Determination 12-25-320136

Partial decline of water damage claim for disputed damage attributed to inherent construction defects

FirmAllianz Australia
Decided2026-07-10
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The insurer paid $5,249.24 cash settlement for new water damage but declined older damage it attributed to construction defects. AFCA found in favour of the insurer and required no further action.

The complainant bore the onus of showing the disputed damage was caused by a covered event, but expert evidence showed it resulted from long-term inherent construction defects which the policy does not cover.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Allianz Australia determinations · Find similar determinations

Text of the determination

Determination | Case number | 12-25-320136 | Financial firm | Allianz Australia Insurance Limited Case number: 12-25-320136 10 July 2026 1 Determination overview 1.1 Complaint The complainant holds a home building and contents insurance policy underwritten by the financial firm (insurer). He lodged a claim for water damage to his home. The insurer accepted part of the claim. It says there was older damage caused to the home due to inherent building defects (disputed damage) that it would not cover. The insurer issued a cash settlement for the new internal damage only. It did not agree to cover the disputed damage. The complainant says the insurer should cover all the claimed damage. 1.2 Issues and key findings Is the insurer liable for all the claimed damage? No. On balance, the damage the insurer did not agree to cover was caused by issues relating to the home’s construction. This disputed damage was not due to one of the policy’s insured events and was not ‘accidental damage’ as defined in the policy. It was damage due to inherent defects, which the policy does not cover. Why is the outcome fair? The complainant bears the onus to show the disputed damage was caused by an event the policy covers. This has not been shown in this instance. It would not be fair to require the insurer to cover the disputed damage as the policy does not respond to it. 1.3 Determination This determination is in favour of the insurer. The insurer is not required to take any further action in relation to this claim or the complaint. 2 Reasons for determination 2.1 Is the insurer liable for all the claimed damage? No. On balance, the damage the insurer did not agree to cover was caused by issues relating to the home’s construction. This disputed damage was not due to one of the policy’s insured events and was not ‘accidental damage’ as defined in the policy. It was damage due to inherent defects, which the policy does not cover. Complainant seeks cover for storm or water-related damage to home The insured home is a two-storey construction with a metal roof and external walls of fibre-cement sheeting. The home is believed to have been built in or about 1999. The complainant lodged a claim on 29 January 2025. He initially told the insurer there was: water leaking in through the ceiling of the property owing to the rain. Water ingress damage had been caused to the plasterboard ceiling, cornice, wall linings and a door jamb in a bedroom. Subsequent investigations showed a leaking box gutter on the roof and historic water ingress damage inside some areas of the home. The complainant previously made a claim for similar damage in 2018. The insurer paid a cash settlement for much of the internal damage. It says this damage was caused by water leakages from the damaged box gutter. However, it did not cover the disputed damage, which includes: · damage to the timber lintel support beam over the garage · the cost to replace the rusted box gutter · the cost to enlarge the overflow outlets, and · any damage it says was caused over time due to the construction of the home. The insurer says this disputed damage was not caused by an event covered under the policy. Further, the dominant or effective cause of this damage was inherent defects in the home’s construction and wear and tear. The policy does not cover damage from those causes. The insurer issued payment for $5,249.24 on 17 June 2025 for the covered damage. Onus on complainant to establish claimable loss The complainant bears the onus of establishing, on balance, that he suffered a loss caused by an event covered under the policy. If the complainant establishes a claimable loss, the onus then shifts to the insurer to demonstrate, on balance, that it is entitled to: · rely on a policy exclusion, or · otherwise reduce its liability or decline the claim. Whilst the insurer made payment to the complainant for some damage, the complainant is still required to show a claimable loss was the cause of the disputed damage. The reference to establishing issues ‘on balance’ means the relevant party must show it is more likely than not. Policy covers listed events subject to terms, conditions and exclusions The policy comprises the policy schedule and the Product Disclosure Statement (PDS). The complainant does not dispute receiving these documents. Cover is typically limited to damage caused by specified insured events. However, the complainant also selected an ‘Accidental damage’ option under the policy for an additional premium. This expands the potential cover the policy offers. Amongst the insured events is cover for loss or damage caused by: · ‘Storm, cyclone, rainwater or run-off’, and · ‘Water or other liquid damage’. Whilst the complainant says water most likely got into the home due to storm events, he has not alleged any singular storm caused the claimed damage. Rather, he says the damage was due to water inundation into areas of the home over time. Water damage was at least partially caused by the bursting, leaking, discharging or overflowing of a fixed gutter or drainpipe (being a box gutter). This is consistent with the cover offered under the ‘Water or other liquid damage’ event. The insurer says its cash settlement to the complainant settled this covered damage. Accidental damage cover extends to ‘accidental unexpected mishaps that are caused unintentionally’. It is defined in the PDS as: damage caused by