Summary

The insurer accepted a storm water damage claim but offered a low cash settlement, citing pre-existing defects. AFCA found the offer unreasonable and ordered a cash settlement based on the complainant's adjusted quotes with a 15% uplift, $3,000 non-financial loss and interest.

A cash settlement must be based on a reasonable quote actionable by a retail customer, and the insurer did not adequately justify its much lower pricing, while claim mishandling caused unusual stress and inconvenience.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interestpay non financial loss

Related

All Hollard determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-322565 | Financial firm | Hollard Insurance Partners Limited Case number: 12-25-322565 17 July 2026 1 Determination overview 1.1 Complaint The complainant held a home and contents policy with the financial firm (insurer). The policy period was for 12 months from 6 December 2024. The building was insured for $583,000.00, and the policy excess was $1,000.00. The complainant lodged a claim on 6 May 2025 for extensive water damage to his home following a storm on 30 April 2025. The insurer accepted the claim. However, due to pre-existing issues with the construction of the property, it says it cannot warrant the repairs. It has offered the complainant a cash settlement. The complainant says the insurer’s cash settlement offer is not fair and reasonable. 1.2 Issues and key findings Is the insurer's cash settlement offer fair and reasonable? No. I am not satisfied the insurer’s cash settlement offer is fair and reasonable. Is the complainant entitled to non-financial loss compensation? Yes. I am satisfied the complainant is entitled to an award of non-financial loss compensation in the circumstances. Why is the outcome fair? It is fair that the insurer is responsible for both the insured damage, and the additional damage that resulted from the delays in identifying the water ingress and conducting the repairs to an appropriate standard. 1.3 Determination The determination is in favour of the complainant. Within 14 days of the insurer receiving written notice of the complainant’s acceptance of this determination, the insurer shall pay to the complainant: · a cash settlement for the repairs in the amount of $63,597.27 (to the extent this has not already been paid) and a 15% uplift. In total, $73,136.86 · $3,000 for non-financial loss compensation · interest on the $18,515.70 offer (payable from 24 March 2026 until the date the payment is made) pursuant to section 57 of the Insurance Contracts Act 1984 (Cth) (the Act) 2 Reasons for determination 2.1 Is the insurer's cash settlement offer fair and reasonable? No. I am not satisfied the insurer’s cash settlement offer is fair and reasonable. Complainant has the initial onus to establish a valid claim The initial onus is with the complainant to establish on the balance of probabilities (that is more likely than not) that the loss or damage claimed is covered by the policy. This is known as a valid claim. Once the complainant has established a valid claim, the onus shifts to the insurer to establish, on balance, the application of a policy exclusion or that it is otherwise entitled to decline or limit the claim under the policy. Policy provides cover for damage resulting from a storm subject to exclusions The policy provides cover (page 34) for loss or damage to the building and contents as a result of a storm. The cover contains an exclusion: What is not covered There is no cover under this Insured Event for … damage caused: - when water enters through an opening that is found to be an existing entry point or as a result of defective design. However, if we can verify by qualified opinion that the water entered with such significant force that it would have entered even in the absence of the existing entry point or design defect, we will not apply this limitation. There is no cover under this Insured Event where a General Exclusion applies The policy also contains general exclusions (page 54): Under this policy there is no cover provided for any loss, damage or liability caused directly or indirectly by or in any way connected with:… 1. defects, structural or design faults, faulty workmanship or faulty design; 2. damage to your building or part of your building that at the time it was built, renovated or installed was not compliant with the relevant local government regulations, or the requirements of any other applicable statutory authority; … 4. wear and tear, rust, corrosion and /or deterioration (except in some instances relating to ‘Sudden escape of liquid’ and ‘Legal liability’ Claims), but we will only apply this exclusion if the loss or damage is directly caused by one or more of these factors; 5. you not maintaining your building and/or contents in reasonably good repair and condition As stated, the complainant must show the damage to his property is covered by the policy to establish a valid claim. Proximate cause When establishing the cause of the damage to the property, it is the proximate cause that must be established. The proximate cause is not necessarily the first, last or the only cause of the damage. It is the dominant or effective or operative cause. The proximate cause of the damage is a question of fact to be determined based on the circumstances. Where there are several causes operating, each must be considered to determine its impact on the resultant damage or loss. If one cause results in the loss or damage in any case, and the other would not without the first, the first is the proximate cause. Assessment of the claim On 5 June 2025, the insurer accepted that the proximate cause of the damage was the storm (the Insured Event). The insurer assessed the extent of the claim related damage. The insurer’s builder, AC, inspected the property on 2 June 2025, where they concluded: In our professional opinion, the damage is consistent with the claimed storm event. Water ingress to the downstairs bedroom has affected