted from winds that occurred around 5 September 2009. The recorded maximum wind gust of 24.9 knots was well within current code requirements and would have also been well within building regulations at the time the fence was built. 202424 Determination 4 of 6  In their opinion collapse of the wall was inadequate construction and design to resist normal loads and accentuated by likely movement in the fence due to differential settlement and rotation of the footings. 29. The BOM Weather Observations tables show maximum wind gusts recorded from 1 September 2009 to 5 September 2009 at: • Frankston were 41kmh, 31kmh, 56kmh, 56kmh and 46kmh • Melbourne were 39kmh, 69kmh, 72kmh, 72kmh and 46kmh 30. The BOM Weather Observations recorded the following maximum wind gust: Frankston 25 August 2009 96kmh 31. The Beaufort Wind Scale reports the following: 88-120kmh Seldom experienced inland, trees uprooted, considerable structural damage 40-50kmh Large branches in motion, whistling herd in telephone wires Pre – loss condition of the wall 32. Consultant HCE considered the construction and design of the wall was inadequate to withstand normal loads, and this contributed to its collapse. HCE was of the opinion the building regulations at the time the wall was built would have required the wall to resist a much higher wind gust than 46kmh. 33. The consultant has not provided any authoritative material to support his opinion. His opinion is also based on wind gusts of 46kmh. 34. On the other hand, the applicant advised he was informed by the owner of the house at the time it was constructed that an architect was appointed. The construction included feature blue stone walls and fireplace in the house in addition to the feature side wall/fence. The architect sought qualified stone masons to carry out the blue stone work on the premises, and all construction was carried out in accordance with the Building Code of the time. 35. The applicant further states he contacted the area town planner who advised that footings required in 1974 in some cases needed to be only 10” deep. 36. Material provided by the applicant shows that a building permit is not required for dividing fences up to 2m height, although the fence must comply with Building Regulations 2005 and Building Code of Australia. 37. Additionally the applicant states that two plunge pool gates with vertical drop bolt-catches were attached to the wall. He argues that had there been more than 1/2mm of movement in the wall than the gates would not lock. A statutory declaration completed by the tenant occupying the property deposes the gates were operating normally until the fence blew over. 38. The applicant says the premises were located about 250 metres from Port Phillip Bay. The wall was about 40 years old. It is generally accepted that properties located close to large areas of open water are subject to wind forces stronger than that which may be experienced further inland. It is therefore reasonable to conclude the wall had withstood the force of extremely strong winds over its 40 year life. 39. With this in mind, it is my opinion that while the wall may not comply with current building regulations, as it was constructed under the supervision of an 202424 Determination 5 of 6 architect, it is reasonable to conclude the construction including the blue stone wall was carried out in accordance with regulations current at that time, and in a competent workmanship like manner. 40. In his statutory declaration, the applicant‟s tenant deposed that in the four years he had lived in the premises, the house and garden were kept in an excellent state of repair. The tenant went on to say, any maintenance requested including cleaning gutters, pool pump replacement and tree pruning was attended to promptly by the applicant. 41. In these circumstances, I am persuaded that there was no reason for the applicant to consider the wall was failing and required maintenance. To the contrary as the tenant noted the pool security gates operated correctly up to the time of the damage, there was no basis for the applicant to believe the wall was in danger of failing or requiring remedial attention. 42. The policy provides cover for wind damage to free standing walls unless it was not kept in good order and repair, or were structurally unsound or not well maintained. Significantly the policy distinguishes between the winds required to cause damage by „storm‟ and w inds which cause damage to fences. That is for „storm‟ cover , the winds must be violent winds, cyclone or tornado. In contrast, the cover provided for free standing walls simply requires that the wall be damaged by wind. Hence the test for damage to free standing walls within the insured event “Storm” differs from that required to other structures insured by the policy. 43. It is not in dispute that the wall collapsed during strong winds at the time. 44. The evidence has established that the maximum wind gust recorded at the time of the damage was 46kmh. Moreover the tenant described the wall collapsed during „gale force‟ winds. 45. For these reasons I consider that the applicant has established a prima facie claim under the policy. Faulty design or workmanship, deterioration, structural failure 46. Consultant HCE offered the opinion that the collapse was due to inadequate design and construction and likely rotation of the footings . 47. In matters involving property design and construction, regard must be had to the prevailing regulations at the time of construction. To do otherwise would render many older properties open to the prospect of having insurance claims challenged on the grounds of non compliance with current regulations. Clearly this practice would not be consistent with good insurance practice or commonsense. 48. It has been established to my satisfaction the wall was constructed under the supervision of an architect, and in turn, in accordance with regulations current at that time. 49. While the wall design may not comply with current building regulations, no evidence has been provided to show that it failed to comply with the building regulations prevailing at the time it was built. 50. In these circumstances, I consider the FSP has not established that the design and construction methods employed to build the wall were faulty. 202424 Determination 6 of 6 Rotation of footings 51. Consultant HCE further was of the opinion the collapse was accentuated by likely movement of the wall due to differential settlement and rotation of the footings which were affected by tree roots from nearby trees. He observed rotation to the lower section of the wall and relied on his experience with sudden wall collapses with no prior movement when in these instances , the remaining lower section was generally plumb. 52. While the consultant observed the lower section of the wall had rotated, he nevertheless considered the rotation accentuated the other conditions of the wall which in his opinion were responsible for the collapse. He has not attributed the collapse to the rotation of the footings. 53. I have considered this matter in conjunction with the tenant‟s evidence that the wall had not rotated to the extent that the gates fitted to the wall or the gate security locks required any adjustment. Had the rotation observed at the lower sections of the wall transferred to any significant degree to the upper sections of the wall to the extent that a change in the centre of gravity contributed to the collapse, then it could be expected there would be some evidence of the wall movement in the area of the pool gates. This was not the case. CONCLUSION 54. Having regard to the available material, I conclude on balance that the FSP has not discharged the onus that rests with it to show the claim does not succeed. 55. Accordingly I determine the applicant is entitled to be indemnified for his proportion of the cost to reinstate the wall.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.