sudden, unforeseen and unintended events. This cover is subject to terms, conditions and exclusions and only applies if none of the insured events caused the claimed loss. Insurer’s claim investigation in 2018 found long-term water damage The complainant first sought cover for water damage to the home in 2018. The insurer arranged for builder MK to inspect the damage. Its report of 1 April 2019 referenced prior investigations from 16 May 2018. MK found a box gutter ran along the rear of the home and the adjoining house next door (which the complainant’s brother owned). The box gutter was full, as the northern downpipe was blocked. After the downpipe was cleared, builder NI removed the internal wall linings to begin repairs on 5 June 2018. It found the internal wall lining was ‘still wet’. MK told the complainant further maintenance work was required. A fire broke out at the neighbouring property on 19 September 2018. The complainant lodged a claim for smoke damage. These repairs were scheduled to be undertaken together with the water-related repairs. The complainant replaced the box gutter soon afterwards. According to MK, NI returned to undertake repairs on 23 November 2018. NI reportedly then found ‘moisture damage to the internal timber framing’. This included wood rot in some areas. MK considered this was consistent with a ‘long-term moisture issue’, not stormwater ingress from the box gutter. After inspecting this damage, MK found: · water was entering the garage wall directly below the aluminium window frames · plasterboard above the aluminium sliding door was installed poorly and needed to be reinstated · timber to the top of the garage opening was not installed properly · some of the repair work observed was not completed by NI · the curve to the ceiling and the timber at the head of the garage door was ‘pre-existing’ and ‘possibly from the time of construction’ · other repairs were completed, however the issues with the garage door were not claim-related and should not be covered. Based on MK’s advice, the insurer says it did not undertake any repair work to the timber lintel above the rear garage door or address other areas now part of the disputed damage. In 2023, at the request of MK, the insurer arranged for engineer LG to review the damage. LG provided a report dated 27 March 2023. This report found: · there was ‘severe decay to the timber lintel and framing elements over the rear opening of the garage’ · construction was non-compliant, noting there was no vapour barrier or cavity to allow drainage of water which penetrated the façade cladding · this meant water would ingress directly to the structural frame · there were no weep holes on top of the garage opening or the window above the garage · the façade was ‘constructed without any drainage provisions or moisture protection’ · the proximate cause of the damage to the timber lintel and frame was ‘non-compliant and inadequate construction and waterproofing provisions to the façade and cladding’ · as timber has a ‘natural durability’ the process of decay was ‘slow and gradual’ · such deterioration likely took about 20 years · the fire event at the neighbour’s home was not relevant to this damage · decay to the timber lintel had ‘compromised the structural integrity of the building’ and it will not be safe for occupancy until this was rectified. Insurer’s 2025 investigation said disputed damage not covered under policy The complainant wanted the matter reviewed for new internal damage in 2025. There was no dispute water entered the home and caused further damage. The insurer arranged for several experts to inspect this damage. Roofer JN prepared a report dated 30 January 2025. JN did not consider a storm created opening was present or that water damage was due to wind driven rain. JN found it was ‘likely’ the rusted box gutter permitted water to enter the home and cause damage. Builder TB attended the home on 4 February 2025. It said the complainant informed it the event occurred ‘approximately’ two years earlier and ‘slowly’ got worse over time. TB found: · the damage was consistent with it occurring over a ‘prolonged period of time’ · it was caused by water entering ‘due to the rusted box gutter’ directly above the upstairs bedroom · water was entering the ceiling and wall cavity and flowing into the bedroom · the rusting of the box gutter was ‘clearly visible’ and appeared to have been present for some time. TB undertook some ‘make safe’ work to ensure the bedroom ceiling did not collapse. Photos of the home show a massive water stain on the ceiling and wall of the bedroom. Water damage was also evident on the window. TB prepared a repair quote for $5,249.24 on 17 February 2025. This was based on all maintenance work being undertaken prior to it starting repairs. It became the basis for the insurer’s settlement offer. Engineer SW prepared a report dated 1 May 2025. It found: · inadequate wall construction (without a weather barrier) meant wind-driven rainfall ingress occurred inside the home through the cracking in the fibre cement sheeting · there were also no signs of flashing installation behind the corner of the sheeting, which contributed to water ingress damage · severe rot and deterioration to timber members were due to prolonged water ingress and exposure over the years · this is unrelated to the overflowing of the box gutter in 2018 · it also considered the ‘tie-down’ of the timber structure to be ‘grossly non-compliant’ with the Australian Standards at the time of construction · it agreed with TB that water inundation from the claimed event was due to the rusting of the box gutter caused by deterioration · it also agreed with LG’s report from 2023 that the deterioration of the timber lintel was due to exposure to moisture over time and the inadequate construction of the weather barrier (which allowed water to enter) · repair of the claimed damage could not be guaranteed without significant other restoration work being done · weatherproofing of the external wall and the window flashing was not ‘adequately constructed’ when the home was built, or compliant with the building code of the time. Complainant maintains insurer should