ceiling and wall lining due to defective finishes to cladding on the exterior right-hand side of the building as well as damaged flashing between the carport and wall lining of the home. As the insurer undertook further assessment of the damage, it raised concerns with the complainant that the property had pre-existing non-compliance and/or quality of workmanship issues, and these had contributed to the damage. The insurer’s independent assessor (IA), on 20 October 2025, reported that: many areas are not completed to a tradesman like finish, nor do they meet current industry standards. These are summarised as: · Ineffective guttering on the roof. A roof report dated 1 August 2025, noted: At the time of my inspection, I found the roof to be in overall good condition throughout. While inspecting the roof area, I believe the cause of water ingress is prolonged rain overflowing the gutter and tracking behind the transition flashing. This is a result of trapped water in the gutter being unable to flow away. I believe this occurs during prolonged/heavy rain as it needs to build up before occurring. · Poor design of the carport roof. A make safe report, dated 21 August 2025, reported that further damage had been caused by prolonged and directional rain and that: The lower carport roof slopes back into the house, this causes water to pool against the wall and can track under the flashing. · A pre-existing leak in the downstairs shower. Leak detection reports, dated 29 August 2025 and 9 September 2025, noted: > high levels of moisture in front of the shower and in the downstairs bathroom > the flood and spray testing of the shower concluded that water was escaping from the shower and sitting in and against the shower screen on the outside of the screen The IA advised the complainant that, due to the compliance issues noted above, AC would be unable to warrant the approved repairs. The complainant agreed to resolve the claim by cash settlement. The complainant reported further leaking at the property In November 2025 the complainant requested the insurer further investigate the leak at the property, and perform the necessary repairs, as water ingress continued to be an issue. On 19 January 2026 a further leak detection report was produced. This outlined the cause of the leak to be: · pooling of water to the carport roof against the house wall due to the carport roof falling towards the house · open gaps between the weatherboard joints above and below the patio allowing water ingress · incorrectly installed barge/ apron flashing to the roof above the walk-in robe The report notes that the shower breach pressure test passed and the ensuite bathroom is not contributing to the claimed damages. On 26 February 2026, the insurer accepted the following damage: · downstairs bedroom: water ingress damage to the plasterboard ceiling and walls, some of the wall framings, the window architraves, skirtings and window jambs, the timber flooring · upstairs main bedroom walk-in robe: water ingress damage to plasterboard ceiling and walls, skirtings, cabinets, subfloor, and carpets · carport roof and flashing: one full length of roofing iron and one length of flashing was damaged by the unsuccessful make safes The insurer considers this to be the damage resulting from the insured event. However, it does not accept liability for repairing the compliance and quality of works issues, which were referenced in IA’s Initial Inspection Report, dated 24 February 2026, to be: · non-compliant roof flashing/ down pipe/ spreader pipe resulting in water finding its way into the ceiling of the walk-in robe and tracking down the walls into the downstairs bedroom · gaps at the front of the dwelling where the veranda timbers enter the structure allowing water to track along these timbers into the downstairs bedroom · various other failed silicone seals The insurer agreed that it was also responsible for the additional damage that occurred to the property while the water ingress continued. However, the IA confirmed that: the only damage that is resultant to the delays in locating the leak is the bedroom wall timber framing which will need replacement due to a deep moulding that cannot be remediated and the early onset of wood rot. In response, the complainant says he is not seeking compensation for improving the areas of the property identified by the insurer as being non-compliant or suffering from poor workmanship. He is, however, wanting his property to be returned to its pre-loss condition. He also disagrees that the property is non-compliant. On 19 February 2026, he produced council records that he says confirm that the dwelling, carport and subsequent alterations/additions were approved and finalised under relevant building approvals. Complainant raised a number of concerns with the way the claim was being managed The complainant raised concerns with the insurer in relation to the repair services provided by AC. The exchanged information confirms that some of the initial repair work was not performed satisfactorily and needed to be readdressed. This included: · repair work to the roof flashing to address the damage it sustained during the initial make safe works · the bedroom repairs, as these had been completed poorly during the original restoration process The complainant also raised on several occasions his concerns in relation to the ongoing water ingress, the length of time it was taking to resolve the issue, and the damage that this was causing to the house and contents. On 31 July 2025, although the approved repairs were almost complete, elevated moisture levels were identified at the property. The IA, in its report dated 20 November 2025, agreed that the previous make safe repairs had been ineffective and that additional leak detection tests would be required. They also advised AC to complete an additional strip out of the downstairs bedroom and upstairs robe to remediate mould growth and to assist in locating the leak by allowing greater access to the ceiling and