Determination 202062

Scope and cash settlement of flood and storm building repairs

FirmFinancial Firm (Unknown - Insurer)
Decided2010-12-14
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$40,513
Non-financial loss—
Amount claimed$55,704
SourceAFCA PDF

Summary

Following storm and flood damage to his home, the applicant disputed the FSP's cash settlement and scope of works. AFCA accepted the applicant's builder quotations and ordered a further cash payment of $40,513.44, rejecting reassessment by a new assessor and the air-conditioner complaint.

Where the insurer's assessor repeatedly missed damage, the reasonable quotes obtained by the insured are accepted and reassessment is not warranted.

Issues

Subjects and remedies

pay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

202062 Determination 1 of 12 DETERMINATION Case number 202062 Home Repairs – settlement SUMMARY OF FACTS 1. The applicant insured his home building and contents for $275,000 and $150,000 respectively, against loss or damage caused by insured events with a $500 policy excess. On 5 April 2009, the applicant lodged a claim for flood water damage to his home building and contents that occurred on 31 March 2009. The FSP recorded the incident as: “*** FLOODS *** 2 x sheds, 1 x garden shed, outside laundry, content damage, Home – floor and wall damage to verandah, bathroom, bedroom, kitchen and room. Power Off approx 18 hours, food spoilage.” 2. The Financial Services Provider (FSP) cash settled the contents claim for $150,000, but a dispute has developed in respect to the extent of repairs to the home buildings. 3. The FSP arranged for a number of assessments of the property, but the applicant has not accepted the Scope of Works that had been prepared by the FSP‟s builder. 4. The FSP has requested a new assessing firm inspect the property to address the applicant‟s concerns. However, the applicant has not accepted this request and wants his dispute determined by the Financial Ombudsman Service (FOS) Panel. ISSUES IN DISPUTE 5. Whether FOS is in a position to determine the dispute; or 6. whether an additional assessor should inspect the property and submit a revised Scope of Works. RELEVANT POLICY PROVISIONS “What you are covered for ... Insured events 1 to 12 When covered under this policy, your home and contents are insured for loss or damage at the insured address by any of the 12 insured events, if they happen in the period of insurance. 1. Storm and flood We cover Loss and damage caused by storm and flood ... How to establish your loss ... Things you must do – allow us to inspect the damaged home or contents 202062 Determination 2 of 12 – allow us to arrange for experts to assess the damaged home or contents and to quote on repair or replacement – provide us with a quote for repair or replacement if we ask for this. If you choose to use our recommended repairers (when available), there is no need to obtain your own quotes – consult an expert if we ask for this. Your co-operation is extremely important. If you do not co- operate we won‟t be able to assess and pay your claim. ... How we settle your claim ... New for old means: – ... – same type, standard and specification as when new We replace or repair to the same type, standard and specification as when new. If the same is not available, it means of a similar type, standard and specification when new. It can be a different brand. ... We choose how your claim is settled If we agree to pay a claim for loss, theft or damage to your home or contents, we will decide if we will: - repair damaged new for old or - replace home or contents new for old or - pay you what it would cost us to repair or replace home or contents new for old. ... We will not: - pay extra to replace your home or contents to a better standard, specification or quality than it was before the loss or damage occurred except as stated in „new for old‟ on the next page - fix a fault that existed before the loss or damage occurred. ... Home claims Repairing or rebuilding damaged parts We will only repair or rebuild the parts that are damaged by an insured incident. You cannot claim to replace undamaged parts of your home to create a uniform appearance, such as when: - ... - an external wall is damaged we will replace the damaged parts of the wall, not undamaged areas of the wall or other sides of your home.” REASONS FOR DECISION 7. The onus of proof is on the applicant to establish, on the balance of probabilities, that he has suffered a loss caused by a risk insured against. Once the applicant has established that the loss was prima facie caused by a risk insured against, the onus shifts to the FSP to show, on the balance of probabilities, that the loss falls within an exclusion in the contract of insurance. 8. There has been an exchange of material which the parties rely on. Each party has had access to the material on which the other party bases its case. As a consequence, it is not necessary to go into all of this material in any great detail. 