Home / Financial Firm (Unknown - Insurer) / Determination 200192
Determination 200192
Earthquake-related home cracking claim refused as soil movement
Summary
The FSP attributed cracking to soil movement and refused the home building claim. AFCA reviewed a recommendation, preferred the applicant's engineer, and ordered the FSP to pay 70 percent of repair costs plus the cost of the applicant's expert report.
The applicant's expert evidence that the March 2009 earth tremor caused or exacerbated the damage was preferred, with cost apportioned 70/30.
Issues
- Claim denial primary · upheld“I prefer the applicant's expert and I accept his opinion that the damage was caused or at least exacerbated by the earth tremors in March 2009”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensation
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
200192 Determination 1 of 3
DETERMINATION
Case Number: 200192
Home – earthquake – proximate cause
SUMMARY OF FACTS
1. This is a Review of a Recommendation by the Service dated 25 August 2010.
The applicant has rejected the Recommendation and pursuant to the Terms of
Reference, the matter has been referred to me for determination.
2. The relevant facts, policy provisions and issues in dispute are set out in the
Recommendation annexed herewith. For the sake of brevity and conciseness, I
will not repeat same.
3. I have read the material submitted by the parties ’ and I have carefully
considered the submissions including the applicant’s further s ubmissions dated
the 14 September 2010 and the 7 October 2010, and the FSP’s further
submissions dated 1 October 2010 and 29th November 2010. I have also read
and carefully considered th e applicant’s expert’s Report (L) dated 17 November
2010 and the FSP’s further consultant’s report ( C) dated 25th November 2010.
4. I have read the Recommendation and I noted with approval, the reasons given
by the Case Manager in support of the Recommendation. Of course, that
Recommendation was based on the material on hand at the time. The Case
Manager did not have the material that is now available to me. As will be seen
from my comments below, and on the basis of the additional material, I have
taken a different view from the Case Manager.
REASONS FOR DECISION
5. The relevant facts are set out in the Recommendation and the central issue in
dispute is whether the cracking to the applicant’s property was caused by
earthquake activity that was recorded in the Gippsland area (Korumburra) in
March 2009. It is well known that an earthquake (4.2) affected a substantial
area including greater Melbourne. Ample evidence has been supplied in
respect of the incident, although the extent of the damage to the property was
only noted some months after the event after the applicant returned from an
overseas trip.
5.1 I will concentrate on the matters at issue that have been addressed in the
supplementary reports. When this matter was before the Case Manager, the
FSP provided a consultant’s report (C) that attributed the damage primarily to
soil movement (excluded under the policy), but the applicant had not taken
expert advice. Since receiving the Recommendation, the applicant has taken
advice from an expert engineer (L).
5.2 In summary, L, a consulting geotechnical and forensic engineer, expressed the
opinion that the damage is not associated with soil (footings) movement, trees
and plant’s and moisture, but rather, “ it is likely that the lateral displacements of
the earth tremor have caused the problem”. The Report is thorough and
appears to be well reasoned.
200192 Determination 2 of 3
5.3 The FSP referred the Report to its consultant (C) who gave a further report
addressing the applicant’s expert’ s opinion that the damage was earthquake
related. The further consultant’s report :
Notes in the introduction, three issues that form the basis of the L’s
report and asks a somewh at bland unresponsive question “ How has
this statement been substantiated or proved” . The three questions are,
in my view, typical of the questions asked of experts in building cases
and C’s question is not easily understood or at least of no real
assistance to me in evaluating L’s report.
The second issue in L’s report deals with “Site Soil Building Conditions”
and notes it has been classified Class M”. C makes the comment that
by definition, this site will experience moderate ground movement and
this allegedly “contradicts the general findings of the report where
movement in sub floor or foundation can be expected”. There is no
additional supporting material to support this contention.
The third issue dealt with in L’s report is “Distress Condition”. C makes
an observation as to a timing issue and notes there appears to be
confusion about the timing of the alleged damage. Again, the criticism
lack’s detail and substance.
The fourth issue in L’s report is “Footing Details”. C states that the
comments on that issue are “hearsay” derived from information
supplied by the applicant. In my opinion, that is normal procedure,
particularly where, as here, the applicant was the builder of the subject
house. C expresses the opinion that there is uncertainty in the
construction method used, but that may not be the case and appears to
run counter to L’s understanding as to the nature of the construction
used by the applicant.
C recounts L’s report in respect of the issue of “Cause of Distress” and
simply makes the comment that the causes articulated have
inaccuracies and uncertainties in certain wording adopted. Again, this is
lacks detail and the explanation does not assist me in my task of
determining the cause of the damage and in weighing the evidence
including the expert evidence.
6. In addressing the difficult issue of deciding between differing consultant’s
opinions, I note that neither consultant expressly qualifies himself as an expert.
The applicant’s consultant is a qualified engineer with a Masters degree , in
addition to his undergraduate degree, whereas the consultant C has no
apparent formal qualification beyond description as Building Consultant and
Licensed builder in Queensland and Victoria.
CONCLUSION
7. Having regard to all of the above matters , I prefer the applicant’s expert and I
accept his opinion that the damage was caused or at least exacerbated by the
earth tremors in March 2009. Because of the number of possible contributing
factors, it is a complex and difficult task and I deem it appropriate to apportion
the cost of the damage on a 70/30% basis in favour of the applicant.
200192 Determination 3 of 3
8 . Accordingly, I determine the FSP pay 70% of the cost of the repairs and I
further determine that the FSP pay for the cost of the applicant’s expert Report.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.