wall cavities. On 24 February 2026, the IA noted in its report, that: various attempts to seal the issues have been completed by the make safe trades, but the dwelling is still allowing water ingress to the downstairs bedroom ceiling. At this time, the complainant queried how he was supposed to stop the leak if the insurer could not. The IA responded that it was the complainant’s responsibility to address the identified compliance and workmanship issues. The complainant disagreed with this position. He was of the view that as the water entry pathway remains active, that external defects must be rectified to stop further damage. He says the insurer is required to: · locate the active point of water ingress · repair and seal the entry pathway · complete reinstatement works after the source of the water ingress is rectified. Further, he says that these works form part of the reinstatement of the property and not an improvement, as they are necessary to restore the property following an insured event. The issue that remains in dispute While the insurer has raised several concerns in relation to pre-existing defects or issues with the property, it has confirmed that the scope of works (SOW), prepared by AC and dated 20 February 2026, covers all of the damage that has resulted from the insured event and ongoing water ingress problems. The complainant has obtained his own quote from his builder, LC, dated 12 March 2026, to address the damage to his property. He has also provided a quote from WC for supplying and installing the cabinetry for the upstairs walk-in robe. In relation to the two building quotes, the areas that have been identified for repair are the same. In this respect, there does not appear to be a dispute in relation to the scope of the repairs that need to be undertaken. However, the complainant says that reinstating the cabinetry in the walk-in wardrobe is not covered in his building quote, and the work outlined in WC’s quote is separate and distinct. The insurer, on the other hand, says this work is covered within its SOW. There is also a substantial difference between the quoted costs for completing these restoration works. AC’s SOW is for the amount of $14,890.70. Whereas LC’s quote was originally for $93,450.19, however this was subsequently reduced to $63,576.39 due to a typographical error in the original quote. The complainant does not consider the offer fair and reasonable The complainant is challenging the quantum of the cash settlement offer. He raises the following concerns: 1. The scope is limited to repairing visible damage and does not address the full extent of damage associated with the confirmed ingress pathways or concealed structural impact. For instance, there has been insufficient cost allocation to rectify the downstairs framing affected by wood rot. Costs are also not included for implementing a moisture barrier. 2. The quote does not reflect the price the complainant will need to pay to hire private trades to complete the work. The insurer confirmed that the quote was: based on agreed industry rates and it allows for rectification of all event-related damage, to restore the insured property to its pre-loss condition The insurer’s cash settlement offer must be fair and reasonable Where an insurer offers a cash settlement to resolve a claim, the settlement amount must be fair and reasonable in the circumstances. In other words, the cash settlement must be based on a reasonable quote for claim related repairs, actionable by a retail customer. An uplift is then typically applied to the quoted amount to allow for contingencies and the loss of the lifetime guarantee that applies to insurer approved repairs. The complainant has provided a quote from a local builder that, in his opinion, more closely reflects the costs that he will incur in repairing the damage to his house. The insurer provided feedback on this quote and noted that some of the line items are overpriced and the actual price of conducting the repairs is likely to be half of the amount quoted. For instance, the complainant is claiming $5,378 to cover the cost of the supply and installation of tiles. This is based on a cost estimate of $336 for each square metre (to cover 16 square metres). The insurer has responded that it is more likely to cost half of this amount, yet their initial building quote for tiling is for $259 ($17 x 15.2m2) which is not even close to $2,700. Similarly, the cost of supplying and installing plasterboard walls is quoted by the complainant to cost $8,663. The insurer has responded that half of this cost is more likely to be fair and reasonable, yet their own quote is $476. To resolve the dispute, the insurer has then requested that the complainant provide an amended quote in line with the recommendations provided by its IA for further consideration. I am not satisfied, on balance, the insurer’s offer is fair and reasonable Based on the information exchanged, I am not satisfied that the insurer’s cash settlement offer is based on a reasonable quote for claim-related repairs, that a retail customer such as the complainant could act on. This is because: · there is a considerable difference between the insurer’s quote of $14,890.70, and the complainant’s quote of $63,576.39. The complainant has obtained a quote from a local builder who has inspected the property and confirmed what he would charge to complete the works. The complainant says that his quote represents a reasonable settlement amount because it reflects what it would cost him to take on the responsibility of the repairs to his property. I am not satisfied that the insurer has adequately responded to this quote · the insurer has responded that its quote is based on industry rates. However, it has not provided sufficient evidence explaining how its significantly lower pricing can realistically be achieved by the complainant in the local market. It is also not clear whether this quote has considered the costs that a retail customer is likely to incur such as