202062 Determination 3 of 12 The Financial Services Provider’s Submission 9. It appointed an external assessor, “R”, a construction company, to attend the insured premises and report on the damage. The assessor confirmed that the premises had been damaged by flood water and storm, and on 23 April 2009 submitted an estimated cost for repairs to the building for the amount of $12,427. 10. The quote was authorised and R was appointed to complete the scope of works. On 2 June 2009, R submitted a variation to the scope of works to include damage to a shed and internal linings for the amount of $8,130. These additional repairs were also authorised to be completed. 11. On 27 July 2009, the applicant sent an email to R stating that numerous items had been left off the scope of works. The additional issues and items were: 1. Piers of the house had moved from the storm and water activity; the applicant requested an engineer inspect and report on the stability of the structure. 2. Surrounding footpaths have moved, some have cracked and seemed to be hollow underneath; 3. Hot water service to be replaced with a Dux solar-3 panel system; 4. Damage to the laundry tub, floorboards, door and wall; 5. Damage to a toilet behind the laundry; 6. Damage to a garden shed wall and corner; 7. Damage to the lino in the sunroom and kitchen; 8. Damaged kitchen cupboard and sink need to be replaced; 9. Damage to frame work of two walls inside the main shed and all timber shelving, spread of mould; 10. There is remaining mud and silt; 11. Roof and ceilings storm damaged; ceilings are sagging; roofing iron damaged by rain; rear sun room and the front verandah are the worst; weight of water on the roof may have buckled the sheets and caused movement and started leaking into the roof cavity; mould in the roof cavity; 12. Clothes line no longer winds up or down and the base is rusting; 13. Repair work on the main rear sheds is not up to a reasonable standard. 14. Water damage to the rear storage cupboard in the sunroom; 15. The original air conditioner was a Fujitsu but has been replaced with a Mitsubishi; he was informed that it would be replaced with a Fujitsu. 12. The assessor building consultant met with the applicant on 12 August 2009 to review the above issues raised. He recommended that an engineer be appointed to inspect and report on the piers and footpath. R also provided an amended scope of works dated 12 August 2009 to include the missing items listed by the applicant and the quote was increased by $11,835. 13. The consultant reported on the issues raised by the applicant as follows: 1. Several of the concrete stumps have a significant lean; the internal brick piers appear to be dry stacked; engineer to be appointed to determine if damage storm related; 2. Engineer to inspect and report on the footpaths; 3. Applicant was cash settled for the hot water service; 202062 Determination 4 of 12 4. Not previously assessed – allowance made to replace the laundry tub and paint the hardwood floor; 5. Not previously mentioned – allowance made to replace the toilet suite; 6. Not previously mentioned – corner of garden shed dented; 7. Remove and replace lino in the sunroom; 8. Water did not enter the kitchen – any movement to the kitchen cupboards would be due to pier movement – engineer to confirm; 9. Allowance made to replace water damaged pine timber wall frames; spray antibacterial on shelving; 10. Mud and silt in yard only; internal areas clean; 11. Masonite ceiling in sunroom has sagged and needs replacing – allowance to replace with plasterboard; External verandah ceiling needs painting due to surface mould; no visible damage to roofing sheets; 12. Rust around base of clothes line not due to storm; damage to winding mechanism a maintenance issue; 13. Repairer to correct issues of minor workmanship rectifications; 14. Not previously mentioned – replace the damaged cupboard and paint; 15. Applicant reported air conditioner was making a significant noise after it runs for an extended period of time – Unit was turned on during assessment without any sign of undue noise – applicant informed that if noise persists, contractor would attend and carry out checks. 14. However, on 4 September 2009 the applicant provided a list of items he considered had not been included in the revised scope of works. These were: 1. Northern and eastern walls of the sunroom blown out and should be replaced when plasterer repairs the ceiling; 2. External cladding was torn from its fixture by the storm; temporary repairs carried out by the applicant; 3. Lino in the kitchen is warped and should be replaced; quote to be provided; 4. Hardwood shelving in the main shed and adjoining shed still wet and creating mould; assessor agreed cheaper to replace than dry out; 5. Insulation on the entry door to the shed was not replaced – it was four sheets of canite; 6. Footpaths that have cracked now hollow; 7. Faulty workmanship to main shed not attended to; if nothing is done applicant will arrange for a contractor to check on the quality. 