cover the damage The complainant says the damage was caused by the negligence of the neighbour (who is his brother) in failing to maintain his home properly. The neighbour’s stormwater plumbing became blocked and rusted. Its failure meant that a dual burden, for the insured home and the neighbour’s home, was placed on the complainant’s box gutter. This box gutter was overwhelmed, which led to the claimed loss. He provided an expert report from builder OB dated 7 January 2023. OB noted it was asked to ascertain the reason for render cracking and external lining movement. It removed a sheet of the external cladding from above the rear garage door and found ‘obvious signs of structural damage below with sagging of the head opening’. OB found ‘fire and water damage to the upper [storey] floor trusses’ and to the level above the garage opening, with ‘what looks to be wood rot’. It considered that the fire had ‘created serious structural issues’ allowing building movement and water leaks. In a later letter of 24 March 2026, OB confirmed it undertook some work at the home in 2018, including replacing the box gutter and installing a rain head. It also upgraded the flashing. The complainant confirms he does not allege this damage was from a single event. He considers excessive water rusted the box gutter. This caused water to leak into his home. He says this excess water was effectively the cause of the claimed damage. Disputed damage not caused by an insured event under the policy I acknowledge water leaked from the rusted box gutter into the complainant’s home, causing damage. This is consistent with a ‘Water or other liquid damage’ event. I consider the extent of this damage was covered by the cash settlement paid by the insurer. The disputed damage is another issue. I consider this was long-term damage caused by inherent construction defects. The insurer had two engineers review this damage and both agreed the proximate (dominant or effective) cause was the home’s construction, not simple water ingress. The experts consider long-term water ingress occurred through the window and the fibre cement sheeting. This, and poor internal construction elements, caused damage over time. Whilst I acknowledge the complainant disagrees, he provided no contrary expert opinion on this issue. SW outlined several concerns (absence of eaves, use of fibre cement sheeting, improperly installed timber lintel support beam) which were due to construction issues. Ultimately, I am not persuaded the disputed damage was: · caused specifically by the leaks from the damaged box gutter · due to any other claimable event under the policy, or · accidental damage, noting it had been present for some time and was not sudden or unforeseen. Even if I accepted the damage was accidental (as the complainant was not aware of it when it started), I am satisfied it was primarily due to the inherent defects highlighted by LG and SW. This means the damage is excluded in any event. There is also no persuasive evidence this damage was agreed to be repaired by the insurer in 2018, or that it was ever part of the work undertaken at that time. I am not satisfied the complainant can establish MK or the insurer caused or contributed to any issue through the handling of the 2018 claim. Insurer not liable for the disputed damage On balance, I am not persuaded the insurer is liable for the disputed damage. This was long-term damage caused by construction issues permitting water ingress into the home. It only came to the parties’ attention due to the claim in 2018. Due to the manner of its construction, the home permitted water ingress through areas other than the damaged box gutter. These were detailed by LG and SW. I am not satisfied these issues arose from a claimable loss. They were not caused by a single storm event, or a water leak from a pipe or other similar conveyance. It was due to water coming in through the areas of the home over time. This includes but is not limited to the fibre cement sheeting (which was not adequately waterproofed and had no eaves installed) and the windows. I acknowledge the complainant says the home was built by a master builder and was an award-winning home. This does not change or lessen the impact of the evidence showing there were inherent building concerns present. I accept these issues were present from the time of construction and were long-term. Given the complainant cannot show the disputed damage was caused by a claimable loss, it is not the insurer’s responsibility to repair it. 2.2 Why is the outcome fair? The complainant bears the onus to show the disputed damage was caused by an event the policy covers. This has not been shown in this instance. It would not be fair to require the insurer to cover the disputed damage as the policy does not respond to it. 3 Supporting information 3.1 The AFCA process AFCA’s approach is based on fairness AFCA has determined this complaint based on what is fair in all the circumstances, having regard to: · the legal principles · applicable industry codes or guidance · good industry practice · previous decisions of AFCA or its predecessor schemes (which are not binding). The respective parties have completed a full exchange of the relevant information, and each party has had the opportunity to address any issues raised. We have reviewed and considered all of the information the parties have provided. While the parties have raised a number of issues in their submissions, we have restricted this determination to the issues that are relevant to the outcome. We assess complaints on available information and circumstances AFCA is not a court of law. We do not have the power to take or test evidence on oath, or to require third parties to give evidence. When we assess complaints, we consider: · available documents · the recollections of the parties · all relevant circumstances. We give more weight to documents created at the time the events occurred. If there are no relevant documents, we will decide what most likely occurred based on the available information. If there are conflicting recollections and these are evenly weighted, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.