call-out fees, minimum rates, and rural charges · the insurer has responded to several line items in the complainant’s quote to state that the costing is excessive, or that about half of the amount quoted is more likely to be reasonable. In doing so, the insurer has indirectly suggested that its original quote may not be adequate · the complainant has provided a quote from WC to have the cabinetry reinstated in his walk-in wardrobe. He claims that this work is not covered in his builder’s quote and it will cost $5,760 to have the work completed. The insurer says this work is covered in their SOW of $14,890.70. I am not satisfied the insurer has adequately explained how the cabinetry works are allowed for in its SOW · to resolve the differences, the insurer has put the onus back onto the complainant to seek out another quote. The complainant had already provided a quote from a local builder willing to perform the work. Requiring another quote may involve additional cost and would likely cause further unnecessary delays, stress and inconvenience. In these circumstances, and based on the exchanged information, I am satisfied that the complainant’s quotes are more likely to reflect the cost of repairs that the complainant will incur in restoring his property. Settlement based on the complainant’s adjusted quotes is fair and reasonable On 25 March 2026, the complainant updated his quote and reduced the cost of painting the walls from $815.49 per square metre to $81.49 per square metre due to a typographical error in the original quote. In light of this adjustment, I note that the cost of painting in the overall quote ranges from $336 per square metre to $55 per square metre. While I accept that there will be some variations due to the complexity of the task in question, I believe adjusting the painting of the bedroom ceilings and skirtings to align to the $81.49 per square metre quote is reasonable. | GROUND FLOOR BEDROOM: | Unit | Original Cost per M2 | Amended cost per M2 | Adjusted amount | Painting - Prepare and paint skirting | 16.00 | 183.22 | 81.49 | 1,303.84 | Painting - Prepare, seal and paint ceiling linings including cornice | 16.00 | 336.13 | 81.49 | 1,303.84 | Painting - Prepare, seal and paint wall linings | 37.00 | 81.49 | 81.49 | 3,015.13 This will bring the complainant’s overall builder’s quote down to $57,304.28 (including GST). There is no dispute that the complainant’s quote from EF, and dated 24 February 2026, for replacing the ground floor bedroom’s floating floor and the carpet in the walk-in robe, overlaps with the complainant’s builder’s quote. As this quote has already been accepted by the insurer, the relevant items have been removed from LC’s quote, which will bring the quote to $54,212.27. For clarity, based on the comments above and the exchanged information, I consider a fair and reasonable cash settlement is as follows: · The repair of the damage to the property (except for the floating floor and carpet) in accordance with LC’s quote with the minor adjustments to the painting quote: $54,212.27 · The replacement of the bedroom floating floor and the carpet in the walk-in robe in accordance with EF’s quote: $3,625.00 · The reinstallation of the carpentry in the walk-in robe in accordance with the quote from WC: $5,760.00 This brings the overall settlement amount to $63,597.27. A 15% uplift is also to be applied to account for the loss of warranty and the transfer of the risk of repairs to the complainant. Interest to be applied to cash settlement The insurer is to pay interest pursuant to section 57 of the Act on its settlement offer of $14,890.70 for the building works, and $3,625.00 for the flooring from 24 March 2026, being the date that the settlement offer was made to the complainant, until the date the payment is made. I consider payment of interest fair because the insurer did not make it clear to the complainant that he could accept this offer while continuing to pursue the disputed amounts. 2.2 Is the complainant entitled to non-financial loss compensation? Yes. It is fair for there to be an award of non-financial loss compensation. AFCA can award compensation for non-financial loss Under our Rules, AFCA can award up to $6,300 compensation for non-financial loss in relation to a complaint lodged after 1 January 2024. This must relate to poor claims handling or other actions of the insurer which cause an unusual degree of stress, delay, or inconvenience. AFCA takes a conservative approach to compensation for non-financial loss. We expect complainants to be moderately robust, and we will not award compensation for the ordinary degree of inconvenience involved in making a claim. I am satisfied the insurer mishandled the claim The complainant faced extended uncertainty while the source of water ingress at their property remained undetermined. The repeated need for additional inspections and remediation, along with ongoing water ingress even after repairs were carried out, resulted in a level of disruption beyond what would normally be expected during a claim. The initial repair work to the downstairs bedroom was also of insufficient quality, requiring it to be removed and redone, contributing further to the overall disruption experienced. In the circumstances, it is fair for the insurer to pay the complainant $3,000 in non-financial loss compensation. 2.3 Why is the outcome fair? It is fair that the insurer is responsible for both the insured damage, and the additional damage that resulted from the delays in identifying the water ingress and conducting the repairs to an appropriate standard. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. ​We assess complaints on available information and circumstances ​AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. ​When we assess complaints, we consider: · ​available documents · ​the recollections of the parties · ​all relevant circumstances. ​We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. ​If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.