15. It responded to the applicant ‟s concerns as follows: 1. The engineer and plasterer advised that the northern and eastern walls did not require replacing, the only sign of water damage is staining and the walls should be painted as per the original scope of works; 2. Damage to external cladding – the engineer advised that he had noted this damage in his report; the assessor stated that he would comment on this when the engineer‟s report has been received. 3. Lino in kitchen – waiting for quote to be submitted. 4. Pine shelving not included in the scope of works, it was the pine wall framing that is to be replaced. Shelving is to be sprayed with antibacterial to eliminate surface mould. 5. Insulation on entry door – to be discussed with carpenter. 6. Engineer to inspect and report on the footpaths. 202062 Determination 5 of 12 7. The carpenter has advised that he is more than happy to address the issues raised regarding workmanship. He will be rectifying the issues when he is onsite carrying out work to the cupboard in the sunroom. 16. On 18 September 2009 it received the engineer‟s report. T he report stated, in part:  There appears to have been some lateral movement of the building as a whole, however from observation of the existing connections, it does not appear that major damage has resulted, or that the building is at risk of collapse;  That there is no effective bracing tie down or restraint of the sub-floor building support structure which is essential for stability in high winds or flood conditions. 17. The report further stated: Analysis of Results and Likely Causes of Foundation Failure The weak foundation material identified to a depth of 0.8 to 1.0 metre below the surface would be capable of supporting foundation loads exerted by the light- weight framed-clad building while the foundation material remains in a relatively dry or slightly moist condition. However, under saturated conditions which can result from inundation for extended periods of time, or from a rising water table, such material would become weakened to the degree that differential settlement of individual footings, or rotation of footings is likely to occur. Cracking of Reinforced Concrete Paving Slabs The engineer considered that the cracking of the reinforced concrete pathway slabs was not the result of the March 2009 storms or inundation. Interior of Dwelling Inundation which occurred in March 2009, where humidity of the interior of the building would have been elevated for several weeks following inundation and saturation of floors and floor coverings, cabinets etc could possibly have caused more severe buckling and warping of hardboard linings. Interior of Garage/Shed It is obvious that inundation would damage pine particle board shelving and the door interior lining. The hardwood timber shelf framing is unlikely to have been affected structurally by the relatively short duration of flooding. Damage to Exterior Cladding Damage to the exterior of the dwelling was limited to the top of the sheet metal (aluminium) cladding at the north-western corner of the dwelling. This had been fixed using “Tek Screw” sheet roof fixing screws. The damage to the aluminium sheet cladding at the north-western corner was reportedly caused by relatively high velocity wind during the March 2009 storms. It is likely the original fixings were not adequate for such a failure to occur. Although it is possible that local high velocity wind can occur, the wind-storms experienced in March/April 2009 were not identified as exceptionally high velocity „cyclonic‟ conditions. It is the engineer‟s view that failure of the cladding fixing occurred as a result of inadequate fixing during the original application of the cladding system . 202062 Determination 6 of 12 18. Based on the engineer‟s report on 24 August 2009 , the assessor included wall linings, fibre cement sheeting, wall skirting, architraves and paint to the scope of works for the amount of $3,486. 19. On 21 September 2009, the applicant advised it that there were still items missing from the scope of works. It offered to have its assessor re-inspect the property one last time only if the applicant provided a list of his issues with his scope of works. 20. On 19 October 2009, the applicant provided it with a report from a building maintenance firm. Its assessor advised that all the mentioned work had been previously addressed within previous reports. 21. On 21 October 2009, it issued a letter to the applicant de nying liability for the damage to the piers to the external walls, water damage to the kitchen cupboards, weatherboard, concrete pathway, garage shelving and external clothes line. It cash settled the applicant for the amount of $15,190.12 less $500 excess for the building repairs. 22. Following the applicant submitting a Referral Notice to FOS, and discussion with FOS, it sought to appoint a new assessor to inspect the premises and complete a new scope of works. The applicant has not agreed to a re- assessment. 23. It considers that the offer of settlement made to the applicant represents the amount that it would have paid to a qualified repairer to rectify the damaged building. 24. It obtained numerous scoped quotations from qualified repairers to repair the property. During the claim process the applicant raised numerous issues regarding the scope of works. The applicant did not raise issues on each inspection, but only after the fact. This required re-assessment each time and created confusion for all parties involved. 25. Due to the complexity of the issues and the number of concerns raised, it has offered a re-inspection by a new assessing firm to walk through the property with the applicant and detail one report that covers each of his disputes. It has attempted to arrange this with the applicant without success. 26. The settlement offer to the applicant has been calculated on a quote provided by a qualified tradesperson. While the applicant suggests the quote is incomplete, he has not agreed to allow a re-inspection of the property to assess the missed items. Based on the evidence available, it believes that is has settled the claim appropriately considering the circumstances of the preceding events. The Applicant’s Submission 27. He appointed a builder to inspect and report on the damage to his house. In the builder‟s report dated 27 September 2009 he stated:  Laundry, outside toilet, lawn locker The area had contaminated water to a depth of approximately 1 metre during the flood. Work needed to repair: – Remove timber floor from laundry and replace with compressed cement flooring, remove asbestos wall cladding and replace with 202062 Determination 7 of 12 Hardie plank; replace both timber doors plus jambs and architraves then paint all new materials; – Replace damaged toilet and replace 2 damaged wall sheets on lawn locker.  Shed – Back room had been flooded to a depth of over 2 metres. Repairs have not been completed. The frame work on shelves was not replaced and the new shelf material grows mould as the moisture comes out of the saturated frame work. – Internal pine stud walls in the garage were to dry before being covered with ply wood lining; the pine studs continue to grow mould and the ply wood lining has not been installed. – The workmanship to install the new cladding to the outside of the shed is far from acceptable with large steps in sheets, screws missing beams and ill fitting trims on all sides. – Overall the workmanship is unsatisfactory and some work has not been completed, e.g, lining to the internal walls. – Repair work required is to replace all shelving materials and to construct; replace internal pine stud walls then cover with ply wood left on site; carry out rectification work to the exterior cladding.  The house – The house had water over the floor in the back 4 rooms, that is, kitchen, bedroom 2, bathroom and rear living room. Due to the water being contaminated by sewerage, a health risk still lingers. – Repair work to be completed is: – New doors to the back entry, bathroom, lined press, kitchen and bedroom 2. New architraves and door jambs to all these doors, architraves and reveals to all windows, skirting boards to the 4 rooms. New handles and hinges; replace vanity in bathroom; replace kitchen cupboards; paint all timber and doors. – The house has had vinyl cladding on the left side come off during the storm. The owner screwed this back up temporarily to prevent further rain entering the dwelling during the height of the storm. The cladding profile would not be able to be successfully matched as it would be over a decade old. The only way of rectifying the problem with the damaged cladding would be to reclad the entire house.  Front verandah – The ceiling and eaves to the front verandah has water damage. Replace both, new quad and paint. 28. He also contends that the following problems are outstanding:  Shed Replacement sheets of cladding have been put onto the walls. However, the original sheets, and in particular their original screws, have left holes and they are beginning to rust and also the purlins and columns of the frame are all showing signs of oxidization and beginning to rust in places. 202062 Determination 8 of 12 He was been informed by the supplier that the entire shed should be replaced. 29. The FSP has stated that he did not report damage to all of the external structures, laundry, garden and main sheds, the sunroom and bathroom, kitchen and spare room. However, he reported the damage to the FSP when he lodged his claim. He also showed the damage to a FSP representative. 30. Although the FSP‟s assessor/builder stated that there are only 2 levels to his house there are in fact 4 levels, 2 of which were damaged in the flood. The lower two levels were damaged by contaminated storm water and also sewerage that was pumped out of the toilets. These rooms were the sunroom, bathroom, kitchen and spare bedroom. 31. The FSP accepted that there was damage to a cupboard and lino/vinyl, but is stating that other areas in the same room have not been damaged. It is beyond any doubt that there was, and is, damage to all rooms that were initially reported as being damaged. Shelving and frames The pine shelving and hardwood shelving frames should be replaced because of the damage caused by the contaminated water. The FSP advised him to spray them with a chlorine and water solution, and let them dry out. However, mould continues to grow on the timber and should be replaced. Outstanding work There are repairs that have commenced and some that have not been started. There are entire walls unfinished and materials left sitting on the floor. Work not included on the Scope of Works He repeatedly stated to the FSP and its assessor that there were many items of damage that had not been included on the Scope of Works. This frustration caused him to obtain inspections and quotes from other tradespeople independent of the FSP and assessor. The additional damage assessed by these tradespeople was then added to his claim. Consideration of each party’s submission 32. The FSP contends that its settlement offer to the applicant has been calculated on a quote provided by a qualified tradesperson. While the applicant contends the quote is incomplete, he has not agreed to allow a re -inspection of his property to assess the missed items. Based on the evidence available , the FSP believes that it has settled the claim appropriately considering the circumstances of the preceding events. 33. The FSP also contends that in view of the complexity of the claim, a re- assessment of the applicant‟s property should occur. 34. The applicant states that the FSP has failed to fully indemnify him for the damage to his property caused by the flood and storm event on 31 March 2009. 35. Following the flood and storm event, the FSP appointed an assessor builder (assessor) to inspect and report on the damage to the applicant‟s property. The assessor inspected the property on 23 April 2009, and prepared a Scope of Works with an estimated cost of repairs for the amount of $12,427. 202062 Determination 9 of 12 36. However, the applicant disputed the assessor‟s Scope of Works as not including all of the damage caused by the flood. As a result, the following additional inspections were carried out:  2 June 2009 – estimated cost of repairs increased by $8,130  12 August 2009 – estimated cost of repairs increased by $11,835  24 August 2009 – estimated cost of repairs increased by $3,486 The estimated cost of repairs now total $35,878. The Panel notes that there were no itemised costs of repairs to support the Scopes of Works. 37. In addition to the disputed flood damage, the applicant also contends that the FSP replaced a damaged Fujitsu air conditioning unit with a Mitsubishi model which he states has not put him in the same position as he was before the flood damage. 38. In spite of its appointed assessor‟s estimated cost of repairs, the FSP elected to cash settle the applicant for the amount of $15,180.12 less the $500 policy excess. In addition, the FSP has paid the following: 5/08/2009  Cash settled the applicant for a hot water system $1,200 7/07/2009  Payment to builder for works carried out $23,503.40 39. The FSP has identified the items it cash settled, in total, from the four scopes of works. However, the following items were not included: 23/04/2009  Garage/shed Remove and replace colourbond external wall cladding Remove and replace wall insulation Replace any capping and flashing required to carry out repairs Test all power points and lights 2/06/2009  Garage/shed Remove and replace colourbond roller door 12/08/2009  External toilet Remove and replace 2 x zincalum wall sheets to right rear corner 24/08/2009  Sunroom Remove and replace the wall linings with hardboard or fibre cement sheeting Remove and replace skirting and architraves to carry out repairs Prepare and paint all new timberwork to match existing 40. The FSP has stated that there was no damage to the kitchen area. However, photographs, and the applicant‟s builder, confirm tha t the kitchen was inundated causing damage to the floor, walls and kitchen cabinets. 202062 Determination 10 of 12 41. The applicant has informed the FOS that the majority of the repairs listed in the scope of works have not been completed or only partially completed. This has also been co nfirmed by the applicant‟s builder. 42. The applicant has submitted that the following revised quotations (the original quotations were revised due to the elapse of time) for repairs which remain outstanding: Item Cost Incl GST 1. Remove and replace damaged kitchen $3,256.00 2. Electrical repairs $1,129.70 3. Supply and lay vinyl floor coverings $5,578.00 4. Plaster repairs to walls and ceilings in bedroom 2, sunroom, kitchen, and bathroom $12,500.00 5. Supply new shower system $1,289.86 NOTE: Applicant’s Builder – The builder, has deducted payments made by the FSP from his quotations for items 6. 7 and 9. Laundry, outside toilet & lawn locker 6. Remove timber floor from laundry and replace with compressed cement flooring, remove asbestos wall cladding and replace with Hardi planking, replace both timber doors, jambs and architraves, paint all new work, replace damaged laundry tub and toilet; replace 2 wall sheets on lawn locker. (Replacement laundry tub and toilet suite paid by FSP) Quote for difference $4,400.00 Main Shed 7. Replace all water damaged timber shelving and frames in the shed/garage and install new wall linings when work completed. Quote for difference $2,200.00 8. Rectify repair work to the external cladding $1,800.00 The House 9. To supply new external back, bathroom, linen press, kitchen and bedroom 2 doors; install new architraves and door jambs to all these doors, architraves and reveals to all windows, skirting boards to the four rooms. New handles and hinges to doors. Replace lami panel; paint all new timber work and doors, paint bathroom, install new shower. Quote for difference • Replace the ceiling and eaves to front verandah $13,200.00 $1,100.00 Additional Repairs • Repairs to footings and piers as per insurer‟s engineer, to remove rotating piers from each side of the house and construct continuous strip footings and brickwork with ant capping $4,250.00 202062 Determination 11 of 12 External wall cladding to the house and garage/shed 10. The builder reported that the external vinyl wall cladding had been torn off and damaged. The colour cannot be matched and he has recommended anallowance be made for the replacement of the damaged cladding to the amount of: $5,000.00 Total additional cost of repairs $55,703.56 Less cash amount paid to the applicant $15,190.12 Amount payable by the FSP $40,513.44 43. The applicant has also submitted a claim to alter sewer pipes to the bathroom, renew hot and cold water pipes, traps and wastes for the basin, bath, shower, toilet and floor waste. 44. The applicant has informed FOS that these works are necessary to check the sub-floor area. However, these works have not been brought to the attention of the FSP, and were not raised by either the FSP‟s assessor or the applicant‟s builder. Therefore, the Panel determines that the applicant is to submit a report from a builder on the proposed works to the FSP for its consideration. If there is any dispute in respect to this issue, the matter may be referred back to the Panel for determination. During the storm a Fujitsu air conditioning unit was damaged requiring its replacement. The unit was replaced with a Mitsubishi model because the FSP stated that a Fujitsu unit was not available in Australia at that time. Due to the delay in sourcing the r equested unit and following the applicant‟s complaint about the delay, the FSP provided an alternative brand of unit with similar functionality. 45. Under the terms and conditions of the policy, the FSP, where a unit of the same type is not available, it is entitled to replace the unit with a similar unit of a different brand. Although the applicant accepted the installation of the alternative unit at that time, he has now submitted that a Fujitsu unit was available, and has provided a copy quote from a local supplier. However the document provided is simply a quote and does not indicate its availability. 46. The applicant subsequently became unhappy that the unit was not as quiet as his previous unit. In response to this, the FSP arranged for the unit to be examined, and it was found to be operating satisfactorily, with no undue noise. 47. In the absence of any clear evidence to the contrary, the Panel is inclined to accept that the Fujitsu unit was not immediately available, and therefore the FSP has discharged its obligation for the air-conditioning unit. CONCLUSION 48. The applicant‟s home sustained considerable damage caused by the flood and storm event. This is supported by the total loss of the contents of the applicant‟s home. 49. However, from the evidence presented by both parties, the claim for damage to the home building could have been more efficiently and effectively by the FSP and its assessor/builder. The assessor first inspected the applicant‟s property on 23 April 2009. However, there were three additional inspections on 2 June, 202062 Determination 12 of 12 12 August and 24 August 2009 which resulted in further repairs being added to the Scope of Works. 50. The FSP suggested that the additional inspections were caused by the applicant failing to report all of the damage. The Panel does not accept this as it would have expected the FSP‟s assessor/builder should have had the experience and knowledge to identify the damage caused by the flood and storm. 51. The FSP has submitted that due to the complexity of the issues raised by the applicant, a re-inspection by a new assessing firm with the applicant be carried out. The Panel does not consider that there are any complex issues that need to be addressed. The only issues to be addressed are the outstanding repairs to the applicant‟s home buil ding. 52. Although the FSP cash settled the applicant for the amount of $15,190.12 and paid the assessor/builder $23,503.40 for repairs, the applicant appointed his own tradespeople and a builder to assess the outstanding damage to his home. 53. The Panel has revi ewed the various quotations and builder‟s reports and finds that they are fair and reasonable. 54. Therefore, the Panel finds that, in view of the quotations and builder‟s reports submitted by the applicant, there is nothing to be gained by having a re- assessment by a new assessor. 55. Accordingly, the Panel determines that the FSP cash settles the applicant‟s claim for the amount of $55,703.56 less the cash payment of $15,190.12 that is $40,513.44.